Port Dbq Logging Prop DemolitioMEM ORANDUM September 24, 2003 TO: FROM: SUBJECT: The Honorable Mayor and City Council Members Michael C. Van Milligen, City Manager Port of Dubuque Logging Properties Building Demolition and Site Clearance Project Sealed bids were received for the Port of Dubuque Logging Properties - Building Demolition and Site Clearance Project. WC Stewart Construction Company submitted the Iow bid in the amount of $69,000, which is 31% under the engineer's estimate. The project will be funded with a $360,000 Federal Economic Development Initiative Grant targeted for property acquisition and site cleanup in the Port of Dubuque. The City has received a release of funds from HUD for this project. I concur with the recommendation and respectfully request Mayor and City Council approval. MCVM/cs Attachment cc: Barry Lindahl, Corporation Counsel Cindy Steinhauser, Assistant City Manager Michael A. Koch, Public Works Director TO: FROM: CITY OF DUBUQUE, IOWA MEMORANDUM Michael C. Van Milligen, City Manager Michael A. Koch, Public Works Director September 25, 2003 SUBJECT: Port of Dubuque Logging Properties Building Demolition and Site Clearance Project INTRODUCTION The enclosed resolution provides for the award of the construction contract for the Port of Dubuque Logging Properties - Building Demolition and Site Clearance Project. BACKGROUND The Demolition and Site Clearance Project includes: the complete demolition of existing structures; the excavation, removal, clean-up, and disposal of all building materials from the former Miller Logging and the Dubuque Hardwoods properties; and the disconnection and abandonment of both City and public utilities to the site. To comply with DNR and federal regulations and to reduce the potential liability of the City, the contractor will be required to dispose of all solid waste demolition materials at the Dubuque Metropolitan Area Solid Waste Agency Landfill. The City, however, shall incur all associated landfill solid waste disposal costs that are estimated at $50,000 to $75,000. The contractor is responsible for providing an off-site disposal area and transport all solid fill, salvageable or scrap materials to the off-site disposal location. The City will not incur any landfill disposal charges for solid fill, salvageable or scrap materials. BID RESULTS Sealed bids were received on the project on August 7, 2003. WC Stewart Construction Company of Dubuque, Iowa submitted the Iow bid in the amount of $69,000. This amount is 31% under the engineer's estimate. A summary of the bids received is as follows: Contractor Name WC Stewart Construction Company Dubuque Barge & Fleeting Service Portzen Construction Tschiggfrie Excavating Drew Cook & Sons Excavating Bid Amount $ 69,000 76,245 79,900 82,200 95,450 PROJECT FUNDING The project will be funded with a $360,000 Federal Economic Development Initiative Grant targeted for property acquisition and site cleanup in the Port of Dubuque. The City received notification on September 25 that the funds from HUD have been released. The summary of the project costs is as follows: Estimate Bid Award Logging Properties Site Demolition (Dubuque Hardwoods, Miller Logging Site) Landfill Disposal Cost Total Project Cost $100,000 $ 69,000 $ 50,000 $ 50,000 $150,000 $119,000 RECOMMENDATION I recommend that the contract be awarded to WC Stewart Construction Company in the amount of $69,000, subject to HUD authorization and the release of Federal Economic Development Initiative Grant funds. ACTION TO BE TAKEN The City Council is requested to adopt the attached resolution awarding the Port of Dubuque Logging Properties - Building Demolition and Site Clearance Project to WC Stewart Construction Company. Prepared by Robert D. Schiesl, Civil Engineer cc: Pauline Joyce, Administrative Services Manager Bill Baum, Community and Economic Development Director Pam Myhre, Community and Economic Development Rich Russell, Building Services Manager Jim Kolf, Durrant RESOLUTION NO. 347-03 AWARDING CONTRACT Whereas, sealed proposals have been submitted by contractors for the Port of Dubuque Logging Properties - Building Demolition and Site Clearance Project pursuant to Resolution No._5~?-P.