Mystique Community Ice Center: Floor Slab Void Filling, Lifting and Leveling Project - Acceptance of Public Improvement ProjectCity of Dubuque City Council Meeting Consent Items # 21. Copyrighted November 15, 2021 ITEM TITLE: Mystique Community Ice Center: Floor Slab Void Filling, Lifting and Leveling Project -Acceptance of Public Improvement Project SUMMARY: City Manager recommending acceptance of the construction contract for the Mystique Community Ice Center Floor Slab Void Filling, Lifting and Leveling Project, as completed by URETEK USA Inc., in the final contract amount of $96,760.76, which is a 40.2% increase from the original contract amount of $69,000.00. RESOLUTION Accepting the Mystique Community Ice Center Floor Slab Void Filling, Lifting and Leveling Project and authorizing the payment to the contractor SUGGESTED Suggested Disposition: Receive and File; Adopt Resolution(s) DISPOSITION: ATTACHMENTS: Description Mystique Floor Slab Void Filling and Leveling-MVM Memo Council Acceptance Memo Acceptance Resolution Uretek Council Accept Floor Plan Exhibit Type City Manager Memo Staff Memo Resolutions Supporting Documentation Supporting Documentation THE CITY DUOF B TEE Masterpiece on the Mississippi TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager SUBJECT: Mystique Community Ice Center Floor Slab Void Filling, Lifting and Leveling Project Acceptance of Public Improvement Project (CIP 3502890) DATE: November 9, 2021 Dubuque All -America City IN 2007.2012.2013 2017*2019 City Engineer Gus Psihoyos is recommending acceptance of the construction contract for the Mystique Community Ice Center Floor Slab Void Filling, Lifting and Leveling Project, as completed by URETEK USA Inc., in the final contract amount of $96,760.76, which is a 40.2% increase from the original contract amount of $69,000.00. The additional cost was based on the actual final quantity polyurethane foam injection beneath the floor slab. The original estimated quantity was 9,000 pounds and the final quantity of foam material injected beneath the floor slab was 12,680 pounds. I concur with the recommendation and respectfully request Mayor and City Council approval. v Mic ael C. Van Milligen MCVM:jh Attachment cc: Crenna Brumwell, City Attorney Cori Burbach, Assistant City Manager Gus Psihoyos, City Engineer Robert Schiesl, Assistant City Engineer THE C DUUB�QFE Masterpiece an the Mississippi TO: Michael C. Van Milligen, City Manager Gus Psihoyos, City Engineer FROM: Robert Schiesl, Assistant City Engineer DATE: November 9, 2021 SUBJECT: Mystique Community Ice Center Floor Slab Void Filling, Lifting and Leveling Project Acceptance of Public Improvement Project (CIP 3502890) INTRODUCTION Dubuque All -America City n 1x�u.�rvM:i�n zn' I 2007-2012.2013 2017*2019 The enclosed resolution provides for the acceptance of the construction contract for the Mystique Community Ice Center Floor Slab Void Filling, Lifting and Leveling Project. BACKGROUND The Mystique Community Ice Center was designed, developed, and built under a Development Agreement between and among DICE, the City, the Dubuque Racing Association (DRA), and Battlefield Dubuque, LLC which later transferred and assigned its interest to Northern Lights Hockey, LLC. The Agreement commenced October 30, 2009. The Center opened September 18, 2010. The building is owned by the City. The Ice Arena was constructed on property in close proximity to the Mississippi River, on less than favorable subsurface soil conditions. During the original design development for the Ice Center, the geotechnical soils report indicated substantial depths of loose fill sand and miscellaneous landfill materials discovered by the subsurface borings. The Ice Arena building structure was constructed