Miss Rvrwalk & Edge Phase IMEMORANDUM
TO:
FROM:
SUBJECT:
October 2, 2003
The Honorable Mayor and City Council Members
Michael C. Van Milligen, City Manager
Mississippi Riverwalk Phase I
River's Edge Plaza and Alternate Component
The RiveCs Edge Plaza Project provided for the construction of a 15,000 square foot
plaza facility, landscaping features and related amenities at the Delta Queen and
Mississippi Queen landing area location outside the floodwall at the Port of Dubuque.
Public Works Director Mike Koch is recommending acceptance of the Mississippi
Riverwalk Phase I, River's Edge Plaza and Alternate Component Project, as completed
by Renaissance Construction, in the final contract amount of $767,761.20, which is a
28% increase from the original contract amount of $599,638.00. Administrative
Services Manager Pauline Joyce budgeted additional funds beyond FY99 to cover the
overage.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
MicHael C. Van Milligen
MCVM/jh
Attachment
cc: Barry Lindahl, Corporation Counsel
Cindy Steinhauser, Assistant City Manager
Michael A. Koch, Public Works Director
CITY OF DUBUQUE, IOWA
MEMORANDUM
October 1, 2003
TO:
Michael C. Van Milligen, City Manager
FROM:
SUBJECT:
Michael A. Koch, Public Works Director
Mississippi Riverwalk Phase I
River's Edge Plaza and Alternate Component
INTRODUCTION
The enclosed resolutions provide for the acceptance of the construction contract for the
Mississippi Riverwalk Phase I, River's Edge Plaza and Alternate Component Projects.
BACKGROUND
The Mississippi Riverwalk Phase I, River's Edge Plaza and Alternate Component was the
first completed component of the $188 million dollar America's River Project.
The River's Edge Plaza Project provided for the construction of a 15,000 square foot plaza
facility, landscaping features and related amenities at the Delta Queen and Mississippi
Queen landing area location outside the floodwall at the Port of Dubuque. The 5,000
square foot main plaza area is decorative buff colored concrete with a stamped slate
texture surface with decorative quarry red slate texture accent banding and quarry red
slate texture cascading concrete stairs, which extend downward to the edge of the
Mississippi River. The project amenities include decorative railings, benches, ornamental
lights, bike racks, trash receptacles, and landscaping.
The alternate phase of the project is located between the floodwall and the Welcome
Center building. The alternate included constructing a small plaza area adjacent to the
floodwall and constructing new decorative concrete sidewalk from the plaza area to the
Welcome Center.
DISCUSSION
The River's Edge Plaza and Alternate Component has been completed by Renaissance
Construction of Dubuque, Iowa, in the final contract amount of $767,761.20, which is a
28% increase from the original contract in the amount of $599,638.00.
As summarized in previous correspondence (copies of which are attached), project costs
increased partially as a result of increased quantities for "as built" unit price items of
construction. Additionally, staff was directed to incorporate the quarry red surface
hardener to the accent banding and cascading stairs, incorporate the cut limestone surface
texture to the concrete retaining wall, and install additional conduit and pedestals for future
telecommunications and power outlet applications. The following is a partial breakdown of
the approved change orders to the River's Edge Plaza project.
Cascading Stairs, Perimeter Foundation Walls: $ 17,600
Reinforcing Steel, Epoxy Coated Upgrade $ 14,500
Construction Quantities Adjustment: $ 50,000
Colored Concrete Surface Hardener: $ 16,300
Limestone Surface Texture, Retaining Wall: $ 15,700
Telecommunications/Power Conduit & Pedestals: $ 10,800
Electric Service Upgrade, 200 Amp: $ 5,200
Pavilion, Foundation Footings: $ 5,300
Ramp, Aluminum Diamond Plate Upgrade: $ 4,600
Approved Change Orders Sub-Total: $140,000
RECOMMENDATION
I recommend that the City Council accept the improvements and recommend that the final
contract amount be established at $767,761.20 for the Mississippi Riverwalk Phase I,
River's Edge Plaza and Alternate Component Projects.