~ and notice to bidders published in a newspaper published in the City of Dubuque, Iowa on the 25th day of July, 2003. Whereas, said sealed proposals were opened and read on the 7th day of August, 2003, and it has been determined that the bid of WC Stewart Construction Company of Dubuque, Iowa, in the amount of $69,000.00 was the lowest bid for the furnishings of all labor and materials and performing the work as provided for in the plans and specifications. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: That the contract for the above improvement be awarded to WC Stewart Construction Company and the Manager be and is hereby directed to execute a contract on behalf of the City of Dubuque for the complete performance of the work, subject to HUD authorization and the release of Federal Economic Development initiative Grant Funds. BE IT FURTHER RESOLVED: That upon the signing of said contract and the approval of the contractor's bond, the City Treasurer is authorized and instructed to return the bid deposits of the unsuccessful bidders. Passed, approved and adopted this 26th day of September ,2003. Terrance M. Duggan, Mayor Attest: Jeanne F. Schneider, CMC, City Clerk CITY OF DUBUQUE - ENGINEERING DIVISION BID TABULATION FORM PROJECT: Port of Dubuque Logging Properties Building Demolition and Site Clearance Project DATE: Thursday, August 7, 2003 BIDDER NAME: WC Stewart Construction Company BID ALTERNATE NO.1 (A) For the LUMP SUM AMOUNT OF, Dollars ( NO BID ) (B) Salvage Value Credit. the LUMP SUM AMOUNT OF, Dollars ( NO BID ) NET AMOUNT FOR BID ALTERNATE NO.1. equal to Part IA) minus Part (B) for the LUMP SUM AMOUNT OF, Dollars [ NO BID ) BID ALTERNATE NO.2 (A) For the LUMP SUM AMOUNT OF, Dollars ~.6__9,000_,.0._0 BIDDER NAME: Dubuque Barge & Fleeting Service BiD ALTERNATE NO.1 (A) For the LUMP SUM AMOUNT OF. Dollars ( NO BID ) (B) Salvage Value Credit, ihe LUMP SUM AMOUNT OF, Dollars ( NO BID ) NET AMOUNT FOR BID ALTERNATE NO.1. equal to Pad (A) m~nus Part (B) for the LUMP SUM AMOUNT OF, Dollars ( NO BID ) BID ALTERNATE NO.2 (A) For the LUMP SUM AMOUNT OF, Dollars 7576j_245.00 BIDDER NAME: Portzen Construction BID ALTERNATE NO.1 (A) For the LUMP SUM AMOUNT OF. Dollars ( NO BID ) (B) Salvage Value Credit the LUMP SUM AMOUNT OF. Dollars ( NO BID ) NETAMOUNT FOR BID ALTERNATE NO.1 eoual to Part (Al minus Part (B) for the LUMP SUM AMOUNT_ OF. Dollars ( NO BID ) BIDDER NAME: Tschiggfrie Excavatin~ BID ALTERNATE NO,1 (A) For the LUMP SUM AMOUNT OF. Dollars ( NO BID ) (B) Salvage Value Credit, the LUMP SUM AMOUNT OF, Dollars [ NO BID ) NET AMOUNT FOR BID ALTERNATE NO.1, equal to Part (A) minus Part (B) for the LUMP SUM AMOUNT OF, Dollars ( NO BID ) BID ALTERNATE NO.2 (A) For the LUMP SUM AMOUNT OF. Dollars $82,;200.00 BIDDER NAME: Drew Cook & Sons Excavatin~g BID ALTERNATE NO.I (A) For the LUMP SUM AMOUNT OF. Dollars ( NO BID ) (B) Salvage Value Credit. the LUMP SUM AMOUNT OF, Dollars ( NO BID ) NET AMOUNT FOR BiD ALTERNATE NO.1. equal to Part (A) minus Part (B) for the LUMP SUM AMOUNT OF, Dollars [ NO BID ) BID ALTERNATE NO.2 (A) For the LUMP SUM AMOUNT OF, Dollars $.9.5~,_.4_50.00_ BID ALTERNATE NO.2 (A) For the LUMP SUM AMOUNT OF. Dollars $79,900.00 MEMORANDUM August13,2003 TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager SUBJECT: Port of Dubuque Logging Properties Building Demolition and Site Clearance Project Sealed bids were received for the Port of Dubuque Logging Properties - Building Demolition and Site Clearance Project. WC Stewart Construction Company submitted the Iow bid in the amount of $69,000, which is 31% under the engineer's estimate. The project will be funded with a $360 O00 Federal Economic Development Initiative Grant targeted for property acquisition and site cleanup in the Port of Dubuque. However, the City has not received release of funds from HUD because of ongoing review by the State Historic Preservation Office. Release of the grant funds may be delayed until mid-September. Because of the delay in receiving the release of funds from HUD, the City is not authorized to execute a contract until that time. Public Works Director Mike Koch recommends that the public hearing be held and the plans and specifications approved, but the award of the contract to WC Stewart Construction Company