Catch Basin Replacement Project 2008_AcceptanceMasterpiece on the Mississippi
TO:
FROM:
SUBJECT:
DATE:
The Honorable Mayor and City Council Members
Michael C. Van Milligen, City Manager
2008 Catch Basin Replacement Project
CIPs 7201081 and 3501041
March 8, 2010
City Engineer Gus Psihoyos is recommending acceptance of the 2008 Catch Basin
Replacement Project, as completed by McDermott Excavating, in the final contract
amount of $92,994, which is a $26,252 (39.4 %) increase from the original contract
amount of $66,692. The replacement of seven additional intakes around the Locust
Street Parking Ramp was added to the project at a cost of $25,845, which is the
majority of the cost increase.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
MCVM:jh
Attachment
cc: Barry Lindahl, City Attorney
Cindy Steinhauser, Assistant City Manager
Gus Psihoyos, City Engineer
Mic ael C. Van Milligen
Dubuque
hail
AlWlmedca City
I HI I
2007
Masterpiece on the Mississippi
TO: Michael C. Van Milligen, City Man ag
FROM: Gus Psihoyos, City Engineer
DATE: March 5, 2010
SUBJECT: 2008 Catch Basin Replacement Project
CIPs 7201081 and 3501041
INTRODUCTION
Dubuque
Al- AmedcaCity
i r
2007
The enclosed resolution provides for the acceptance of the construction contract for the
2008 Catch Basin Replacement Project.
BACKGROUND
The 2008 Catch Basin Replacement Project involved the replacement of 22 catch
basins that are located on streets that were resurfaced as part of the 2008 Public Works
Asphalt Overlay Program.
The project was awarded based on a competitive quotation process for public
improvements in accordance with Iowa Code, Section 26.14.
DISCUSSION
The 2008 Catch Basin Replacement Project was completed by McDermott Excavating
of Dubuque, Iowa, of Dubuque, Iowa, in the final contract amount of $92,994.00, which
is a $26,252.00 (or 39.4 %) increase from the original contract amount of $66,692.00.
The replacement of seven additional intakes around the Locust Street Parking Ramp
was added to the project at a cost of $25.845.00 which is the majority of the cost
increase.
RECOMMENDATION
I recommend that the City Council accept the improvements and authorize the payment
of the contract amount of $92,994.00 to McDermott Excavating for the 2008 Catch
Basin Replacement Project.
BUDGET IMPACT
The total cost for the 2008 Catch Basin Replacement Project is as follows:
Construction Contract
Contingency
Miscellaneous Costs
Engineering
Total Project Cost
The project funding summary is as follows:
CIP No.
7201081
3501041
ACTION TO BE TAKEN
Fund Description
Catch Basin/Westside Storage
Curb /Catch Basin Replacement
Total Project Funding
The City Council is requested to adopt the attached resolution to accept the
improvements and to authorize the payment of the contract amount of $92,994.00 to
McDermott Excavating for the 2008 Catch Basin Replacement Project.
cc: Jenny Larson, Budget Director
Deron Muehring, Civil Engineer II
Award
$ 66,692.00
6,669.20
7,336.12
$ 80,697.32
Final
$92,994.00
0
343.90
2,113.65
$95,451.55
Fund Amount
$69,606.55
25,845.00
$95,451.55
RESOLUTION NO. 77-10
ACCEPTING THE 2008 CATCH BASIN REPLACEMENT PROJECT AND
AUTHORIZING THE PAYMENT OF THE CONTRACT AMOUNT TO THE
CONTRACTOR
Whereas, the Public Improvement Contract for the 2008 Catch Basin
Replacement Project (the Project) has been completed and the City Engineer has
examined the work and filed a certificate stating that the Project has been completed
according to the terms of the Public Improvement Contract and that the City Engineer
recommends that the Project be accepted; and
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF DUBUQUE, IOWA:
Section 1. The recommendation of the City Engineer is approved and the Project
is hereby accepted.
Section 2. The Finance Director is hereby directed to pay to the Contractor from
the Catch Basin Maintenance, Catch Basin/Westside Storage, and Curb /Catch Basin
Replacement appropriations for the contract amount of $92,994.00 less any retained
percentage provided for therein as provided in Iowa Code chapter 573, and to pay such
retainage only in accordance with the provisions of Iowa Code chapter 573.
Passed, approved and adopted this 15th day of March 2010.
Attest:
anne F. Schneider, CMC, City Clerk
Roy D. Buol, Mayor
CITY ENGINEER'S CERTIFICATE OF FINAL COMPLETION OF THE 2008 CATCH
BASIN REPLACEMENT PROJECT
The undersigned City Engineer of the City of Dubuque, Iowa, hereby certifies that
he has inspected the 2008 Catch Basin Replacement Project, that the Project has been
performed in compliance with the terms of the Public Improvement Contract, and that
the total cost of the completed work is $95,451.55.