PROJECT FUNDING
The project cost summary for the Mississippi Riverwalk Phase I, River's Edge Plaza and
Alternate Component Projects are as follows:
River's Edge Plaza
Alternate Component
Contingency (15%)
Total Project Cost
Estimate Bid Final
$393,844.00 $478,349.50 $654,917.55
73,439.00 121,288.50 112,843.65
59,076.00 59,076.00 0
$526,359.00 $658,714.00 $767,761.20
The project funding for the Mississippi Riverwalk Phase I, River's Edge Plaza and
Alternate Component Projects are as follows:
Bid Final
General Fund $486,195.00 $767,761.20
Private Sources 51,231.00 0
Total Project Funding
$537,426.00 $767,761.20
Sealed bids on this project were received in September, 1999 in the amount of
$478,349.50 plus a contingency allowance of $59,077, for a total budget of $537,426.
The overage of $126,092 based on the bid and contingency required, was reduced from
the overall Riverwalk project contingency.
A change order was issued in February 2000 to correct concrete quantities from the
original bid documents at a cost impact of $39,734. This change left a contingency
balance of $19,342.
Another change taken to City Council in February 2000 included changing the concrete
surface to the full depth red colored concrete, shake hardener and stamped slate texture.
The additional cost associated with this change was $21,000. This change order used the
balance of contingency funds and put the project slightly over budget.
in April, 2001, a bid alternate of $121,288 for the landside nautilus plaza and sidewalk
along the harbor between the Pot[side Building and River's Edge Plaza was honored by
the contractor at the original unit bid price and was added to the River's Edge Plaza
contract. This increased the budget for the River's Edge Plaza to $658,714.The bid
alternate amount was taken from the funding for Phase II of the Riverwalk, since that is
where this component had originally been budgeted.
When the decision was made to move the pavilion from the landside nautilus to the River's
Edge Plaza, footings ($5,300) and electrical conduit and service ($10,800) were required
to be added to the Phase I budget, but again reduced from the cost for Phase II. The
limestone texture was added to the retaining wall at a cost of $15,700. Other change
orders explained further in the memo from City Engineer Mike Koch added another
$77,247 to the project cost. These additional costs were reduced from the Riverwalk
Contingency, which was replenished as cost estimates for Phase II were finalized and the
City went through the FY 2002 through FY 2003 ClP process.
ACTION TO BE TAKEN
The City Council is requested tO adopt the attached resolutions accepting the improvement
and establishing the final contract amount for the Mississippi Riverwalk Phase I, River's
Edge Plaza and Alternate Component Projects.
Prepared by Robert Schiesl, P.E., Civil Engineer
cc: Pauline Joyce, Administrative Services Manager
Laura Carstens, Planning Services Manager
RESOLUTION NO. 368-03
ACCEPTING IMPROVEMENT
Whereas, the contract for the Mississippi Riverwalk Phase I - River's
Edge Plaza and Alternate Component has been completed and the City Manager
has examined the work and filed his certificate stating that the same has been
completed according to the terms of the contract, plans and specifications and
recommends its acceptance.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF DUBUQUE, IOWA:
Section 1. That the recommendation of the City Manager be approved
and that said improvement be and the same is hereby accepted.
BE IT FURTHER RESOLVED that the City Treasurer be and he is hereby
directed to pay to the contractor from the General Fund in amount equal to the
amount of his contract, less any retained percentage provided for therein.
Passed, approved and adopted this 6th
day of October , 2003.
Terrance M. Duggan, Mayor
Jeanne F. Schneider, CMC, City Clerk
RESOLUTION NO. 369-03
FINAL ESTIMATE
Whereas, the contract for the Mississippi Riverwalk Phase I - River's
Edge Plaza and Alternate Component has been completed and the City Engineer
has submitted his final estimate showing the cost thereof including the cost of
estimates, notices and inspection and all miscellaneous costs.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF DUBUQUE, IOWA:
Section 1. That the cost of said improvement is hereby determined to
be $767,761.20 and the said amount shall be paid from the General Fund.
Passed, approved and adopted this 6th day of October, 2003.
Terrance M. Duggan, Mayor
Attest:
Jeanne F. Schneider, CMC, City Clerk
Te~'rance M. Dugg~'or
City of Dubuque - Engineering Division
Final Payment Form
PARTIAL PAYMENT NO: COUNCIL FINAL
DATE: 26-Sep-03
PROJECT:
pHASE I - RIVER'S EDGE PLAZA CONSTRUCTION
MISSISSIPPI R1VERWALK PROJECT
CONTRACTOR: RENAISSANCE CONSTRUCTION CORPORATION
CONTRACT AMOUNT: $478,349.50
BIDITEM UNIT UNIT COST
Qu33qT1TY AMOUNT EARNED
TO DATE TO DATE
1 MOBILIZATION
2 CONSTRUCTION FENCE (FIELD FENCE)
3 CONSTRUCTION ]LAYOUT STAKING
4 SILT FENCE, 2tYPE I~VY DUTY
5 CLEAR AND GRUB TREE
6 SAWCUT BITUMINOUS PAVEMENT
7 REMOVE AND S32LVAGE pARK BENCH
8 REMOVE AND DISPOSE ASPHALT PATH
9 REMOVE AND DISPOSE CONCRETE PAD AND FOUNDATION
10 COMMON EXCAVATION
11 RIPP~P
12 O RANULAR F1LL(LE. PERVIOUS FILL)
13 COLOKED CONCRETE WALK
14 COLORED CONCRETE RETAINING WALL
15 NORMAL CONCRETE FOOTING FOR RKrAINTNG WALL
16 COLORED CONCRETE STEPS
17 DECORATIVE GUARDRAIL
18 METAL HA/'IDRAIL
19 ]~'p,_NISH AND INSTALL MOORING CLEAT
20 FURIqlSH AND INSTALL REMOVABLE STEEL RAMP AND
HANDRAIL
21 FLrRN1SH AND INSTALL NEaRr LIGHT FIXTURES - TWO
LUMINA1RES
22 g6 CONDUCTOR/GROUND
23 fi8 CONDUCTOR/GROUND
24 #1/0 WG (CU) CONDUCTOR/GROUND
25 1-1/4" RIGID PVC CONDUIT
26 2" RIG1D PVC CONDLqT
27 2" RIGID STEEL CONDUIT
28 ELECTRICAL SERVICE CONNECTION SERVICE POINT
EQUIPMENT ENCLOSURE
29 EXTERIOR ELECTRICAL RECEPTACLE
30 PAINT EXISTING BOLLARDS
31 pRAIRIE SEED MIX
32 pRAIP-IE PLANTS (PEAT POT)
LUMP SUM $9,000.00 I $9,000.t}0
LIN FF $3.00 350 $1,050.00
LUMP SUM · $8,250.00 l $8,250.00
LIN 1Fr $2.00 DELETED
EACH $65.00 DELETED
L1NFT $250 20 $50.00
EACH $30.00 DELETED
S.F. $0.40 3688 $1,475.20
$6.00 2374 $14,244.00
C.Y. $11.00 451 $4,96l .00
C.Y. $30.00 445 $13,350.00
TON $12.00 3052.14 $36,625.68
St. $7.50 12226.85 $91,70128
C.F. $22~0 41715 $91,773.00
Ct. $10.00 3034.63 $30,346.30
S.F. $70.00 1722.9 $120,603.00
LIN FI' $148.00 134.7 $19,935.60
LIN Fr $52.00 453.7 $23,592.40
EACH $1,000.00 DELETED
LUMP $8,809.00 1 $8,809.00
EACH $6,090.00 6.00 $36,540.00
LIN FT $l.00 870 $870.00
LIN FT $0.70 435 $304.50
LIN Fl? $2.00 1015 $2,030.00
LIN Fl' $7.30 754 $5,504.20
LINi~T $15.70 339 $5~22.30
LIN FT $171.00 10 $1,710.00
EACH $9,531.00 1 $9,531.00
EACH $580.00 1 $580.00
EACH $40.00 3 $120.00
S.F. $0.35 DEL~
EACH $5.20 DELETED
ADD CHANGE ORDER - EXTRA WOPdK ITFJql
33 CASCADING STAIRS, PERIMPTER FOUNDATION WALLS,
COMPLETE
34 REINFORCING STEEL, EPOXY COATED
