ITEM TITLE: Southwest Arterial Project: North Cascade Road, English Mill Road,
Military Road Bridges - Bridge Railing and Decorative Concrete Post
Coloring Project Iowa DOT Project No. STP-U-2100 (693)--70-31
SUMMARY: City Manager recommending acceptance of the construction contract for
the Southwest Arterial - North Cascade Road, English Mill Road, and
Military Road - Local Bridge Railing and Decorative Concrete Post
Coloring Project, as completed by Taylor Construction, Inc. in the final
contract amount of $530,170, which is a 0.7% decrease from the original
contract amount of $533.905.00.
RESOLUTION Accepting Southwest Arterial North Cascade Road,
English Mill Road, and Military Road Local Bridge Railing and Decorative
Concrete Post Coloring Project, Iowa DOT Project No. Stp-U-21 00
(693)--70-31 and authorizing the payment to the contractor
SUGGESTED Suggested Disposition: Receive and File; Adopt Resolution(s)
DISPOSITION:
ATTACHMENTS:
Description Type
Acceptance of Southwest Arterial Project-MVM Memo City Manager Memo
Staff Memo Staff Memo
Resolution Resolutions
I DOT Statement of Completion Final Acceptance Supporting Documentation
Final Payment Supporting Documentation
THE CITY OF
DUUB-.-*.-TE
Masterpiece on the Mississippi
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: Southwest Arterial Project
North Cascade Road, English Mill Road, Military Road Bridges
Bridge Railing and Decorative Concrete Post Coloring Project
Iowa DOT Project No. STP-U-2100 (693)--70-31
DATE: June 16, 2021
Dubuque
*Awrin CHY
2007-2012-2013
2017*2019
Assistant City Engineer Bob Schiesl is recommending acceptance of the construction
contract for the Southwest Arterial - North Cascade Road, English Mill Road, and
Military Road - Local Bridge Railing and Decorative Concrete Post Coloring Project, as
completed by Taylor Construction, Inc. in the final contract amount of $530,170, which
is a 0.7% decrease from the original contract amount of $533.905.00.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
Micl�ael C. Van Milligen'
MCVM:jh
Attachment
cc: Crenna Brurnwell, City Attorney
Cori Burbach, Assistant City Manager
Gus Psihoyos, City Engineer
Robert Schiesl, Assistant City Engineer
THE CITY OF
DUtB
Masterpiece on the Mississippi
TO: Michael C. Van Milligen, City Manager
Gus Psihoyos, City Engineer
FROM: Robert Schiesl, Assistant City Engineer
SUBJECT: Southwest Arterial Project
North Cascade Road, English Mill Road, Military Road Bridges
Bridge Railing and Decorative Concrete Post Coloring Project
Iowa DOT Project No. STP-U-2100 (693)--70-31
DATE: June 15, 2021
INTRODUCTION
Dubuque
All-AmericaCiq
2007-2012-2013
2017*2019
The enclosed resolution provides for the acceptance of the construction contract for the
Southwest Arterial - North Cascade Road, English Mill Road, and Military Road - Local
Bridge Railing and Decorative Concrete Post Coloring Project, Iowa DOT Project No.
STP-U-2100 (693)--70-31.
BACKGROUND
Through the collaborative partnership between the Iowa DOT staff and the City, the
Southwest Arterial Memorandum of Understanding (MOU), was signed on August 9,
2013, and the Transfer of Roadway Jurisdiction (TOJ), was signed on November 7,
2016.
Following the execution of the MOU and TOJ, the City continued as the lead agency for
the multiple project development phases for completing the Southwest Arterial and was
responsible for completing the following improvement projects:
Project Description
Status
Final Engineering Design
Completed
Right -of -Way Property Acquisition
Completed
BHE Gas Pipeline Utility Relocation
Completed
BP Gas Pipeline Utility Relocation
Completed
ITC Transmission Line Relocation
Competed
North Cascade Road Reconstruction
Completed
English Mill Road Reconstruction
Completed
Military Road Reconstruction
Completed
Bridge Railing / Decorative Concrete
Completed
Due to the significant visual impact that the Southwest Arterial / US 20 Interchange and
the Southwest Arterial / US 151-61 Interchange have to motorist as they enter the City,
the interchange bridges have a "Gateway" appearance. The "Gateway" appearance was
achieved by integrating unique and context sensitive architectural components to the
bridge structures and associated features. A partial list of the bridge enhancement
elements are as follows:
• Decorative formliner concrete to replicate cut limestone that complement the
historical use of native limestone found so prominently in the Dubuque area.
• Bridge piers with a scale and material appearance reminiscent of historical
Dubuque based structures and icons.
• Steel -arch truss bridge members over the main bridge span in keeping with
Dubuque's visual bridge identity.
• High efficiency and high impact enhancement lighting to allow the bridge
structure to illuminate at night to create a signature visual presence.
The architectural bridge enhancements developed were presented at several public
informational meetings and were well received by the public with strong support to
maintain some visual scale and material continuity along the Southwest Arterial corridor
bridges. This was achieved by incorporate many of the same design components and
enhancement treatments into the North Cascade Road, English Mill Road, and Military
Road bridges.
DISCUSSION
The Southwest Arterial - North Cascade Road, English Mill Road, and Military Road -
Local Bridge Railing and Decorative Concrete Post Coloring Project was completed by
Taylor Construction, Inc. of New Vienna, Iowa in the final contract amount of
$530,170.00. This is a 0.7% decrease from the original contract amount of $533,905.00.
RECOMMENDATION
I recommend that the City Council accept the improvements and authorize the payment
of the contract amount of $530,170.00 to Taylor Construction, Inc. for the Southwest
Arterial - North Cascade Road, English Mill Road, and Military Road - Local Bridge
Railing and Decorative Concrete Post Coloring Project.
BUDGETIMPACT
The project summary cost for the North Cascade Road, English Mill Road, and Military
Road - Local Bridge Railing and Decorative Concrete Post Coloring Project is as
follows:
Estimate
Award
Final
Construction Contract
$ 564,000.00
$ 533,905.00
$ 530,170.00
Contingency
50,000.00
50,000.00
0.00
Contract Admin/Construction Engineering
75,000.00
75,000.00
33,600.06
Total Project Cost
$ 689,000.00
$ 658,905.00
$ 563,770.06
The project funding summary is as follows:
CIP No.
Fund Source Description
Fund Amount
3001287
DMATS STBG Funding (80%)
$ 424,136.00
3001287
City Funding (10%)
69,817.03
3001287
1 Dbq County Funding (10%)
69,817.
Total Project Funding
$ 563,770.07
The DMATS STBG Funding covers 80% of eligible construction costs. The local match
funding covers the 20% local match for the eligible construction costs and 100% of the
engineering and administrative costs.
ACTION TO BE TAKEN
I recommend that the City Council adopt the attached resolution to accept the
improvements and to authorize the payment of the contract of $530,170.00 to Taylor
Construction, inc. for the North Cascade Road, English Mill Road, and Military Road -
Local Bridge Railing and Decorative Concrete Post Coloring Project (Iowa DOT Project
No. STP-U-2100 (693)--70-31).
cc: Jenny Larson, Director of Finance and Budget
Kent Ellis, Iowa DOT
Chandra Ravada, ECIA
F:\PROJ ECTS\SOUTHW EST ARTERAL\NCR English Mill Military Bridge (693) - Railing Decorative Concrete\Council and
Staff Documents\Public Hearing - Acceptance
Prei)ared by Robert Schiesi City of Dubuque Engineering 50 W. 1311 St. Dubuque, [A 52001 (563)589-4270
Return to Adrienne N. Breitfelder City Clerk City of Dubuque, 50 W. 1311 St. Dubuque, 1A 52001 (563)589-4100
RESOLUTION NO. 207-21
ACCEPTING SOUTHWEST ARTERIAL NORTH CASCADE ROAD, ENGLISH MILL
ROAD, AND MILITARY ROAD LOCAL BRIDGE RAILING AND DECORATIVE
CONCRETE POST COLORING PROJECT, IOWA DOT PROJECT NO. STP-U-2100
(693)--70-31 AND AUTHORIZING THE PAYMENT TO THE CONTRACTOR
WHEREAS, the public improvement contract for the Southwest Arterial - North
Cascade Road, English Mill Road, and Military Road - Local Bridge Railing and
Decorative Concrete Post Coloring Project, Iowa DOT Project No. STP-U-2100 (693)--
70-31, (the Project) has been completed by the Contractor, Taylor Construction, Inc.
