North Cascade Road Reconstruction Project Phase 1 Bridge Over Catsifh Creek to Edval Lane_Initiate Copyrighted
February 4, 2020
City of Dubuque Items to be set for Public Hearing # 2.
ITEM TITLE: North Cascade Road Reconstruction Project Phase 1 -
Bridge over Catfish Creek to Edval Lane
SUMMARY: City Manager recommending initiation of the public bidding
procedure through the lowa Department of Transportation
forthe North Cascade Road Reconstruction Project—
Phase 1 — Bridge Over Catfish Creek to Edval Lane, and
further recommends that a public hearing be set for
February 17, 2020.
RESOLUTION Preliminaryapproval of plans,
specifications, form of contract, and estimated cost; setting
date of public hearing on plans, specifications, form of
contract, and estimated cost
SUGGESTED DISPOSITION: Suggested Disposition: Receive and File; Adopt
Resolution(s), Set Public Hearing for February 17, 2020
ATTACHMENTS:
Description Type
North Cascade Road Reconstruction Project-MVM City Manager Memo
Memo
Staff Memo Staff Memo
Resolution Resolutions
Property Acquisition O�rview Map Supporting Documentation
Project Limits Overview Map Supporting Documentation
Dubuque
THE CITY OF �
uI�AaMca cih
DuB E � �
I � � I
Maste iece on the Mississi i Zoo�•zoiz•zois
YP pp zoi�*zoi9
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: North Cascade Road Reconstruction Project
Phase 1 - Bridge Over Catfish Creek to Edval Lane
lowa DOT Project No. STBG-SWAP-2100 (669)--SG-31
DATE: January 28, 2020
Assistant City Engineer Bob Schiesl recommends initiation of the public bidding
procedure through the lowa Department of Transportation for the North Cascade Road
Reconstruction Project — Phase 1 — Bridge Over Catfish Creek to Edval Lane, and
further recommends that a public hearing be set for February 17, 2020.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
�
Mic ael C. Van Milligen
MCVM:jh
Attachment
cc: Crenna Brumwell, City Attorney
Teri Goodmann, Assistant City Manager
Cori Burbach, Assistant City Manager
Gus Psihoyos, City Engineer
Bob Schiesl, Assistant City Engineer
Dave Baker, Dubuque County Board Chair
Anthony Bardgett, Dubuque County Engineer
Dubuque
THE CITY OF �
All•America City
U B E ��o���K�,���
� � � ►
�
Maste iece on the Mississi i z°°'*2°12�z°13
�`P pp zoi�*zoi9
TO: Michael C. Van Milligen, City Manager
Gus Psihoyos, City Engineer
FROM: Robert Schiesl, Assistant City Engineer
SUBJECT: North Cascade Road Reconstruction Project
Phase 1 — Bridge over Catfish Creek to Edval Lane
lowa DOT Project No. STBG-SWAP-2100 (669)--SG-31
DATE: January 27, 2020
INTRODUCTION
The purpose of this memorandum is to provide the City Council with information related to
the North Cascade Road Reconstruction Project, Phase 1 from the bridge over Catfish
Creek to Edval Lane, lowa DOT Project No. STBG-SWAP-2100 (669)--SG-31 and request
concurrence to initiate the public bidding procedure and establish the date for the public
hearing.
BACKGROUND
With the upcoming completion of the Southwest Arterial (US 52) and the location of the
Middle Interchange at North Cascade / English Mill Road, traffic volumes are expected to
increase on North Cascade Road. The existing roadway is narrow, substandard in design
and is inadequate to accommodate future traffic and development growth.
The Timber Hyrst residential subdivision is under development and connects Creekwood
Drive to North Cascade Road between Edval Lane and the Catfish Creek bridge. The
development agreement for this subdivision between the City of Dubuque and North
Cascade Road Developers, LLC., in addition to a pre-annexation development agreement
with Gary Valentine stipulates that the City will complete safety related improvement to
North Cascade Road.