on a deep foundation system, however the lower -level main floor was constructed as an unsupported slab -on -grade. Since initial construction, the foundation supported structure has displayed no signs of settlement or movement. However, the unsupported slab -on -grade lower level has developed significant differential settlement throughout the main floor. In November 2020, the City completed a full interior building scan of the Mystique Ice Center which indicated settlement in the range of zero to 4 plus inches throughout the main floor concrete slab. The differential settlement has caused operational issues with the ice rink, rotational movement of the stadium bleachers, movement in the unsupported interior CMU walls, and settlement of ice system mechanical equipment. In the spring and summer of 2021, additional ongoing settlement was observed. As a result, staff felt that it was important to limit and restrict occupancy the northeast portion of the facility while a ground penetrating radar (GPR) scan assessment of the lower- level main floor. The GPR scan results indicated that there were no major voids (greater the 1-foot or more) under the concrete floor slab. The GPR scan indicated possible voids up to 4" in various locations. Based on the increased frequency of additional observed settlement and the presence of minor voids under the main floor concrete slab, City staff and Mike Shimkus P.E., S.E. (WHKS) evaluated options for interim remediation options to slow down the floor slab settlement and allow for occupancy use until full remediation work can be performed. The recommended remediation approach utilized a 2-part expanding polyurethane foam which was injected beneath the slab to fill voids, while lifting and re -leveling the floor slab. The interior locations within the Ice Center where work was performed to as part of the Floor Slab Void Filling, Lifting and Leveling Project are shown as yellow highlighted areas on the attached floor plan exhibit provided. The City solicited proposals from specialty geotechnical contractors to complete the polyurethane foam injection beneath the floor slab. The bid proposals included an estimated 9,000 pounds of polyurethane foam to be used. The City received three (3) bid proposals and are summarized as follows: Contractor Name Total Bid URETEK USA Inc. $ 69,000 Keller North America $ 92,750 GeoStabilization International (GSI) $ 123,800 Mystique Community Ice Center Floor Slab Void Filling, Lifting and Leveling Project was awarded to URETEK USA Inc. DISCUSSION The Mystique Community Ice Center Floor Slab Void Filling, Lifting and Leveling Project was completed by URETEK USA Inc. of Tomball, Texas in the final contract amount of $96,760.76 which is a 40.2% increase from the original contract amount of $69,000.00. The additional cost was based on the actual final quantity polyurethane foam injection beneath the floor slab. The original estimated quantity was 9,000 pounds and the final quantity of foam material injected beneath the floor slab was 12,680 pounds. RECOMMENDATION I recommend that the City Council accept the public improvements and authorize the payment of the contract amount of $96,760.76 to URETEK USA Inc. for the Mystique Community Ice Center Floor Slab Void Filling, Lifting and Leveling Project. 