TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: North Fork Catfish Creek Stormwater and Sanitary Sewer Improvements
Project - Phase 11
DATE: October 25, 2010
City Engineer Gus Psihoyos is recommending acceptance of the public improvements
project and the construction contract for the North Fork Catfish Creek Stormwater and
Sanitary Sewer Improvements Project – Phase II, as completed by Portzen
Construction, Inc., in the final contract amount of $1,052,308.47, which is a 5.5%
increase from the original contract amount of $997,168.00. The main reason for the
increase was due to soil conditions that required a wider trench resulting in more backfill
and pavement restoration.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
MCVM:jh
Attachment
cc: Barry Lindahl, City Attorney
Cindy Steinhauser, Assistant City Manager
Gus Psihoyos, City Engineer
4
//—----
Michael C. Van Milligen
Masterpiece on the Mississippi
TO: Michael C. Van Milligen, City Manager
FROM: Gus Psihoyos, City Engineer
SUBJECT: North Fork Caffish Creek Stormwater and Sanitary Sewer Improvements
Project — Phase II
DATE: October 22, 2010
INTRODUCTION
The enclosed resolution provides for the acceptance of the public improvements project
and the construction contract for the North Fork Catfish Creek Stormwater and Sanitary
Sewer Improvements Project — Phase II.
BACKGROUND
The North Fork Catfish Creek Stormwater and Sanitary Sewer Improvements Project —
Phase II involved the replacement of 1,595 feet of 12 -inch diameter clay sanitary sewer
with 24 -inch diameter ductile iron sewer from Kensington Place, through the
Pennsylvania /John F. Kennedy intersection, north to Keystone Drive.
DISCUSSION
The North Fork Catfish Creek Stormwater and Sanitary Sewer Improvements Project —
Phase II was completed by Portzen Construction, Inc. of Dubuque, Iowa, in the final
contract amount of $1,052,308.47, which is a 5.5% increase from the original contract
amount of $997,168.00. The main reason for the increase was due to soil conditions that
required a wider trench resulting in more backfill and pavement restoration.
RECOMMENDATION
I recommend that the City Council accept the improvements and authorize the payment of
the contract amount of $1,052,308.47 to Portzen Construction, Inc. for the North Fork
Caffish Creek Stormwater and Sanitary Sewer Improvements Project — Phase II.
BUDGET IMPACT
The summary of costs for the North Fork Caffish Creek Stormwater and Sanitary Sewer
Improvements Project — Phase II is as follows:
Award
Construction Contract $ 997,168.00 $1,052,308.47
Contingency 91,901.46
Engineering 111,091.61 157,864.94
Property Acquisitions 5,000.00 5,643.83
Total Project Cost $1,205,161.07 $1,215,817.24
Final
Dubuque
NI- AmedcaCl4
11 11 1'
2007
The sanitary sewer portion of the project will be funded from the Fiscal Year 2007, 2008,
and 2009 appropriations for the North Fork Catfish Creek Interceptor Upgrade — University
Avenue to the Northwest Arterial (CIP #7101802) in the amount of $1,904,250. The
stormwater improvements will be funded from the Fiscal Year 2005 appropriation for the
Pennsylvania /John F. Kennedy Culvert Improvement (CIP #7201658) in the amount of
$169,125.
Sanitary sewer improvements associated with all three phases of the North Fork Catfish
Creek Stormwater and Sanitary Sewer Improvements Project are eligible for the FEMA
Hazard Mitigation Grant Program funds. The City borrowed the balance of funds through
the State Revolving Loan Fund (SRF) program and was awarded ARRA stimulus funds
through the SRF program in the form of a forgivable loan. The funding source breakdown
for all three phases of North Fork Catfish Creek Stormwater and Sanitary Sewer
Improvements Project is outlined below:
Phase I
Phase II
Phase III
TOTAL PROJECT COST $ 3,960,327.84
Sanitary Sewer Construction Funds
Stormwater Utility Funds
FEMA HMGP Funds
ARRA Funds
TOTAL PROJECT FUNDING $ 3,960,327.84
ACTION TO BE TAKEN
The City Council is requested to adopt the attached resolution to accept the improvements
and to authorize the payment of the contract amount of $1,052,308.47 to Portzen
Construction, Inc. for the North Fork Catfish Creek Stormwater and Sanitary Sewer
Improvements Project — Phase II.