A portion of North Cascade Road Reconstruction Project, between the bridge over Catfish
Creek to Edval Lane is located within the corporate limits of the City, while a segment
remains within Dubuque County jurisdiction. The City has coordinated the road
reconstruction project with the County Engineer, Anthony Bardgett, and are fully supportive
of the proposed roadway safety improvements. Dubuque County will not be contributing
funding towards the project.
This roadway is classified as a collector under the FHWA Street Classification. The
existing 24-foot rural roadway has granular shoulders and typical rural ditch grading and
drainage. The existing sight distance along this stretch of North Cascade Road is less than
desirable and the realignment of the existing curves in this area will improve safety for the
motoring public.
DISCUSSION
The City has developed a project to reconstruct North Cascade Road between the bridge
over Catfish Creek to the future intersection of North Cascade Road and the Southwest
Arterial. The project will be developed into 2 phases; Phase 1 (2020) - from Catfish Creek
bridge to Edval Lane; and Phase 2 (2022) - from Edval Lane to Southwest Arterial.
The current 24-foot rural roadway will be widened to accommodate a 35-foot urban
"complete street" section with 5-foot paved shoulders / bike lanes on each side and
grading for future sidewalks on each side of the road. The existing curves on North
Cascade Road are substandard and will be realigned to improve safety and allow for better
sight distance.
The attached aerial photo corridor map shows the proposed Phase 1 project limits for the
North Cascade Road Reconstruction, from the bridge over Catfish Creek to Edval Lane.
Figure 1 below shows the proposed "complete street" typical roadway section.
35' -
1�lORTH SIDE CENT RLINE SOUTH SIDE
5.5' 12' 12' S.5'
� �
-_�� � s� r-� �
� �
� -
\_ ;� . , _: I `II
�- -- '� � i- , ��- �` - - 3
_I .- -- - -- , _.
- - - -`: - j ' � - _. `:_. i _ �
_ _j - - - / _ \ ,,,
12'DRIVE � \
5'WIDE BIKE � 12'DRIVE LANE GRADE FOR FUTURE
LANE LANE YELLOW 10'WIDE BIKE PATH
S�RIPING
NORTH CaSCADE RD. 5'WIDE BIKE
LANE
35'WIDE COMPLETE STREET
Figure 1
As part of the North Cascade Road Reconstruction project, the City will be installing a new
12-inch water main along North Cascade to Creekwood Drive (Timber Hyrst subdivision).
Once the water main is extended and connected at Creekwood Drive, a critical water main
distribution loop will then be completed while also positioning the water main system to
support future expansion and growth towards the Southwest Arterial corridor.
PROPERTY ACQUISITION
With the widening of North Cascade Road to accommodate a 35-foot urban "complete
street" section and the realignment of the two (2) curves to improve safety, it was
necessary for the City to acquire property from eleven (11) impacted properties. All right-
of-way, including fee title acquisitions, permanent easements, and temporary construction
easements have been acquired. The attached aerial photo corridor map shows the
impacted properties that were purchased.
PUBLIC OUTREACH - COORDINATION
In an effort to inform the general public and impacted property owners along North
Cascade Road and the nearby Timber Hyrst subdivision, the Engineering Department staff
will be hosting a public informational meeting. The meeting will be held in March, following
the bid letting which will allow the City knows who the contractor will be and their
anticipated construction schedule. The open forum meeting will allow staff to discuss the
scope of the project, construction staging, road closures, detours and schedule, as well as
to answer any questions relating to the project.
Since North Cascade Road will be closed during construction, allowing for local access
only to property owners within the work area, the public informational meeting will provide
mutual benefit to both staff, the contractor, residents and the general public. With the North
Cascade Road construction closure, the posted detour will be using English Mill Road.
