TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: Dubuque Levee and Floodwall Certification - PAL Progress Report #2
DATE: July 13, 2010
Planning Services Manager Laura Carstens is transmitting the July 2010 Provisionally
Accredited Levee (PAL) Progress Report to FEMA for certification of the Dubuque levee
and floodwall system along the Mississippi River. This progress report is the first of
bi- monthly updates to the One -Year PAL Progress Report submitted in May 2010.
MCVM:jh
Attachment
cc: Barry Lindahl, City Attorney
Cindy Steinhauser, Assistant City Manager
Laura Carstens, Planning Services Manager
Michael C. Van Milligen
Masterpiece on the Mississippi
TO: Michael Van Milligen, City Manager
FROM: Laura Carstens, Planning Services Manager - >c'
SUBJECT: Dubuque Levee and Floodwall Certification — PAL Progress Report #2
DATE: July 2, 2010
Dubuque
herl
AN- America CRY
t r
2007
INTRODUCTION
This memorandum transmits the July 2010 PAL Progress Report to FEMA for certification of
the Dubuque levee and floodwall system along the Mississippi River. This progress report is
the first of bi- monthly updates to the One -Year PAL Progress Report submitted in May,
2010. FEMA requested bi- monthly updates as part of the City of Dubuque's Provisionally
Accredited Levee (PAL) Agreement with FEMA.
DISCUSSION
The City of Dubuque PAL agreement expires on May 17, 2011. The City of Dubuque must
certify the Dubuque levee system complies with federal regulations concerning provision of
100 -year flood protection for the community. This certification must be submitted before
May 17, 2011 and be signed by a professional engineer. We plan to have a member of the
City's Engineering Department provide this certification.
City staff is reviewing the June 2010 Engineering Technical Review Report prepared by the
U.S. Army Corps of Engineers (USACE) on the Dubuque Levee System. Overall, our levee
system appears to meet or exceed most standards according to the report. The USACE
identified areas that require further analysis. City staff will evaluate the results of the
USACE report and additional engineering analyses to complete certification of the Dubuque
flood protection system. City staff is scheduled to meet with you to discuss the findings of
the USACE report on July 29, 2010.
REQUESTED ACTION
The requested action is to transmit the July 2010 PAL Progress Report to the City Council
as an informational item. No Council action is required.
Attachments
cc: Don Vogt, Public Works Director
Gus Psihoyos, City Engineer
John Klostermann, Streets & Sewers Supervisor
Bob Schiesl, Assistant City Engineer
Deron Muehring, Civil Engineer
Kyle Kritz, Associate Planner
Planning Services Department
City Hall
50 West 13th Street
Dubuque, IA 52001 -4864
(563) 589 -4210 phone
(563) 589 -4271 fax
(563) 690 -6678 TDD
planning@cityofdubuque.org
Melissa Janssen, Chief
Risk Analysis Branch
FEMA Region VII
9221 Ward Parkway Ste 300
Kansas City MO 64114
RE: July 2010 PAL Progress Report
Dear Ms. Janssen:
This letter transmits the July 2010 PAL Progress Report for certification of the Dubuque levee
and floodwall system along the Mississippi River. This progress report is the first of bi- monthly
updates to the One -Year PAL Progress Report submitted in May, 2010. You requested bi-
monthly updates as part of the City of Dubuque's PAL Agreement with FEMA.
The City of Dubuque is reviewing the June 2010 Engineering Technical Review Report
prepared by the U.S. Army Corps of Engineers (USACE) on the Dubuque Levee System.
Overall, our levee system appears to meet or exceed most standards according to the report.
The USACE identified areas that require further analysis. The City of Dubuque will evaluate the
results of the USACE report and additional engineering analyses to complete certification of the
Dubuque flood protection system.
Please feel contact me if you have any questions or need additional information.