35 REINFORCING STEEL, STEPS, ADDITIONAL LABOR
36 COLORED CONCRETE STEPS, ADD COLOR HARDENER TO
TRED AND RISER STEP SURFACES
37 COLOREI) CONCRETE WALK, ADD COLOR HARDENER TO
QUARRY RED BANDING FLATWORK
38 RETAINING WALL FORM LINER, 24" CUT LIMESTONE
UNIT UNIT COST QUANTITY AMOUNT EARNED
TO DATE TO DATE
LIN FI' $262.42 67 $17,582.14
LUMP SUM $14,449.06 I $14,449.06
LUIvIP SUM $5,497.00 1 $5,497.00
S.F. $4.60 2650.7 $12,193.22
S.F. $1.35 3051 $4,118.85
LUMP SUM $15,715.00 I $15,715.00
39 LIGHT FIXTU1LE, MULTI42OLOR POLE, FACTORY SETUP
CHARGE
40 ELECTRIC SERVICE Dt~RADE, 200 Amp, 3 PHASE SERVICE
41 ADD TELCOM CONDUIT, POWER & TELCOM PEDESTALS
42 STAINLESS STEEL ANCHOR BOLTS FOR LIGIfT BASES
43 4" PVC SCIf 80 - STUB FOR FUTURE SPRENvKLER SYSTEM
44 FILLCONCRE'f~, SMALL WALL, LOWERRAMP
45 BANDING, EROSION CONTROL WALL
46 PAVILION, FOUNDATION FOOTINGS
47 CLAY, 6", FURNISH & pLACEMENT
48 TOPSOIL, 6", FURNISIt & PLACEMENT
49 SODDING, EQUIPMENT PLACEMENT
50 SODDING, HAND pLACEMENT
51 SANDBLAST RETAINING WALL SUP&ACE, 24" CUT
LIMESTONE
52 REMOVABLE RAMP, CItANGE TO ALUMINUlVl DIAMOND
PLATE
53 BASE STONE, TEM?ORARY FLOOD GATE RAMP
54 RIPRAP, 6 ", ItAND PLACEMENT
55 FLOOD GATE, 'I~EMPORARY WOOD RAMP
56 MOORIlqG ANCHORS, SPIRIT OF DUBUQUE
57 RETAINING WALL FOPdM LINER, 12"CUTLIMESTONE, LOVvnI~R
RAM?
58 CAST STONE pIER CAP, LABOR & CRANE TO SET CAP
59 FILTER FABRIC UNDER CONCRETE PAVEMENT
60 CASCADING STA1RS, LOWER FOUNDATION WALL,
TEMPOgARY HEAT
61 RETAINING WALL CAP STONE, PASTE & TEXIUItE
62 DEDUCT- REDO CHAULK JOINTS
LUMP SUM $480.00 I $480.00
LUMP SUM $5,165.00 1 $5,165.00
LUI~IP SUM $10,765.00 1 $10,765.00
EACH $25.00 24 $600.00
LiN FF $20.00 10 $200.00
C.Y. $100.00 2 $200.00
C.Y. $150.00 2 $300.00
LUMP SUM $5,335.85 I $5,335.85
C.Y. $15.00 161~ $2,422.50
C.Y. $21.00 162 $3,402.00
S.Y. $6.90 560 $3,864.00
S.Y. $6.90 258 $1,780.20
LUMP SDld $780.00 1 $780.00
LUMP SUM $4,636.74 1 $4,636.74
TON $10.00 12.98 $129.80
TON $23.07 10.53 $242.93
LUMP SUM $820.00 I $820.00
LUMP SUM $260.00 I $260.00
LUMP SUM $1,200.00 I $1,200.00
LLrMPSUM $560.00 I $560.00
S.F. $0.16 12227.00 $1,956.32
LLrMPSUM $73339 1 $733.39
LUMP SUM $2,250.00 1 $2,250.00
LUMPSLrM ($1,000.00) 1 ($1,000.00)
TOTAL DUE CONTRACTOR: [ $654,917.55 J
CERTIFICATE OF THE CITY MANAGER:
I hereby certify that the above state~nent shows in de~il the correct mount of all work required to completo the above improve~nent.