PROJECT SCHEDULE
The project development schedule for the North Cascade Road Reconstruction Project,
Phase 1 from the bridge over Catfish Creek to Edval Lane is as follows:
lowa DOT Advertisement for Bids January 22, 2020
City Initiate Concurrence in Public Bidding Process February 4, 2020
City Publish Public Hearing Notice on Plans &Specifications February 7, 2020
City Public Hearing on Plans & Specifications February 17, 2020
lowa DOT Receipt of Bid Proposals (Bid-�etting) February 18, 2020
City Award Construction Contract (subject to iowa �oT Approvaq March 2, 2020
Public Informational Meeting March 2020
lowa DOT Late Start Date May 25, 2020
Contract Completion Date 100 Working Days
Completed Fall 2020
RECOMMENDATION
I recommend City Council concurrence with initiating the public bidding procedure through
the lowa DOT and set February 17�h, 2020, as the date for a public hearing on the North
Cascade Road Reconstruction Project.
BUDGETIMPACT
The estimate of probable cost for the North Cascade Road Reconstruction Project is as
follows:
Description Estimate
Construction Contract $ 1 ,820,000
Contingency 273,000
Right-of-Way Property Acquisition 129,000
Engineering Design 209,000
Contract Admin / Construction Engineering 157,000
Total Project Cost $ 2,588,000
The anticipated project funding is summarized as follows:
CIP Fundinq Source Amount
300 2021 DMATS SWAP Funding $ 2,077,000
350 2021 North Cascade Road Reconstruction 366,000
740 2525 North Cascade Water Main Extension 145,000
Total Project Funding $ 2,588,000
The North Cascade Road Reconstruction Project will be the City's first project to be
developed and constructed under the Federal Aid SWAP Policy which will use State
Primary Road funds to reimburse the City for 100°k of eligible roadway construction and
property acquisition costs which eliminates the requirement for a 20°k local match. All
other associated costs, such as engineering design, contract administration, construction
engineering and inspection will be funded solely with City funding.
ACTION TO BE TAKEN
The City Council is requested to concur with initiating the public bidding procedure through
the lowa DOT and set the date for a public hearing on the North Cascade Road
Reconstruction Project, Phase 1 from the bridge over Catfish Creek to Edval Lane through
adoption of the enclosed resolution.
cc: Jenny Larson, Director of Finance and Budget
Denise Ihrig, Brant Schueller, Kerry Leppert, Water Department
Nate Kieffer, P.E., Land Surveyor
Nathan Steffen, P.E., Civil Engineer
Kent Ellis, lowa DOT
F:\PROJECTS\North Cascade Rd Reconstruction(669)\Council&Staff Documents\Initiate
Prepared by Bob Schiesl, Asst. City Engineer, 50 W. 13th St., Dubuque, IA 52001, 563-589-4276
Return to Kevin Firnstahl, City Clerk, 50 W. 13th St., Dubuque, IA 52001, 563-589-4100
RESOLUTION NO. 40-20
NORTH CASCADE ROAD RECONSTRUCTION PROJECT PHASE 1 -
BRIDGE OVER CATFISH CREEK TO EDVAL LANE
IOWA DOT PROJECT NO. STBG-SWAP-2100 (669)--SG-31
PRELIMINARY APPROVAL OF PLANS, SPECIFICATIONS, FORM OF CONTRACT,
AND ESTIMATED COST; SETTING DATE OF PUBLIC HEARING ON PLANS,
SPECIFICATIONS, FORM OF CONTRACT, AND ESTIMATED COST
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
DUBUQUE, IOWA THAT:
Section 1. The proposed plans, specifications, form of contract and estimated cost for
the North Cascade Road Reconstruction Project, Phase 1 from the bridge over Catfish
Creek to Edval Lane, Iowa DOT Project No. STBG-SWAP-2100 (669)--SG-31, in the
estimated amount $2,588,000, are hereby preliminarily approved and ordered filed in the
office of the City Clerk for public inspection.
