Old Hwy 20 Water Main II finalMEMORANDUM September 3, 2003 TO: FROM: SUBJECT: The Honorable Mayor and City Council Members Michael C. Van Miiligen, City Manager Final Acceptance of the Old U.S. Highway 20 Water Main Phase II Extension Project Water Department Manager Bob Green ~s recommending acceptance of the Old U.S. Highway 20 Water Main Extension Project, as completed by Drew Cook & Sons Excavating, in the final contract amount of $94,121.38, which is $16,517.88 over the odginal bid pdce due to the need to bore under Highway 20. The additional money needed to support this project is available within the approved CIP. It is also recommended that City Council authorize the final payment to Drew Cook & Sons Excavating in the amount of $4,706.07. I concur with the recommendation and respectfully request Mayor and City Council approval. Michael C. Van Milligen MCVM/jh Attachment cc: Barry Lindahl, Corporation Counsel Cindy Steinhauser, Assistant City Manager Bob Green, Water Department Manager CITY OF DUBUQUE, Iowa MEMORANDUM Augu~ 25,2003 TO: Michael C. Van Milligen, City Manager FROM: Bob Green, Water Department Manager._.~_~- SUBJECT: Final Acceptance of the Old U. S. Highway 20 Water Main Phase II Extension Project INTRODUCTION: This memorandum is recommending final acceptance of the Old U. S. Highway 20 Water Main Extension at a final cost of $94,121.38. DISCUSSION: On October 21, 2002 the City of Dubuque Water Department entered into an agreement with Drew Cook & Sons Excavating for the installation of approximately 1,700 feet of 12 inch ductile iron water main along the north side of Old U. S. Highway 20 from intersection of Radford Road and proceeding west on Highway 20. This improvement will supply water service to residences in this area and is a part of a multiphase project in providing a second water main feed line to the Westside Industrial Park. The original bid pdce for the project was in the amount of $77,603.50. Because of the need to bore under Highway 20 created 3 change orders resulting in additional expense in the amount of $16, 517.88, making the total project cost $94,121.38. The additional monies needed to su~)port this project is available within this approved C.I.P. ACTION REQUESTED: Staff and I.are requesting your approval and recommehdation to the City Council that they adopt the two resolutions, one approving the project and one approving the final cost of $94,121.38 and authorizing the final payment to Drew Cook & Sons Excavating in the a_mount of $4,706.07 in accordance with the State of Iowa Statute. Preparer: Robert M. Green, Water Department Manager 1902 Hawthorne Street 589-4291 RESOLUTION NO. 315-03 ACCEPTING IMPROVEMENT Whereas, the Contract for the Old U. S. Highway 20 Water Main Phase II Extension Improvement Project has been completed and the City's Consultant I. I. W. Engineers and Surveyors of Dubuque, Iowa recommend acceptance of the project. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: Section 1. That the recommendation of the City Manager be approved and that said improvement be accepted. Passed, approved and adopted this 15t~ day of September, 2003. Terrance M. Duggan, Mayor Jeanne F. Schneider, City Clerk cc: File Preparer: Robert M. Green, Water Department Manager 1902 Hawthorne Street 589-4291 RESOLUTION NO.316-03 FINAL ESTIMATE Whereas, the contract for the Old U. S. Highway 20 Water Main Phase II Extension Improvement Project has been completed and the City has submitted the final estimate showing the cost thereof. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: Section 1. That the cost of said improvement is hereby determined to be $94,121.38 dollars. Section 2. That the final payment of $4,706.07 be paid to Drew Cook & Sons Excavating in accordance with the State Statute from funds in the Water Department's FY '03 CIP Budget. Passed, approved and adopted this 15th day of September, 2003. Terrance M. Duggan, Mayor Attest: Jeanne F. Schneider, City Clerk