be deferred until the September 2, 2003 Council meeting. This is allowed under the project specifications, which require the contractor to guarantee the bid through September 7, 2003. I concur with the recommendation and respectfully request Mayor and City Council approval. Michael C. Van Milligen MCVM/jh Attachment cc: Barry Lindahl, Corporation Counsel Cindy Steinhauser, Assistant City Manager Michael A. Koch, Public Works Director CITY OF DUBUQUE, IOWA MEMORANDUM August 13, 2003 TO: Michael C. Van Milligen, City Manager FROM: SUBJECT: Michael A. Koch, Public Works Director Port of Dubuque Logging Properties Building Demolition and Site Clearance Project INTRODUCTION The following is a request to delay the award of the construction contract for the Port of Dubuque Logging Properties - Building Demolition and Site Clearance Project until the September 2. 2003 Council meeting. BACKGROUND The Demolition and Site Clearance Project includes: the complete demolition of existing structures; the excavation, removal, clean-up, and disposal of all buitding materials from the former Miller Logging and the Dubuque Hardwoods properties; and the disconnection and abandonment of both City and public utilities to the site. To comply with DNR and federal regulations and to reduce the potential liability of the City, the contractor will be rec Jired to dispose of all solid waste demolition materials at the Dubuque Metropolitan Area Solid Waste Agency Landfill. The City, however, shall incur all associated landfill solid waste disposal costs that are estimated at $50.000 to $75,000. The contractor is responsible for providing an off-site disposal area and transport all solid fill, salvageable or scrap materials to the off-site disposal location. The City will not incur any landfill disposal charges for solid fill, salvageable or scrap materials. BID RESULTS Sealed bids were received on the project on August 7, 2003. WC Stewart Construction Company of Dubuque, Iowa submitted the Iow bid in the amount of $69,000. This amount is 31% under the engineer's estimate. A summary of the bids received is as follows: Contractor Name WC Stewar[ Construction Company Dubuque Barge & Fleeting Service Portzen Construction Tschiggfrie Excavating Drew Cook & Sons Excavating Bid Amount $ 69,000 76,245 79.900 82.200 95,450 PROJECT FUNDING The project will be funded with a $360.000 Federal Economic Development Initiative Grant targeted for property acquisition and site cleanup in the Port of Dubuoue. However. the City has not received release of funds from HUD because of ongoing review by the State Historic Preservation Office. Release of the grant funds may be delayed until mid-September The summary of the project costs is as follows: Estimate Bid Award Logging Properties Site Demolition (Dubuque Hardwoods, Miller Logging Site) Landfill Disposal Cost Total Project Cost $100,000 $ 69,300 $ 50,000 $ 50,000 $150,000 $119,000 Because of the delay n receiving the release of funds from HUD sometime in about mid- September, the City is not authorized to execute a contract until that time. At the September 2. 2003 Council meeting, City staff should have more information on the anticipated date of the HUD release of funds. Two options exist with regard to the award of this contract. The first would be a conditional award with a voluntary extension of the bid guarantee from the contractor beyond the normal 30-day period, or by September 2, HUD may have already released the funds and the award would be straightened with no contingencies. Knowing this release date at the time of the award will allow the City to make a more informed award of this contract. RECOMMENDATION I recommend that the award of this contract to WC Stewart Construction Company be deferred until the September 2, 2003 Council meeting. This is allowed under the project specifications. which require the contractor to guarantee the bid through September 7. 2003. The public hearing and the adoption of the final plans and specifications were set for August 18. 