(Contractor), the City Engineer has examined the work and recommends that the Project
be accepted; and
WHEREAS, the final contract amount for the Project is $530,170.00;
WHEREAS, the Contractor has previously been paid $514,264.90, leaving a
balance of $15,905.10; and
WHEREAS, the City Council finds that the recommendation of the City Engineer
should be accepted.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
DUBUQUE, IOWA:
Section 1. The recommendation of the City Engineer is approved, and the
Project is hereby accepted.
Section 2. The Finance Director is hereby directed to pay to the Contractor the
balance of the retainage of $15,905.10 as provided in Iowa Code chapter 573, and to pay
such retainage in accordance with the provisions of Iowa Code chapter 573 or Iowa Code
chapter 26.13.
Passed, approved and adopted this 21st day of June 2021.
Attest:
Adrienne N. Breitfelder, City Clerk
Danny/C.-Wank, mayor Pro Tern
CITY ENGINEER'S CERTIFICATE OF FINAL COMPLETION OF THE SOUTHWEST
ARTERIAL NORTH CASCADE ROAD, ENGLISH MILL ROAD, AND MILITARY
ROAD LOCAL BRIDGE RAILING AND DECORATIVE CONCRETE POST
COLORING PROJECT, IOWA DOT PROJECT NO. STP-U-2100 (693)--70-31
The undersigned City Engineer of the City of Dubuque, Iowa, hereby certifies that
he has inspected the Southwest Arterial - North Cascade Road, English Mill Road, and
Military Road - Local Bridge Railing and Decorative Concrete Post Coloring Project,
Iowa DOT Project No. STP-U-2100 (693)--70-31 has been performed in compliance with
the terms of the Public Improvement Contract, and that the total cost of the completed
work is $563,770.06.
Dated this 16 th day of June 2021.
Gus Psihoyos, City Engineer
Filed in the office of the City Clerk on the 16 th day of June 2021.
Adrienne N. Breitfelder, City Clerk
Form 830435
`- 'k
05-18 W10WADOT
SMARTER I SIMPLER I CUSTOMER DRIVEN
STATEMENT OF COMPLETION AND FINAL ACCEPTANCE OF WORK
Contractor Taylor Construction, Inc.
Work Type Bridge Rehabilitation, Concrete Post Coloring, Railing
Accounting ID(s) 35450
Project Number(s) STP-1-1-2100 (693)--70-31
Otdditional Comments
Type of Contract
Specified Start Date
Approximate Start Date
RV( Late Start Date 07/31/2019
RCompletion Date Contract
Actual Start Date 06/12/2019
Field Completion Date 05/21/2020
Letting Date 10/16/2018
Contract ID 31-2100-693
Site No.(s)
00
Working Days Specified:
40
Working Days Charged:
39
Closure Days Specified:
Closure Days Charged:
Recommended for Acceptance
Iowa DOT Contract Acceptance
Signature T S_ I. . I
Signature
Pr6ject Engineer
District Construction Engineer
Date 06/18/2021
Date
Dubuque
County this 21st Day of June 2021
Year
Signature A_4�
/ Dankfy C. Sprank, Mayor Pro Tern
IRecorded Finance I Recorded Construction & Materials
NOTE: On county administered projects, the County Engineer is required to sign "Recommended for Acceptance" and
"Approved and Work Accepted on Behalf of the Board of Supervisors".
Project Engineer — Send original to District District —Forward original to Office of construction& Materials and copy to Project Engineer.
City of Dubuque - Engineering Department
City Council Final Payment Form
PAYMENT NO: COUNCIL FINAL
IROJECT NAME: Southwest Arterial - North Cascade Road, English Mill Road, Military Road Bridges
-Bridge Railing and Decorative Concrete Post Coloring Project
-Iowa DOT Project No. STP-U-2100 (693)--70-31
CONTRACTOR: -Taylor Construction, Inc. AWARDED CONTRACT AMOUNT: $533,905.00
THE C1TY OF
DUB E
Masterpiece on the Mississippi
FINAL COST ACCEPTANCE
ADDRESS: P.O. Box 110, 7314 Columbus Street
CONTRACT RECONCILIATION:
$
(3,735.00)
DATE:
June 21, 2021
CITY, STATE, ZIP: New Vienna, IA 52065
FINAL CONTRACT AMOUNT:
$
530,170.00 -0.7%
LINE
CONTRACT
TOTAL TO -DATE
CURRENT PAY PERIOD
FINAL
9
BID ITEM DESCRIPTION
-
NO.
