Roof Repair Opera & M CenterCITY OF DUBUQUE, IOWA MEMORANDUM June 23, 2003 TO: FROM: SUBJECT: Michael C. Van Milligen, City Manager Don Vogt, Operations & Maintenance Department Manager Operations & Maintenance Center Roof Repair Project INTRODUCTION The attached resolutions provide for the acceptance of the construction contract for the Operations & Maintenance Center Roof Repair Project. The contract provided for the removal and replacement of selected metal roof panels, associated flashing and sealants. DISCUSSION This project was awarded to Pdsm Corporation of Kieler, Wisconsin on Apdl 15th, 2002. Due to the inability of Prism Corporation to fully complete the project, Employers Mutual Casualty Insurance Company retained Prostruct Construction, inc. of Ankeny, Iowa to complete the project. Work has been . .. completed by_ Prostruct which included three change orders for the final contract amount of $25,165.53. I recommend that the City Council accept the improvement and the final contract price be established at $25,165.53. BUDGET IMPACT A summary of the project is as follows: Estimate Bid Final Construction Contract $23,175.00 $18,027.00 $18,027.00 Contingency $ 3,477.00 $ 3,477.00 $ 7,138.53 Engineering $ 5,800.00 $ 5,800.00 $ 5,800.00 TOTAL $32,452.00 $27,304.00 $30,965.53 This project was funded with monies budgeted ($65,000) specifically for this project in our department's FY2002 capital improvement budget. ACTION TO BE TAKEN The City Council is requested to adopt the attached resolutions accepting the improvement and establishing the final construction cost. RESOLUTION NO. -~3 ACCEPTING IMPROVEMENT Whereas, the contract for the Operations and Maintenance Center's Garage Roof Repair Project has been completed and the City Manager has examined the work and filed his certificate stating that the same has been completed according to the terms of the contract, plans and specifications and recommends it acceptance. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: Section 1. That the recommendation of the City Manager be approved and that said improvement be and the same is hereby accepted. BE IT FURTHER RESOLVED that the Finance Director be and he is hereby directed to pay to the contractor from the General Fund equal to the amount of this contract, less any retained percentage provided for therein. Passed, approved and adopted this day of ,2003. Terrance M. Duggan, Mayor Attest: Jeanne F. Schneider, City Clerk RESOLUTION NO. __-03 FINAL ESTIMATE Whereas, the contract for the Operations and Maintenance Center's Garage Roof Repair Project has been completed and the Operations and Maintenance Department Manager has submitted his final estimate showing the cost thereof including the cost of estimates, notices and inspection and all miscellaneous costs; NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: Section 1. That the cost of said improvement is hereby determined to be $25,165.53 and the said amount shall be paid from the General Fund of the City of Dubuque, Iowa. Passed, approved and adopted this __ day of ,2003. Te~anceM. Duggan, Mayor Attest: Jeanne F. Schneider, City Clerk CITY OFDUBUQUE Date: June 23, 2003 FINAL ESTIMATE FOR: Operations and Maintenance Center's Roof Repair Project. Furnish all labor and materials for the Operations and Maintenance Center's Roof Repair Project. Total Due Contractor Engineering Total Construction Cost $25,165.53 $ 5,800.00 $30,965.53 I hereby certify that the above statement shows in detail the correct amount of all work required to complete the above improvement. Approved: Manager Michael C. Van Milligen Cify Manager Dona~ Operations & Maintenance The undersigned, , contractor for the above improvement, does hereby accept the above "Total Due Contractor", as full settlement for all claims for said improvements. Contractor: Prostruct Construction Inc. By: