Eagle Valley Sub San Sewer ExtMEMORANDUM July 29, 2003 TO: FROM: SUBJECT: The Honorable Mayor and City Council Members Michael C. Van Milligen, City Manager Eagle Valley Subdivision Sanitary Sewer Extension Project Assistant City Engineer Gus Psihoyos recommends initiation of the bidding process for the Eagle Valley Subdivision Sanitary Sewer Extension Project, and further recommends that a public hearing be set for August 18, 2003. I concur with the recommendation and respectfully request Mayor and City Council approval. Michael C. Van Milligen MCVM/jh Attachment cc: Barry Lindahl, Corporation Counsel Cindy Steinhauser, Assistant City Manager Gus Psihoyos, Assistant City Engineer Mike Koch, Public Works Director TO: FROM: SUBJECT: CITY OF DUBUQUE, IOWA MEMORANDUM July 29, 2003 Michael C. Van Milligen, City Manager Gus Psihoyos, Assistant City Engineer Eagle Valley Subdivision Sanitary Sewer Extension Project INTRODUCTION The enclosed resolutions authorize the bidding procedure for the Eagle Valley Subdivision Sanitary Sewer Extension Project. BACKGROUND On July 15, 2003, the developer, Fondell Excavating, requested the City's financial assistance and cooperation in several facets of its 20-acre, owner- occupied affordable housing subdivision along Roosevelt Road. Consistent with the Affordable Housing Task Force report, staff recommends that the City finance the cost of sanitary sewer service in the same manner as it financed the Harvest View development. This project would extend approximately 4,400 feet of 8-inch ductile pipe to service the 87 lots in this residential, owner-occupied development. In addition, laterals will be extended to all lots to service the individual properties within this development. DISCUSSION The project will be funded through the Sanitary Sewer Extension Funds. A connection fee would be established for each lot and would be payable to the City of Dubuque by the developer, successors, or assignees upon the sale of each lot. The schedule for the project is as follows: Advertisement for Bids Notice of Public Hearing Receipt of Bids Public Hearing Award of Contract Completion Augu~ 5,2003 August8,2003 August12,2003 August18,2003 August18,2003 November1,2004 RECOMMENDATION It is recommended that the City Council establish the date of the public hearing and to authorize the City Clerk to advertise for proposals. BUDGET IMPACT The estimate for the project is: Construction Contract $308,780.00 Contingency 30,870.00 Total Project Cost $339,658.00 The project will be funded from capital improvement programs for extensions to new developments, with a current balance of $570,415. ACTION REQUESTED The City Council is requested to establish the date of the public hearing and to authorize the City Clerk to advertise for proposals through the adoption of the enclosed resolutions. MAK/vjd cc: Michael A. Koch, Public Works Director RESOLUTION NO. 263-03 PRELIMINARY APPROVAL OF PLANS AND SPECIFICATIONS NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: That the proposed plans, specifications, form of contract and estimated cost for the Eagle Valley Subdivision Sanitary Sewer Extension Project in the estimated amount $339,658.00 are hereby approved and ordered filed in the office of the City Clerk for public inspection. Passed, adopted and approved this 4th day of August, 2003. Terrance M. Duggan, Mayor Attest: Jeanne F. Schneider, CMC, City Clerk 4th dayof August ,2003. l~errance M. Dugg~, Mayor RESOLUTION NO. 264-03 FIXING DATE OF HEARING ON PLANS AND SPECIFICATIONS Whereas, the City Council of the City of Dubuque, Iowa has given its preliminary approval on the proposed plans, specifications, and form of contract and placed same on file in the office of the City Clerk for public inspection of the Eagle Valley Subdivision Sanitary Sewer Extension Project. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: That a public hearing will be held on the 18th day of August, 2003, at 6:30 p.m. in the Public Library Auditorium at which time interested persons may appear and be heard for or against the proposed plans and specifications, form of contract and cost of said improvement, and the City Clerk be and is hereby directed to cause a notice of time and place of such hearing to be published in a newspaper having general circulation in the City of Dubuque, Iowa, which notice shall be not less than four days nor more than twenty days pdor to the day fixed for its consideration. At the hearing, any interested person may appear and file objections to the proposed plans, specifications, contract, or estimated cost of the improvement. Passed, adopted and approved this 4th day of August, 2003. Terrance M. Duggan, Mayor Attest: Jeanne F. Schneider, CMC, City Clerk RESOLUTION NO. 265-03 ORDERING BIDS NOW THEREFORE, BE IT RESOLVED BY THE COUNCIL OF THE CITY OF DUBUQUE, iOWA: That the Eagle Valley Subdivision Sanitary Sewer Extension Project is hereby ordered to be advertised for bids for construction. BE IT FURTHER RESOLVED, that the amount of the security to accompany each bid shall be in an amount which shall conform to the provisions of the Notice to Bidders hereby approved as a part of the plans and specifications heretofore adopted. That the City Clerk is hereby directed to advertise for bids for the construction of the improvements herein provided, to be published in a newspaper having general circulation in the City of Dubuque, Iowa, which notice shall not be less than four days nor more than forty-five days prior to the receipt of said bids at 2:00 p.m. on the 12th day of August, 2003. Bids shall be opened and read by the City Clerk at said time and will be submitted to the Council for final action at 6:30 p.m. on the 18th day of August, 2003. Passed, adopted and approved this 4th day of August, 2003. Terrance M. Duggan, Mayor Attest: Jeanne F. Schneider, CMC, City Clerk NOTICE OF HEARING ON PLANS AND SPECIFICATIONS Notice of public hearing on proposed plans and specifications, proposed form of contract and estimate of cost for the Eagle Valley Subdivision Sanitary Sewer Extension Project: Extension of approximately 4,400 feet of 8-inch ductile pipe to service 87 lots in this development, This project will also include the installation of 29 manholes and sanitary sewer service laterals to each lot. NOTICE IS HEREBY GIVEN: The City Council of Dubuque, Iowa will hold a public hearing on the proposed plans, specifications, form of contract and estimate of cost for the Eagle Valley Subdivision Sanitary Sewer Extension Project in accordance with the provisions of Chapter 384, City Code of Iowa, at 6:30 p.m., on the 18th day of August, 2003, in the Public Library Auditorium, 360 West 11th Street, in Dubuque, Iowa. Said proposed plans, specifications, form of contract and estimate of cost are now on file in the office of the City Clerk. At said hearing any interested person may appear and file objections thereto or to the cost of the improvements. Any visual or hearing-impaired persons needing special assistance or persons with special accessibility needs should contact the City Clerk's office at (563) 589-4120 or TDD at (563) 690-6678 at least 48 hours prior to the meeting. Published by order of the City Council given on the ., 2003. day of Jeanne F. Schneider, CMC, City Clerk RESOLUTION NO. RESOLUTION ADOPTING PLANS AND SPECIFICATIONS Whereas, on the 30th day of July, 2003, plans, specifications, form of contract and estimated cost were filed with the City Clerk of Dubuque, Iowa for the Eagle Valley Subdivision Sanitary Sewer Extension Project. Whereas, notice of hearing on plans, specifications, form of contract, and estimated cost was published as required by law. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: That the said plans, specifications, form of contract and estimated cost are hereby approved as the plans, specifications, form of contract and estimated cost for said improvements for said project. Passed, adopted and approved this day of ,2003. Terrance M. Duggan, Mayor Attest: Jeanne F. Schneider, CMC, City Clerk