2003 when the project was initiated. It is, therefore, necessary that the public hearing proceed as planned and that the project plans and specifications are given final approval at this meeting. ACTION TO BE TAKEN The City Council is requested to hold the public hearing or the project and to adoo[ the Resolution Approwng the Final Plans and Soecifications. The City Council is requested to defer the award of the contract for the Port of Dubuque Logging Properties - Building Demolition and Site Clearance Project to WC Stewart Construction Company until the September 2, 2003 Council meeting. Prepared by Robert D. Schiesl, Civil Engineer cc: Pauline Joyce, Administrative Services Manager Bill Baum, Community and Economic Development Director Dam Myhre, Community and Economic Development Rich Russell. Building Services Manager Jim Kolf, Durrant CITY OF DUBUQUE - ENGINEERING DIVISION BID TABULATION FORM PROJECT: Port of Dubuque Logging Properties Building Demolition and Site Clearance Projeci BIDDER NAME: WC Stewart Construction Company BID ALTERNATE NO.1 (A) For the LUMP SUM AMOUNT OF, Dollars ( NO BID ) (B) Salvage Value Credit. the LUMP SUM AMOUNT OF, Dollars ( NO BID ) NET AMOUNT FOR BID ALTERNATE NO,I. equal to Part (A) minus Pall (B) for the LUMP SUM AMOUNT OF, Dollars [ NO BID ) BID ALTERNATE NO.2 (A) For the LUMP SUM AMOUNT OF Dollars BIDDER NAME: Dubuque Barge & Fleeting Service BID ALTERNATE NO. 1 (A) For the LUMP SUM AMOUNT OF, Dollars ( NO BID ) (B) Salvage Value Credit, the LUMP SUM AMOUNT OF. Dollars ( NO BID ) NET AMOUNT FOR BID ALTERNATE NO.1, equal to Part (A) minus Part (B) for the LUMP SUM AMOUNT OF Dollars ( NO BtD) BID ALTERNATE NO.2 (A) For the LUMP SUM AMOUNT OF, Dollars ~76~.245.00 BIDDER NAME: Portzen Construction BID ALTERNATE NO.1 (A) For the LUMP SUM AMOUNT OF, Dollars ( NO BtD) (B) Salvage Value Credit, the LUMP SUM AMOUNT OF, Dollars ( NO BID ) NET AMOUNT FOR BID ALTERNATE NO.1. equal to Part (A) minus Part (B) for the LUMP SUM AMOUNT. OF, Dollars ( NO BID ) DATE: Thursday, August 7. 2003 BIDDER NAME: Tschig.qfrie Excavating BID ALTERNATE NO.1 (A) For the LUMP SUM AMOUNT OF. Dollars [ NO BID ) (B) Salvage Value Credit, the LUMP SUM AMOUNT OF. Dollars ( NO BID ) NET AMOUNT FOR BID ALTERNATE NO,I. equal to Part IA) minus Part (B) for the LUMP SUM AMOUNT OF, Dollars ( NO BID ) BID ALTERNATE NO.2 (A) For the LUMP SUM AMOUNT OF. Dollars $~.g=,22Q0.0.0_ BIDDER NAME: Drew Cook & Sons Excavating BID ALTERNATE NO.1 (A) For the LUMP SUM AMOUNT OF. Dollars ( NO BID ) (B) Salvage Value Credit, the LUMP SUM AMQUNT OF Dollars ( NO BID ) NET AMOUNT FOR BID ALTERNATE NO.1. equal to Part IA) minus Part (B) for the LUMP SUM AMOUNT OF. Dollars ( NO BID ) BID ALTERNATE NO.2 (A) For the LUMP SUM AMOUNT OF. Dollars $95,¢50.00 BID ALTERNATE NO.2 (A) For me LUMP SUM AMOUNT OF. Dollars $79,900.00 MEM ORANDUM July 15, 2003 TO: FROM: SUBJECT: The Honorable Mayor and City Council Members Michael C. Van Milligen, City Manager Port of Dubuque Logging Properties Building Demolition and Site Clearance Project Assistant City Engineer Gus Psihoyos recommends initiation of the bidding process for the Port of Dubuque Logging Properties Building Demolition and Site Clearance Project, ant further recommends that a public hearing be set for August 18, 2003. This pro.~ect is funded with a $360,000 Federal Economic Development Initiative Grant targeted for property acquisition and site cleanup in the Port of Dubuque. I concur with the recommendation and respectfully request Mayor and City Council approval. MCVM/jh Attachment cc: Barry Lindahl, Corporation Counsel Cindy Steinhauser, Assistant City Manager Gus Psihoyos, Assistant City Engineer Mike Koch. Public Works Director CITY OF DUBUQUE, IOWA MEMORANDUM July 15, 2003 TO: FROM: SUBJECT: Michael C. Van Milligen. City Manager Gus Psihoyos. Assistant City Engineer ~9~,~ Port of Dubuque Logging Properties Building Demolition and Site Clearance Project INTRODUCTION The enclosed resolutions authorize the public bidding procedures for the Port of Dubuque Logging Properties Building Demolition and Site Clearance Project. BACKGROUND On July 1. 