APPROVED:
Michael Van Milligen, City Manager
City of Dubuque, Iowa
Michael A. Koch, Public Works Director
City of Dubuque, Iowa
CERTIFICATE OF THE CONTRACTOR:
The [mdersigned,
contractor for the above improvement, does hexeby
City of Dubuque - Engineering Division
Final Payment Form
PARTIAL PAYMENT NO: COUNCIL FINAL
PROSECT: RIVER'S EDGE PLAZA CONSTRUCTION - ALTERNATE COMPONENT
MISSISSIPPI RIYERWALK PROJECT
CONTRACTOR: RENAISSANCE CONSTRUCTION CORPORATION
BID ITEM UNIT
DATE: 26-Sep-03
CONTRACT AMOUNT: $121,288.50
UNIT COST QUANTITY AMOUNT EARNED
TO DATE TO DATE
I KEMOVE AND DISPOSE CONCRETE SIDEWALK S.F $0.85 3126.6 $2,657.61
2 REMOVE AND DISPOSE CONCRETE STEPS S.F. $10.00 16 $160.00
3 SAWCUT BITUMINOUS PAVEMENT LIN Fr $2.00 122.5 $245.00
4 SAWCUT CONCRETE PAVEMENT LIN let $4.00 9 $36.00
5 REMOVE ANrD DISPOSE CONCRETE CURB AND GU 11ER LINFT $5.00 184 $920.00
6 REMOVING RAILING LIN FT $4.00 20- $80.00
7 RELOCATE ELECTRICAL PANEL EA $3,125.00 1 $3,125.00
8 COMMON EXCAVATION C.Y. $11.00 280 $3,080.00
9 GRANULAR FILL (I.E. PERVIOUS FILL) C.Y. $24.00 178.21 $4,277.04
10 R1PRAP C.Y. $30.00 25.74 $772.20
11 FURNISH AND INSTALL NEW BIKE RACI< EACH $125.00 DELETE
12 F&I NEWLIGHTFIXTLrRES-TWOLUMINAIRES EACH $6,090.00 4 $24,360.00
13 g6 CONDUCTOR/GROUND LINFT $1.00 582.0 $582.00
14 #8 CONDUCTOR/GROUND LIN FT $0.70 291.0 $203.70
15 # 10 CONDUCTOR/GROUND L1NFT $0.65 DELETE
16 1 - 1/4" RIGID PVC CONDU1T LINFT $7.30 30t.0 $2,197.30
17 COLORED CONCRETE WALK S.F. $7.50 5461.28 $40,959.60
t8 CONCRETE WALK S.F. $2.75 163.88 $450.67
19 CONCRETE CUP, B AND GUTrER LINFT $15.00 100.9 $1,513.50
20 ASPHALTIC CONCRETE BINDER PATCH TON $100.00 52.54 $5,254.00
21 PEDESTRIAN CURB RAMP EA $475.00 1.0 $475.00
22 4" WIDE SOLID PAINT STR1PE LINFT $1.00 DELETE
23 PAVEMENT MESSAGE (HANDICAP) EACH $25.00 DELETE
24 SOD S.Y. $6.90 731 $5,043.90
25 IRRIGATION SYSTEM LUMP $7,475.00 DELETE
26 CONSTRUCTION LAYOUT STAKING LUMP SUM $4,230.00 DELETE
BASE BID CARRY-OVER ITEMS & EXTRA WORK 1TEMS
UNIT UNIT COST QUANTITY AMOUNT EARNED
TO DATE TO DATE
27 CLEAR AND GRUB TREE EACH $65.00 1 $65.00
28 REMOVE AND DISPOSE ASPHALT PAVEMENT S.F. $0.40 2804.26 $1,121.70
29 COLORED CONCRETE WALK, ADD COLOR HARDENER TO S.F. $1.35 1616.88 $2,182.79
QUARRY RED BANDING FLATWORK
30 CONCRETE PAVE~ - ADDITIONAL THICKNESS S.F. $3.75 1243 $4,661.25
31 TRENCH EXCAVATION FOR UTILITY RELOCATION (SPIRIT LUMP SUM $2,896.50 1 $2,896.50
OF DBQ.)
32 ELECTRIC SERVICE, RECONFIGURE CONDUIT (SPIRIT OF LUMP SUM $625.60 I $625.60
DBQ.)
33 CONCRETE FOUDATION - UTILITY PAD (SPIRIT OF DBQ.) LUMP SUM $1,037.30 1 $1,037.30
34 SEGMENTAL RETAINING WALL - UTILITY PAD (SPIR1T OF LUMP SUM $726.05 I $726.05
DBQ.)
