Request for Work Session: Airport Master Plan UpdateCity of Dubuque
City Council Meeting
Action Items # 10.
Copyrighted
July 6, 2021
ITEM TITLE: Request for Work Session: Airport Master Plan Update
SUMMARY: City Manager requesting the City Council schedule a work session for
September 20, 2021, at 5:30 p.m. to review the Airport Master Plan
Update.
SUGGESTED Suggested Disposition: Receive and File; Council
DISPOSITION:
ATTACHMENTS:
Description Type
Request to Schedule Work Session on Airport Master City Manager Memo
Plan Update-MVM Memo
Airport Master Plan Update Memo Staff Memo
THE C
DUUB-.-*.-TE
Masterpiece on the Mississippi
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: Airport Master Plan Update City Council Work Session Request
DATE: June 21, 2021
Dubuque
*Amrin Cia
2007-2012.2013
2017*2019
Airport Director Todd Dalsing requests the City Council schedule a work session for
Monday, September 20, 2021, at 5:30 p.m. to review the Airport Master Plan Update.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
Mic ael C. Van Milligen
MCVM:jh
Attachment
cc: Crenna Brumwell, City Attorney
Cori Burbach, Assistant City Manager
Todd Dalsing, Airport Director
Q O _O.] Telephone : (563) 589-4233
Fax : (563) 589-4108
e-mail: tdalsing@cityofdubuque.org
DUBUQUE REGIONAL AIRPORT
Memorandum
To: Mike Van Milligen, City Manager
From: Todd Dalsing, Airport Director
Date: June 17, 2021
Subject: Airport Master Plan Update City Council Work Session Request
Mike,
On behalf of the Dubuque Regional Airport Commission, I respectfully request a City
Council Work Session to be held on Monday, September 20, 2021, at 5:30 p.m. to review
the Airport Master Plan Update project.
A Coffman and Associates' representative and Airport staff will be giving a 30-minute
presentation, followed by a question -and -answer period.
Brief overview:
The Dubuque Regional Airport Master Plan has been prepared to evaluate Airport needs
and guide facility development over the next 20 years. The plan followed an FAA -
prescribed process that included collection of existing data, aviation demand forecasts,
facility needs, alternatives to meet facility needs, and finally, a recommended
development concept and capital plan, with public involvement opportunities throughout
the process.
A full copy of the Masterplan Update can be found at:
https://dubugue.airportstudV.com/master-plan-documents/