Dated this 10th day of March, 2010.
Filed in the office of the City Clerk on the 10th day of March, 2010
City Engineer
2010.
Jeanne F. Schneider, CMC, City Clerk
Project Name:
CIP Number:
Project Contract Amount:
Project Completion Date:
INTAKE REPLACEMENT
PROJECT
7201066
$66,692.00
22 Jul - 09
ITEM
NO.
CONTRACT ITEM
DESCRIPTION
CONTRACT ITEM
QUANTITY UNIT UNIT PRICE
PROJECT TOTAL
QUANTITY TOTAL
PERCENT
COMPLETE
Iowa @ 10th Street - Intake 101 -B, NW Corner
1 LS $ 2,625.00
1 $ 2,625.00
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
1
2
Iowa @ 10th Street - Intake 101 -B, NE Corner
1 LS $ 2,700.00
1 $ 2,700.00
3
Iowa @ 12th Street - Intake 101 -B Special, NW Corner
1 LS $ 3,173.00
1 $ 3,173.00
4
Iowa @ 13th Street - Intake 101 -B Special, NW Corner
1 LS $ 3,173.00
1 $ 3,173.00
5
10th @ Main Street - Intake 101 -B Special, NW Corner
1 LS $ 3,173.00
1 $ 3,173.00
6
10th @ Central Avenue - Intake 101 -B Special, SW Corner
1 LS $ 3,048.00
1 $ 3,048.00
7
12th @ Main Street - Intake 101 -B Special, SW Corner
1 LS $ 3,383.00
1 $ 3,383.00
8
12th @ Main Street - Intake 101 -B Special, NW Corner
1 LS $ 3,258.00
1 $ 3,258.00
9
3rd Street @ Parkway - Intake 101 -B, North Side
1 LS $ 2,575.00
1 $ 2,575.00
10
3rd Street @ Parkway - Intake 101 -B Special, South Side
1 LS $ 3,269.00
1 $ 3,269.00
11
Kane Street (Across From 1100) - Intake 101 -B
1 LS $ 2,785.00
1 $ 2,785.00
12
Kane Street (In Front Of 1100) - Intake 101 -B Special
1 LS $ 3,098.00
1 $ 3,098.00
13
Kane Street (West End of Wahlert) - Intake 104 -B Special
1 LS $ 4,169.00
1 $ 4,169.00
14
1150 Edina Street - Intake 101 -B
1 LS $ 2,863.00
1 $ 2,863.00
15
1161 Edina Street - Intake 101 -B
1 LS $ 2,700.00
1 $ 2,700.00
16
1111 Vernon Street - Intake 101 -B
1 LS $ 2,625.00
1 $ 2,625.00
17
1150 Vernon Street - Intake 101 -B
1 LS $ 2,575.00
1 $ 2,575.00
18
1207 Washington St. (Across The Street) - Intake 101 -B Specia
1 LS $ 3,258.00
1 $ 3,258.00
19
1502 Washington St. - Intake 101 -B Special
1 LS $ 2,942.00
1 $ 2,942.00
20
1598 Washington St. - Intake 101 -B Special
1 LS $ 3,258.00
1 $ 3,258.00
21
1608 Washington St. - Intake 101 -B Special
1 LS $ 2,942.00
1 $ 2,942.00
22
Cox Street @ Graber Center - Intake 101 -B Special
1 LS $ 3,100.00
1 $ 3,100.00
CHANGE ORDER
1
Repair Storm Pipe at Johnson & Lincoln
1 LS $ 457.00
1.00 $ 457.00
2
Additional Intakes @ Locust St Ramp (7)
1 LS $25,845.00
1.00 $ 25,845.00
Payment Totals $ 92,994.00
anager
APPROVED:
Michael Van illigen, C
Dubuque, Iowa
City of Dubuque
Engineering
50. W. 13th Street
Dubuque, IA 52001
(563) 589 -4270
I hereby certify that the above statement shows, in detail, the correct
amount of all work requ' - to complete the above improvement.
Gus Psihoyos, City Engineer
Dubuque, Iowa
PROJECT CLOSE OUT FORM
Contractor Name:
Contractor Address:
City, State, Zip:
Contractor Telephone:
McDermott Excavating
14407 Highway 20 West
Dubuque, Iowa 52003 -9709
563 -583 -4633
Total Contract Work Performed to Date:
Total Change Order Work Performed to Date:
Total Contract and Change Order Work Performed to Date:
Miscellaneous Costs
Engineering
APPROVED:
BY:
66,692.00
26,302.00
92,994.00
343.90
2,113.65
TOTAL FINAL PROJECT COSTS: $ 95,451.55