TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: Approval of Iowa State Energy Program Grant Submission
DATE: July 1, 2010
Dubuque
kratell
All-Am t1caCity
1111 !
2007
Stimulus Coordinator Will Hoyer is recommending approval of a $69,831 grant
application to the Iowa Office of Energy Independence to cover 1/3 of the total cost
related to the building envelope, lighting, HVAC systems and energy monitoring
equipment in the 18 and Central Building.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
MCVM:jh
Attachment
cc: Barry Lindahl, City Attorney
Cindy Steinhauser, Assistant City Manager
Will Hoyer, Stimulus Coordinator
Michael C. Van Milligen
Masterpiece on the Mississippi
TO: Michael C. Van Milligen, City Manager
FROM: Will Hoyer, Stimulus Coordinator
SUBJECT: Approval of Iowa State Energy Program grant submission
DATE: June 28, 2010
INTRODUCTION
RECOMMENDATION:
Staff requests Council approval of the State of Iowa SEP grant submission.
cc: Cindy Steinhauser, Assistant City Manager
Cori Burbach, Sustainable Community Coordinator
Steve Brown, Project Manager
Jenny Larson, Budget Director
Dubuque
btall
AJ AmedcaCily
11111 !
2007
The purpose of this memorandum is to bring to your attention that the City of Dubuque
has submitted a grant application to the Iowa Office of Energy Independence for
$69,831 to cover 1/3 of the total costs related to the building envelope, lighting, HVAC
systems and energy monitoring equipment in the 18 and Central Building slated for re-
construction in the upcoming year.
BACKGROUND
The State Energy Program (SEP) grant is an ARRA- funded program intended to fund
municipal energy efficiency improvements. This particular SEP grant required a 2:1
match and was intended for a "comprehensive" project — one that addressed windows,
insulation, lighting, hot water, etc. As such the planned retrofit of the old Housing
building for use by Operation: New View and the Crescent Community Health Center,
which was already funded in the FY2010 -11 CIP made it a logical choice.
DISCUSSION
Using modeling completed by EcoSmart Building, recommended building envelope
(windows, insulation, etc), lighting, solar thermal hot water, and HVAC systems were
selected along with a building energy monitoring and sensing system. When combined
these improvements are expected to cost a total of $209,493, but will save $14,430
annually in energy costs in the building.
wen%irants
l of 11
3646 - Iowa ARRA State Energy Program (SEP -R2)
4700 - Comprehensive Retrofit of 18th and Central Building
State Energy Program
Status:
Signature:
Applicant Information
Project Officer
First Name* Will
First Name
Title:
Email:
Address:
City Dubuque Iowa 52001 -4805
City State /Province Postal Code /ZIp
Phone:* 563 - 589 -4110
Phone Ext.
Program Area of American Recovery &
Interest Reinvestment Act
Fax:
Cover Sheet
Authorized Official
Name
Title
Organization
Address
City /State /Zip*
Telephone Number
E -Mail
Fiscal Officer
Name
Title
Application
Submitted Submitted Date:
Will Hoyer Submitted By:
Middle Name
whoyer@cityofdubuque.org
City Manager's Office
50 West 13th St
Hoyer
Last Name
Phone:
https: // www. iowagrants. gov/ getApplicationPrintPreview .do ?docume...
2010 -06 -21 08:47:32
Will Hoyer
Organization Information
Organization Name: City of Dubuque
Organization Type: City Government
Tax ID: 42- 6004596
DUNS: 09- 310 -5302
Organization
Website:
Address:
www.cityofdubuque.org
City Hall
50 West 13th St
Fax: 563- 589 -4149
Dubuquelowa 52001-48b5
City State /ProvincePostal Code /Zip
563 -589 -4110
Michael Van Milligen
City Manager
City of Dubuque
50 West 13th St
Ken Tekippe
Finance Director
Ext.
Dubuquelowa52001 -4805
City State Zip
563 -589 -4110
ctymgr@cityofdubuque.org
6/28/2010 2:56 PM
WebGrants
Organization
Address
City /State /Zip
Telephone Number
E -Mail
County(ies) Participating, Involved, or Affected by this Proposal
Congressional District(s) Involved or Affected by this Proposal
Iowa Senate District(s) Involved or Affected by this Proposal
Iowa House District(s) Involved or Affected by this Proposal
SEP Applicant Information
Name of Applicant Entity:
Street Address 1:
Street Address 2:
City:
State:
ZipCode:
County
State Tax ID (example XX- XXXXXXX):
Federal Tax ID (example XX- XXXXXXX):
Phone Number:
Fax Number:
E -mail Address:
If you do not have a DUNS number, please contact DNB to acquire.
DUNS Number (example)XX - XXXXXXX:
Congressional District:
SEP Applicant's Chief Executive Office
Person Authorized to Sign Contract
Chief Executive Officer's Name:
Chief Executive Officer's Salutation:
Chief Executive Officer's Title:
Chief Executive Officer's Mailing Address 1:
Chief Executive Officer's Mailing Address 2:
Chief Executive Officer's City:
Chief Executive Officer's State:
Chief Executive Officer's ZipCode:
Chief Executive Officer's Phone Number:
Chief Executive Officer's Fax Number:
Chief Executive Officer's E -mail Address:
https: // www. iowagrants. gov/ getApplicationPrintPreview .do ?docume...
City of Dubuque
50 West 13th St
City of Dubuque
50 West 13th St
Dubuquelowa52001
City State Zip
563 -589 -4133
ktekippe @cityofdubuque.org
Dubuque County
1 - Bruce Braley
Congressional Map
14
District Map
28
District Map
Dubuque
Iowa
52001
Dubuque County
42- 6004596
42- 6004596
563 - 589 -4110
563 -589 -4149
sbrown @cityofdubuque.org
1- 866- 705 -5711
09- 3105302
1 - Bruce Braley
Michael Van Milligen
Mr.
City Manager
City Manager's Office
50 West 13th Street
Dubuque
Iowa
52001
563- 589 -4110
563 - 589 -4149
ctymgr@cityofdubuque.org
2of11 6/2R/201n2.56 PM
Weblirants
SEP Preparer /Staff Contact Information
Name of Preparer:
Salutation of Preparer:
Title of Preparer:
Affiliation:
Address of Preparer:
City:
State:
ZipCode:
Phone Number:
Fax Number:
E -Mail Address:
Certification
Enter your full legal name.
Signature of Preparer:
Date:
Budget Detail
Budget Detail
Cost Estimates
Administrative Costs (limited to 5% of the total project cost or
$5,000 whichever is smaller)
Cost of Improvements (must match table 10. Energy Savings)
List all costs separately
Other Costs 1
Other Costs 2
Other Costs 3
Other Costs 4
Other Costs Detail
Other Costs 1 Detail
Other Costs 2 Detail
Other Costs 3 Detail
Other Costs 4 Detail
Project Budget Factors
https: / /www. iowagrants. gov/ getApplicationYrmtYreview .do7docume...
Steve Brown
Mr.
Project Manager
City of Dubuque
50 West 13th Street
Dubuque
Iowa
52001
563- 589 -4270
563 - 589 -4205
sbrown@cityofdubuque.org
Steven Sampson Brown
04/09/2010
SEP Requested
($)
$0.00
$69,831.00
$0.00
$0.00
$0.00
$0.00
Totals $69,831.00
Other Funding Total Project
Sources ($) Budget
$0.00
$139,662.00
$0.00
$0.00
$0.00
$0.00
$139,662.00
$0.00
$209,493.00
$0.00
$0.00
$0.00
$0.00
$209,493.00
3 of 11 6/28/2010 2:56 PM
weourants
This project budget reflects the cost to comply with the Davis -Bacon Act, National
Environmental Policy Act, National Historic Preservation Act, and the Buy American Act.
Budget Attachments(CLICK BACK BUTTON TO USE)
SEP Sources of Other Funds
Source and Cash In -Kind
Type of Funds Value
Total ($) Amount
of In -kind + Cash
Value
Date Funds
Will Be
Secured
DRA Distribution $985,000.00 $0.00 $985,000.00 07/01/2010
- local
EcoSmart
Building LLC
$0.00 $25,000.00
Federal ARRA
funding to City $200,000.00 $0.00 $200,000.00
for CCHC
Federal cash
rebate for EE $58,657.00 $0.00 $58,657.00 10/31/2011
improvements
$58,657.00
Utility rebates $40,000.00 $0.00 $40,000.00 06/30/2011
estimated
No
https: // www. iowagrants. gov /getApplicationPrintPreview.do ?docume...
Yes
Budget
r
narrative.doc
Briefly explain any other funding sources,
whether funds are sufficienct to complete the
project, and your determination as to whether
the project will be cost - effective. Please attach
support letters from all sources of leverage.
Applicants must consider whether their projects
are eligible for a local utility rebate and note this
in the narrative.
This money is for the overall renovation of the
building and is not exclusively for the energy
management improvements. It would cover some
improvements but not to the level of energy
performance we would like to achieve.
$985,000.00
$25,000.00 06/15/2010 Funds for energy management improvement
modeling
$25,000.00
$200,000.00
$40,000.00
$1,308,657.00
SEP Project Information
Please enter same project title as named above under "Project Title ".
Project Name: Comprehensive Retrofit of 18th and Central Bldg
Project Site Address, City,
State, Zip and County(Site of 1805 Central Avenue
Physical Address Where Dubuque, IA 52001
Project is Taking Place, if
applicable. If multiple Dubuque County
places, please list all
locations):
Age of Building: 100
Is the Building Location in a
Historic District?
This money is intended for capital improvements for
the Crescent Community Health Center's portion of
05/01/2010 the 1805 Central Ave building and will help cover
some of the energy management improvements, but
will not allow for the achievement of the level of
energy performance desired for the project.
Rebate amount estimate based on estimated cost for
improvements by EcoSmart Building.
Final rebate amount can not yet be determined but is
estimated by EcoSmart Building
4 of 11 6/28/2010 2:56 PM
W e u
5 of 11
Does this project disturb Yes
ground?
SEP Scope of Work
Estimated Project Start
Date
Estimated Project
Completion Date:
Project Narrative /Scope of
Work: Description must
answer: WHO
Project Narrative /Scope of
Work: Description must
answer: WHAT
Project Narrative /Scope of
Work: Description must
answer: WHEN
Project Narrative /Scope of
Work: Description must
answer: WHERE
Project Narrative /Scope of
Work: Description must
answer: WHY
Project Narrative /Scope of
Work: Description must
answer: HOW
Describe the Projects Goals
and Objectives:
07/01/2010
naps:// w ww. iowagranis. govigeuippncationrrmtrrevlew .uo: uocume...
09/01/2011
The City of Dubuque is pleased to submit this application for funding from the Offic(
The City of Dubuque will hire contractors to do all installations of windows, doors, in
The City of Dubuque will comprehensively retrofit and remodel an old firestation that
Proposed project details:
Lighting system 3
Cree Lighting model LR24- 32SKA35 2x4 recessed static troffer. 43W LED lamp. (
Service Hot Water System 2
Indirect HWH from condensing boiler, 80 gal., 50 gaVhour at 90degF recovery. Effie
Solar thermal system
3 Panel Flat Plate Propylene Glycol Collection Systems
119 Gallon Double Wall, Double Coil Heat exchanger tank (boiler backup)
20 Gallon Drain Back Tank for the Propylene Glycol fluid
Pump and Piping Options TBD
HVAC System 3:
(4) Air handling units. (2) units /zones per floor. Geoexchange water -water heat purr
Envelope System 1
Highest performing thermal, air and moisture barrier.
Walls - R -35 (assembly) with R -14 c.i. and closed cell spray foam filling joist cavities
Roof - R-48 (assembly) with R -14 c.i. and closed cell spray foam filling 5" of joist ca
Slab - R -14 (assembly), $1.58/s.f. slab area
Agilewaves Monitoring — is a real -time utility grade monitoring system. Deployment
Either utility smart meter for water, gas and electric for building energy use, if there
Complete modeling details for the above improvements are included in the Life Cyc
The project will begin immediately with construction scheduled to begin in Decembei
All work will occur in or around the building located at 1805 Central Ave in downtown
This building has been vacant for many years due to significant water issues but the
The project will comprehensively address lighting, hot water heating, the building env
The project aims to comprehensively retrofit an unused municipal building with state
6/28/2010 2:56 PM
VV cuvi ttuw
Explain your status in
obtaining necessary
licenses and permits
Describe the Expected
Project Benefits to the
Community
Tasks and Performance Measures
Task
RFPs distributed
RFPs due
Design contract
awarded
Commence design
Schematic design
Design development 09/02/2010
Construction
documents
Initiate bidding
Award project by
City Council
Commence
construction
Deconstruction
Building envelope
MEP Rough In
Finish carpentry
work
FF & E installation
Substantially
complete
Final completion
Job Impact
Row
Jobs Created
Jobs Retained
Start Date Completion Performance Measures
Date
07/01/2010 07/01/2010 RFPs are made available and distributed to consultants
07/15/2010 07/15/2010 RFPs submitted to City Hall- Engineering Department by 2 pm
07/22/2010 07/22/2010 Prepared design contract is sent to consultant for execution
08/19/2010 08/19/2010 Consultant receives "Notice to Proceed" with design
08/19/2010 09/02/2010
11/04/2010
12/16/2010
01/13/2011
02/03/2011
02/03/2011
02/24/2011
05/26/2011
06/24/2011
07/29/2011
08/31/2011
https : / /www. iowagrants. gov /getApplicationPrintPreview.do ?docume...
The only permits necessary at this time are construction and building permits. Thes
The scope of work falls under a NEPA categorical exclusion and for a variety of rea
The project will provide numerous benefits to the community as it will give useful cor
11/04/2010
12/02/2010
12/16/2010
01/13/2011
02/03/2011
02/24/2011
05/26/2011
03/24/2011 06/23/2011
07/28/2011
07/22/2011
07/29/2011
08/31/2011
First stage of design commences and is completed with an owner
review of the 30% design plans
Second stage of design commences which considers changes
stated in the schematic design review. Review of 60% design plan
is approved.
Final stage of design includes changes state in design
development review. Includes owner review of the 90% plans and
specifications
Construction plans and specs are completed and prepared for City
Council approval to bid project. Plans and specs are distributed to
contractors.
Lowest bid is presented to the City Council for award of the
project
General Contractor prepares construction site and begins
construction according to the design plans and specs
Complete work according to plans and specifications
Complete work according to plans and specifications (payment =
15 %)
Complete work according to plans and specifications (payment =
60 %)
Complete work according to plans and specifications (payment =
25 %)
Deliver and install
Design consultant performs a final inspection and reviews any
remaining punchlist items
All pumchlist items are completed.
Narrative Information Regarding Jobs Created or Retained
Expected
Payment
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$31,424.00
$125,696.00
$52,373.00
$0.00
$0.00
$0.00
Total Hours Effective Date Duration in Months
11720 08/15/2010 12
6 of l l 6/28/2010 2:56 PM
WebGrants
If you would like to add
narrative information
regarding jobs created or
retained, please do so
here:
Summary of Projects
Electricity
Savings
(kWh)
If you would like to add
narrative information
regarding energy savings,
please do so here:
Hours were estimated as follows
Design phase 8/15 -12/15 (18 weeks)
Assumption: 4 FTE, 40hr /wk
2880 total hours
Construction phase 2/1 -8/1 (26 weeks)
Assumption 8.5 FTE, 40hr /wk
8840 total hours
https: / /www. iow agrants. gov /getApplicationPrintPreview. do ?docume...
Energy
Management
Improvement
Title
HVAC3 /Building
Envelope 1
Lighting System
3*
Service hot
water system 2 *
Building
Submetering and 19153.37 67343.24 168.8 $3,122.40 $30,000.00 9.61 25 Yes
Control System
Solar Thermal
System
Electric Natural Other Annual Cost Net Estimated Simple Useful
Demand Gas Fuel Savings Cost ($) Payback Life
Reduction Savings Savings ($IYr) (Yrs) (Yrs)
(kW) (Therms) (units)
40619.63 142818.61 4378.0 $6,621.00 $128,993.00 19.48 25 Yes
11717.8 41199.78 0.0 $1,910.00 $35,250.00 18.46 25 Yes
0.0 0.0 323.3 $277.00 $4,000.00 14.44 25 Yes
0.0 0.0 2500.0
71,490.80 251,361.63 7,370.10 0 $14,430.40 $209,493.00 66.49 120
Narrative Information Regarding Energy Savings
If using other fuel savings,
please specify unit type and
cost per unit.
SEP Readiness
If you choose No ", please explain why and whether there are plans for that item to be completed
All necessary funds other
than SEP resources have Yes
been secured
Explanation (if necessary):
Plans and specifications are
completed and Yes
documentation is attached
Explanation (if necessary):
Is this
project
cost
effective?
$2,500.00 $11,250.00 4.5 20 Yes
7 of 11 6/28/2010 2:56 PM
WebUrants https:// www. iowagrants. gov/ getApplicationPrintPreview .do ?docume...
Energy assessment or audit
is completed and Yes
documentation is attached
Explanation (if necessary):
Staffing and/or Contractors No
are in Place
Explanation (if necessary): Contractors will be hired nearer to the anticipated start of construction through the C
SEP Comprehensiveness
Briefly describe how this project encompasses a comprehensive approach to energy improvements. You may include past energy
projects completed by your entity as well as current energy plans.
Comprehensiveness The City of Dubuque is taking a comprehensive approach to energy improvements I
SEP Administrative Capability
Briefly describe why your organization has the ability or will have the ability to provide all of the required oversight reporting, and
accounting for timely and accurate reporting. Specifically address how you will meet weekly, monthly, and quarterly state and
federal reporting requirements. Additionally, address how your office will comply with the following federal laws affecting the Iowa
SEP funds: National Environmental Policy Act (NEPA), National Historic Preservation Act, Davis -Bacon Act, and Buy American
Act. Please attach resumes or other biographical information for project managers.
Administrative Dubuque has a strong record of meeting the reporting requirements for state and fel
Capability
Please upload ALL attachments as one pdf file.
Administrative
Capability
Attachments(CLICK
BACK BUTTON TO
USE)
StevenBrown resume.pdf
SEP Waste Stream
Prior to the expenditure of Federal funds to dispose of sanitary or hazardous waste, 0E1 is required to provide documentation to
U.S. Department of Energy demonstrating that an adequate disposal plan has been prepared for sanitary or hazardous waste
generated by the proposed activities.
Applicants are therefore required to submit information on the expected waste stream of the proposed project. Sanitary or
hazardous waste includes, but is not limited to, old light bulbs, lead ballasts, piping, roofing material, discarded equipment,
debris, asbestos, etc.
Applicants should:
• indicate if the proposed project will generate a waste stream.
• Describe the identified waste stream, if applicable.
• Describe the proposed methodology for waste handling and disposal. For example, how would mercury or sodium vapor lamps
be disposed of? How will potentially hazardous material (e.g. asbestos containing materials, PBC's, etc.) be handled and
disposed of?
Waste This project will generate a waste stream. The waste stream consists of standard bL
Stream
8of11 6/7R /20111 7•56PM
weourants
9 of 11
Please upload ALL attachments as one pdf file.
Any other Attachments
(CLICK BACK BUTTON TO ,r`;
USE)
https: / /www. iow agrants. gov /getAppl icationPrintPreview .do ?docume...
SEP National Historic Preservation Act
Exhibit C - National Historic Preservation Act (REQUIRED SHPO REVIEW°
I have completed Attachment B and Attachment C or D as applicable and this will be included as an attachment.
Download Attachment B here, fill out your form, scan and name your file and attach your Attachment B here.
Attachment B Preparer Checklist (CLICK BACK BUTTON TO USE)
Download Attachment C here, fill out your form, scan and name your file and attach your Attachment C here, if applicable.
Attachment C Exempt from SHPO Review, Project Determination (CLICK BACK BUTTON TO USE)
Download Attachment D here, fill out your form, scan and name your file and attach your Attachment D here, if applicable.
Attachment D Request for SHPO Comment on a Project (CLICK BACK BUTTON TO USE)
National Environmental Protection Act
By checking this box, the applicant certifies that its proposed project is categorically excluded from NEPA because it falls within
the categories described in Attachment E of this RFP and does not involve extraordinary circumstances" within the meaning of 10
C.F.R. Section 1021.410. All applicants are required to fill out Attachment E, if not categorically excluded in Attachment E
applicants are required to fill out Attachment F in addition to Attachment E.
1 certify that this proposed project is categorically excluded from NEPA Yes
Download Attachment E here, fill out your form, scan and name your file and attach your Attachment E here.
Attachment E NEPA Certification (CLICK BACK BUTTON TO USE)
Download Attachment F here, fill out your form, scan and name your file and attach your Attachment F here.
Attachment F NEPA Environmental Checklist(CLICK BACK BUTTON TO USE)
Yes
L
E,J
SEP Other
If there are other relevant details about the proposed project or applicant that have not been expressed elsewhere in the
application, please enter them here.
Other Because the iowagrants.gov website is responding with error messages whenever v
Attachment B (Preparer Checklist)
1) The structure, object, or building, associated with this project is less than forty five (45) years of age and
there are no ground disturbing activities.
If you checked box 1, please fill out the "Exempt from SHPO review" form (ATTACHMENT C). No further action is required — sign,
and submit this form to OEI. If box one is NOT checked, please continue to number2.
2) I am receiving Weatherization Assistance Program (WAP) funds.
If you checked box 2, please continue to box number 3. If you did not check box 2, please proceed to box 5.
3) All my project activities are included within Appendix A, either in sub - section A (exterior work), or /and
sub - section B (interior work), and I have no ground disturbing activities associated with my project. [See
pages 2 -3 of this document]
if you checked box number 3, please stop and fill out the "Exempt from SHPO review" form (ATTACHMENT C). No further action
is required — sign, and submit this form to OEI. If you did NOT check box 3, proceed to number 4.
4) A single work item, or numerous items, do not fit within the excluded activities specified in Appendix A, Yes
and /or I have ground disturbing activities. [See pages 4 -6 of this document].
6/28/2010 2:56 PM
Weblirants https:// www. iowagrants. gov/ getApplicationPrintPreview .do ?dacume...
If you checked box number 4, please fill out the "Request for SHPO Comment on a Project" form (ATTACHMENT D) along with all
the requested information, documentation, and project specifications for review.
5) I am receiving either State Energy Program (SEP) and /or Energy Efficiency Community Block Grant Yes
(EECBG) funds for my project.
If box 5 is checked, please continue to box number 6. If box 5 is not applicable, and you are sure box 2 is also not applicable, then
fill. out the "Request for SHPO Comment on a Project" form (ATTACHMENT D) along with all requested material and submit to
OEI for review.
6) My project is excluded from review because all my activities are included in Appendix B and I have no
ground disturbing activities. [See pages 4 -6 of this document].
If box 6 is checked, stop and fill out the "Exempt from SHPO review" form (ATTACHMENT C). No further action is required — sign,
and submit this form to OE1. If box 6 is NOT checked, please continue to number 7.
7) Not all my project activities for this project are excluded under Appendix B and /or I have ground Yes
disturbing activities associated with my project. [See pages 4 -6 of this document]
Preparer's Name: Steve
Brown
Date: 04/26/2010
Minority Impact Statement
Question # 1
1. The proposed grant
programs or policies could
have a disproportionate or No
unique POSITIVE IMPACT
on minority persons.
If YES, describe the positive
impact expected from this
project
Indicate the group(s)
positively impacted.
Question # 2
2. The proposed grant
project programs or policies
could have a No
disproportionate or unique
NEGATIVE IMPACT on
minority persons.
If YES, describe the
negative impact expected
from this project.
If YES, present the rationale
for the existence of the
proposed program or
policy.
If YES, provide evidence of
consultation with
representatives of the
minority groups impacted.
Indicate the group(s)
negatively impacted.
Question # 3
3. The proposed grant
project programs or policies
are NOT EXPECTED TO
HAVE A Yes
DISPROPORTIONATE OR
UNIQUE IMPACT on minority
persons.
If YES, present the rationale We have no reason to believe that an energy efficient building renovation project sul
for determining no impact.
10 of 11 6/28/2010 2:56 PM
ry cuvi aiiw
•
11 of 11
Certification
I hereby certify that the
information on this form is
complete and accurate, to
the best of my knowledge.
Name of Person Submitting
Certification.
Title of Person Submitting
Certification
SEP Attachments
Description
Yes
WiII Hoyer
Stimulus Coordinator
naps ://www.lowagants.govigetApplicationPrmtlleview.do?docume...
File Name
6/28/2010 2:56 PM