Asbury Road_IA32 Traffic Signal & Grading Project AwardMasterpiece on the Mississippi
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: Asbury Road and IA 32 Traffic Signal & Grading Project
(Iowa DOT Project No. TSF -32- 1(28)-- 92 -31)
(CIP 3002029, 2501814 and 2501815)
DATE: May 12, 2010
Sealed bids were received for the Asbury Road and IA 32 Traffic Signal & Grading
Project. City Engineer Gus Psihoyos recommends award of the contract to the low
bidder, McDermott Excavating, in the amount of $316,462.55, which is 33.08% under
the engineer's estimate.
concur with the recommendation and respectfully request Mayor and City Council
approval.
MCVM:jh
Attachment
cc: Barry Lindahl, City Attorney
Cindy Steinhauser, Assistant City Manager
Gus Psihoyos, City Engineer
Michael C. Van Milligen
Dubuque
keetil
All- AmerIcaCity
2007
t
Masterpiece on the Mississippi
TO: Michael C. Van Milligen, City Manager
FROM: Gus Psihoyos, City Engineer / J .�
DATE: May 11, 2010
SUBJECT: Asbury Road and IA 32 Traffic Signal & Grading Project
(Iowa DOT Project No. TSF -32- 1(28)-- 92 -31)
(CIP 3002029, 2501814, and 2501815)
INTRODUCTION
Dubuque
hteftil
Al4mm tcaltr
'�11 c'
2007
The enclosed resolutions authorize the award of the Asbury Road and IA 32 Traffic
Signal & Grading Project - Iowa DOT Project No. TSF -32- 1(28)-- 92 -31.
DISCUSSION
The Asbury Road and IA 32 Traffic Signal & Grading Project will provide for the
following: grading of the southbound right -turn lane to accommodate shifting of through
lanes for southbound and northbound dual left -turn lanes at Asbury Road and IA 32
(Asbury Road); milling HMA pavement; traffic signal modifications; HMA paving;
temporary pavement marking; and drainage improvements.
BID RESULTS
The City of Dubuque received the following bids for the Asbury Road and IA 32 Traffic
Signal & Grading Project - Iowa DOT Project No. TSF -32- 1(28)-- 92 -31. On May 11,
2010:
Contractor Name
McDermott Excavating
TopGrade Excavating
Tschiggfrie Excavating
Total Bid
$316,462.55
$329,613.65
$344,148.55
1
RECOMMENDATION
I recommend that the contract for the Asbury Road and IA 32 Traffic Signal & Grading
Project - Iowa DOT Project No. TSF -32- 1(28)- -92 -31 be awarded to McDermott
Excavating of Dubuque, Iowa, in the amount of $316,462.55, which is 33.08% under the
engineers estimate. This project has a start date of June 1, 2010 with a contract
completion date of August 16, 2010.
BUDGET IMPACT
The summary of project costs is as follows:
Estimate Award
Construction Contract $ 472,907 $316,462.55
Contingency 47,290 47,290.00
Engineering /Contract Administration 70,500 70,500.00
Equipment Pre - Purchase 63,777 63,777.00
Project Cost Phase I $654,474 $498,029.55
The project funding summary is as follows:
CIP Funding Source Amount
3002029 Iowa DOT Traffic Safety Grant $343,555.55
3002029 Iowa DOT U -STEP Grant 48,388.00
2501814 NW Arterial Capacity Improvements 39,590.00
2501815 Traffic Consultant Services 66,496.00
Total Project Funding $498,029.55
ACTION TO BE TAKEN
I recommend that the City Council adopt the attached resolution awarding the Asbury
Road and IA 32 Traffic Signal & Grading Project - Iowa DOT Project No. TSF-32- 1(28) --
92-31 to McDermott Excavating in the amount of $316,462.55
Prepared by David Ness, Civil Engineer II
cc: Julie Neebel, IIW Engineers & Surveyors, PC
Kent Ellis, Local Systems Engineer District 6 - IDOT
Jenny Larson, Budget Director
Bob Schiesl, Assistant City Engineer
RESOLUTION NO. 155 -10
AWARDING PUBLIC IMPROVEMENT CONTRACT FOR THE ASBURY ROAD
AND IA 32 TRAFFIC SIGNAL & GRADING PROJECT — IOWA DOT PROJECT
NO. TSF -32 -1(28) - -92 -31
Whereas, sealed proposals have been submitted by contractors for the Asbury
Road and IA 32 Traffic Signal & Grading Project - Iowa DOT Project No. TSF-32- 1(28) --
92-31 (the Project) pursuant to Resolution No. and Notice to Bidders published in
a newspaper published in the City of Dubuque, Iowa on the 23 day of April, 2010.
