Provisionally Accredited Levee Progress ReportMasterpiece on the Mississippi Dubuque kilkd All- Amedca City 1 2007 TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager SUBJECT: Dubuque Levee and Floodwall Certification - PAL Progress Report #2 DATE: July 13, 2010 Planning Services Manager Laura Carstens is transmitting the July 2010 Provisionally Accredited Levee (PAL) Progress Report to FEMA for certification of the Dubuque levee and floodwall system along the Mississippi River. This progress report is the first of bi- monthly updates to the One -Year PAL Progress Report submitted in May 2010. MCVM:jh Attachment cc: Barry Lindahl, City Attorney Cindy Steinhauser, Assistant City Manager Laura Carstens, Planning Services Manager Michael C. Van Milligen Masterpiece on the Mississippi TO: Michael Van Milligen, City Manager FROM: Laura Carstens, Planning Services Manager - >c' SUBJECT: Dubuque Levee and Floodwall Certification — PAL Progress Report #2 DATE: July 2, 2010 Dubuque herl AN- America CRY t r 2007 INTRODUCTION This memorandum transmits the July 2010 PAL Progress Report to FEMA for certification of the Dubuque levee and floodwall system along the Mississippi River. This progress report is the first of bi- monthly updates to the One -Year PAL Progress Report submitted in May, 2010. FEMA requested bi- monthly updates as part of the City of Dubuque's Provisionally Accredited Levee (PAL) Agreement with FEMA. DISCUSSION The City of Dubuque PAL agreement expires on May 17, 2011. The City of Dubuque must certify the Dubuque levee system complies with federal regulations concerning provision of 100 -year flood protection for the community. This certification must be submitted before May 17, 2011 and be signed by a professional engineer. We plan to have a member of the City's Engineering Department provide this certification. City staff is reviewing the June 2010 Engineering Technical Review Report prepared by the U.S. Army Corps of Engineers (USACE) on the Dubuque Levee System. Overall, our levee system appears to meet or exceed most standards according to the report. The USACE identified areas that require further analysis. City staff will evaluate the results of the USACE report and additional engineering analyses to complete certification of the Dubuque flood protection system. City staff is scheduled to meet with you to discuss the findings of the USACE report on July 29, 2010. REQUESTED ACTION The requested action is to transmit the July 2010 PAL Progress Report to the City Council as an informational item. No Council action is required. Attachments cc: Don Vogt, Public Works Director Gus Psihoyos, City Engineer John Klostermann, Streets & Sewers Supervisor Bob Schiesl, Assistant City Engineer Deron Muehring, Civil Engineer Kyle Kritz, Associate Planner Planning Services Department City Hall 50 West 13th Street Dubuque, IA 52001 -4864 (563) 589 -4210 phone (563) 589 -4271 fax (563) 690 -6678 TDD planning@cityofdubuque.org Melissa Janssen, Chief Risk Analysis Branch FEMA Region VII 9221 Ward Parkway Ste 300 Kansas City MO 64114 RE: July 2010 PAL Progress Report Dear Ms. Janssen: This letter transmits the July 2010 PAL Progress Report for certification of the Dubuque levee and floodwall system along the Mississippi River. This progress report is the first of bi- monthly updates to the One -Year PAL Progress Report submitted in May, 2010. You requested bi- monthly updates as part of the City of Dubuque's PAL Agreement with FEMA. The City of Dubuque is reviewing the June 2010 Engineering Technical Review Report prepared by the U.S. Army Corps of Engineers (USACE) on the Dubuque Levee System. Overall, our levee system appears to meet or exceed most standards according to the report. The USACE identified areas that require further analysis. The City of Dubuque will evaluate the results of the USACE report and additional engineering analyses to complete certification of the Dubuque flood protection system. Please feel contact me if you have any questions or need additional information. Laura Carstens Planning Services Manager Enclosure Masterpiece on the Mississippi cc: Dawn Kinsey, Community Outreach Specialist, FEMA Region VII Michael Van Milligen, City Manager Don Vogt, Public