Section 2. A public hearing will be held on the 17th day of February 2020, at 6:00 p.m.
in the Historic Federal Building Council Chambers (second floor), 350 West 6th Street,
Dubuque, Iowa, at which time interested persons may appear and be heard for or against
the proposed plans and specifications, form of contract and estimated cost of said Project,
and the City Clerk be and is hereby directed to cause the attached notice of the time and
place of such hearing to be published in a newspaper having general circulation in the
City of Dubuque, Iowa, which notice shall be published not less than four days nor more
than twenty days prior to the date of such hearing. At the hearing, any interested person
may appear and file objections to the proposed plans, specifications, form of contract, or
estimated cost of the Project.
Passed, approved and adopted this 4th day of February 2020.
poy D. Buol, Mayor
Attest:
Kevi S. Firnstahl, CMC, City Clerk
NOTICE OF PUBLIC HEARING ON PLANS, SPECIFICATIONS, FORM OF
CONTRACT, AND ESTIMATED COST FOR THE NORTH CASCADE ROAD
RECONSTRUCTION PROJECT, PHASE 1 — BRIDGE OVER CATFISH CREEK TO
EDVAL LANE, IOWA DOT PROJECT NO. STBG-SWAP-2100 (669)--SG-31
NOTICE IS HEREBY GIVEN: The City Council of the City of Dubuque, lowa will
hold a public hearing on the proposed plans, specifications, form of contract and
estimated cost for the North Cascade Road Reconstruction Project, Phase 1 from the
bridge over Catfish Creekto Edval Lane, lowa DOT Project No. STBG-SWAP-2100 (669)-
-SG-31 , in accordance with the provisions of Chapter 26, Code of lowa, at 6:00 p.m., on
the 17�h day of February, 2020, in the Historic Federal Building Council Chambers (second
floor), 350 West 6�h Street, Dubuque, lowa. Said proposed plans, specifications, form of
contract and estimated cost are now on file in the office of the City Clerk. At said hearing
any interested person may appear and file objections thereto.
The scope of the Project is as follows:
. The project will provide for the reconstruction of North Cascade Road (grading,
paving, storm sewer, and water main), from the bridge over Catfish Creek to
Edval Lane.
Any visual or hearing-impaired persons needing special assistance or personswith
special accessibility needs should contact the City Clerk's office at (563) 589-4120 or
TDD at (563) 690-6678 at least 48 hours prior to the meeting.
Published by order of the City Council given on the 7�h day of February , 2020.
Kevin S. Firnstahl, CMC, City Clerk
Special Achievement in GIS � � rHearroF
� 2018AwardWinner North Cascade Road Reali nment Pro ect DUB " E
Masterpiece on the Mississiqpi
STBG-SWAP-2100 (669)--SG-31
� � ! q �¢ i yr � i a� S �.r r �,( �+� y � b�y �a� P",. ..`� � -.e.. � :r:
` � '" i/r hd'�: �'�.� i � ��� � ' k� ; , '"�'z, � ., � ��� ,�' � �� ` fy.�; ` r.; •�x;i � }�' :��, *'�<r�j..;.
�,^' 4 �: ,.r �k � � � � s �S r
� �E� �. �� y.� x"fi� � /; � ��� � }� f '�r dsr c ?e r: y "`�+it/�fi ,.
g f Ya xl � v i ��' � r :i� � � � t"
� � � , ��i /' s a „ij ;l r . � . ���r� a< i� � `A '��
/ � ✓ '; / � .
� � .�� � ".- p"` 7 w.sr � '� l; �, " '�a �<� A �a'' �. (�iy ,�`�, ��,
+ '� �,�i� � / 4 y / '� �, �r�' " � . V'f ' . .
�
� �!/ x " v � � f � ,/" i � l � ; � C
t °=� �" � _;t/� _ �f � i ,a
r� /�J� . ; , _ � �l,i ' r ,�k r,� r- ��� �,
�d � ��A, r "taGn J t '; � � ,•� qr �� . . .... Y , � �k` u(� r,��`� Yi�°�"'.'� /, �r-',� �:'� � .
