Accepting the 2020 Asphalt Overlay Ramp Project Three Section A an B Copyrighted
October 5, 2020
City of Dubuque Consent Items # 11.
City Council Meeting
ITEM TITLE: Accepting the 2020 Asphalt Overlay Ramp Project Three Section A and
B
SUM MARY: City Manager recommending acceptance of the construction contract for
the 2020 Asphalt Overlay Access Ramp Project Three Section A& B as
completed by S&S Builders.
RESOLUTION Accepting the 2020 Asphalt OverlayAccess Ramp
Project Three Section A& B and authorizing the final payment to the
contractor.
SUGGESTED Suggested Disposition: Receive and File;Adopt Resolution(s)
DISPOSITION:
ATTACHMENTS:
Description Type
2020 Asphalt Overlay Ramp Project Three-MVM Memo City Manager Memo
Staff Memo Staff Memo
Resolution Resolutions
Dubuque
THE CITY OF �
ui-Aseria cih
DuB E , . � . ,
� II �
Maste iece on tj2e Mississi i zoo�•zoiz•zois
YP pp zoi�*zoi9
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: 2020 Asphalt Overlay Access Ramp Project Three Section A & B
(CIP 3001227)
DATE: September 30, 2020
City Engineer Gus Psihoyos is recommending acceptance of the construction contract
for the 2020 Asphalt Overlay Access Ramp Project Three Section A & B, as completed
by S&S Builders, in the final contract amount of $73,548.33, which is a 3.62% increase
from the original contract amount of$70,980.53 due to additional curb and sidewalk
work.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
�
Mic ael C. Van Milligen
MCVM:jh
Attachment
cc: Crenna Brumwell, City Attorney
Cori Burbach, Assistant City Manager
Gus Psihoyos, City Engineer
Dubuque
THE CITY OF �
All•America Cit�
D B E �n���v���K�,����
U ' I 1�►
� �
Maste iece on the Mississi i 2oo�•zoiz�zoi3
�P pp zoi��zoi9
TO: Michael C. Van Milligen, City Manager
FROM: Gus Psihoyos, City Engineer
SUBJECT: 2020 Asphalt Overlay Access Ramp Project Three Section A & B
(CIP 3001227)
DATE: September 28, 2020
INTRODUCTION
The enclosed resolution provides for the acceptance of the construction contract for the
2020 Asphalt Overlay Access Ramp Project Three Section A & B.
BACKGROUND
The project replaced twenty-one non-compliant access ramps with twenty-six compliant,
directional ramps as per Public Right of Way Accessibilities Guidelines (PROWAG)
specifications in conjunction with the Public Works Asphalt Overlay Program in the area
of Amy Court, Marjorie Circle, Alicia Street, Donovan Drive, Cora Drive, Andrea Street.
DISCUSSION
The 2020 Asphalt Overlay Access Ramp Project Three Section A & B was completed
by S&S Builders of Dubuque, IA in the final contract amount of$73,548.33. This is a
3.62% increase of the original contract amount of$70,980.53. The increase was due to
additional curb and sidewalk work.
BUDGETIMPACT
The summary of project costs for the 2020 Asphalt Overlay Access Ramp Project Three
Section A & B is as follows:
Description Award Final
Construction Contract $70,980.53 $ 73,548.33
Contingency $7,098.05 0.00
Construction Administration & Inspection $11,711.79 $7,354.83
Total Construction Cost $89,790.37 $80,903.16
The project funding is summarized below:
CIP No. Fund Description Fund
Amount
3001227 Curb Ramp Program $ 80,903.16
Total Project Funding $ 80,903.16
REQUESTED ACTION
The City Council is requested to adopt the attached resolution accepting the
improvements and authorize the final payment of the contract amount of$73,548,33 to
S&S Builders for the 2020 Asphalt Overlay Access Ramp Project Three Section A & B.
Prepared by: Luke Steger, Engineering Technician
cc: John Klostermann, Public Works Director
Arielle Swift, Assistant Public Works Director
Jenny Larson, Budget Director
Jon Dienst, Civil Engineer II
Paul Davis, Public Works Supervisor
2
Prepared by Gus Psihoyos, City Engineer, 50 W. 13th St., Dubuque, IA 52001, 563-589-4276
Return to Kevin Firnstahl, City Clerk, 50 W. 13th St., Dubuque, IA 52001, 563-589-4100
RESOLUTION NO. 311-20
ACCEPTING THE 2020 ASPHALT OVERLAY ACCESS RAMP PROJECT THREE
SECTION A & B AND AUTHORIZING THE FINAL PAYMENT TO THE
CONTRACTOR
WHEREAS, the public improvement contract for the 2020 Asphalt Overlay
Access Ramp Project Three Section A & B, (the Project) has been completed by the
Contractor, S & S Builders (Contractor), and the City Engineer has examined the work
and signed a certificate stating that the Project has been completed according to the
terms of the Public Improvement Contract and that the City Engineer recommends that
the Project be accepted; and
WHEREAS, the final contract amount for the Project is $73,548.33; and
WHEREAS, the Contractor has previously been paid $69,870.91, leaving a
balance of $3,677.42; and
WHEREAS, the City Council finds that the recommendation of the City Engineer
should be accepted.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
DUBUQUE, IOWA THAT:
Section 1. The recommendation of the City Engineer is approved, and the Project
is hereby accepted.
Section 2. The Finance Director is hereby directed to pay to the Contractor from
the Curb Ramp Program CIP appropriations for the contract amount of $73,548.33 less
any retained percentage provided for therein as provided in Iowa Code.
Section 3. The Finance Director is hereby directed to pay to the Contractor the
balance of the retainage of $3,677.42 as provided in Iowa Code chapter 573, and to pay
such retainage in accordance with the provisions of Iowa Code chapter 573 or Iowa
Code chapter 26.13.
Passed, approved and adopted this 5th day of October 2020.
Roy D.ol, Mayor
Attest:
Key' Firnstah', CM T City Clerk
CITY ENGINEER'S CERTIFICATE OF FINAL COMPLETION OF 2020 ASPHALT
OVERLAY ACCESS RAMP PROJECT THREE SECTION A& B
The undersigned City Engineer of the City of Dubuque, Iowa, hereby certifies that
he has inspected the 2020 Asphalt Overlay Access Ramp Project Three Section A & B,
and that said Project has been performed in compliance with the terms of the Public
Improvement Contract, and that the total cost of the completed work is $80,903.16.
Dated this 29th day of September 2020.
Gus Psihoyos, City Engineer