Loading...
Carter Road Detention BasinMEMORANDUM TO: FROM: SUBJECT: October 1, 2003 The Honorable Mayor and City Council Members Michael C. Van Milligen, City Manager Carter Road Detention Basin Project Award The Carter Road Detention Basin will be the first improvement to be constructed in the Bee Branch Drainage Basin and the second improvement in the City's Master Plan. The first improvement in the Master Plan was the enlargement of the Northwest Arterial Detention Basin between Pennsylvania Avenue and Asbury Read. The project is mainly comprised of an earthen dam that will be approximately 350 feet long and 40 feet high with 3:1 (horizontal: vertical) side slopes. The principal outlet will be a 15-inch culvert and a 24-inch gated culvert. The high flow outlet is a 48-inch diameter dser pipe that is approximately 37-feet high. A 350-foot long asphalt access road will provide access to the outlet structure for operation and maintenance needs. In addition, the project includes the reconstruction of the sanitary sewer under the proposed dam. The proposed sanitary sewer will be constructed in such a manner to prevent future sewer maintenance needs. The plans and specifications are currently under review by the DNR. In mid-September, the DNR informed Engineering that the review of the Carter Road Detention Basin should be completed in 45 days, approximately around the end of October. Although Veenstra & Kimm communicated with the DNR throughout the design process to ensure that the DNR would approve a permit, the possibility exists that the DNR might require modifications to the plans. As a result, the contract execution should be delayed until the DNR issues a permit for the project. One of the conditions of each bid was to extend the period that the bid is valid: from 30 to 60 days, until the end of November. Sealed bids were received for the Carter Road Detention Basin Project. Public Works Director Mike Koch recommends award of the contract to the Iow bidder, Tschiggfrie Excavating Co., in the amount of $590,316.35, which is 14.15% under the engineer's estimate. In addition, he recommends that the City delay the contract execution until the DNR permits are issued for the project. I concur with the recommendation and respectfully request Mayor and City Council approval. Michael C. Van Milligen MCVM/jh Attachment cc: Barry Lindahl, Corporation Counsel Cindy Steinhauser, Assistant City Manager Gus Psihoyos, Assistant City Engineer Mike Koch, Public Works Director TO: FROM: SUBJECT: CITY OF DUBUQUE, IOWA MEMORANDUM October 1,2003 Michael C. Van Milligen, City Manager Gus Psihoyos, Assistant City Engineer~_,9. ~ Carter Road Detention Basin Project Award INTRODUCTION The enclosed resolution provides for the award of the Carter Road Detention Basin Project. BACKGROUND The Carter Road Detention Basin will be the first improvement to be constructed in the Bee Branch Drainage Basin and the second improvement in the City's Master Plan. (The first improvement in the Master Plan was the enlargement of the Northwest Arterial Detention Basin between Pennsylvania Avenue and Asbury Road.) The project is mainly comprised of an earthen dam that will be approximately 350 feet long and 40 feet high with 3:1 (horizontal: vertical) side slopes. The principal outlet will be a 15-inch culvert and a 24-inch gated culvert. The high flow outlet is a 48-inch diameter riser pipe that is approximately 37-feet high. A 350-foot long asphalt access road will provide access to the outlet structure for operation and maintenance needs. In addition, the project includes the reconstruction of the sanitary sewer under the proposed dam. The proposed sanitary sewer will be constructed in such a manner to prevent future sewer maintenance needs. In May of 2003, the City Council approved the selection of Veenstra & Kimm, Inc. to provide engineering and design services for the Carter Road Detention Basin. In July of 2003 the City Council approved the outlet structure design for the project. When the project was initiated by the City Council in August, the Council endorsed an "out of order" review request that was submitted along with the plans and specifications to the Iowa Department of Natural Resources (DNR). DISCUSSION Sealed bids were received on September 30, 2003. Tschiggfrie Excavating Co. of Dubuque, Iowa submitted the Iow bid in the amount of $590,316.35. This amount is 14.15% under the engineer's estimate of $687,590.00. A summary of the bids received is as follows: Tschiggfrie Excavating Co. WC Stewart Construction Fischer Excavating Horsfield Construction Portzen Construction '$590,316.35 $649,644.08 $709,058.88 $717,663.00 $849,796.47 The plans and specifications are currently under review by the DNR. In mid-September, the DNR