' � � ✓r �I� l � t'� � i� . l ,, � � q.'. �..� �, ���
, .'` G� , �y a�
�� ' ���� �„a � � ���"� .
/
' '`` ��� x � `� � STE�E�F2,�'�.�O�HN � ���� �,N,� Eo�
� � � �,� � � � °��� �`� `�� STEGER, JOHN F �,
° � �:'� & TJARFES MEYCS�H. �, � �
.��, �,r.�,�_ .�;� �� , ';, �. & TJARKS, HEYO H. a �
'q <� ^ .
$ .
��SHELDON, CHERYL A �` ",���7���� :. �<�� � �- ��� ���� ��
�. �
-� � :k�� .�� ��r .��:,r � � ���
I � E� �Y�w Proposed Edge of Road �� �`
; �'� � � �� APEL, WILLIAM E z��� " � � �
,, �„ ;�� �, � �
"'';� ; TILL, CHARLES P ����s,�;�� � � � '
� & DARLA K �� �•� � �, � ; _ " � °� �
; ,.�
,�
r-, .n x T � ,
_ , , .
�
_ � � � �g , � �»
� �
� � ��,w,+� ��w� � � � rg�, � "��',�^ z ,�. 'y#. °�� ��/�
s'C.- � '� ,1 (Q yj ;�, ��'�� � �-s' �� �,��+�; �� ��'� ���'������ ,q�� ����' '��S
�
. _ \ � :-
ti _
.� �� � �e�' , �„ �i� ��,� � ' ,� �x +�� y �,�, �,� �"�"�,`�"��
✓ O tl � '�
.� ' •� �J � ;, � � '�����. Proposed ROW �. � .��,. -�� ��
� �-�' ARENSDORF, ��
, �VALENTINE GA l( �� � ��, °���� ��� �� ��. �P ,,� ��..
� �,
� � � � ' � �';�. �.. ?�: ;,,� , ,,,:>� �„ ";� ,�,. F � r '�'" ' ��, HOWARD W �;�
� � �� � '�� — � ..y��;:
� A� ;�` ; � ..���` �". NORTH CASCADE ROAD ��� � & SANDRA L. �����s.�
�, � � $ ,��r , � �� �'I DEVELOPERS LLC � �-�,1 �� , �`,�`��;.
. �. � � , , * R � �., O �,�� v
. w., � �� ��� � MAQUOKETA VALLEY � � ;
� !y � RURAL ELECTRIC COOP '� O ; ARENSDORF, JEFFREY � ;��,,�;•
."� ` '`
� �.��� ' � � �� � � � �� ��� � � &ARENSDORF, HOWARD & SANd�tA.L "��
,� ' '� �, ��
�
�,�� � .t:�.�� - �
���
, �
� L6 �� � � �,� '� � ,`�
�' OP � � �,�� ;'� ��� ° � � `: ���
.'�".'u .,,� , `�, r �,� ��r
� �r.�ii' ":✓ l E'�.;i � ,+5
5 . ......._. mPlled , .. , � . - . . ±. .
'ng the Dub q A G og ph' I formaton SVstem
�oAcis� wn n i a a e e a ev eom me cn oF ��'��'N� Map Prepared By: NMS
o�e�a�e a�d o�e�a�e co��N. ie�s��de�srood mae,wnue
me ciev oF o�e�q�e a�d pa�eidpaei�g age�d��ewzed me City of Dubuque
mo��,��e�ca�d a���ce��fo�mac�o�a�auabie,oA��s a�d 1 ineh = 300 feet nn T Engineering Division
ie�s�,vvue�s do�oe wa��a�e me a����a�v o�����e��v of ine 1"1\�l EC 1
mr��maeio�o�dar��o�eai�ed ne�em rne ciev a�d Pa�ei�iPaei�g 50 West 13th St�eet
age��i�snau�oe ee neia uaeie Fo�a�v ai�e�e,i�ai�e�e,i��iae�eai, Dubuque,lowa 52001
���a�e�eiai,v��ieroe,o�svedai damae�,wneme�ro��eaeie o�
�����eeaeie,a��s��g o�e oF me a�eno��zea o���a�mo��zea��oF 300 150 0 300 Feet P R E # Phone:(563)589-4270
mis daea o�me i�aewev eo��mis daea o�o�e oF a�v e�ea�n oF
wa��a�ry wna�oe�� Fax.(563)589-4205
F:\PROJECTS\North Cascade Rd Reconstruction(669)\Property Acquisition\North Cascade Road Realignment 02292012.mxd
TDu$ E North Cascade Road Realignment Project
MnsterpieceontheMississippi 51-+P-11 —21���669�— -7�-31
� ,���I f r,. � �, � �� _ r , �, ,� � � � �' . , . . -.� �- ;. _ .