2 BUDGETIMPACT The project cost summary for the Mystique Community Ice Center Floor Slab Void Filling, Lifting and Leveling Project is summarized below: Description Award Final Construction Contract - URETEK $ 69,000.00 $ 96,760.76 Total Construction Cost $ 69,000.00 $ 96,760.76 The proposed project funding is summarized as follows: CIP No. Fund Description Fund Amount 3502890 Mystique Settlement Remediation $ 96,760.76 Total Project Funding $ 96,760.76 REQUESTED ACTION The City Council is requested to adopt the attached resolution to accept the public improvements and to authorize the payment of the contract amount of $96,760.76 to URETEK USA Inc. for the Mystique Community Ice Center Floor Slab Void Filling, Lifting and Leveling Project. cc: Jenny Larson, Director of Finance and Budget Marie Ware, Leisure Services Manager Mike Shimkus, WHKS FAPROJECTS\Mystique Community Ice Center\Floor Void Lifting Leveling - 2021\Council & Staff Documents\Acceptance 3 Prepared by Robert Schiesl City of Dubuque Engineering 50 W. 13" St. Dubuque IA 52001 (563)589-4270 Return to Adrienne N. Breitfelder City Clerk City of Dubuque, 50 W. 1311 St. Dubuque, IA 52001 (563)589-4100 RESOLUTION NO. 396-21 ACCEPTING THE MYSTIQUE COMMUNITY ICE CENTER FLOOR SLAB VOID FILLING, LIFTING AND LEVELING PROJECT AND AUTHORIZING THE PAYMENT TO THE CONTRACTOR WHEREAS, the public improvement contract for the Mystique Community Ice Center Floor Slab Void Filling, Lifting and Leveling Project, (the Project) has been completed by the Contractor, URETEK USA Inc. of Tomball, Texas (Contractor), the City Engineer has examined the work and recommends that the Project be accepted; and WHEREAS, the final contract amount for the Project is $96,760.76; and WHEREAS, the Contractor has previously been paid $91,922.72, leaving a balance of $4,838.04; and WHEREAS, the City Council finds that the recommendation of the City Engineer should be accepted. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: Section 1. The recommendation of the City Engineer is approved, and the Project is hereby accepted. Section 2. The Finance Director is hereby directed to pay to the Contractor the balance of the retainage of $4,838.04 as provided in Iowa Code chapter 573, and to pay such retainage in accordance with the provisions of Iowa Code chapter 573 or Iowa Code chapter 26.13. Passed, approved and adopted this 15th day of November 2021. WI ae� Roy D. uol, Mayor Attest: A4c,'� /7 &&& Adrienne N. Breitfelder, City Clerk Prepared by Robert Schiesl City of Dubuque Engineering 50 W. 131h St. Dubuque, IA 52001 (563)589-4270 Return to Adrienne N. Breitfelder City Clerk City of Dubuque, 50 W. 13th St. Dubuque, IA 52001 (563)589-4100 CITY ENGINEER'S CERTIFICATE OF FINAL COMPLETION OF MYSTIQUE COMMUNITY ICE CENTER FLOOR SLAB VOID FILLING, LIFTING AND LEVELING PROJECT The undersigned City Engineer of the City of Dubuque, Iowa, hereby certifies that he has inspected the Mystique Community Ice Center Floor Slab Void Filling, Lifting and Leveling Project has been performed in compliance with the terms of the Public Improvement Contract, and that the total cost of the completed work is $96,760.76. Dated this 9th day of November 2021. Gus Psihoyos, City Engineer Filed in the office of the City Clerk on the 9th day of November 2021. h Adrienne N. Breitfelder, City Clerk F:\PROJECTS\Mystique Community Ice Center\Floor Void Lifting Leveling - 2021\Council & Staff Documents\Acceptance City of Dubuque - Engineering Department City Council Final Payment Form PAYMENT NO: COUNCIL FINAL °ROJECT NAME: Mystique Ice Center Floor Slab Void Filling, Lifting and Leveling CIP 3502890 CONTRACTOR: URETEK USA Inc. ADDRESS: 13900 Humble Road CITY, STATE, ZIP: Tomball, Texas 77375 AWARDED CONTRACT AMOUNT: CONTRACT RECONCILIATION: $ FINAL CONTRACT AMOUNT: $ THE CITY OF DUB E Masterpiece on the Mississippi $69,000.00 FINAL COST ACCEPTANCE 27,760.76 96,760.76 40.23% DATE: November 15, 2021 LINE CONTRACT TOTAL TO -DATE CURRENT PAY PERIOD FINAL NO. BID ITEM DESCRIPTION QUANTITY UNIT UNIT COST QUANTITY AMOUNT QUANTITY AMOUNT QUANTITY AMOUNT 1 MOBILIZATION 1.0 LS $4,000.00 1.00 $ 4,000.00 $ - 1.0 $ 4,000.00 2 POLYURETHANE MATERIAL 