Loading...
Chavenelle Road - Northwest Arterial to Radford Road Reconstruction ProjectCity of Dubuque City Council Meeting Action Items # 1. Copyrighted July 19, 2021 ITEM TITLE: Chavenelle Road - Northwest Arterial to Radford Road Reconstruction Project SUMMARY: City Manager recommending award of the construction contract to the low bidder, Horsfield Construction, Inc., in the amount of $1,864,873.50, which is 29.35% under the estimate of probable cost. RESOLUTION Awarding Public Improvement Contract for the Chavenelle Road — NW Arterial to Radford Road Reconstruction Project SUGGESTED Suggested Disposition: Receive and File; Adopt Resolution(s) DISPOSITION: ATTACHMENTS: Description Type Chavenelle Road Reconstruction Project-MVM Memo City Manager Memo Staff Memo Staff Memo Resolution Resolutions Bid Tab Supporting Documentation THE C Dubuque DUUB-.-*.-TE *Awiu Ciq ' iece on the Mississippi Masterpiece PP zoo�•zoi 2-2013 zoi7*2019oi9 TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager SUBJECT: Chavenelle Road - NW Arterial to Radford Road Reconstruction Project CIP #3602551, 7201180 DATE: July 14, 2021 Sealed bids were received for the Chavenelle Road — Northwest Arterial to Radford Road Reconstruction Project. City Engineer Gus Psihoyos recommends award of the construction contract to the low bidder, Horsfield Construction, Inc., in the amount of $1,864,873.50, which is 29.35% under the estimate of probable cost. Even though the bids came in substantially lower than the engineering estimate, final assessments will be calculated once the project is completed. Based on bid prices and expected engineering and contingency costs, the reduction in assessments from the original estimate is expected to range from 23% to 30% lower depending on if the property owner has a sidewalk assessment or not. I concur with the recommendation and respectfully request Mayor and City Council approval. k�4 Mic ael C. Van Milligen MCVM:jh Attachment cc: Crenna Brumwell, City Attorney Cori Burbach, Assistant City Manager Gus Psihoyos, City Engineer Dubuque THE C DUUB*TE AII•Ameriea C14 k Masterpiece on the Mississippi � pP Z°°''z°�z=z° 13 2017*2019 TO: Michael C. Van Milligen, City Manager FROM: Gus Psihoyos, City Engineer RE: Chavenelle Road — NW Arterial to Radford Road Reconstruction Project CIP# 3602551, 7201180 DATE: July 9, 2021 INTRODUCTION The attached resolution authorizes the award of the construction contract for the Chavenelle Road — NW Arterial to Radford Road Reconstruction Project. BACKGROUND Chavenelle Road between Radford Road and the NW Arterial (IA 32) was originally constructed in 1981 as part of the Dubuque Industrial Center development. The 8" thick concrete pavement has served out its life and is now in a state requiring reconstruction. At the time of original construction, a 4-lane road section was selected to accommodate the anticipated large truck traffic volumes. The pavement width of Chavenelle Road is currently 49 feet. The City has received public feedback from some large employers in the corridor concerning the condition of the street. The roadway acted as part of the detour for trucks when the SW Arterial was constructed. This detour also contributed to the pavement decline. The City did apply for a