Eagle Valley San Sewer Ext ProMEMORANDUM August13,2003 TO: FROM: SUBJECT: The Honorable Mayor and City Council Members Michael C. Van Milligen, City Manager Eagle Valley Subdivision Sanitary Sewer Extension Project Sealed bids were received for the Eagle Valley Subdivision Sanitary Sewer Extension Project. Assistant City Engineer Gus Psihoyos recommends award of the contract to the Iow bidder, Fondell Excavating, in the amount of $278,426, which is 9.8% under the engineer's estimate. I concur with the recommendation and respectfully request Mayor and City Council approval. Michael C. Van Milligen MCVM/jh Attachment cc: Barry Lindahl, Corporation Counsel Cindy Steinhauser, Assistant City Manager Gus Psihoyos, Assistant City Engineer Mike Koch, Public Works Director CITY OF DUBUQUE, IOWA MEMORANDUM August 12, 2003 TO: FROM: SUBJECT: Michael C. Van Milligen, City Manager Gus Psihoyos, Assistant City Engineer Eagle Valley Subdivision Sanitary Sewer Extension Project INTRODUCTION The enclosed resolution provides for the award of the Eagle Valley Subdivision Sanitary Sewer Extension Project. DISCUSSION The Eagle Valley Subdivision Sanitary Sewer Extension Project would extend 4,400 feet of 8-inch ductile pipe to service 87 lots in the 20-acre owner-occupied, affordable housing Eagle Valley Subdivision along Roosevelt Road. Consistent with the Affordable Housing Task force report, staff recommended that the City finance the cost of sanitary sewer service within the subdivision. The developer will repay the City as each lot is sold, with a five-year balloon payment. Assistance is only provided for owner-occupied housing. Sealed bids were received on the project on August 12, 2003. Fondell Excavating of Dubuque, Iowa, submitted the Iow bid in the amount of $278,426.00. This amount is 9.8% under the engineer's estimate. A summary of the bids received is as follows: Fondell Excavating McClain Excavating Company, Inc. McDermott Excavating Drew Cook & Sons Excavating, Inc. $278,426.00 281,862.00 287,955.80 415,346.00 RECOMMENDATION I recommend that the contract be awarded to Fondell Excavating in the amount of $278,426.00. BUDGET IMPACT The summary of the project costs is as follows: Construction Contra,ct Contingency Total Project Estimate 8308,780.00 30,870.00 $339,650.00 Bid Award $278,426.00 30,870.00 $309,296.00 The project will be funded from the capital improvement programs for extensions to new developments, with a current balance of $570,415. ACTION TO BE TAKEN The City Council is requested to adopt the attached resolution awarding the Eagle Valley Subdivision Sanitary Sewer Extension Project to Fondell Excavating. Prepared by Deron Muehring, City Engineer cc: Michael A, Koch, Public Works Director RESOLUTION NO. 291-03 AWARDING CONTRACT Whereas, sealed proposals have been submitted by contractors for the Eagle Valley Subdivision Sanitary Sewer Extension Project pursuant to Resolution No. 265-03 and notice to bidders published in a newspaper published in the City of Dubuque, Iowa on the 5th day of August, 2003. Whereas, said sealed proposals were opened and read on the 12th day of August, 2003, and it has been determined that the bid of Fondell Excavating of Dubuque, Iowa, in the amount of $278,426.00 was the lowest bid for the furnishings of all labor and materials and performing the work as provided for in the plans and specifications. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: That the contract for the above improvement be awarded to Fondell Excavating and the Manager be and is hereby directed to execute a contract on behalf of the City of Dubuque for the complete performance of the work. BE IT FURTHER RESOLVED: That upon the signing of said contract and the approval of the contractor's bond, the City Treasurer is authorized and instructed to return the bid deposits of the unsuccessful bidders. Passed, approved and adopted this 18th day of August, 2003. Patricia A. Cline, Mayor Pro-Tem Attest: Jeanne F. Schneider, CMC, City Clerk RESOLUTION NO. 290-03 RESOLUTION ADOPTING PLANS AND SPECIFICATIONS Whereas, on the 30t~ day of July, 2003, plans, specifications, form of contract and estimated cost were filed with the City Clerk of Dubuque, Iowa for the Eagle Valley Subdivision Sanitary Sewer Extension Project. Whereas, notice of headng on plans, specifications, form of contract, and estimated cost was published as required by law. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: That the said plans, specifications, form of contract and estimated cost are hereby approved as the plans, specifications, form of contract and estimated cost for said improvements for said project. Passed, adopted and approved this 18th day of Auqusf. ,2003, Patricia A. Cline, Mayor Pro-Tem Attest: Jeanne F. Schneider, CMC, City Clerk EAGLE VALLEY SUBDIVISION SITE IMPROVEMENTS - SANITARY SEWER BID TABULATION 12-Aug-03 NO. DESCRIPTION QUANTITY IMIsCELLANE°Us I 1 ~'DIP 2142 LF 2 A*Lok Manholes 17 EA Engineer's Estimate UNIT TOTAL PRICE PRICE $40.00 $85,680,00 $1,900.00 $32,300.00 BIDDER BIDDER BIDDER BIDDER Fondell Excavating, Inc McClain Excavating McDermott Excavating UNIT TOTAL UNIT TOTAL UNIT TOTAL PRICE PRICE PRICE PRICE PRICE PRICE $37.00 $79,254.00 $35.50 $76,041.00 $39.60 $84,823.20 $1,510,00 $27,523.00 $1,975.00 $33,575,00 . $1,550.00 $26,350.00 Drew Cook Excavating UNIT TOTAL PRICE PRICE $55.00 $117,810.00 $2,000.00 $34,000,00 3 4" Latarals 55 EA $900.00 $49,500.00 $869.00 4 6" Laterals 2 EA $975.00 $1,950.00 $1,120.00 5 Performance Bond& Payment Bond 1 LS $4,180.00 $4,180.00 $3.137.00 SubTotal I $173,610.00 ~ SubTotal SANITARY SEWER ~ 8" DIP 2006 LF $40.00 A-Lok Manholes 11 EA $1,900.00 4" Laterals 31 EA $900.00 6" Laterals 2 EA $975.00 performance Bond & Payment Bond ILS $4,180.00 % Over/Under(-) Sub Total Total $47,795.00 $870.00 $47,850.00 $840.00 $46,200.00 $2,240.00 $925.00 $1,850.00 $950.00 $1,900.00 $3,137.00 $2,500.00 $2,500.00 $2,38§.00 I $159,949.00 ~ Sub Total ~ Sub Total $70,210.00 $33.50 $67,201.00 $39.60 $16,784.00 $1,775.00 $19,525.00 $1,550.00 $28,939.00 $870.00 $23.970.00 $840.00 $1,000.00 $55,000.00 $2,600.00 $4,000.00 $2,389.00 . $10,500.00 $10,500.00 $80,240.00 $35.00 $20,900,00 $1,524.00 $27,900.00 $860.00 $4,180.00 $2,324.00 $135,170.00 ~ Sub Total $2,240.00 $925.00 $1,850.00 $950.00 $1,900.00 $2,324.00 $4,500.00 $4,500.00 $1,866.00 $1,866.00 1__$118,477.oo ~ Sub Total ~ Sub Total I $126,203.60 $2,000.00 $4,000,00 $9,200.00 $9,200.00 Sub Total ~ -9,83% -8.72% -6.74% 34.51%