9,000.00 LBS $7.00 12,680.108 $ 88,760.76 $ - 12,680.108 $ 88,760.76 3 GPR- UTILITY LOCATES 1.0 LS $2,000.00 1.00 $ 2,000.00 $ - 1.0 $ 2,000.00 4 DCP TESTING 4.0 EA $500.00 4.00 $ 2,000.00 $ - 4.0 $ 2,000.00 BASE BID AMOUNT EARNED: S 86,760.76 LINE DESCRIPTION -CHANGE ORDER /EXTRA WORK ITEMS CONTRACT PREVIOUS TO -DATE CURRENT PAY PERIOD TOTAL TO -DATE NO. QUANTITY UNIT UNIT COST QUANTITY AMOUNT QUANTITY AMOUNT QUANTITY AMOUNT $ - $ - 0.00 $ - $ - $ - 0.00 $ - $ - $ - 0.00 $ - FINAL PROJECT COST SUMMARY CERTIFICATE OF THE CITY MANAGER I hereby certify that the above statement shows in detail the correct amount of all work required to complete the above improvement. APPROVED: Michael Van Milligan, City Manager City of Dubuque, Iowa FINAL CHANGE ORDER AMOUNT EARNED: FINAL TOTAL CONTRACT AMOUNT EARNED: $ 96,760.76 AWARDED CONTRACT AMOUNT: 1 $69,000.00 BID ITEM(S) OVER / UNDER RECONCILIATION: $ 27,760.76 TOTAL CONTRACT CHANGE ORDER(S): I $ - TOTAL PUBLIC IMPROVEMENT CONSTRUCTION COST: $96,760.76 CERTIFICATE OF THE CITY ENGINEER I hereby certify that the above statement shows in detail the correct amount of all work required to complete the above improvement. APPROVED: Gus Psihoyos, City Engineer City of Dubuque, Iowa CERTIFICATE OF THE CONTRACTOR The undersigned, URETEK USA Inc. contractor for the above public improvement, does hereby accept the above "Total Due Contractor", as full settlement for all costs and claims for said puplic improvement construction project. CONTRACTOR: URETEK USA Inc. DATE: BY: Edward Hibbard TITLE: Senior Vice President o, d /9 o� / MEN WOME 0 0 0 0 VENDING FIRE EXIT i CORRIDOR hUI 4 CONNECTION FOR FUTURE RINK T I I � STOR. t jLOCKER' li VISITING I� ROOM TEAM LOCKER LL L_, rTTTTT ~FIRE EXIT I I I I I COMMUNITY FIRE LOBBY LOCKERS & E rr BENCHES T I I I I O ICJ lu I N I N r I r I s � ----------------- RISER 5TR44TURE E OFFICE CONTROL III COUNTER OFFICE VICE OFFICE jif FIRE EXIT FIRE EVENT EXIT LOBBY I I I UP STOR. LOCKERRoom FIRE FIRE EXIT enkr°ne EXIT ELEV. I 1 EQUIP. � KNO BOX LOCA TION CONCRETE ENTRY PLAZA O \ i llllll� MECH. � o STOR. H5 TEAM Fi REFS. 5TOR. LOCKER 1 F1 I I II ___________________________________ __ RISER STRUCTURE �r DJIsL 5,000 SEATS ' NHL SIZE RINK 55' x 200' J41L IF RISER STRUCTURE I I I I I I I I I I I I I I I I I I LOCKER LOCKER ROOM ROOM I 2 I I 5 I I I � I I II C • 0 _______________ RISER STRUCTURE____ I STOR. I I' I STOR. SHOWER I li LOCKER ROOM 4 j MECH. � J LOWER LEVEL "Qte FIR"�?7E PL�4N SCALE • T T I RErSU ACER EVIL I r I Ir ------------ ICE EQUIP. RISER STRUCTURE ELECTRICAL ROOM FUTURE STORAGE OOOLING AREA TO-R �r LOCATION J L I I -1 F I I I I I I I I I I i I I RISER I STRUCTURE I I J L I I I I I I I I I I I I I L I FIRE EXIT FIRE EXIT �.,ImI -1 F I I I I I I iJ I i A R15ER STRUCTURE ---------------- 0 'COACH COACH 0 li I� SKATES 0 TEAM TEAM LOCKER CONDITIONING Il, r g INFIRM. FIRE EXIT 1 PROJECT INFORMATION: OCCUPANCY ......... Ad (ASSEMBLY FOR VIEWING INDOOR SPORTING EVENTS WITH SPECTATOR SEATING) CONSTRUCTION ....... TYPE 11-B GROSS AREA........ 63,340 SQ.FT. 1ST FLOOR ........ 28,965 SQ.FT. MEZZANINE ALLOWABLE AREA.... UNLIMITED (PER IBC SECTION 507.3 WITH EXCEPTION 2.) FIRE PROTECTION .... FIRE SPRINKLER SYSTEM THROUGHOUT BUILDING HEIGHT: 30'-0" TYPICAL EAVE HEIGHT 34'-6"+/- PEAK HEIGHT 36'-8" PARAPET HEIGHT AT NORTH EXIT IMPERVIOUS PAVED AREA: PARKING LOT 63,317 SO. FT. SIDEWALLKS 12,900 FIRE ACCESS DRIVE 4,176 TOTAL: 80,393 SO. FT. SITE AREA: 6.61 ACRES MORE OR LESS (287.932 SQ. FT.) FROST FOOTING (TYP) LARRISON & ASSOCIATES ARCHITECTS Quad Cities • Des Moines Date: 12/15/200q Designed by: Drawn by: Checked by: Revisions: \ U O E O U U Co co C o CT L ti 06 Q Project No. 10525 Sheet Content: LOWER LEVEL FIRE CODE PLAN Sheet No. FC-101 Of