informed Engineering that the review of the Carter Road Detention Basin should be completed in 45 days, approximately around the end of October. Although Veenstra & Kimm communicated with the DNR throughout the design process to ensure that the DNR would approve a permit, the possibility exists that the DNR might require modifications to the plans. As a result, the contract execution should be delayed until the DNR issues a permit for the project. One of the conditions of each bid was to extend the period that the bid is valid: from thirty (30) to sixty (60) days, until the end of November. Veenstra & Kimm recommends that the City award the contract in the amount of $590,316.35 to the Iow bidder, Tschiggfrie Excavating Co. In addition, they recommend that the City delay the contract execution until DNR permits are issued for the project. RECOMMENDATION I respectfully request that the City Council award the contract for the Carter Road Detention Basin project, contingent on the issuance of DNR permits, to Tschiggfrie Excavating Co. in the amount of $590,316.35 BUDGET IMPACT The summary of the project costs is as follows: Estimate Bid Award Construction Contract Contingency Engineering Property & Easement Acquisitions Potential Maximum Bonus 687,590.00 68,759.00 132,000.00 150,000.00 67,500.00 590,316.35 68,759.00 132,000.00 150,000.00 67,500.00 Total Project Estimate $1,105,849.00 $1,008,575.35 The project will be funded from the storm sewer construction fund from the Fiscal Year 2004 appropriation of $875,000. The remaining amount of $135,575.35 will be funded from the repdoritization of the Windsor Avenue Storm sewer project ($142,000) and Terminal Street storm sewer project ($72,000) which engineering will recommend to be re-budgeted. ACTION TO BE TAKEN The City Council is requested to adopt the attached resolution awarding the Carter Road Detention Basin Project, subject to permit issuance from the Iowa Department of Natural Resources (DNR). MAK/vjd Prepared by Deron Muehring cc: Michael Koch, Public Works Director Pauline Joyce, Administrative Services Deron Muehring, Civil Engineer II Leo Foley, Veenstra & Kimm - Project Engineer 10/01/2083 11:13 13194~6t008 VEENSTRA & KI~M PA~E 02 VEENSTRA & KIMM, INC. 860 22n~ A venue-Suite 4 · Coralville~ Iowa 522 41~1565 31~.466.1000 · $19.46 ~- I O0 8( FAX) ,, October 1, 2003 City of Dubuque (Engineering) C/O Gus Psihoyos 50 West 13th Street Dubuque, Iowa 52001-4864 DUBUQUE, IOWA CARTER ROAD DETENTION BASIN RECOMMENDATION TO AWARD CONTRACT The City of Dubuque received and opened bids for the Carter Road Detention Basin project on September 30, 2003. A total of five bids were received as follows: Fisher Excavatin& Inc. Horsfield Conduction, Inc. Portzen Construetion, Inc. W.C. Stewart Construction, Inc. Tschi~gfrie E~cavatin§ Co. $709~058.00 $717,663.00 $849,796.47 $ 9,64.4.0B $590,316.35 The apparent Iow bid was submitted by TschiggfTie Excavating Co. of Dubuque, Iowa in the amount of $590,316.35. ^ bid tabulation is attached for review. The Engineer's EstJmate of' cost for construction of the project was $687,590. The Iow bid submitted by Tschiggfrie Excavating Co. was $97,273.65 or 14,1% below the Engineer's Estimate of cost, In reviewing the bid submitted by Tschiggfrie Excavating Co. it appears the main reason why the bid was lower than the Engineer's E~mate of cost was the line item price for Unclassified Excavation/Borrow. The cost for the unclassified excavation was $61,800 lower than the Engineers Estimate of cost for tJ~at line item. Veenstra & Kimm, Inc. believes that Tschiggfrie must have a site where specified clay material is readily available. We also believe the bid 'climate for projects that may have work that could be completed in the winter is very -~avorable at this time. Based on a review of the bid received it would be our recommendation that the bid is fair and reasonable and responsive to the bidding documents. We would recommend that the City of Dubuque award the contract to Tschiggfi'ie Excavating Co. in the amount of $590,316.35 based on its bid received on September 1, 2003. However we recommend waiting to award the conl~act until the 1DNR construction permit is obtained. The project specifications West De~ Molne~ , Coralville . Omaha * Mol~ne * Ma~on c~ · 5~oux CI~y 18/81/2883 11:13 13194561008 V~ENSTR~ & KIMM PA6E 03 Gus Psihoyos October 1, 2003 Page 2 . indicated that all permits will be obtained by November 17, 2003. Further discussions with IDNR staff indicate that they will begin the review of the permit next week. If you have any questions or comments concerning the project, please contact us at 319-466- 1000. VEENSTR~ & KIMM, INC. Leo F. Foley, P.E. ',-. 34313 1~.45 E~(~4,~% ~ 1.16 DEI~Rf$ CONqROL FEN~ING PO~T LF 180 !~2.