35 BASE STONE, ACC PAVEMENT TON $10.00 18.03 $180.30
36 TOPSOIL, 6", FLrRNISH & PLACEMENT C.Y. $21.00 20 $420.00
37 2" RIGID PVC CONDUIT LINFT $15.70 55 $863.50
38 4' RIGID PVC CONDUIT LIN FT $4.31 243 $1,047.33
39 FILTER FA BRIC LrNDER CONCRETE PAVEMENT
40 DEDUCT - REDO CHAULK JOINTS
S.F. $0.16 5461.28 $873.80
LUMP SUM ($250.00) t ($250.00)
TOTAL DUE CONTRACTOR:
CERTIFICATE OF ~ CITY MANAGER:
$112,843.65 ]
I hereby certify that the above statement shows in detail the correct amount of a~l work required to complete the above improvement.
APPROVED:
Michael Van Milligen, City Manager
City of Dubuque, Iow;
Michael A. Koch, Public Works Director
City of Dubuque, Iow~
CER I'IIqCATE OF '1'1-I~ CONTRACTOR:
The undersigned, contractor for the above improvement, does hereby
accept the above ~Totat Due Con~cactor", as full settlement for all claims for said improvement. ~'~£P
CITY OF DUBUQUE, IOWA
MEMORANDUM
COPY
April 2, 2001
TO:
Michael C. Van Milligen, City Manager
Michael A. Koch, Public Works Director
FROM: Robert Schiesl, Civil Engineer
SUBJECT: River's Edge Plaza Project Construction Alternative
The purpose of this correspondence is to update you on the status of the River's Edge Plaza
project, and obtain direction on the request to proceed with the alternate component of the project.
Steve Boge, of Renaissance Construction, has requested that the City authorize his company to
proceed with the alternate bid component, and has a~:eed to honor his bid unit prices. To briefly
summarize, sealed bids were received on the River's Edge Plaza project on September 14, 1999.
The following is a summary of the bids received:
Base Bid
Base Bid Alternate with Alternate
Renaissance Construction
Portzen Construction
Tschiggfrie Excavating
$478,349.50
$617,457.90
$770,637.35
$121,288.50
$110,978.25
$140,064.65
$599,638.00
$728,436.15
$910,702.00
The construction contract was awarded to Renaissance Construction for the base bid component
only. The alternate phase of the project was not awarded due to uncertainty with the new casino
owners and ~hotel development.
The alternate phase of the project is located between the floodwall and the Welcome Center
building. The alternate includes the removal of the existing sidewalk, constructing .a small plaza
area adjacent to the floodwall, constructing new sidewalk from the plaza area to the Welcome
Center and the installation of three (3) ornamental light fixtures. The esthetic appearance of the
alternate components Will match those of the base bid (River's Edge Plaza), including buff
colored field areas, quarry red accent banding and a stamped slate texture surface.
In reviewing the bids received in September 1999, Renaissance was low on the base bid and the
overall 'bid (base,-plus alternate), however, when you look at the alternate bids separately,
Renaissance was not [ow1 Giving consideration ti) the overall low bid, and the co,remitment of
Renaissance to honor there bid unit prices, which are 1-'½ 'y~ars old, it is my recorm~endation
that the City authorize the construction of th~ alternate components.
Should the City elect to re-bid the River's Edge Plaza alternate components, it is ~iifficult to
predict if bids would come in competitive With those previously received. Given the increase in
fuel costs, this has a direct impact on raw mater/al and equipment costs, however, it is difficult to
judge or predict the hungry factor of perspective contractors.