Whereas, said sealed proposals were opened and read by the City of Dubuque
on the 11 day of May, 2010 and it has been determined that McDermott Excavating of
Dubuque, Iowa, with a bid in the amount of $316,462.55, is the lowest responsive,
responsible bidder for the Project.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF DUBUQUE, IOWA:
That a Public Improvement Contract for the Project is hereby awarded to
McDermott Excavating, subject to the concurrence by Iowa Department of
Transportation (Iowa DOT), and the City Manager is hereby directed to execute a Public
Improvement Contract on behalf of the City of Dubuque for the Project.
Passed, approved and adopted this 17th day of May
anne F. Schneider, CMC, City Clerk
, 2008.
Roy D. Buol, Mayor
May 11, 2010
Dave Ness, P.E.
City of Dubuque
50 West 13 Street
Dubuque, IA 52001
Re: City of Dubuque
Asbury Road and IA 32 Traffic Signal and Grading Project
Award Recommendation
IDOT Project No.: TSF -32- 1 (28)- -92-31
IIW Project No.: 09192 -03
Dear Dave:
In accordance with owner instructions, bids for the Asbury Road and IA 32 Traffic Signal and
Grading project were opened and read at 2 :00 p.m. on May 11, 2010. Three (3) bids were
received for this project. A tabulation of the bids is enclosed.
After reviewing the bids, it was determined the low bid was submitted by McDermott
Excavating of Dubuque, Iowa, in the amount of $316,462.55.
McDermott Excavating has the experience, workforce and equipment to properly complete this
contract. We recommend award of Asbury Road and 1A 32 Traffic Signal and Grading project
to McDermott Excavating in the amount of $316,462.55 pending approval by the DOT, who
needs to review and approve the award in accordance with the Traffic and Safety funding
agreement.
The engineer's estimate for this project was $472,907.00. The low bid of $316,462.55 is
$156,444.45 or 33% below the engineer's estimate.
Sincerely,
IIW ENGINEERS & SURVEYORS, P.C.
JLKie Neebel, P.E.
Project Engineer
Enc.
Copy:
McDermott Excavating
Kent Ellis, IDOT
I I W E n g i n e e r s & Surveyors, P . C .
Dubuque, IA I laze! Green. WI
INTEGRITY EXPERTISE. SOLUTIONS.