~0 ~,~2D.O~ 1.17 6' G~ANUL~R SUB BASE TON~ 125 .~18,gO $t.875,CO 1.1e 4' ACC- PAVEMENT TONS UN~PR~E TOTAL (34 Corah. i~, ]e,~a ·~'c::',-Leo F. ~.': · ~: Foley _-. 1 ? 70O 0 RESOLUTION NO. 308-03 PRELIMINARY APPROVAL OF PLANS AND SPECIFICATIONS NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: That the proposed plans, specifications, form of contract and estimated cost for the Carter Road Detention Basin Project, in the estimated amount $1,105,849.00 are hereby approved and ordered filed in the office of the City Clerk for public inspection. Passed, adopted and approved this 2nd Attest: F. Schneider, CMC, City Clerk TerCance M. Dugga~l~/or RESOLUTION NO. 309-03 FIXING DATE OF HEARING ON PLANS AND SPECIFICATIONS Whereas, the City Council of the City of Dubuque, Iowa has given its preliminary approval on the proposed plans, specifications, and form of contract and placed same on file in the office of the City Clerk for public inspection of the Carter Road Detention Basin Project. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: That a Public Hearing will be held on the 6th day of October, 2003, at 6:30 p.m. in the Public Library Auditorium at which time interested persons may appear and be heard for or against the proposed plans and specifications, form of contract and cost of said improvement, and the City Clerk be and is hereby directed to cause a notice of time and place of such hearing to be published in a newspaper having general circulation in the City of Dubuque, iowa, which notice shall be not less than four days nor more than twenty days prior to the day fixed for its consideration. At the hearing, any interested person may appear and file objections to the proposed plans, specifications, contract, or estimated cost of the improvement. Passed, adopted and approved this 2nd day of September , 2003. r ne F. Schneider, CMC, City~Cl~rk RESOLUTION NO. 310-03 ORDERING BIDS NOW THEREFORE, BE IT RESOLVED BY THE COUNCIL OF THE CITY OF DUBUQUE, IOWA: That the Carter Road Detention Basin Project is hereby ordered to be advertised for bids for construction. BE IT FURTHER RESOLVED, that the amount of the security to accompany each bid shall be in an amount which shall conform to the provisions of the Notice to Bidders hereby approved as a part of the plans and specifications heretofore adopted. That the City Clerk is hereby directed to advertise for bids for the construction of the improvements herein provided, to be published in a newspaper having general circulation in the City of Dubuque, Iowa, which notice shall not be less than four days nor more than forty-five days prior to the receipt of said bids at 2:00 p.m. on the 30t~ day of September, 2003. Bids shall be opened and read by the City Clerk at said time and will be submitted to the Council for final action at 6:30 p.m. on the 6~h day of October, 2003. Passed, adopted and approved this 2nd day of September , 2003. Attest: ~_~anne F. Schneider, CMC, Cit~--C~erk RESOLUTION NO. 380-03 RESOLUTION ADOPTING PLANS AND SPECIFICATIONS Whereas, on the 27th day of August, 2003, plans, specifications, form of contract and estimated cost were filed with the City Clerk of Dubuque, iowa for the Carter Road Detention Basin Project. Whereas, notice of hearing on plans, specifications, form of contract, and estimated cost was published as required by law. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: That the said plans, specifications, form of contract and estimated cost are hereby approved as the plans, specifications, form of contract and estimated cost for said improvements for said project. Passed, adopted and approved this 6th day of October ,2003. Terrance M. Duggan, Mayor Jeanne F. Schneider, City Clerk RESOLUTION NO. 381-03 AWARDING CONTRACT Whereas, sealed proposals have been submitted by contractors for the Carter Road Detention Basin Project pursuant to Resolution No. 310-03 and notice to bidders published in a newspaper published in the City of Dubuque, Iowa on the 5th day of September, 2003. Whereas, said sealed proposals were opened and read on the 30th day of September, 2003, and it has been determined that the bid of Tschiggfrie Excavating Co. of Dubuque, Iowa, in the amount of $590,316.35 was the lowest bid for the furnishings of all labor and materials and performing the work as provided for in the plans and specifications. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: That the contract for the above improvement be awarded to Tschiggfde Excavating Co., contingent upon permit issuance by the Iowa Department of Natural Resources, and the Manager be and is hereby directed to execute a contract on behalf of the City of Dubuque for the complete performance of the work. BE IT FURTHER RESOLVED: That upon the signing of said contract and the approval of the contractor's bond, the City Treasurer is authorized and instructed to return the bid deposits of the unsuccessful bidders. Passed, approved and adopted this 6th day of October, 2003. Terrance M. Duggan, Mayor Attest: Jeanne F. Schneider, CMC, City Clerk dayof October ,2003. NOTICE TO BIDDERS OF THE RECEIPT OF BIDS FOR THE CARTER ROAD DETENTION BASIN PROJECT Sealed proposals will be received by the City Clerk of the City of Dubuque, iowa, at the Office of City Clerk in City Hall no later than 2:00 o'clock p.m. on the 30~ day of September, 2003. for the construction of Car[er Road Detention Basin Project. Copies of the plans and specifications may be obtained in the City Engineer's office at City Hall. No plan deposit is required. Payment to the contractor will be made from funds as may be legally used for such purposes. All work herein provided for shall be commenced within ten (10) days after the Notice To Proceed has been issued, and shall be fully completed by the 30~h day of June, 2004. All bids must be submitted on the Bid Form bound in the specifications. Each bid shall be accompanied by a satisfactory Bid Bond executed by the Bidder and an acceptable surety; or a cashier's or certified check payable to the City Treasurer, City of Dubuque. drawn on a bank in Iowa or a bank chartered under the laws of the United States, in the amount of ten percent (10%) of the bids submitted as security that the bidder will enter into a contract for doing the work and will give bond with proper securities for the faithful performance of the contract in the form attached to the specifications. The successful bidder will be required to furnish a performance bond in an amount equal to one hundred percent I100%) of the contract price. Said bond is to be issued by a responsible surety company approved and acceptable to the City Council, and shall guarantee the' faithful performance of the contract and terms and conditions therein contained, and shall guarantee the prompt payment of all materials and labor and protect and save harmless the City of Dubuque, Iowa, from claims and damages of any kind caused by the operations of the Contractor. Said Bond shall also guarantee the material and the maintenance of the improvement(s) constructed for a minimum period of two (2) years from and after its completion and acceptance by the City Council. No bid submitted by any Contractor which contains a condition or qualification shall be recognized or accepted by the City Council and any letter or communication accompanying the bid which contains a conditio~ or qualification upon the bid which has the effect of qualifying or modifying any provision of the specifications in any manner will be construed as a non-qualifying bid and will be rejected by the City Council as not responsive. All proposals must be made on blanks furnished by the City Engineer and each bidder will be required to state his prices for doing all the items in each section on which he makes a bid and for all things necessary to make a complete job. The Bidder's attention is directed to the City of Dubuque's Affirmative Action Program which is included in the Contract Specifications and the provisions thereof and hereby made a part of the Contract Documents by reference and incorporated therein. The Contractor, when requested by the City of Dubuaue, will furnish a statement of his financial and practical qualifications as provided for in the General Requirements of the Specifications. By virtue of statutory authority, a preference will be g rven to products and provisions grown and coal produced within the State of Iowa and to Iowa Domestic Labor. The City Council reserves the right to reject any and all bids or to waive any technical ties and irregularities. All bids will be publicly opened and read by the City Clerk at 2:00 o'clock p.m on the 30t~ day of September, 2003, and will be submitted to the City Council for final action at a meeting to be held in the Public Library Auditorium. 360 West 11t" Street, at said City at 6:30 p.m. on the 6th day of October, 2003. A contract will be awarded at that time or such subsequent time as /he City may determine. Published by order of the City Council of the City of Dubuque, Iowa and dated this of ,2003. Jeanne F. Schneider, CMC, City Clerk CONSTRUCTION SCHEDULE AND LIQUIDATED DAMAGES Work herein provided for shall be commenced within the (10) days after notice to proceed has been issued and shall be fully completed by June 30, 2004. For each calendar day that any work shall remain uncompleted beyond the completion schedule, $750.00 per calendar day will be assessed, not as a penalty but as predetermined and agreed liquidated damages. The contractor will ~e separately invoiced for this amount, and final payment will be withheld until payment has been made of this invoice. The assessment of liquidated damages shall not constitute a waiver of the City's right to collect any additional damages which the City may sustain by failure of the contractor to carry out the terms of his contract. An extension of the contract period may be granted by the City for any of the following reasons: 1. Additional work resulting from a modification of the plans. 