Catfish Creek Pumping Station Generator Project Bid AwardMasterpiece on the Mississippi TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager SUBJECT: Bids for the Catfish Creek Generator Project DATE: August 9, 2010 Sealed bids were received for the Catfish Creek Generator Project. Water Pollution Control Plant Manager Jonathan Brown recommends award of the contract to the low bidder, A &G Electric, in the amount of $92,100. Standby generators have been added at two of the three major pumping stations serving the sanitary sewer collection system of the City of Dubuque. The generator at Cedar Street was included in the major rebuild of the station from 2005 -2007 and the Terminal Street Station generator was added during the electrical upgrades in 2008- 2009. This project will complete the installation of standby power at the major pumping stations. The small stations are served by two portable generators and the ability to use a diesel powered portable pump. By completing this series of projects, the City of Dubuque will greatly reduce the risk of sanitary sewer overflows caused by power outages. I concur with the recommendation and respectfully request Mayor and City Council approval. Michael C. Van Milligen MCVM:jh Attachment cc: Barry Lindahl, City Attorney Cindy Steinhauser, Assistant City Manager Jonathan R. Brown, Water Pollution Control Plant Manager Dubuque AM-America city 2007 Masterpiece on the Mississippi August 9, 2010 INTRODUCTION BACKGROUND DISCUSSION Michael C. Van Milligen, City Manager TO: FROM: Jonathan R. Brown, WPCP Manager SUBJECT: MEMORANDUM in Bids for the Catfish Creek Generator Project The purpose of this memo is to transmit to you the results of the bids for the Catfish Creek Generator Project and to request the authorization to negotiate and execute the contract with the low bidder. The City Council authorized advertising bids for this project at their July 6, 2010 council meeting, with a bid opening date of August 6, 2010. There were seven bids received for the project. The bids are as follows: Firm Lump Sum Bid A &G Electric $92,100.00 Giese Sheet Metal $92,789.00 Morse Electric $97,700.00 Midwest Electric $97,922.00 Precision Drive and Control $104,000.00 Westphal Electric $106,880.00 Faith Technologies $113,678.00 The engineer's estimate for the project was for $120,000.00. The low bid was submitted by A &G Electric of Dubuque in the amount of $92,100.00. This project will be funded from CIP # 7102149 in the fy11 budget. Standby Generators have been added at two of the three major pumping stations serving the sanitary sewer collection system of the City of Dubuque. The generator at Cedar Street was included in the major rebuild of the station from 2005 -2007 and the Terminal Street Station generator was added during the electrical upgrades in 2008- 2009. This project will complete the installation of standby power at the major pumping stations. The smaller stations are served by two portable generators and the ability to use a diesel powered portable pump. By completing this series of projects the City of Dubuque will greatly reduce the risk of sanitary sewer overflows caused by power outages. ACTION TO BE TAKEN I respectfully request that the City Council authorize the City Manager to negotiate and execute the contract with A &G Electric Dubuque, Iowa for the bid amount of $92,100.00. Attachments: cc: Jenny Larson, Budget Director RESOLUTION NO. 323-10 Whereas, sealed proposals have been submitted by contractors for the Catfish Creek Pumping Station Generator Project pursuant to Resolution No. 231 -10 and notice to bidders published in a newspaper published in the City of Dubuque, Iowa on the 9 day of July, 2010. Whereas, said sealed proposals were opened and read on the 6th day of August, 2010, and it has been determined that the bid of A &G Electric, of Dubuque, Iowa, in the amount of $92,100.00 was the lowest bid for the furnishings of all labor and materials and performing the work as provided for the plans and specification. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: That the contract for the above improvements be awarded to A &G Electric, and the Manager be and is hereby directed to execute a contract on behalf of the City of Dubuque for the complete performance of the work. Attest: AWARDING CONSTRUCTION CONTRACT FOR THE CATFISH CREEK PUMPING STATION GENERATOR PROJECT BE IT FURTHER RESOLVED: That upon the signing of said contract and the approval of the contractor's bond, the City Treasurer is authorized and instructed to return the bid deposits of the unsuccessful bidders. Passed, approved and adopted this 16th eanne F. Schneider, CMC, City Clerk ay of August , 2010. Roy D. ol, Mayor