The project funding summary for the current contract (River's Edge Plaza base bid) is as follows:
Construction Contract
Contingency
Total Project Budget:
Renaissance Contract
$478,349.50
$ 59,076.60
$537~426.10
As presented in a previous memo, the projects costs have increased as a result of discrepancies
with the construction plans, incorrect "per plan" concrete quantities and design constmctability
issues. Additionally, staff was authorized to incorporate the application of the quarry red surface
hardener to the accent banding and cascading stairs, incorporate the cut limestone surface texture
to the concrete retaining wall, and install additional conduit and pedestals for future
telecommunications and power outlet applications. The following is a breakdown of the current
contract (base bid) projects costs:
Renaissance Construction Contract: $478,349
Cascading Stairs Foundation Walls: $ 15,500
Construction Quantities Adjushment: $ 40,000
Colored Concrete Surface Hardener: $ 16,000
Limestone Surface Texture, Retaining Wall: $ 11,250
Telecommunications/Power Conduit & Pedestals: $ 11,000
Electric Service Upgrade, 200 Amp: $ 5,000
Current Contract (Base Bid) Projected Cost: $5777100
Should you concur with the recommendation to authorize Renaissance proceed with the
construction of the alternate components, the project cost surm~ary for the River's Edge Plaza
project is as follows:
Renaissance Construction Contract:
Adjusted Quantities & Approved Change Orders:
River's Edge Plaza Alternate Component:
Total Projected Construction Cost:
BUDGETIMPACT
$478,349
$ 98,750
$121,289
$698.389
The current contract (River's Edge Plaza base bid) is approximately $39,700 over budget. Should
the City proceed with the alternate components, the total construction cost is projected at
$698,389, which is approximately $161,000 over budget. Upon reviewing the available funding
options with Pauline, there exists sufficient contingency in the remaining components of the
Riverwalk project to cover the overage.
ACTION STEP
Upon reviewing the River's Edge Plaza project with Barry, he has advised me that the City could
issue a change order to the existing contract and authorize Renaissance proceed with the
construction of the alternate components, and advise or request City Council concurrence via
Please provide direction on a course of action for the alternate component of the River's Edge
Plaza project. Should you have any questions, please advise.
CC:
Pauline Joyce, Administrative Services Manager
Laura Carstens, Planning Services Manager
CITY OF DUBUQUE, IOWA
MEMORANDUM
February 18, 2000
TO:
Michael C. Van Milligen, City Manager
Michael A. Koch, Public Works Director
FROM: Robert Schiesl, Civil Engineer
SUBJECT: River's Edge Plaza Project Status
The purpose of this correspondence is to update you on the status of the River's
Edge Plaza construction and advise you of the anticipated increased cost associated
with the project.
Renaissance Construction has completed the lower foundation wall for the cascading
stairs and are continuing to construct the step perimeter foundation wails which
extend up to the plaza area. The contractor anticipates having the lower elevation
foundation walls, which are susceptible to spring river levels completed within the
next two (2) weeks. The contractor will then start construction of the cascading
stairs, beginning with the bottom lower elevation stair(s) and work their way out of
the potential high water areas.
According to the Corps of Engineers, within the weeks to follow, the river will begin
to rise as a result of the projected unseasonably warm temperatures and spring snow
melt to the north.
Over the past month, I have had several conversations and meetings with
Renaissance Construction, Architectural Concrete Systems (subcontractor) and BRW
to resolve discrepancies with the construction plans and to resolve design issues.
During this process, it was brought to my attention by the contractor that the
concrete construction quantities do not appear to be accurate. Given this, I decided
to check and recalculate the "per plan" concrete quantities. In doing so, I discovered
that the concrete quantities provided by BRW in the bid documents and subsequent
construction contract are not correct and do not accurately reflect the "per plan"
construction quantities. In recalculating the "per plan" concrete quantities and using
the contract unit prices, BRW under estimated the concrete quantities by
approximately $39,734.
The project funding summary for the River's Edge Plaza construction project is as
follows:
Construction Contract
Contingency
Total Project budget:
Renaissance Contract
$478,349.50
$ 59.076.60
9537.426.10
Based on the recalculated "per plan" quantities and using the contract unit prices for
the project, outlined below per bid item are the adjusted project quantities and the
associated contract cost adjustment.
Contract Bid Items
Colored Concrete Walk
Colored Concrete Retaining Wall
Concrete Footing for Retaining Wall
Colored Concrete Steps
Ornamental Lights
Bid Contract
Quantity
Recalculated Contract Cost
Quantity Ad!ustment
12275 SF $ - 3,186.00
3695 CF + 15,290.00
2853 CF + 1,940.00
1650 SF + 19,600.00
6 Each + 6.090.00
Total Contract Increase: (;39,734.00
12700 SF
3000 CF
2659 CF
1370 SF
5 Each
Construction Contract:
Quantities Adjustment:
Adjusted Project Cost:
Contingency Balance:
(;478,349.50
$ 39.734.00
(;518,083.50
(; 19,342.60
I have informed BRW of the discrepancy in the plan quantities and forwarded copies
of my recalculation documentation for their review. BRW has concurred with my
recalculations and has yet to provide an acceptable justification for what I consider to
be an unacceptable error or omission.
