Prescott Street Retaining Wall Project AwardMasterpiece on the Mississippi
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: Prescott Street Retaining Wall - CIP 3501029, 2501029
DATE: May 28, 2010
Dubuque
kiltil
AI-America City
2007
Through the competitive quotation process for public improvements, the Prescott Street
Retaining Wall Project was awarded on May 13, 2010, to Tschiggfrie Excavating, Inc., in
the amount of $58,481.58.
City Engineer Gus Psihoyos recommends that the award for the Prescott Street
Retaining Wall Project be officially recorded in the minutes of the City Council.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
MCVM:jh
Attachment
cc: Barry Lindahl, City Attorney
Cindy Steinhauser, Assistant City Manager
Gus Psihoyos, City Engineer
Michael C. Van Milligen
Masterpiece on the Mississippi
TO: Michael C. Van Milligen, City Mana
FROM: Gus Psihoyos, City Engineer
SUBJECT: Prescott Street Retaining Wall — CIP 3501029, 2501029
DATE: May 24, 2010
This project involves the reconstruction of 80 feet of the Prescott Street Retaining Wall.
A 40 foot portion of the wall failed in April 2010. Engineering is replacing 80 feet of 6'
high limestone wall and resetting capstones on an additional 40 feet of retaining wall.
The following is a summary of the bids received:
Tschiggfrie Excavating, Inc.
Top Grade Excavating, Inc.
Drew Cook & Sons Excavating, Inc.
cc: Barry Lindahl, City Attorney
Jenny Larson, Budget Director
Bob Schiesl, Assistant City Engineer
Jon Dienst, PE
$100.35/SF
$116.67/SF
$205.83/SF
Dubuque
hittril
Al-America City
11111 !
2007
Based on Iowa Code § 384.103 and § 364.12(3)(c), and through the competitive quotation
process for public improvements, this project was awarded on May 13, 2010 to
Tschiggfrie Excavating, Inc. of Dubuque, IA, in the amount of $58,481.58.
In accordance with the competitive quotation requirements of Iowa Code, Section 26.14,
it is necessary that the award for the Prescott Street Retaining Wall Reconstruction
Project be officially recorded in the minutes of the City Council.