Dennis F Waugh, PE: SE"
Charles A Cate, PE
Gary D. Sejkora, PE
Michael A. Jansen. PE
Ronald A. Balmer, PE /SE
John M. Tranmer, PLS
1 unothy 3 Tranel, PE*
John F. Wandsnider, PE
Julie P Neebel, PE
James P Kaune. PE
Thomas J Oster, PLS
Wray A. Childers, PLS
<ieoffry L. Blandm, I'E
Mark t' Jobgen. PE
Lauren N Ray, PE /SE"
Bradley J. Moot?, PE SE
Cody 1. Austin. PE"
Marc D. Ruden. PF
Mark R Fassbinder, Al 5"
Michael A. Ruden, AIA"
Alice M Ohrtinann, PE
L.E.ELYk AP
Civil Engineering
Structural Engineering
Environmental Engineering
Municipal Engineering
Transportation Engineering
Architectural Engineering
Land Surveying
Construction Services
4155 Pennsylvania Avenue
Dubuque. Iowa 52002 -2628
(563) 556-2464
(S63)556-7811 fax
www. iiwengr.com
CITY OF DUBUQUE - ASBURY ROAD AND IA 32 TRAFFIC SIGNAL AND GRADING PROJECT
IDOT Project No.: TSF -32 -1(28)- -92 -31 IIW Project No.: 09192 -03
BID TAB
McDermott
NO. ITEM CODE DESCRIPTION QUANTITY UNIT PRICE TOTAL PRICE UNIT PRICE TOTAL PRICE UNIT PRICE TOTAL PRICE
1 2102- 2710070 EXCAVATION. CLASS 10. ROADWAY AND BORROW CY 1000 511.05 511.050.00 51400 514,00000 513.95 513,95000
2 2105-8425005 TOPSOIL FURNISH & SPREAD CY 259 520 85 55,400.15 520.00 55,180.00 521.30 55,516 70
3 2115 - 0100000 MODIFIED SUBBASE CY 710 527.70 519,667.00 52400 517,04000 522.45 515,939.50
4 2123- 7450000 SHOULDER CONSTRUCTION, EARTH STA 11 5475.00 55,225 00 $450.00 54,950.00 5212.00 52,332.00
5 2214 - 5145150 PAVEMENT SCARIFICATION SY 6855 52.75 518,851.25 $3.25 522,278.75 $2.91 519,948.05
6 2303 - 0001000 HOT MIX ASPHALT MIXTURE, WEDGE. LEVELING OR STRENGTHENING COURSE TON 11 5160.00 51,760.00 514500 51,595 00 5145.00 $1,595 00
7 2303. 0042500 HOT MIX ASPHALT MIXTURE (3.000,000 ESAL. INTERMEDIATE COURSE. 112114 MIX TON 1100 543.00 547,300.00 539.09 542,99900 539.10 543,010 00
8 2303-0246428 ASPHALT BINDER, PG 64-28 TON 65 $635 00 541,275.00 5575.00 $37,375 00 5575 00 537,375.00
9 2435-0250110 INTAKE, SW -501 MODIFIED EA 2 52,200.00 $4,400.00 51,600.00 53,20000 51,903.00 53,80600
10 2435-0251100 INTAKE SW -511 EA 3 52,220.00 56,660.00 51,400.00 54,200.00 51,93900 55,817.00
11 2502 -8212024 SUBDRAIN LONGITUDINAL (BACKSLOPE) 4' D1A LF 400 510.85 54 340.00 513.00 55,200.00 5860 53,440.00
12 2502 - 8220193 SUBDRAIN OUTLET (RF -19C) EA 1 575.00 575.00 580.00 580.00 5156.00 5156.00
13 2502 - 8220197 SUBDRAIN OUTLET (RF -19F) EA 4 5120.00 5480.00 $80 00 5320 00 5245 00 5980.00
14 2503-0114215 STORM SEWER GRAVITY MAIN, TRENCHED. RCP 2000D.15' LF • 160 547.50 57,600,00 552.00 58,320.00 550.00 58,00000
15 2503 - 0200036 REMOVE STORM SEWER PIPE LESS THAN OR EQUAL TO 36 IN. LF 20 520.00 5400.00 510.00 5200.00 510 75 5215.00