2. Delays caused by the City. Other reasons beyond the control of the Contractor, which in the City's opinion, would justify such extension. MEMORANDUM TO: FROM: SUBJECT: August 29, 2003 The Honorable Mayor and City Council Members Michael C. Van Milligen, City Manager Carter Road Detention Basin Project Initiation Assistant City Engineer Gus Psihoyos recommends that a public hearing be set for October 6, 2003 for bid award for the Carter Road Detention Basin Project. Veenstra & Kimm, Inc. has finished the plans and specifications for the proposed detention basin. The earthen dam will be approximately 350-feet long and. 40-feet high with 3:1 side slopes. As approved by the City Council in July, the dam principal spillway will be a 15-inch conduit and a 24-inch gated conduit. The high flow outlet is a 48-inch diameter riser pipe that is approximately 37-feet high. A 350-foot long asphalt access road is included to provide access to the outlet structure for operation and maintenance needs. In addition, the project includes the reconstruction of the sanitary sewer under the proposed dam because the original sewer was not designed for the depth that will result when the embankment is completed. The proposed sanitary sewer will be constructed in such a manner to prevent future sewer maintenance needs. VVhile there is an outside chance that the detention basin could be functional prior to spring 2004 rainstorms, the Engineering Department and V&K believe a completion date prior to June 30, 2004 would result in a significant increase in the cost of construction. However, the Engineering Department recommends that the project include an incentive bonus for the contractor to complete all work prior to June 30. 2004. This bonus would amount to $750,000 per calendar day for each day the project is completed before the June 30, 2004 date. The maximum incentive would be $67,500.00 (90 bonus days). In addition, we are including a $750.00 liquidated damages for every day beyond the June 30, 2004 deadline that the project is not complete. V&K is anticipating that the appropriate authorities will grant all permits by November 17, 2003. If permits are not in the City's hands and authorization for the contractor to begin work is not granted by that date, the contract deadline and bonus incentive would be adjusted accordingly. Assistant City Engineer Gus Psihoyos is further recommending that a request be made to IDNR for an out-of-order review to expedite this project. I concur with the recommendation and respectfully request Mayor and City Council approval. MCVM/ksf Attachment cc: Barry Lindahl, Corporation Counsel Cindy Steinhauser, Assistant City Manager Gus Psihoys, Assistant City Engineer MEMORANDUM August29,2003 TO: FROM: SUBJECT: Michael G. Van Milligen, City Manager Gus Psihoyos, Assistant City Engineer Carter Road Detention Basin Project Initiation INTRODUCTION The enclosed resolutions authorize the bidding procedure for the construction of the Carter Road Detention Basin. BACKGROUND In December of 2001, the City Council adopted the Drainage Basin Master Plan (DBMP) produced by HDR Engineering. The DBMP addresses drainage issues in two major watersheds in Dubuque, the North Fork Catfish Creek and Bee Branch watersheds, recommending over $24 million in improvements. The first recommended improvement to be constructed was the NW Arterial Detention Basin located in the North Fork Catfish Creek watershed. The detention basin was fully operational prior to the spdng rainstorm of 2002. With the adoption of the Fiscal Year 2004 Capital Improvement Budget, the City Council established funding for the Carter Road Detention Basin in the Bee Branch watershed. In May of 2003, the City Council approved the selection of Veenstra & Kimm, Inc. to provide engineering and design services for the Carter Road Detention Basin project. In July of 2003 the City Council approved the outlet structure design for the Carter Road Detention Basin. DISCUSSION Veenstra & Kimm, Inc. has finished the plans and specifications for the proposed detention basin. The earthen dam will be approximately 350-feet long and 40-feet high with 3:1 side slopes. As approved by the City Council in July, the dam principal spillway will be a 15-inch conduit and a 24-inch gated conduit. The high flow outlet is a 