October 25 - 29
Architect to review schematic design
with structural and heating, ventilating,
and air conditioning consultants and
consider structural and mechanical
concepts.
Architect to review schematic design
with electrical consultant and consider
electrical and lighting concepts
November 4
Approval of selection of special con-
sultants by Five Flags Center Committee
November 8 - 19
Architect to review schematic design
with acoustical, theatre, and ice rink
consultants
Architect initial meeting with manage-
ment consultant
Architect and representatives of Five
Flags Center Committee to visit arenas
in Twin Cities and Duluth area. (Tenta-
tively set for November 17 and 18)
Acoustical, theatre, and ice rink con-
sultants to submit concept recommenda-
tions to Architect
November 24
Architect to review schematic design and
recommendations of special consultants
with management consultant
December 2
Progress report by Architect to Five
Flags Center Committee, and review of
user group requirements
December 2 - 16
Architect and consultant prepare analysis
of schematic design
December 16
Presentation of Schematic Design Analysis
by Architect and management consultant
Glercn North Allen Madison, yllsconsin wsa 53705 boa-23a-7626
ld✓.-w u'V L\\I."a...i..�ba:w u.i r-i •'- a';l t
Ronald Gene 0owen aia
FIVE FLAGS CIVIC CENTER Henry Kanazawa aia
Frederick E. Zimmermann aia
DUBUQUE, IOWA Rolland H. Williamson
TENTATIVE TIME SCHEDULE
CONVENTIONAL DESIGN - BID
November 4, 1976
City of Dubuque award Architectural -
Engineering contract for Civic Center
Analyze schematic design to verify
potential and intended use and operation
thru assistance of a management con-
sultant
Review schematic design analysis with
Commission
December 16, 1976
Evaluate construction systems and
relative costs thru comprehensive
value engineering
Develop design development documents
including sketches, models, plans,
details and outline specifications
Preparation of a quantity cost estimate.
Submit design development documents
and cost estimate to Commission for
review and approval
February 1, 1977
Preparation of contract documents
including plans, details, specifications,
and alternatives
Completion of documents and reviews
by appropriate City of Dubuque agencies
May 12, 1977
Documents out for bid to contractors
June 1977
Take bids, evaluation, and awards of
contracts
September 1978
Completion of construction
October 1.978
Owner occupancy