Acceptance of 2017 Windsor Avenue Sanitary Sewer Manhole Project Copyrighted
January 22, 2019
City of Dubuque Consent Items # 17.
ITEM TITLE: Acceptance of 2017 Windsor Avenue Sanitary Sewer
Manhole Project
SUMMARY: City Manager recommending acceptance of the public
improvement construction contract for the 2017 Windsor
Avenue Sanitary Sewer Manhole Project as completed by
Drew Cook& Sons Excavating.
RESOLUTION Accepting the 2017 WindsorAvenue
Sanitary Sewer Manhole Project
SUGGESTED DISPOSITION: Suggested Disposition: Receive and File; Adopt
Resolution(s)
ATTACHMENTS:
Description Type
2017 W indsor Avenue Sanitary Sewer Manhole City Manager Memo
Project-NNM Memo
Staff Memo Staff Memo
Resolution Resolutions
Engineer's Cert Supporting Documentation
THE CITY OF Dubuque
�
AIFA�erlwGh
UB E '�� III►
Masterpiece on the Mississippi Z°°'�w'2
7A13 2017
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: 2017 Windsor Avenue Sanitary Sewer Manhole Project
(CIP 7101335)
DATE: January 16, 2019
City Engineer Gus Psihoyos is recommending acceptance of the public improvement
construction contract for the 2017 Windsor Avenue Sanitary Sewer Manhole Project, as
completed by Drew Cook & Sons Excavating, in the final contract amount of
$18,390.38, which is a 0.6°k decrease from the original contract amount of$18,500.00.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
�� �� ���
Mic ael C. Van Milligen �� �
MCVM:jh
Attachment
cc: Crenna Brumwell, City Attorney
Teri Goodmann, Assistant City Manager
Cori Burbach, Assistant City Manager
Gus Psihoyos, City Engineer
THE CITY OF Dubuque
�
�•���s�
UB � �:���. , ��r
��
Masterpiece on the Mississippi Z°°''�'2
20t3•2017
TO: Michael C. Van Milligen, City Manager __.�
p ��- �?
FROM: Gus Psihoyos, City Engineer �� f '�J
��� .
DATE: January 14, 2019
RE: 2017 Windsor Avenue Sanitary Sewer Manhole Project
(CIP 7101335)
INTRODUCTION
The enclosed resolution provides for the acceptance of the public improvement
construction contract for the 2017 Windsor Avenue Sanitary Sewer Manhole Project.
BACKGROUND
The City of Dubuque, lowa is under a Consent Decree according to Case
2:11-cv-01001-EJM, United States of America and the State of lowa v. the City of
Dubuque, IA (N.D. lowa), Civil Action Number 2008V00041, DOJ Case Number
90-5-1-1-09339 effective June 27, 2011. The City is required to submit Corrective Action
plans for each of the Sanitary Sewersheds identified in the Consent Decree. The
FY2017 budget appropriated funds for sanitary sewer manhole improvements in the
Consent Decree Correction Action Plan.
DISCUSSION
The 2017 Windsor Avenue Sanitary Sewer Manhole Project was completed by Drew
Cook & Sons Excavating of Dubuque, lowa, in the final contract amount of $18,390.38
which is a 0.6% decrease from the original contract amount of $18,500.00. The project
included the removal of two (2) manholes and replacement with 8" connecting pipe and
the replacement of two (2.) manholes in Sewershed 10.
BUDGETIMPACT
The summary of project costs for the 2017 Windsor Avenue Sanitary Sewer Manhole
Project is as follows:
Award Final
Construction Contract $ 18,500.00 $ 18,390.38
Contin ency (10%) 1,850.00 0.00
Construction Engineerin & Inspection 15% 2,035.00 2 758.56
Total Project Cost 2 .0 1 14 9
T'he funding fc�r this project will be di�trik�utecf Frc�m the CIP i�ientifiPd befow:
CIP No. Fund Descri tion Fund Amount
7101335 Sanita SewEr M�nhole Re lac�ment & Rehabilit�tion $21 ,148.�
Total Project Fundin 21 148.9
RECOMMENDATION
The City Council is requested to adopt the attac;h�d resolution fio accepfi the
improvements and to authorize the payrrient of th� contract amount of $127,349.21 tc�
Drew Cook & Sons Excavating for thE 2017 Windsor Avenuc Sanitary Sewer Manhole
Project,
Pr�pared by: Jon Dienst, P.E.
cc: Jenny Larson, Budget Director
Denise Ihrig, PE, Wat�r Department Man�ger
Deron Muehring, Civil Engineer II
i
z
RESOLUTION NO. 31-19
ACCEPTING THE 2017 WINDSOR AVENUE SANITARY SEWER MANHOLE
PROJECT
WHEREAS, the public improvement contract for the 2017 Windsor Avenue Sanitary
Sewer Manhole Project, (the Project) has been completed by the Contractor, Drew
Cook & Sons Excavating (Contractor), the City Engineer has examined the work and
recommends that the Project be accepted; and
WHEREAS, the final contract amount for the Project is $18,390.38; and
WHEREAS, the Contractor has previously been paid $17,470.86, leaving a balance
of $919.52; and
WHEREAS, the City Council finds that the recommendation of the City Engineer
should be accepted.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
DUBUQUE, IOWA:
Section 1. The recommendation of the City Engineer is approved, and the Project is
hereby accepted.
Section 2. The Finance Director is hereby directed to pay to the Contractor the
balance of the retainage of $919.52 as provided in Iowa Code chapter 573, and to pay
such retainage in accordance with the provisions of Iowa Code chapter 573 or Iowa
Code chapter 26.13.
Passed, approved, and adopted this 22nd day of January 2019
AT 9
Roy D. Buol, Mayor
Attest:
Key'in S. Firnstahl, City Clerk
CITY ENGINEER'S CERTIFICATE OF FINAL COMPLETION OF 2017 WINDSOR
AVENUE SANITARY SEWER MANHOLE PROJECT
The undersigned City Engin�er of the City of Duk�uqu�, low�, her�;by certifies that
he has inspected the 2()17 Windsor Av�nu� Sanit�ry S�wer Manhol� Project, sand that
s�id Proj�ct h�s been perform�d in compliancP with the tPrms of the Public
Impr�verr�snt Contr�ct, �nd that th�; total co�t of th� completecl work is $21,148.�34.
-i�-- , �
Dated this ` �� __day af �'��� � . � '�C� , 2019. — -
, t 1 . `' 1 F
;• ` �l., JJ '�,
�;• � ������`�`�_
c � . '`-�,.t_�,_—�,._:'
Gus Psihc�yos, City Engineer
.��
Filed in the office of the City Clerk on the�Cr� day of �'`11l , 2019.