BRW's response has been to provide what they call "value engineering
considerations" which would bring the project cost down to "near budget numbers"
by reducing the quantity of plaza constructed. BRW has proposed shortening the
cascading steps thus reducing the stair square footage and a potential saving of
approximately (;10,360. BRW also proposed reducing the width of the large curved
retaining wall from 24"(as bid) to 18" wide, which would potentially save (;21,946. ~
questioned BRW on the proposed wall modifications and they advised me that an 18"
wall design will be structurally sufficient and that the 24" wide wall was for
architectural esthetics.
The "value engineering considerations" proposed by BRW would not work because
the foundation walls for the cascading steps are partially in-place. Additionally, I
discussed the proposed wall modifications with Renaissance Construction and they
will not agree to a deduct of approximately 821,946 for the curved retaining wall.
The contractor's position is that certain cost are present including rented curved
formwork, reinforcing steel, labor and equipment and the concrete cost savings
would not offset the associated fixed costs. I concur with the assessment of the
contractor.
In an attempt to resolve discrepancies with the construction plans which do not
clearly show nor provide details for the construction of step perimeter foundation
walls, I directed BRW to revise the plans to include the necessary step foundation
walls and provide cross-sections for construction. Since the step perimeter
foundation walls are a required structural element and the construction plans failed to
provide adequate information for the contractor to include in their step square foot
unit cost, I have directed the contractor to construct the necessary step foundation
walls and authorize this work to be performed under an extra work item. The current
contract does not have a specific bid line item for cascading step walls thus the
contractor will be performing this work on a cost-plus basis. I have estimated the
cost of the extra work item to be in the range of $15,000.
Construction Contract:
9478,349.50
Quantities Adjustment:
Extra Work - Step Foundation Walls:
Adjusted Project Cost:
Contingency Balance:
$ 39,734.00
~ 15,000.00
~533,083.50
$ 4,342.60
It should be noted that the project has just begun and the contingency funding
allocated has been reduced from $59,076 to approximately $4,342. Additionally,
since the project is in such an early stage, there are certain unknown conditions
which may further effect construction quantities and potentially increase final project
costs.
.ACTION STEP
This memo is for informational purposes only, should you have any further questions
please advise.
CC:
Pauline Joyce, Administrative Services Manager
Laura Carstens, Planning Services Manager
CERTIFICATE of COMPLETION and
FINAL ACCEPTANCE of AGREEMENT WORK
COMPANY: BRW COUNTY/CITY: _Dubuque/Dubuque_
ADDRESS: 700 Third Street South, Minneapolis, MN _ 5415 PROSECTNO,: STP-E-2100 ~)-8V-31
KIND OF WORK: Prelimina~_Desi _gn m~d Eng~eer~i.n_$.g fg~r_t)~e Mi.s.~i Riverwalk
AGREEMENT DATE: ~Jtme 5~ 1996 FIELD COMPLETION DATE: Jnne t2, 2003
This is to certify that the work covered by tho above referenced agreement has been completed in accordaace with said
agreement and is hereby accepted, subject to final audit of costs.
~'~OJ~ A~. ~~ DATE: Septembe~ 5 2003
SIGNATURE:
~ec{ F,n~il err (ResY-C~cfion) (Res. Main[chance) (Coun~>) (City) (C ) Year
*SIGNATORE: DATE: ,
I){siriet (Cx)~tl",;clion) (Maint~ane~) (Local Systen~s) F, ngln cer Year
^pproved enid work accepted by tho Board of Supervisors/City Couucil of Dubuque
this 5th Day of September .., 2003
.............. year
SIGNATURE: ,
Acknowledge completion of project in a<or&nce with referenced agreement by ~e Iowa Dep~ment of Tmnspogation
this ......... Day of
SIGNATURE:
*On Local State Assisted
Projects District does
NOT certify but
ack~owlodges