Laura Carstens
Planning Services Manager
Enclosure
Masterpiece on the Mississippi
cc: Dawn Kinsey, Community Outreach Specialist, FEMA Region VII
Michael Van Milligen, City Manager
Don Vogt, Public Works Director
Gus Psihoyos, City Engineer
John Klostermann, Streets & Sewers Supervisor
Bob Schiesl, Assistant City Engineer
Deron Muehring, Civil Engineer
Kyle Kritz, Associate Planner
Service People Integrity Responsibility Innovation Teamwork
Dubuque
had
Apr
1 1111 F
2007
July 2, 2010
PAL Progress Report July 2010 Map Modernization Quarterly Report
Provisionally Accredited Levee Progress Report
7/2/2010
FEMA
I. Levee Identification
PAL Scenario:
B
IPAL Period: Start Date: May 17, 2009 End Date: May 17, 2011
Progress Report due date 12 months after 91st day of PAL Period.
Progress Report Due Date: 17- Jul -10 FEMA Received Date:
FEMA Region: VII
State/Territory: IA
County: Dubuque County
Community: City of Dubuque
Levee Owner Name: City of Dubuque
Contact information: Laura Carstens
Project Officer (FEMA): Dawn Kinsey
Levee Owner Agency: same
Phone #: 563.589.4210
Phone #: 816.283.7055
I II. Status Report: Report By Certification Requirement (44 CFR 65.10)
Requirement #: 1 Description: Demonstrate that all levees provide the minimum required freeboard [44
CFR 65.10(b)(1)].
Completion Dates and Status: N/A due to USACE Certification? no
30- Jun -10 :Planned
13- Jun -10 : Actual
100% : Estimated % Work
Complete
Summary: (Significant milestones, problem identification, etc; Reason for slippage of scheduled objectives are not met; If no activity during period, just
': state No Activity'.)
The June 2010 USACE engineering technical review report concluded that the Dubuque Levee system meets
the minimum required freeboard.
Requirement #: 2 Description: Demonstrate that all openings have been provided with appropriate closure
• devices that are a structural part of the system [44 CFR 65.10(b)(2)].
Completion Dates and Status:
NIA due to USACE Certification? no
30- Jun -10 :Planned
13- Jun -10 : Actual
90% : Estimated % Work
Complete
Summa • (Significant milestones, problem identification, etc; Reason for slippage of schedule if objectives are not met; If no activity during period, just
�': state' No Activity.)
The June 2010 USACE report concluded that all openings in the Dubuque Levee system have appropriate
closure devices. The report recommended operation and maintenance items for the City to address.
Page 1 of 25
PAL Progress Report July 2010
Map Modernization Quarterly Report
7/2/2010
Demonstrate through engineering analyses that no appreciable erosion of
Requirement #: 3 Description: the levee embankment can be expected during the base flood [44 CFR
65.10(b)(3)].
Completion Dates and Status:
N/A due to USACE Certification? no
30 Jun - 10 :Planned
13- Jun -10 : Actual
100% ' Estimated % Work
Complete
Summa • (Significant milestones, problem identification, etc; Reason for slippage of schedule if objectives are not met; If no activity during period, just
�': state No Activit?.)
The June 2010 USACE report concluded that there is no appreciable erosion of the levee embankment
expected during the base flood.
Requirement #: 4 Description: Evaluate through engineering analyses the levee embankment stability [44
CFR 65.10(b)(4)].
Completion Dates and Status:
N/A due to USACE Certification?
30 Sep - 10 :Planned
: Actual
50% ' Estimated % Work
Complete
Summary:
(Significant milestones, problem identification, etc; Reason for slippage of schedule if objectives are not met; If no activity during period, just
� state'No Activity')
The June 2010 USACE report included a limited structural analysis of the levee embankment stability. City staff
are reviewing the report's findings, and will discuss the findings with the City Manager on July 29, 2010.
Assess the potential and magnitude of future losses of freeboard as a result
Requirement #: 5 Description: of levee settlement and demonstrate that freeboard will be maintained [44
CFR 65.10(b)(5)].
Completion Dates and Status:
N/A due to USACE Certification? no
30 Jun - 10 :Planned
13- Jun -10 : Actual
100% ' Estimated % Work
Complete
Summary: (Significant milestones, problem identification, etc; Reason for slippage of schedule if objectives are not met; If no activity during period, just
ry: state "No Activity") .
The June 2010 USACE report concluded that settlement is not an issue and the freeboard will be maintained.
