Iowa 32 Hike Bike Trail Phase 2 Project_Covering OveragesMasterpiece on the Mississippi TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager SUBJECT: Covering Overages for Iowa 32 Hike /Bike Trail Phase 2 DATE: August 31, 2010 Dubuque Itittri AN- AmedcaCity 11111 ! 2007 The City of Dubuque received a REAP grant in 2008 for $200,000 for the Iowa 32 Hike /Bike Trail Phase 2 Project. The original construction project of $202,027 was approved by Council in late July 2009. The project, through a series of four change orders most relating to drainage and additional engineering costs, is now estimated to be $291,333. Leisure Services Manager Marie Ware recommends City Council approval of the reallocation of money from the Eagle Point Park Overlook Sidewalk CIP and utilizing savings from the Pamela /Ramona Joint Repair Project and the Library HVAC Maintenance Project to cover the additional $91,333 needed for this project. I concur with the recommendation and respectfully request Mayor and City Council approval. MCVM:jh Attachment cc: Barry Lindahl, City Attorney Cindy Steinhauser, Assistant City Manager Marie L. Ware, Leisure Services Manager /1 3- --- --..,_____ Midael C. Van Milligen Masterpiece on the Mississippi TO: FROM: SUBJECT: DATE: Michael C. Van Milligen, City Manager Marie L. Ware, Leisure Services Manager Covering overages for Iowa 32 Hike /Bike Trail Phase 2 August 30, 2010 Dubuque AI- Amedca City 1 ' 2007 INTRODUCTION The purpose of this memorandum is to provide the account changes to accommodate the overages for the Iowa 32 Hike /Bike Trail Phase 2 project that runs from JFK to Plaza Drive. BACKGROUND The City of Dubuque received a REAP grant in 2008 for $200,000 for the project. The original construction project of $202,027 was approved by Council in late July of 2009. This small overage was to come from savings by other FY 2010 Park Division CIP's. The project through a series of four change orders most relating to drainage and additional engineering costs is now estimated to be $291,333. This is $91,333 over the REAP grant. DISCUSSION Jenny Larson and I have worked on the following plan: FY 10 Pamela /Ramona Joint Repair savings $39,980 (not enough $ to cover entire project, will rebudget) Library HVAC Maintenance $17,275 (not needed as it is now a new system) $57,255 FY 10 project brought forward to FY 11 CIP 3501453 Eagle Point Park Overlook Sidewalk I have walked the Eagle Point overlook sidewalk. The sidewalk has not declined as fast as was predicted. The recommendation would be to leave the remainder ($30,446) in the CIP project line 3501453 and expend it to create a plan and cost estimate for the future sidewalk project for Eagle Point. RECOMMENDATION Jenny and 1 recommend the above plan to cover the overage. ACTION REQUESTED I request approval of recommendation. cc: Laura Carstens Gus Psihoyos Jon Dienst Jenny Larson Bob Fritsch $34,078 $91,333 Masterpiece on the Mississippi TO: FROM: SUBJECT: DATE: cc: Laura Carstens Gus Psihoyos Jon Dienst Jenny Larson Bob Fritsch Michael C. Van Milligen, City Manager Marie L. Ware, Leisure Services Manage Covering overages for Iowa 32 Hike /Bike Trail Phase 3 August 30, 2010 DISCUSSION Jenny Larson and I have now worked on the following plan: RECOMMENDATION Jenny and I recommend the above plan to cover the overage. ACTION REQUESTED I request approval of recommendation. Dubuque blerd A1- America City 1 1 r 2007 INTRODUCTION The purpose of this memorandum is to provide the account changes to accommodate the overages for the Iowa 32 Hike /Bike Trail Phase 3 project that runs from Plaza Drive to Asbury Road and then on to Pennsylvania. BACKGROUND In January of 2009, the City Council approved engineering services of Buessing and Associates for Phase 2 and Phase 3. Phase 2 engineering was budgeted as a part of the REAP grant received in 2008. Phase 3 engineering was initiated prior to any grant approvals because of possible funding through stimulus money. A memo from Gil Spence on January 20, 2009 outlined the funding for Phase 3 engineering recommended at $25,955 would come from CIP project #1021871 — BMX Bike Track. Stimulus funding was not received for the project. In researching this project recently it was found the CIP project #1021871 outlined in the 1 -20 -09 memo was used in FY 09 for Partitions for Restrooms (CIP #1011062) $20,699, Park Maint Headquarters Improv (CIP #1011471) $1,447, Skate Park - Rebuild Ramps (CIP #1011874) $3,672, and Miller Riverview Rip Rap (CIP #1001170) $4,074 instead of this project. The City of Dubuque received a REAP grant in 2009 for $200,000 for the Iowa 32 Hike /Bike Trail Phase 3 in the fall of 2009. Expenditures for engineering prior to receiving the grant are not grant eligible. $15,076 has been spent that was not REAP grant eligible. FY 10 project brought forward to FY 11 CIP 3501453 Eagle Point Park Overlook Sidewalk $15,076 I have walked the Eagle Point overlook sidewalk. The sidewalk has not declined as fast as was predicted. The recommendation would be to leave the remainder ($30,446) in the CIP #3501453 and expend it to create a plan and cost estimate for the future sidewalk project for Eagle Point. Any further expenses for engineering for Phase 3 will be REAP grant eligible.