2003, the City completed the land acquisition of both the Miller Logging and the Dubuque Hardwoods properties. Miller .ogglng and the Dubuque Hardwoods operations have been relocated and have since completely vacated the property. Prior to the grand opening for the Conference and Education Center ant to clean up the 5TM Street entry corridor into the Port of Dubuque, the City intends to raze all existing building structures and clear the site of the former logging properties. DISCUSSION The :~emolition and Site Clearance Project shall include the complete demolition of existing structures, which includes the excavation of building foundations and the removal, clean-up, and disposal of all building materials from the fo'mer Miller Logging and the Dubuque Hardwoods properties. The project shall also include the disconnection and abandonment of both City and public utilities to the site. Based upon both DNR and federal solid waste landfill regulations, all 'naterials with foam. cork, insulation attached which cannot be separated, all timber and wood building materials, roofing materials and rail*oad ties, are classified as solid waste and are required to be disposed at a permitted landfill. To comply with DNR and federal regulations and to reduce the potential liability of the City, the contractor will be required to dispose of alt solid waste demolition materials at the Dubuque Metropolitan Area Solid Waste Agency Landfill. In an attempt to encourage competitive lump sum bid proposals and eliminate the contractor's cost, profit plus an unknown contingency factor to cover landfill disposal charges, the City shall incur all landfill solid waste disposal costs associated with the project. Based upon review of building materials on-site. staff has estimated that the landfill disposal charges could range from $50,000 to $75,OOO. The contractor shall be respc~sible for providing an off-site disposal area and transport all solid fill, salvageable or scrap materials to the off-site disposal location. The City will not incur any landfill disposal charges for solid fill. salvageable or scrap materials PROJECT SCHEDULE The schedule for the project will be as follows: Initiate Public Bidding Process Advertisement for Bids Recei pt of Bids Notice of Public Hearing on Plans & Specifications Public Heating Award of Contract Completion Date July 21,2003 July 25.2003 August7.2003 August8,2003 August 18.2003 August 18. 2003 October 10, 2003 RECOMMENDATION t would recc 'nmend that the City Council establish the date for the public hearing, and authorize the City Clerk to advertise for proposals for the Port of Dubuque Logging Properties Building Demolition and Site Clearance Project. BUDGET IMPACT The estimate of probable cost for the Port of Dubuque Logging Properties Building Demolition and Site Clearance Project is as follows: Estimated Cost Dubuc Je ~ardwoods Site Miller Logging Site Landfill Disposal Cost $100,000 $ 50,000 $ 50,000 Total Project Cost $200,000 The project will be fuqded with a $360,000 Federal Economic Development nitiative Grant targeted for ~roperty acquisition and site c~eanu2 in the Port of Dubuque. ACTION TO BE TAKEN The City Council is requested to establish the date for the public hearing and To authorize the City Clerk to advertise for proposals through a(~option of the attached resolutions. MAKJvjd Prepared by ~,obert D. Schiesl, Civil Engineer cc: Pauline Joyce, Ad ministrative Services Manager Bill Baum, Community and Economic Development Director Para Myhre, Community and Economic Development Rich Russell, Building Services Manager Jim Kolf, Durrant RESOLUTION NO. PRELIMINARY APPROVAL OF PLANS AND SPECIFICATIONS NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: That the proposed plans, specifications, form of contract and estimated cost for the Pod of Dubuque Logging Prooerties - Building Demolition and Site Clearance Project in the estimated amount of $200,000 are hereby approved and ordered filed in the office of the City Clerk for public inspection. Passed, adopted and approved this day of 2003. Terrance M. Duggan, Mayor Attest: Jeanne F. Schneider, CMC, City Clerk RESOLUTION NO. FIXING DATE OF HEARING ON PLANS AND SPECIFICATIONS Whereas. the City Council of the City of Dubuque. Iowa has given its preliminary approval on the proposed plans, specifications and form of contract and placed same on file 'n the office of the City Clerk for public 'nspection of the Port of Dubuque Logging Properties - Building Demolition and Site Clearance Project. NOW