Works Director Gus Psihoyos, City Engineer John Klostermann, Streets & Sewers Supervisor Bob Schiesl, Assistant City Engineer Deron Muehring, Civil Engineer Kyle Kritz, Associate Planner Service People Integrity Responsibility Innovation Teamwork Dubuque had Apr 1 1111 F 2007 July 2, 2010 PAL Progress Report July 2010 Map Modernization Quarterly Report Provisionally Accredited Levee Progress Report 7/2/2010 FEMA I. Levee Identification PAL Scenario: B IPAL Period: Start Date: May 17, 2009 End Date: May 17, 2011 Progress Report due date 12 months after 91st day of PAL Period. Progress Report Due Date: 17- Jul -10 FEMA Received Date: FEMA Region: VII State/Territory: IA County: Dubuque County Community: City of Dubuque Levee Owner Name: City of Dubuque Contact information: Laura Carstens Project Officer (FEMA): Dawn Kinsey Levee Owner Agency: same Phone #: 563.589.4210 Phone #: 816.283.7055 I II. Status Report: Report By Certification Requirement (44 CFR 65.10) Requirement #: 1 Description: Demonstrate that all levees provide the minimum required freeboard [44 CFR 65.10(b)(1)]. Completion Dates and Status: N/A due to USACE Certification? no 30- Jun -10 :Planned 13- Jun -10 : Actual 100% : Estimated % Work Complete Summary: (Significant milestones, problem identification, etc; Reason for slippage of scheduled objectives are not met; If no activity during period, just ': state No Activity'.) The June 2010 USACE engineering technical review report concluded that the Dubuque Levee system meets the minimum required freeboard. Requirement #: 2 Description: Demonstrate that all openings have been provided with appropriate closure • devices that are a structural part of the system [44 CFR 65.10(b)(2)]. Completion Dates and Status: NIA due to USACE Certification? no 30- Jun -10 :Planned 13- Jun -10 : Actual 90% : Estimated % Work Complete Summa • (Significant milestones, problem identification, etc; Reason for slippage of schedule if objectives are not met; If no activity during period, just �': state' No Activity.) The June 2010 USACE report concluded that all openings in the Dubuque Levee system have appropriate closure devices. The report recommended operation and maintenance items for the City to address. Page 1 of 25 PAL Progress Report July 2010 Map Modernization Quarterly Report 7/2/2010 Demonstrate through engineering analyses that no appreciable erosion of Requirement #: 3 Description: the levee embankment can be expected during the base flood [44 CFR 65.10(b)(3)]. Completion Dates and Status: N/A due to USACE Certification? no 30 Jun - 10 :Planned 13- Jun -10 : Actual 100% ' Estimated % Work Complete Summa • (Significant milestones, problem identification, etc; Reason for slippage of schedule if objectives are not met; If no activity during period, just �': state No Activit?.) The June 2010 USACE report concluded that there is no appreciable erosion of the levee embankment expected during the base flood. Requirement #: 4 Description: Evaluate through engineering analyses the levee embankment stability [44 CFR 65.10(b)(4)]. Completion Dates and Status: N/A due to USACE Certification? 30 Sep - 10 :Planned : Actual 50% ' Estimated % Work Complete Summary: (Significant milestones, problem identification, etc; Reason for slippage of schedule if objectives are not met; If no activity during period, just � state'No Activity') The June 2010 USACE report included a limited structural analysis of the levee embankment stability. City staff are reviewing the report's findings, and will discuss the findings with the City Manager on July 29, 2010. Assess the potential and magnitude of future losses of freeboard as a result Requirement #: 5 Description: of levee settlement and demonstrate that freeboard will be maintained [44 CFR 65.10(b)(5)]. Completion Dates and Status: N/A due to USACE Certification? no 30 Jun - 10 :Planned 13- Jun -10 : Actual 100% ' Estimated % Work Complete Summary: (Significant milestones, problem identification, etc; Reason for slippage of schedule if objectives are not met; If no activity during period, just ry: state "No Activity") . The June 2010 USACE report concluded that settlement is not an issue and the freeboard will be maintained. Page 2 of 25 PAL