Page 2 of 25
PAL Progress Report July 2010
Map Modernization Quarterly Report
7/2/2010
Analyze the interior drainage; identify the source(s) of such flooding, the
Requirement #: 6 Description: extent of the flooded area, and, if the average depth is greater than one
foot, the water - surface elevation(s) of the base flood [44 CFR 65.10(b)(6)].
Completion Dates and Status:
N/A due to USACE Certification? no
30 Sep - 10 :Planned
: Actual
50% : Estimated % Work
Complete
Summa (Significant milestones, problem identification, etc; Reason for slippage of schedule if objectives are not met If no activity during period, just
�': state No Activity')
The June 2010 UJSACE report included an interior drainage analysis. This analysis will be provided to the
engineering firm hired by the City to provide a technical analysis of interior drainage for compliance with NF1P.
Requirement #: 7 Description: Adopt and submit an official operation manual [44 CFR 65.10(c)].
Completion Dates and Status:
5- May -10 :Planned
5- May -10 : Actual
100% : Estimated % Work
Complete
Summa . (Significant milestones, problem identification, etc; Reason for slippage of schedule if objectives are not met; If no activity during period, just
�' • state • No Act )
The Dubuque City Council officially adopted the July 2002 Operation and Maintenance Manual for the Dubuque
levee and floodwall system on 05/03/10 for submittal to FEMA.
Requirement #: 8 Description: Adopt and submit an official maintenance plan [44 CFR 65.10(d)].
Completion Dates and Status:
5- May -10 :Planned
5- May -10 : Actual
100% : Estimated % Work
Complete
(Significant milestones, problem identification, etc; Reason for slippage of schedule if objectives are not met; If no activity during period, just
Summary: state 'No Activity')
The Dubuque City Council officially adopted the July 2002 Operation and Maintenance Manual for the Dubuque
levee and floodwall system on 05/03/10 for submittal to FEMA.
Page 3 of 25
PAL Progress Report July 2010
Map Modernization Quarterly Report
If the USACE is certifying the Levee, Requirement # 10 may be used in lieu of Requirements # 1 -6 & 9
Page 4 of 25
7/2/2010
Requirement #: 9 Description: Submit as -built plans of the levee certified by a Professional Engineer [44
CFR 65.10(e)].
Completion Dates and Status:
5- May -10 :Planned
5- May -10 : Actual
100% : Estimated % Work
Complete
Summary:
(Significant milestones, problem identification, etc; Reason for slippage of schedule if objectives are not met; If no activity during period, just
': state • No Activity
The City of Dubuque submitted the as -built plans of the Dubuque levee and floodwall system certified by a
Professional Engineer, and plans for the City improvements made to the levee and floodwall system, to FEMA.
Requirement #: 10 Description: Submit certification and supporting documentation that the levee provides
protection from the base flood [44 CFR 65.10(e)].
Completion Dates and Status:
N/A due to non -USACE Certification?
no
17- Apr -11 :Planned
: Actual
: Estimated % Work
50/0 Complete
Summa . (Significant milestones, problem identification, etc; Reason for slippage of schedule if objectives are not met; If no activity during period, just
r3' state No A ctivity ' .)
The City of Dubuque will evaluate the results of the June 2010 USACE report and additional engineering
analyses to complete this step.
PAL Progress Report July 2010
Map Modernization Quarterly Report
7/2/2010
IV. Overall Levee Certification Progress:
Estimated Total Progress Completed:
Schedule:
Levee Certication Proceeding on Schedule:
How Much?
50%
Select Units
If certification progress is not proceeding as scheduled, please describe problems or issues with
the potential to impact completion date or overall ability to certify levee.
(Attach documentation as required)
V. Progress Code:
Green (On track for complete 65.10 submission as planned)
Yellow (Problems/issues potential to impact 65.10 submission schedule)
Red* (Complete 65.10 package submission will likely not meet deadline)
* FEMA may require a meeting to discuss inadequate process and determine the next course of
action (continue with collection of 65.10 requirements, proceed to de- accredit the levee, or other)
VI. Additional Comments:
Page 5 of 25