16 2510 - 6745850 REMOVAL OF PAVEMENT SY 926 520.50 51,898.30 51200 51.111.20 51000 592600
17 2510-6750600 REMOVAL OF INTAKE AND UTILITY ACCESS EA 9 5250.00 52,250.00 $400 00 53,600.00 5936.30 58,426.70
18 2511- 6745900 REMOVAL OF SIDEWALK SY 72 8 56.50 $473.20 59.00 5655.20 58.00 5582.40
19 2524 - 6765010 REMOVE AND REINSTALL SIGN AS PER PLAN EA 7 5100.00 5700 00 $85 00 5595.00 585.00 5595.00
20 2524-9275100 WOOD POSTS FOR TYPE A OR B SIGNS. 4 I X 4 IN IF 78 $10.35 $807 30 S9 00 5702.00 59.00 5702.00
21 2525. 0000100 TRAFFIC SIGNALIZATION LS 1 $66,536.00 566,536.00 $67,500.00 567,500.00 579,449.00 579,449.00
22 2525 - 0000120 REMOVAL OF TRAFFIC SIGNALIZATION LS 1 $6,672.00 $6,672 00 $6,700 00 56,700.00 516,179.90 516,179.90
23 2526 - 8285000 CONSTRUCTION SURVEY LS 1 57,935.00 57,93500 57,500.00 57,500.00 56,900.00 $6,900.00
24 2527 - 9263109 PAINTED PAVEMENT MARKING, WATERBORNE OR SOLVENT -BASED STA 15 590.00 51,350.00 576.00 $1 140.00 576.00 51,140.00
25 2527 - 9263130 REMOVABLE TAPE MARKINGS STA 1.5 5175.00 5262 50 5150.00 5225.00 5150.00 5225.00
26 2527 - 9263137 PAINTED PAVEMENT SYMBOLS & LEGENDS. WATERBORNE OR SOLVENT -BASED EA 4 5105.00 5420.00 590.00 5360.00 590.00 $360 00
27 2527 - 9263180 PAVEMENT MARKINGS REMOVED STA 375 5115.00 5431.25 5100.00 5375.00 5100.00 5375.00
28 2528-8445110 TRAFFIC CONTROL LS 1 522,76000 522.760.00 519,790.00 519,790.00 519,790.00 519,790.00
29 2533-4980005 MOBILIZATION LS 1 512,700.00 512, 700.00 540, 000.00 540,000.00 534,192.00 534,192.00
30 2599- 9999005 CONNECT TO EXISTING HANDHOLE EA 2 554700 51.09400 5320.00 $640 00 5165.95 533190
31 2599- 9999005 REMOVABLE TAPE PAVEMENT SYMBOLS AND LEGENDS EA 4 5145 00 5580.00 5125 00 5500.00 5125.00 5500.00
32 2599-9999009 CONDUIT. RIGID PVC, TRENCHED. 7 LF 19 543.50 $82650 530.00 5570.00 534.90 5663.10
33 2599 - 9999009 REMOVE MEDIAN FENCING LF 554 5290 51,606.60 52.25 51,246.50 51.50 583100
34 2599 - 9999009 REINSTALL MEDIAN FENCING LF 554 55.75 53,18550 55.25 52,908.50 56.00 53,324.00
35 2599- 9999020 SUBGRADE STABILIZATION TON 100 518.95 51,895.00 518.00 51,800.00 520.40 52,040.00
36 2601- 2634100 MULCH ACRE 032 $4,025.00 51,288.00 53,000.00 5960.00 51.12000 5358.40
37 2601-2636043 SEED & FERTILIZE (RURAL) ACRE 0 32 54,025.00 51,288.00 53,000.00 5960.00 51,120.00 5358.40
38 2602 -0000020 SILT FENCE LF 1660 52.00 53,320.00 51.25 52.075.00 51.85 53,071.00
39 2602 -0000030 SILT FENCE FOR DITCH CHECK LF 50 55.00 5250 00 51.25 $62.50 51.95 $9750
40 2602- 0000090 CLEAN OUT OF SILT FENCE LF 600 52.00 51,200.00 51.00 5600.00 51.00 $600.00
41 2602.0000100 CLEAN OUT OF SILT FENCE FOR DITCH CHECK LF 50 55.00 5250.00 52.00 5100 00 5100 550.00
TOTAL OF BID
I 5316,462,55 1
Top Grade Tschiggfie
I $329,613.651