Progress Report July 2010 Map Modernization Quarterly Report 7/2/2010 Analyze the interior drainage; identify the source(s) of such flooding, the Requirement #: 6 Description: extent of the flooded area, and, if the average depth is greater than one foot, the water - surface elevation(s) of the base flood [44 CFR 65.10(b)(6)]. Completion Dates and Status: N/A due to USACE Certification? no 30 Sep - 10 :Planned : Actual 50% : Estimated % Work Complete Summa (Significant milestones, problem identification, etc; Reason for slippage of schedule if objectives are not met If no activity during period, just �': state No Activity') The June 2010 UJSACE report included an interior drainage analysis. This analysis will be provided to the engineering firm hired by the City to provide a technical analysis of interior drainage for compliance with NF1P. Requirement #: 7 Description: Adopt and submit an official operation manual [44 CFR 65.10(c)]. Completion Dates and Status: 5- May -10 :Planned 5- May -10 : Actual 100% : Estimated % Work Complete Summa . (Significant milestones, problem identification, etc; Reason for slippage of schedule if objectives are not met; If no activity during period, just �' • state • No Act ) The Dubuque City Council officially adopted the July 2002 Operation and Maintenance Manual for the Dubuque levee and floodwall system on 05/03/10 for submittal to FEMA. Requirement #: 8 Description: Adopt and submit an official maintenance plan [44 CFR 65.10(d)]. Completion Dates and Status: 5- May -10 :Planned 5- May -10 : Actual 100% : Estimated % Work Complete (Significant milestones, problem identification, etc; Reason for slippage of schedule if objectives are not met; If no activity during period, just Summary: state 'No Activity') The Dubuque City Council officially adopted the July 2002 Operation and Maintenance Manual for the Dubuque levee and floodwall system on 05/03/10 for submittal to FEMA. Page 3 of 25 PAL Progress Report July 2010 Map Modernization Quarterly Report If the USACE is certifying the Levee, Requirement # 10 may be used in lieu of Requirements # 1 -6 & 9 Page 4 of 25 7/2/2010 Requirement #: 9 Description: Submit as -built plans of the levee certified by a Professional Engineer [44 CFR 65.10(e)]. Completion Dates and Status: 5- May -10 :Planned 5- May -10 : Actual 100% : Estimated % Work Complete Summary: (Significant milestones, problem identification, etc; Reason for slippage of schedule if objectives are not met; If no activity during period, just ': state • No Activity The City of Dubuque submitted the as -built plans of the Dubuque levee and floodwall system certified by a Professional Engineer, and plans for the City improvements made to the levee and floodwall system, to FEMA. Requirement #: 10 Description: Submit certification and supporting documentation that the levee provides protection from the base flood [44 CFR 65.10(e)]. Completion Dates and Status: N/A due to non -USACE Certification? no 17- Apr -11 :Planned : Actual : Estimated % Work 50/0 Complete Summa . (Significant milestones, problem identification, etc; Reason for slippage of schedule if objectives are not met; If no activity during period, just r3' state No A ctivity ' .) The City of Dubuque will evaluate the results of the June 2010 USACE report and additional engineering analyses to complete this step. PAL Progress Report July 2010 Map Modernization Quarterly Report 7/2/2010 IV. Overall Levee Certification Progress: Estimated Total Progress Completed: Schedule: Levee Certication Proceeding on Schedule: How Much? 50% Select Units If certification progress is not proceeding as scheduled, please describe problems or issues with the potential to impact completion date or overall ability to certify levee. (Attach documentation as required) V. Progress Code: Green (On track for complete 65.10 submission as planned) Yellow (Problems/issues potential to impact 65.10 submission schedule) Red* (Complete 65.10 package submission will likely not meet deadline) * FEMA may require a meeting to discuss inadequate process and determine the next course of action (continue with collection of 65.10 requirements, proceed to de- accredit the levee, or other) VI. Additional Comments: Page 5 of 25