48-inch diameter dser pipe that is approximately 37-feet high. A 350-foot long asphalt access road is included to provide access to the outlet structure for operation and maintenance needs. In addition, the project includes the reconstruction of the sanitary sewer under the proposed dam because the odginal sewer was not designed for the depth that will result when the embankment is completed. The proposed sanitary sewer will be constructed in such a manner to prevent future sewer maintenance needs. In addition to the sewer that is immediately impacted by the embankment, other sanitary sewers within the detention basin flooding limits will be reviewed to see if any modifications are needed to prevent infiltration and inflow of stormwater into the sanitary sewer. Depending on the condition of the existing sanitary sewer, some of the work might have to be completed before the detention basin is fully operational. These costs will be funded from the Infiltration and Inflow (l&l) Reduction Program with a balance of $234,000. Although engineering firms advised that a fall 2003 deadline is not doable due to easement acquisitions; permitting from DNR and other associated agencies; and the need for suitable construction conditions in the fall, the request for proposals outlined the City's goal to have the detention basin operational prior to spring 2004 rainstorms. Although V&K has been in constant contact with the DNR, getting input and feedback throughout the design phase of the project, the DNR requires completed plans and specifications pdor to review. Plans and specifications will be submitted on September 3, 2003 with a request for an "out of sequence" review. It will take between 30 to 60 days to obtain a permit from the DNR and construction of the Carter Road Detention Basin cannot proceed until the DNR permit is obtained. Attached is a letter to the DNR requesting that this project be given "out of order'' review based on the flooding potential that exists for the approximately 1,200 properties downstream of the proposed detention basin. If an "out of order'' review is granted, it could help the City reach its initial goal to have the basin operational by spdng 2004. While there is an outside chance that the detention basin could be functional prior to spdng 2004 rainstorms, the Engineering Department and V&K believe a completion date pdor to June 30, 2004 would result in a significant increase in the cost of construction. However, the Engineering Department recommends that the project include an incentive bonus for the contractor to complete all the work prior to June 30, 2004. This bonus would amount to $750.00 per calendar day for each day the project is completed before the June 30' 2004 date. The maximum incentive would be $67,500.00 (90 bonus days). In addition, we are including a $750.00 liquidated damages for every day beyond the June 30, 2004 deadline that the project is not complete. V&K is anticipating that the appropriate authorities will grant all permits by November 17, 2003. If permits are not in the City's hands and authorization for the contractor to begin work is not granted by that date the contract deadline and bonus incentive would be adjusted accordingly. The schedule for the project is as follows: Advertisement for Bids Notice of Public Hearing Receipt of Bids Public Hearing Award of Contract Completion September 5, 2003 September 26, 2003 September 30, 2003 October 6, 2003 October 6, 2003 June 30, 2004 BUDGETIMPACT The estimate for this project is as follows: Construction Contract Contingency Engineering Property and Easement Acquisitions Potential Maximum Bonus 687,590.00 68,759.00 132,000.00 150,000.00 67,500.00 Total Project Cost 1,105,849.00 The project will be funded from the storm sewer construction fund from the Fiscal Year 2004 appropriation of $875,000. The remaining amount of $230,849.00 will be funded from the repriodtization of the Windsor Avenue Storm sewer project ($142,000) and Terminal Street storm sewer project ($72,000) which engineering will recommend to be re-budgeted. The remaining $18,849 will be funded from the General Storm Sewer Construction Fund. ACTION TO BE TAKEN Engineering respectfully requests that the City Council establish the date of public hearing, authorize the City Clerk to advertise for proposals through the adoption of the enclosed resolutions, and endorse the "out of order" request to the DNR be submitted along with the plans and specifications on September 3, 2004. CC: Michael Koch, Public Works Director Pauline Joyce, Administrative Services Manager Deron Muehring, Civil Engineer II Leo Foley, Project Engineer for Veenstra & Kimm / EMBANKMENT '" SITE LOCATION MAP NOT TO SCALE NORTH CARTER ROAD DETENTION BASIN ~'~ -- ~,~.~ ~ ~-~ EXHIBIT