Revitalize Iowa's Sound Economy (RISE) funding for this project. The Iowa DOT advised the City that this project does not fit their grant criteria. DISCUSSION The proposed improvements to Chavenelle Road from the NW Arterial (IA 32) to Radford Road will include the removal and replacement of the PCC pavement, construction of stone sub -base, replacement of driveways, reconstruction of storm sewer intakes, and installation of pavement subdrains. Additionally, there will be watermain replacement in the corridor which will be funded by the Watermain Replacements fund. The project will be phased so access to driveways and the roadway is maintained. The anticipated construction timeframe is estimated to take approximately 4 months to allow for staging and pavement curing. The project was bid with paving alternates. This allows both the asphalt and concrete industry to bid on the project. The pavements being considered were equivalent in structural number. With the recent completion of the SW Arterial, the completion of the Chavenelle Hike/Bike Trail from Radford Road to Seippel Road, the future hike/bike trail phases along Seippel Road and the SW Arterial and the reconstruction of Chavenelle Road combine to provide for significant upgrade to the City industrial parks. All these projects improve the attractiveness of the industrial parks for future growth of businesses. Phase 2 of the Chavenelle Road Hike/Bike trail from the NW Arterial to Radford Road is planned for bidding through the Iowa DOT this fall. In FY 24 matching grant funds are tentatively budgeted for the trail section from Chavenelle Road at Seippel Road to the SW Arterial. PUBLIC ENGAGEMENT City staff have sent letters to all the abutting property owners in this corridor. Virtual meetings were scheduled and held with most of the property owners. Staff also discussed the project with the post office annex staff since their delivery routes will be affected. Staff will continue to update property owners during the project. Out of the meetings held with the property owners the majority supported one-way traffic during reconstruction of the street. This facilitates a safer construction zone and quicker construction. BID RESULTS The City received sealed bids on July 8, 2021, for the Project. Horsfield Construction of Epworth, IA, submitted the low bid in the amount of $1,864,873.50. This bid is 29.35% under the estimate of probable cost. A summary of the bid proposals received is as follows: Contractor Name Total Bid Horsfield Construction, Inc. $1,864,873.50 Portzen Construction, Inc. $2,072,082.50 Top Grade Excavating $2,075,883.66 River City Paving, a division of Mathy Construction $2,127,805.01 CJ Moyna & Sons $2,687,349.91 PIRC-Tobin Non -responsive RECOMMENDATION I recommend awarding the contract for the Chavenelle Road — NW Arterial to Radford Road Reconstruction Project to Horsfield Construction, of Epworth, Iowa in the amount of $1,864,873.50. BUDGETIMPACT The estimate of probable cost for the Chavenelle Road — NW Arterial to Radford Road Reconstruction Project is as follows: Description Estimate Award Construction Contract $ 2,639,595.00 $1,864,873.50 Contingency 263,959.00 263,959.00 Construction Engineering & Inspection 290,356.00 290,356.00 Total