THEREFORE. BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE. IOWA: That a public hearing will be held on the 18th day of August, 2003. at 6:30 p.m. in the Public Library Auditorium at which time interested persons may appear and be heard for or against the proposed plans and specifications, form of contract and cost of said improvement, and the City Clerk be and is hereby directed to cause a notice of time and place of such hearing to be published in a newspaper having general circulation in the City of Dubuque, Iowa. which notice shall be not less than four days nor more than twenty days prior to the day fixed for its consideration. At the hearing, any interested person may appear and file objections to the proposed plans, specifications, contract, or estimated cost of the improvement. Passed, adopted and approved this day of ,2003. Terrance M. Duggan, Mayor Attest: Jeanne F. Schneider, CMC, City Clerk NOTICE OF HEARING ON PLANS AND SPECIFICATIONS Notice of public hearing on proposed plans and specifications, proposed form of contract and estimate of cost for the Port of Dubuoue Logginc~ Properties - Building Demolition and Site Clearance Project: Complete demolition of existing structures, which includes the excavation of building foundations and the removal, cleanup, and disposal of all building materials. NOTICE IS HEREBY GIVEN: The City Council of Dubuque, Iowa will hold a public headng on the proposed plans, specifications, form of contract and estimate of cost for the Port of Dubuque Logging Properties - Building Demolition and Site Clearance Project 'n accordance with the provisions of Chapter 384, City Code of Iowa. at 6:30 p.m.. on the 18th day of August, 2003. in the Public Library Auditorium. 360 West 11TM Street, in Dubuque. Iowa. Said proposed plans, specifications, form of contract and estimate of cost are now on file in the office of the City Clerk. At said hearing any interested person may appear and file objections thereto or to the cost of the improvements. Any visual or hearing-~mpaired persons needing special assistance or persons with special accessibility needs should contact the City Clerk's office at (563) 589-4120 or TDD at (563) 690~6678 at least 48 hours prior to the meeting. Published by order of the City Council given on the ,2003, day of Jeanne F. Schneider, CMC, City Clerk RESOLUTION NO, RESOLUTION ADOPTING PLANS AND SPECIFICATIONS Whereas. on the 16th day of July, 2003, plans, specifications, form of contract and estimated cost were filed with the City Clerk of Dubuque, owa for the Port of Dubuque Logging Properties - Building Demolition and Site Clearance Project. Whereas. notice of hearing on plans, specifications, form of contract, and estimated cost was published as required by law. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: That the said plans, specifications, form of contract and estimated cost are hereby approved as the plans, specifications, form of contract and estimated cost for said improvements for said project. Passed, adopted and approved this day of ,2003. Terrance M. :)uggan, Mayor Attest: Jeanne F. Schneider. CMC, City Clerk RESOLUTION NO. ORDE RING BIDS NOW THEREFORE, BE IT RESOLVED BY THE COUNCIL OF THE CITY OF DUBUQUE, IOWA: That the Port of Dubuque Logging Properties - Building Demolition and Site Clearance Project is hereby ordered to be advertised for bids for construction. BE IT FURTHER RESOLVED. that the amount of the security to accompany eacn bid shall be in an amount which shall conform to the provisions of the Notice To Bidders hereby approved as a part of the plans and specifications heretofore adopted. That the City Clerk is hereby directed to advertise for bids for the construction of the improvements herein provided, to be published m a newspaper having general circulation in the City of Dubuque. iowa. which notice shall not be less than four days nor more than forty-five days prior To the receipt of said bids at 2:00 pm. on the 7TM day of August, 2003. Bids shall be opened and read by the City Clerk at said time and will be submitted to the Council for final action at 6:30 p.m. on the 18TM day of August, 2003. Passed, adopted and approved this day of ,2003. Terra nce M. Duggan, Mayor Attest: Jeanne F. Schneider, CMC, City Clerk