�"�<.T� ¢.°����h �� �v s � � �t� � ; r el�' ���/ . �r q��< 7., �... .
M� 4 7 . t -3, F : �:F �, . . s� � .
� .�� �',: � J,.�, r y� :1 � �,� , ,a, .
vd� r r ,F., ✓ �, ��.� � ��" . _ �
1 /
� . . ; �', p a Y`Y �r s� ' ;�n .
. . � ; / � :� p � �:
�� � �� r ��� n, ,�
� � f � �'���` ' �� � ; �,., � , " ' �
, ,� . .� � �
�� � x� ���� �� � � ,¢ � �
�
,+� , � . % _ � �"` / l,y �y� � . -.. . a
y ��
� � -� � r- `` y
�� , � �; '� ��` 'a� '�*zs EDR� r � �
,-
,
. . ,.. _ . .��'`'+� �,:- '� . ^�.y-a.� �''�' .. � .
.
P e -
4 rt �«�. , .� .
� �, ,
�
s. , , � �: r .. _�.. � . t� � . . '�
�� � : `" �'.:, i �'_ �: �a�fM� .
f .�. '��" � - ' .,,.��` �
�g � I
� �� ;� � Proposed Edge of Road , e� � �
� '� � � c <,. , � � ; :- �"�� ��
� �" � ` �"��° �'
, � �£ �� Proposed Water�
� � � �' �.�►' �
� �� _�M^"'��„ . � - Main Extension
.. ■■..■■� � � �' '°` �` �
��.�■.�. �..r...:�
.
. � �� DE RD :� � �
,� � - T . �,I'� �
„ -n.. _.
��
� � s , �
.
, ,
,.....� ��� ���i.�/�" �rt �a �"` '�F,Q
�� �� ��� � �� �� ., S
� � � �• �
. :
.. . � � � � � <
. � � �� � �' �
, ,
'@� �• �. �,�:� � �� � � �, � 4�� �
�- ��, � ..�<�. �,
« ��� � ���,a��� � �"��. �� � -'` �p� � � ��„� � �
� � Pr sed ROW � � �
�< r � �
<;;a � 1 �:�'�n �' �` '�� �J,�� ��'��� �„ ✓`r.
� �+� .' �� �; �' '����-,:� �
% � �
♦ �„'.��� �-�'`�iF �rrt°'�,.�f..
f. Y/ „., { - `s�',.
� �s $i i
,�LL •�' �� Q �o
y �
_� ��... ��,��� g� ��
; � < .:,; a � �,
.
�
�, ♦ ,� � � 0 �� �:
,��:
•
� ��
O � `
: 'L9 � - �
. =� � � �.
�
� ���� � ,..� �� . � �� `` ,..;; �
N Map Prepared By: NMS
City of Dubuque
1 inch = 300 feet Engineering Division
W E 50 West 13th Street
Dubuque,lowa 52001
300 150 0 300 Feet c Phone:(563)589-4270
�7 Fax.(563)589-4205
F:\PROJECTS\North Cascade Rd Reconstruction(669)\Civil 3D\Project Exhibit\Project Exhibit.mxd