Project Cost $3,193,910.00 $2,419,188.50 The project funding summary is as follows: CIP Fund Source Amount 3602551 Chavenelle Road Rehabilitation $ 1,956,848.69 Special Assessment — Street Improvement, Commercial 351,346.48 Special Assessment — Commercial Deficiency 32,129.00 Special Assessment — Sidewalks 100% 78,864.33 Total Project Funding $ 2,419,188.50 The City of Dubuque received very favorable bids for this project. There were a number of bidders and the use of paving alternates between HMA and PCC helped facilitate competition. PROPERTY ASSESSMENTS Even though the bids came in substantially lower than the engineering estimate, final assessments will be calculated once the project is completed. Based on bid prices and expected engineering and contingency costs, the reduction in assessments from the original estimate is expected to range from 23% to 30% lower depending on if the property owner has a sidewalk assessment or not. These assessments include sidewalk assessments along the south side of the corridor. Because sidewalks don't currently exist, the abutting properties are assessed at 100% of the cost of the sidewalk installation. Special assessments may be paid in full or in part without interest within 30 days of receiving the Final Notice of Special Assessment. After 30 days, the remaining balance will be transferred to the County Treasurer's office to be collected in the same manner as the owner's property taxes. In cases where the remaining balance is $500 or more, the remaining balance may be financed over a period of 15 years at 3% interest. 3 ACTION TO BE TAKEN The City Council is requested to award the construction contract for the Chavenelle Road — NW Arterial to Radford Road Reconstruction Project through the adoption of the enclosed resolution to Horsfield Construction, Inc. in the amount of $1,864,873.50. Attach. Prepared by Jon Dienst, P.E. cc: Crenna Brumwell, City Attorney Jenny Larson, Budget & Finance Director John Klostermann, Public Works Director Deron Muehring, Civil Engineer 12 Prepared by Jan Dienst City of Dubuque Engineering 50 W 131h St Dubuque, fowa 52001 (5631589-4270 Return to Adrienne N. Breitfeider City of Dubuque City Clerk 50 W 13'h St Dubuque, Iowa 52001 (563)589-4100 RESOLUTION NO. 255-21 AWARDING PUBLIC IMPROVEMENT CONTRACT FOR THE CHAVENELLE ROAD — NW ARTERIAL TO RADFORD ROAD RECONSTRUCTION PROJECT NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: Whereas, sealed proposals have been submitted by contractors for Chavenelle Road -- NW Arterial to Radford Road Reconstruction Project, (the Project) pursuant to Resolution No. 191-21 and Notice to Bidders published on the City of Dubuque, Iowa website and plan room service with statewide circulation on the 10th day of June 2021. Whereas, said sealed proposals were opened and read on the 8th day of July 2021 and it has been determined that Horsfield Construction, Inc. of Epworfh, Iowa, submitted low bid in the amount of $1,864,873.50, and is the lowest responsive, responsible bidder for the Project. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: That a Public Improvement Contract for the Project is hereby awarded Horsfield Construction, Inc. and the City Manager is hereby directed to execute a Public Improvement Contract on behalf of the City of Dubuque for the Project. Passed, adopted and approved this 19th day of i-gly 2021. /111oy D. Buol, Mayor Attest: Trish L. Gleason, Assistant City Clerk THE CITY OF DUB E Masterpiece on the Mississippi City of Dubuque, Iowa Bid Tabulation Project Name: CHAVENELLE ROAD Radford to N.W. Arterial - 4 LANE ( )( ) Bid Date Engineer's 9 Estimate Horsfield Construction Portzen Construction To Grade p Excavating 9 River CityPavin 9 CJ Mo na 8. Sons Y PIRC-Tobin 8-Jul-21 R E BID ITEM DESCRIPTION I UNIT ESTIMATED TOTAL PRICE BPRICE TOTAL PRICE TOTAL PRICE TOTAL PRICE BID TOTAL PRICE TOTAL PRICE BID TOTAL PRICE NO NUMBER QUANTITYLAN UNIT PRICE UNI UNIT PRICE UNIT PRICE UNIT PRICE UNIT PRICE UNIT RICE Division 2010 - Earthwork, Subgrade, and Subbase 1 2010-108-D-3 Topsoil, Off -site 600.00 CY $ 23.51 $ 14,106.00 $ 33.50 $ 20,100.00 $ 36.00 $ 21,600.00 $ 57.80 $ 34,680.00 $ 45.00 $ 27,000.00 $ 20.00 $ 12,000.00 $ 2 2010-108-1-0 Subbase, Special Backfill - Gradation 30 500.00 TON $ 18.42 $ 9,210.00 $ 13.50 $ 6,750.00 $ 15.00 $ 7,500.00 $ 19.80 $ 9,900.00 $ 15.00 $ 7,500.00 $ 18.40 $ 9,200.00 $ 3 2010-108-1-0 Subbase, Granular Subbase- Gradation 12a 4575.00 TON $ 18.00 $ 82,350.00 $ 13.00 $ 59,475.00 $ 14.00 $ 64,050.00 $ 19.80 $ 90,585.00 $ 15.00 $ 68,625.00 $ 14.60 $ 66,795.00 $ 4 2010-108-1-0 Subbase, Coarse Aggregate Subbase -3"Breaker 13211.00 TON $ 18.00 $ 237,798.00 $ 13.25 $ 175,045.75 $ 13.50 $ 178,348.50 $ 18.40 $ 243,082.40 $ 14.50 $ 191,559.50 $ 13.90 $ 183,632.90 $ 5 2010-108-L-0 Compaction Testing 1.00 LS $ 3,000.00 $ 3,000.00 $ 5,800.00 $ 5,800.00 $ 4,500.00 $ 4,500.00 $ 5,500.00 $ 5,500.00 $ 4,500.00 $ 4,500.00 $ 4,500.00 $ 4,500.00 $ Sub Total $ 346,464.00 Sub Total $ 267,170.75 Sub Total # $ 275,998.50 Sub Total # $ 383,747.40 Sub Total # $ 299,184.50 Sub Total # $ 276,127.90 Sub Total # $ Division 3010 - Trench Excavation and Backliill 6 3010-108-B-0 Rock Excavation 100.00 CY $ 100.00 $ 10,000.00 $ 150.00 $ 15,000.00 $ 85.00 $ 8,500.00 $ 2000. $ 2,000.00 $ 85.00 $ 8,500.00 $ 150.00 $ 15,000.00 $ 7 3010-108-D-0 Trench Foundation -3" Breaker 75.00 TON $ 17.00 $ 1,275.00 $ 9.65 $ 723.75 $ 24.00 $ 1,800.00 $ 23.50 $ 1,762.50 $ 24.00 $ 1,800.00 $ 40.00 $ 3,000.00 $ 8 3010-108-D-0 Bedding Material, 1" Commercial Clean Stone 115.00 TON $ 20.00 $ 2,300.00 $ 12.00 $ 1,380.00 $ 18.00 $ 2,070.00 $ 13.50 $ 1,552.50 $ 18.00 $ 2,070.00 $ 36.00 $ 4,140.00 $ 9 3010-108-L-0 Rigid Insulation Board 100.00 SF $ 2.50 $ 250.00 $ 10.00 $ 1,000.00 $ 15.00 $ 1,500.00 $ 12.00 $ 1,200.00 $ 15.00 $ 1,500.00 $ 40.00 $ 4,000.00 $ Sub Total $ 13,825.00 Sub Total $ 18,103.75 Sub Total # $ 13,870.00 Sub Total # $ 6,515.00 Sub Total # $ 13,870.00 Sub Total # $ 26,140.00 Sub Total # $ Division 3020 - Trenchless Construction 10 3020-108-A-0 Directional Drilling, w/ Pipe 200.00 LF $ 45.00 $ 9,000.00 $ 45.00 $ 9,000.00 $ 45.00 $ 9,000.00 $ 45.00 $ 9,000.00 $ 45.00 $ 9,000.00 $ 150.00 $ 30,000.00 $ Sub Total $ 9,000.00 Sub Total $ 9,000.00 Sub Total # $ 9,000.00 Sub Total # $ 9,000.00 Sub Total # $ 9,000.00 Sub Total # $ 30,000.00 Sub Total # $ Division 4020 - Storm Sewers 11 4020-108-A-1 Storm Sewer Gravity Main, Trenched, 15" RCP 50.00 LF $ 70.00 $ 3,500.00 $ 75.00 $ 3,750.00 $ 62.00 $ 3,100.00 $ 95.00 $ 4,750.00 $ 