1 QUANTITY
UNIT
UNIT COST
QUANTITY
AMOUNT
QUANTITY AMOUNT
QUANTITY
AMOUNT
0010
2403-7303000
STRUCTURAL CONCRETE COATING
ENGLISH MILL ROAD BRIDGE
1,471.00
SY
$ 62.50
1,471.00
$
91,937.50
$
1471.00
$ 91,937.50
NORTH CASCADE ROAD BRIDGE
1,437.00
SY
$ 62.50
1,437.00
$
89,812.50
$
1437.00
$ 89,812.50
MILITARY ROAD BRIDGE
1,978.00
SY
$ 62.50
1,978.00
$
123,625.00
$
1978.00
$ 123,625.00
0020
2414-6444100
STEEL PIPE PEDESTRIAN HAND RAILING
ENGLISH MILL ROAD BRIDGE
295.00
LF
$ 75.00
295.00
$
22,125.00
$
295.00
$ 22,125.00
MILITARY ROAD BRIDGE
391.00
LF
$ 75.00
391.00
$
29,325.00
$
391.00
$ 29,325.00
0030
2414-6445100
STRUCTURAL STEEL PEDESTRIAN HAND RAILING
ENGLISH MILL ROAD BRIDGE
313.00
LF
$ 155.00
313.00
$
48,515.00
$
313.00
$ 48,515.00
MILITARY ROAD BRIDGE
386.00
LF
$ 155.00
386.00
$
59,830.00
$
386.00
$ 59,830.00
0040
2528-8445110
TRAFFIC CONTROL
1.00
LS
$ 1,800.00
-
$
-
$
0.00
$ -
0050
2528-8445113
FLAGGERS
5.00
EACH
$ 480.00
-
$
-
$
0.00
$ -
0060
2533-4980005
MOBILIZATION
1.00
LS
$ 65,000.00
1.00
$
65,000.00
$
1.00
$ 65,000.00
FINAL BASE BID AMOUNT EARNED:
LINE
CONTRACT
TOTAL TO -DATE
CURRENT PAY PERIOD
FINAL
DESCRIPTION - CHANGE ORDER EXTRA WORK ITEMS
-QUANTITY
�QUANTITY
-
NO.
QUANTITY
UNIT
UNIT COST
QUANTITY
AMOUNT
AMOUNT
AMOUNT
$
$
0.00
$
$
$
0.00
$
$
$
0.00
$
$
$
0.00
$
$
$
0.00
$
FINAL CHANGE ORDER AMOUNT EARNED:
FINAL TOTAL CONTRACT AMOUNT EARNED:
FINAL PROJECT COST SUMMARY
CERTIFICATE OF THE CITY MANAGER
I hereby certify that the above statement shows in detail the correct
amount of all work required to complete the above improvement.
APPROVED:
Michael Van Milligen, City Manager
City of Dubuque, Iowa
AWARDED CONTRACT AMOUNT:
$533,905.00
BID ITEM(S) OVER I UNDER RECONCILIATION-
$ (3,735.00)
TOTAL CONTRACT CHANGE ORDER(S):
I $
FINAL CONTRACT AMOUNT I TOTAL DUE CONTRACTOR:
RIGHT-OF-WAY ACQUISITION:
$
ENVIRONMENTAL - ARCHEOLOGICAL SERVICES:
$
GEOTECHNICAL SERVICES:
$
ENGINEERING DESIGN SERVICES:
$
ADMIN / CONSTRUCTION ENGINEERING & INSPECTION:
$ 33.600.06
TOTAL PUBLIC IMPROVEMENT CONSTRUCTION COST:
CERTIFICATE OF THE CITY ENGINEER
I hereby certify that the above statement shows in detail the
correct amount of all work required tocomplete the above improvement.
CERTIFICATE OF THE CONTRACTOR
APPROVED:
Gus Psihoyos, City Engineer
City of Dubuque, Iowa
The undersigned, Taylor Construction, Inc. contractor for the above public improvement, does hereby accept the above "Total Due Contractor",
as full seftlement for all costs and claims for said puplic improvement construction project.
CONTRACTOR:
Taylor Construction, Inc.
BY:
DATE: 6-11-2021