62.00 $ 3,100.00 $ 64.00 $ 3,200.00 $ 12 4020-108-A-1 Storm Sewer Gravity Main, Trenched, 18" RCP 46.00 LF $ 75.00 $ 3,450.00 $ 80.00 $ 3,680.00 $ 66.00 $ 3,036.00 $ 110.00 $ 5,060.00 $ 66.00 $ 3,036.00 $ 66.00 $ 3,036.00 $ 13 4020-108-C-0 Removal of Storm Sewer, 15" RCP 8.00 LF $ 50.00 $ 400.00 $ 32.50 $ 260.00 $ 15.00 $ 120.00 $ 50.00 $ 400.00 $ 15.00 $ 120.00 $ 8.90 $ 71.20 $ 14 4020-108-C-0 Removal of Storm Sewer, 18" RCP 30.00 LF $ 55.00 $ 1,650.00 $ 18.00 $ 540.00 $ 15.00 $ 450.00 $ 50.00 $ 1,500.00 $ 15.00 $ 450.00 $ 8.90 $ 267.00 $ Sub Total $ 9,000.00 Sub Total $ 8,230.00 Sub Total # $ 6,706.00 Sub Total # $ 11,710.00 Sub Total # $ 6,706.00 Sub Total # $ 6,574.20 Sub Total # $ Division 4040 - Subdrains and Footing Drain Collectors 15 4040-108-A-0 Subdrain, 6" Perforated CPE 8240.00 LF $ 11.65 $ 95,996.00 $ 8.50 $ 70,040.00 $ 11.00 $ 90,640.00 $ 10.40 $ 85,696.00 $ 11.00 $ 90,640.00 $ 14.80 $ 121,952.00 $ 16 4040-108-D-0 Subdrain Outlets and Connections, Core Drill, 6" 16.00 EA $ 250.00 $ 4,000.00 $ 1,100.00 $ 17,600.00 $ 550.00 $ 8,800.00 $ 550.00 $ 8,800.00 $ 550.00 $ 8,800.00 $ 1,400.00 $ 22,400.00 $ Sub Total $ 99,996.00 Sub Total $ 87,640.00 Sub Total # $ 99,440.00 Sub Total # $ 94,496.00 Sub Total # $ 99,440.00 Sub Total # $ 144,352.00 Sub Total # $ Division 6010 - Structures for Sanitary and Storm Sewers 17 6010-108-E-0 Manhole Adjustment, Minor 4.00 EA $ 1,056.28 $ 4,225.12 $ 750.00 $ 3,000.00 $ 750.00 $ 3,000.00 $ 1,300.00 $ 5,200.00 $ 750.00 $ 3,000.00 $ 780.00 $ 3,120.00 $ 18 6010-108-F-0 Manhole Adjustment, Major 1.00 EA $ 3,000.00 $ 3,000.00 $ 1,300.00 $ 1,300.00 $ 1,600.00 $ 1,600.00 $ 2,700.00 $ 2,700.00 $ 1,600.00 $ 1,600.00 $ 11900.00 $ 1,900.00 $ 19 6010-108-H-0 Remove Manhole 1.00 EA $ 600.00 $ 600.00 $ 500.00 $ 500.00 $ 500.00 $ 500.00 $ 650.00 $ 650.00 $ 500.00 $ 500.00 $ 880.00 $ 880.00 $ 20 6010-108-H-0 Remove Intake 1.00 EA $ 500.00 $ 500.00 $ 500.00 $ 500.00 $ 350.00 $ 350.00 $ 550.00 $ 550.00 $ 350.00 $ 350.00 $ 520.00 $ 520.00 $ 21 Intake Type, CIP, 104-B 1.00 EA $ 4,000.00 $ 4,000.00 $ 4,000.00 $ 4,000.00 $ 4,800.00 $ 4,800.00 $ 4,450.00 $ 4,450.00 $ 4,800.00 $ 4,800.00 $ 10,300.00 $ 10,300.00 $ 22 6010-108-E-0 Intake Adjustment, Minor 7.00 EA $ 1,000.00 $ 7,000.00 $ 1,150.00 $ 8,050.00 $ 450.00 $ 3,150.00 $ 1,400.00 $ 9,800.00 $ 450.00 $ 3,150.00 $ 1,400.00 $ 9,800.00 $ 23 6010-108-F-0 Intake Adjustment, Major 1.00 EA $ 3,000.00 $ 3,000.00 $ 1,330.00 $ 1,330.00 $ 1,500.00 $ 1,500.00 $ 2,100.00 $ 2,100.00 $ 1,500.00 $ 1,500.00 $ 2,700.00 $ 2,700.00 $ Sub Total $ 22,325.12 Sub Total $ 18,680.00 Sub Total # $ 14,900.00 Sub Total # $ 25,450.00 Sub Total # $ 14,900.00 Sub Total # $ 29,220.00 Sub Total # $ Division 7010 - Portland Cement Concrete Pavement 24 7010-108-E-0 Curb and Gutter, 30" (Width), 6" (Thickness) 50.00 LF $ 30.00 $ 1,500.00 $ 25.00 $ 1,250.00 $ 37.00 $ 1,850.00 $ 22.00 $ 1,100.00 $ 37.00 $ 1,850.00 $ 41.00 $ 2,050.00 $ Sub Total $ 1,500.00 Sub Total $ 1,250.00 Sub Total # $ 1,850.00 Sub Total # $ 1,100.00 Sub Total # $ 1,850.00 Sub Total # $ 2,050.00 Sub Total # $ Division 7020 - Hot Mix Asphalt Pavement 25 7020-108-A-0 Pavement or Overlay, HMA 400.00 TON $ 126.15 $ 50,460.00 $ 100.00 $ 40,000.00 $ 90.00 $ 36,000.00 $ 63.00 $ 25,200.00 $ 120.00 $ 48,000.00 $ 140.00 $ 56,000.00 $ Sub Total $ 50,460.00 Sub Total $ 40,000.00 Sub Total # $ 36,000.00 Sub Total # $ 25,200.00 Sub Total # $ 48,000.00 Sub Total # $ 56,000.00 Sub Total # $ Division 7030 - Sidewalks, Shared Use Paths, and Driveways 26 7030-108-A-0 Removal of Driveway 1599.00 SY $ 6.00 $ 9,594.00 $ 9.50 $ 15,190.50 $ 10.00 $ 15,990.00 $ 5.30 $ 8,474.70 $ 10.00 $ 15,990.00 $ 14.00 $ 22,386.00 $ 27 7030-108-E-0 Sidewalk, PCC, 6" (Thickness) 25.00 SY $ 48.69 $ 1,217.25 $ 100.00 $ 2,500.00 $ 85.00 $ 2,125.00 $ 60.00 $ 1,500.00 $ 85.00 $ 2,125.00 $ 50.00 $ 1,250.00 $ 28 7030-108-G-0 Detectable Warning 20.00 SF $ 50.00 $ 1,000.00 $ 41.25 $ 825.00 $ 45.00 $ 900.00 $ 40.00 $ 800.00 $ 45.00 $ 900.00 $ 43.00 $ 860.00 $ 29 7030-108-H-1 Driveway, Paved, PCC, 8" (Thickness) 1599.00 SY $ 58.32 $ 93,253.68 $ 58.00 $ 92,742.00 $ 60.00 $ 95,940.00 $ 75.00 $ 119,925.00 $ 60.00 $ 95,940.00 $ 78.00 $ 124,722.00 $ 30 7030-108-E-0 Sidewalk, PCC, 4" (Thickness) 2103.00 SY $ 48.00 $ 100,944.00 $ 30.00 $ 63,090.00 $ 40.00 $ 84,120.00 $ 40.00 $ 84,120.00 $ 40.00 $ 84,120.00 $ 40.00 $ 84,120.00 $ _ Sub Total $ 206,008.93 Sub Total $ 174,347.50 Sub Total # $ 199,075.00 Sub Total # $ 214,819.70 Sub Total # $ 199,075.00 Sub Total # $ 233,338.00 Sub Total # $ Division 7040 - Pavement Rehabilitation 31 7040-108-H-0 Removal - Pavement 20211.00 SY $ 7.00 $ 141,477.00 $ 5.00 $ 101,055.00 $ 7.50 $ 151,582.50 $ 4.30 $ 86,907.30 $ 7.50 $ 151,582.50 $ 11.20 $ 226,363.20 $ Sub Total $ 141,477.00 Sub Total $ 101,055.00 Sub Total # $ 151,582.50 Sub Total # $ 86,907.30 Sub Total # $ 151,582.50 Sub Total # $ 226,363.20 Sub Total # $ IDOT Division 2527 - Pavement Marking 32 IDOT 2527.04-A-1 DCY4: Double Centerline (Yellow) 82.00 STA $ 25.00 $ 2,050.00 $ 55.00 $ 4,510.00 $ 55.00 $ 4,510.00 $ 55.00 $ 4,510.00 $ 55.00 $ 4,510.00 $ 55.00 $ 4,510.00 $ 33 IDOT 2527.04-A-1 BLW4: Broken Lane Line (White) 20.50 STA $ 25.00 $ 512.50 $ 55.00 $ 1,127.50 $ 55.00 $ 1,127.50 $ 55.00 $ 1,127.50 $ 55.00 $ 1,127.50 $ 55.00 $ 1,127.50 $ 34 IDOT 2527.04-A-1 SLW2: Stop Line (White) 0.36 STA $ 150.00 $ 54.00 $ 300.00 $ 108.00 $ 300.00 $ 108.00 $ 300.00 $ 108.00 $ 300.00 $ 108.00 $ 300.00 $ 108.00 $ 35 IDOT 2527.04-A-1 SLW4: Solid Lane Line (White) 0.25 STA $ 200.00 $ 50.00 $ 300.00 $ 75.00 $ 300.00 $ 75.00 $ 300.00 $ 75.00 $ 300.00 $ 75.00 $ 300.00 $ 75.00 $ 36 IDOT 2527.04-A-1 CBW6: Crosswalk Bar (White) 10.00 EA $ 50.00 $ 500.00 $ 30.00 $ 300.00 $ 30.00 $ 300.00 $ 300.00 $ 3,000.00 $ 30.00 $ 300.00 $ 30.00 $ 300.00 $ Project Name: CHAVENELLE ROAD Radford to N.W. Arterial - 4 LANE ( )( ) Bid Date Engineer's Estimate 9 Horsfield Construction Portzen Construction To Grade Excavating p 9 River City Paving Y 9 CJ Moyne & Sons Y PIRC-Tobin 8-Jul-21 PLAN QUANTITY UNIT ESTIMATED UNIT RICE TOTAL PRICE UNIT PRICE TOTAL PRICE BID UNIT PRICE TOTAL PRICE UNIBPRICE TOTAL PRICE UNIT PRICE TOTAL PRICE UNI BPRICE TOTAL PRICE UNIT PRICE TOTAL PRICE F0.R NUMBER E BID ITEM DESCRIPTION 37 IDOT 2527.04-A-4 ONLW: Only Word Marking (White) 5.00 EA $ 100.00 $ 500.00 $ 150.00 $ 750.00 $ 150.00 $ 750.00 $ 150.00 $ 750.00 $ 150.00 $ 750.00 $ 150.00 $ 750.00 $ 38 IDOT 2527.04-A-4 RTAW: Right Turn Arrow (White) 5.00 EA $ 100.00 $ 500.00 $ 100.00 $ 500.00 $ 100.00 $ 500.00 $ 100.00 $ 500.00 $ 100.00 $ 500.00 $ 100.00 $ 500.00 $ 39 IDOT 2527.04-A-4 LTAW: Left Turn Arrow (White) 1.00 EA $ 100.00 $ 100.00 $ 100.00 $ 100.00 $ 100.00 $ 100.00 $ 100.00 $ 100.00 $ 100.00 $ 100.00 $ 100.00 $ 100.00 $ 40 IDOT 2527.04-A-4 STAW: Straight Arrow (White) 1.00 EA $ 100.00 $ 100.00 $ 100.00 $ 100.00 $ 100.00 $ 100.00 $ 100.00 $ 100.00 $ 100.00 $ 100.00 $ 100.00 $ 100.00 $ Sub Total $ 4,366.50 Sub Total # $ 7,570.50 Sub Total # $ 7,570.50 Sub Total # $ 10,270.50 Sub Total # $ 7,570.50 Sub Total # $ 7,570.50 Sub Total # $ IDOT Division 2528 -Traffic Control 41 IDOT2528.04-A Traffic Control 1.00 LS $ 60,000.00 $ 60,000.00 $ 10,400.00 $ 10,400.00 $ 11,500.00 $ 11,500.00 $ 17,000.00 $ 17,000.00 $ 10,400.00 $ 10,400.00 $ 24,000.00 $ 24,000.00 $ Sub Total $ 60,000.00 Sub Total # $ 10,400.00 Sub Total # $ 11,500.00 Sub Total # $ 17,000.00 Sub Total # $ 10,400.00 Sub Total # $ 24,000.00 Sub Total # $ Division 9010 - Seeding 42 9010-108-13-0 Hydraulic - Seeding, Fertilizing, and Mulching, Type 1 1.20 AC $ 15,000.00 $ 18,000.00 $ 7,500.00 $ 9,000.00 $ 7,500.00 $ 9,000.00 $ 8,000.00 $ 9,600.00 $ 7,500.00 $ 9,000.00 $ 7,500.00 $ 9,000.00 $ Sub Total $ 18,000.00 Sub Total # $ 9,000.00 Sub Total # $ 9,000.00 Sub Total # $ 9,600.00 Sub Total # $ 9,000.00 Sub Total # $ 9,000.00 Sub Total # $ Division 9040 - Erosion and Sediment Control #REF! #REF! 43 9040-108-A-1 SWPPP Preparation 1.00 LS $ 5,000.00 $ 5,000.00 $ 1,000.00 $ 1,000.00 $ 2,100.00 $ 2,100.00 $ 3,500.00 $ 3,500.00 $ 1,500.00 $ 1,500.00 $ 1,500.00 $ 1,500.00 $ 44 9040-108-D-1 Filter Socks, 12" 300.00 LF $ 5.00 $ 1,500.00 $ 8.00 $ 2,400.00 $ 8.00 $ 2,400.00 $ 8.00 $ 2,400.00 $ 8.00 $ 2,400.00 $ 8.00 $ 2,400.00 $ 45 9040-108-D-2 Filter Socks, Removal 300.00 LF $ 1.00 $ 300.00 $ 2.00 $ 600.00 $ 2.00 $ 600.00 $ 0.50 $ 150.00 $ 2.00 $ 600.00 $ 2.00 $ 600.00 $ 46 9040-108-T-1 Inlet Protection Device, _ (Type) 11.00 EA $ 100.00 $ 1,100.00 $ 300.00 $ 3,300.00 $ 300.00 $ 3,300.00 $ 300.00 $ 3,300.00 $ 300.00 $ 3,300.00 $ 300.00 $ 3,300.00 $ 47 9040-108-T-2 Inlet Protection Device, Maintenance 11.00 EA $ 20.00 $ 220.00 $ 100.00 $ 1,100.00 $ 100.00 $ 1,100.00 $ 100.00 $ 1,100.00 $ 100.00 $ 1,100.00 $ 100.00 $ 1,100.00 $ 48 9040-108-N-3 Silt Fence or Silt Fence Ditch Check, Removal of Device 11.00 EA $ 10.00 $ 110.00 $ 100.00 $ 1,100.00 $ 100.00 $ 1,100.00 $ 100.00 $ 1,100.00 $ 100.00 $ 1,100.00 $ 100.00 $ 1,100.00 $ 49 9040-108-P-1 Dust Control, Water 165.00 MGAL $ 50.00 $ 8,250.00 $ 25.00 $ 4,125.00 $ 75.00 $ 12,375.00 $ 150.00 $ 24,750.00 $ 60.00 $ 9,900.00 $ 50.00 $ 8,250.00 $ Sub Total $ 16,480.00 Sub Total # $ 13,625.00 Sub Total # $ 22,975.00 Sub Total # $ 36,300.00 Sub Total # $ 19,900.00 Sub Total # $ 18,250.00 Sub Total # $ Division 11 - Miscellaneous 50 1090-105-D Mobilization 1.00 LS $ 135,000.00 $ 135,000.00 $ 26,000.00 $ 26,000.00 $ 45,000.00 $ 45,000.00 $ 61,500.00 $ 61,500.00 $ 41,000.00 $ 41,000.00 $ 230,000.00 $ 230,000.00 $ 51 11010-108-B-0 Monument Preservation and Replacement 1.00 LS $ 4,000.00 $ 4,000.00 $ 3,150.00 $ 3,150.00 $ 3,500.00 $ 3,500.00 $ 3,000.00 $ 3,000.00 $ 3,500.00 $ 3,500.00 $ 12,500.00 $ 12,500.00 $ Sub Total $ 139,000.00 Sub Total # $ 29,150.00 Sub Total # $ 48,500.00 Sub Total # $ 64,500.00 Sub Total # $ 44,500.00 Sub Total # $ 242,500.00 Sub Total # $ NonSUDAS - Miscellaneous 52 IDOT4196 Subsurface Drainage Fabric - IDOT 4196 22790.00 SY $ 5.00 $ 113,950.00 $ 1.50 $ 34,185.00 $ 2.00 $ 45,580.00 $ 1.50 $ 34,185.00 $ 2.00 $ 45,580.00 $ 3.40 $ 77,486.00 $ 53 2113-0001100 Subgrade Stabilization Material, Polymer Grid 10000.00 SY $ 7.00 $ 70,000.00 $ 5.50 $ 55,000.00 $ 5.85 $ 58,500.00 $ 3.60 $ 36,000.00 $ 5.85 $ 58,500.00 $ 7.90 $ 79,000.00 $ Sub Total $ 183,950.00 Sub Total # $ 89,185.00 Sub Total # $ 104,080.00 Sub Total # $ 70,185.00 Sub Total # $ 104,080.00 Sub Total # $ 156,486.00 Sub Total # $ Total Est. $ 1,321,852.55 Total Bid $ 884,407.50 Total Bid $ 1,012,047.50 Total Bid $ 1,066,800.90 Total Bid $ 1,039,058.50 Total Bid $ 1,487,971.80 Total Bid $ Over / Under (-) -33.09 % -23.44 % -19.30 % -21.39 % 12.57% -100.00 Horsfield Construction River City Paving CJ Moyne & Sons PIRC-Tobin Engineer's Estimate Portzen Construction Top Grade Excavating Alternate Bid Items INE LINE ITEM NUMBER ITEM DESCRIPTION y UNITESTIMATED QUANTITY T PRICE TOTAL PRICE UNIT PRICE TOTAL PRICE UNIT PRICE TOTAL PRICE UNI BPRICE TOTAL PRICE UNIT PRICE TOTAL PRICE UNIT PRICE TOTAL PRICE UNIT PRICE TOTAL PRICE PCC Pavement Alternate 54 7010-108-A-0 9-inch PCC Pavement w/CD Joints & Integral Curb and Gutter, Class C-SUD, 22866.00 SY $ 60.00 $ 1,371,960.00 $ 40.00 $ 914,640.00 $ 43.00 $ 983,238.00 $ - $ - $ - $ - 55 2010-108-A-0 Excavation Class 13, Roadway and Borrow 10971.00 CY $ 10.00 $ 109,710.00 $ 6.00 $ 65,826.00 $ 7.00 $ 76,797.00 $ - $ - $ - $ - Sub Total $ 1,481,670.00 Sub Total $ 980,466.00 Sub Total $ 1,060,035.00 Sub Total $ - Sub Total # $ - Sub Total # $ - Sub Total # $ HMA Paving Alternate 56 7020-108-A-0 HOT MIX ASPHALT, VERY HIGH TRAFFIC, SURFACE COURSE, 1/2 IN. MI; 2204.00 TON $ 75.00 $ 165,300.00 $ - $ $ 68.65 $ 151,304.60 $ 68.65 $ 151,304.60 $ 68.65 $ 151,304.60 $ 57 7020-108-A-0 HOT MIX ASPHALT, VERY HIGH TRAFFIC, INTERMEDIATE COURSE, 1/2 1 2204.00 TON $ 75.00 $ 165,300.00 $ - $ - $ 70.09 $ 154,478.36 $ 70.09 $ 154,478.36 $ 70.09 $ 154,478.36 $ - 58 7020-108-A-0 HOT MIX ASPHALT, STANDARD TRAFFIC, INTERMEDIATE COURSE, 1/2 1 2840.00 TON $ 65.00 $ 184,600.00 $ - $ - $ 56.63 $ 160,829.20 $ 56.63 $ 160,829.20 $ 56.63 $ 160,829.20 $ - 59 7020-108-A-0 HOT MIX ASPHALT, STANDARD TRAFFIC, BASE COURSE, 1/2 IN. MIX, N( 4545.00 TON $ 65.00 $ 295,425.00 $ - $ - $ 56.63 $ 257,383.35 $ 56.63 $ 257,383.35 $ 56.63 $ 257,383.35 $ - 60 7010-108-A-0 30-INCH PCC CURB & GUTTER 8300.00 LF $ 30.00 $ 249,000.00 $ $ $ 23.20 $ 192,560.00 $ 31.00 $ 257,300.00 $ 38.00 $ 315,400.00 $ 61 2010-108-A-0 EXCAVATION, CLASS 13, ROADWAY AND BORROW 11939.00 CY $ 5.00 $ 59,695.00 $ - $ - $ 7.75 $ 92,527.25 $ 9.00 $ 107,451.00 $ 13.40 $ 159,982.60 $ - Sub Total # $ 1,119,320.00 Sub Total # $ - Sub Total # $ Sub Total # $ 1,009,082.76 Sub Total # $ 1,088,746.51 Sub Total # $ 1,199,378.11 Sub Total # $ NON RESPONSIVE BID Total Bid Amount $ 1,321,852.55 $ 884,407.50 $ 1,012,047.50 $ 1,066,800.90 $ 1,039,058.50 $ 1,487,971.80 $ Total Selected Alternate(s) Amount $ 1,481,670.00 $ 980,466.00 $ 1,060,035.00 $ 1,009,082.76 $ 1,088,746.51 $ 1,199,378.11 $ Contract Award Amount: $ 2,803,522.55 $ 1,864,873.50 $ 2,072,082.50 $ 2,075,883.66 $ 2,127,805.01 $ 2,687,349.91 $ Council Estimate $ 2,639,595.00 -29.35% -21.50% -21.36% -19.39% 1.81