Prepared by Deron Muehring
cc: Barry Lindahl, City Attorney
Jenny Larson, Budget Director
Ken TeKippe, Finance Director
Deron Muehring, Civil Engineer II
Project Cost
$ 896, 932.65
$ 1,215,817.24
$ 1,847,577.95
$ 1,102, 959.13
$ 875,945.88
$ 1,627,112.50
$ 354, 310.33
THE CITY OF
DUB
Masterpiece on the Mississippi
n
EMBASSY CT
CHAVENELLE RD
EC ee
O z s . v _ g
is
b m z re
1 SHORT ST C
1 AURORA ST I cp cm -1
o
u.
cm
-1 KEYSTONE DR X n To
0 F KEYMONT DR ! e..
Z 0°G1
Z.
to so tC
0 Wo DR to
rn DANIELS ST
IDEAL LN
4.
r A 41%
STONEMAN RD 4, 41, 0
70
DISCLAIMER: Informal., was compiled
ususing Dubuque o. area . I bn System
(OASIS), S), which which Includes day data created by both by both the CID of
Dubuque O. DDubuque County. ft 4 understood that, while
the any of t Dubuque and .MDdp.rq agencies marred the
»d xcurete Mforneu» ayMbe1, DADIS one
htf motio ha not w ntar d *. M oCcun»c y of tlw
Mf� tbn or data c» n 1 11. here,,. Me any »d , Incidental,
m shag not be e o en Ogle eo tlrM, indeed, ,see
u is Oats r M e M edl out of e t authorized
dauthorized zed out unauthorized of any eac use of
this data o Me „abgty to use this or a,n f any breach of
w«r»er wnameyer.
WE
Interceptor Sewer Improvements s
North Fork Catfish Creek
Phase I
Phase II
Phase III
re
G
F
z
W
re
0
W re
0 01(0 4 Gi
1 inch = 1,000 feet
500 250 0 500 Feet
UNIVERSITY AV CONN
DODGE ST
Dubuque
an- 8menca cm
2007
Map Prepaired by
City of Dubuque
Engineering Department
50 West 13th Street
Dubuque, Iowa 52001
Phone: (563) 589 -0270
Fax: (563) 589 -4205
RESOLUTION NO. 418 -10
ACCEPTING THE NORTH FORK CATFISH CREEK STORMWATER AND SANITARY
SEWER IMPROVEMENTS PROJECT — PHASE II AND AUTHORIZING THE
PAYMENT OF THE CONTRACT AMOUNT TO THE CONTRACTOR
Whereas, the Public Improvement Contract for the North Fork Catfish Creek
Stormwater and Sanitary Sewer Improvements Project — Phase II (the Project) has
been completed and the City Engineer has examined the work and filed a certificate
stating that the Project has been completed according to the terms of the Public
Improvement Contract and that the City Engineer recommends that the Project be
accepted; and
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF DUBUQUE, IOWA:
Section 1. The recommendation of the City Engineer is approved and the Project
is hereby accepted.
Section 2. The Finance Director is hereby directed to pay to the Contractor from
the Catfish Interceptor Reconstruction, North Fork Sanitary Sewer Improvements, and
the Pennsylvania /John F. Kennedy Culvert Improvement appropriations for the contract
amount $1,052,308.47 less any retained percentage provided for therein as provided in
Iowa Code chapter 573, and to pay such retainage only in accordance with the
provisions of Iowa Code chapter 573.
Attes
Passed, approved and adopted this 1s t day of November, 2010.
y,69,U
Roy D. Buol, Mayor
eanne F. Schneider, CMC, City Clerk
CITY ENGINEER'S CERTIFICATE OF FINAL COMPLETION OF THE NORTH FORK
CATFISH CREEK STORMWATER AND SANITARY SEWER IMPROVEMENTS
PROJECT — PHASE II
The undersigned City Engineer of the City of Dubuque, Iowa, hereby certifies that
he has inspected the North Fork Catfish Creek Stormwater and Sanitary Sewer
Improvements Project — Phase 11, that the Project has been performed in compliance
with the terms of the Public Improvement Contract, and that the total cost of the
completed work is $1,215,817.24.
Dated this d1.• day of (k.ros , 2010.
Filed in the office of the City Clerk on thec ay o I 2010.
City ngineer
eanne F. Schneider, CMC, City Clerk
ITEM
NO.
CONTRACT ITEM
DESCRIPTION
CONTRACT ITEM
QUANTITY UNIT UNIT PRICE
FINAL
QUANTITY TOTAL
PERCENT
COMPLETE
FEMA Eligible Ductile Iron Sanitary Sewer (24 -Inch)
1 Mobilization
1.00 LS $ 15,000.00
1.00 $ 15,000.00
100.00%
2 Clearing and Grubbing
1.00 LS $ 5,000.00
1.00 $ 5,000.00
100.00%
3 24" DIP Class 51 Sanitary Sewer, Depth less than 14'
1365.00 LF $ 98.00
1298.44 $ 127,247.12
95.12%
4 24" DIP Class 51 Sanitary Sewer, Depth greater than 14'
935.00 LF $ 235.00
1000.11 $ 235,025.85
106.96%
5 6" PVC SDR 26 Sanitary Sewer Lateral
10.00 LF $ 75.00
17.00 $ 1,275.00
170.00%
6 24" x 12" Reducer and Connection to Existing Sewer
1.00 EA $ 2,500.00
1.00 $ 2,500.00
100.00%
7 Select Sanitary Sewer Trench Backfill
855.00 LF $ 175.00
870.75 $ 152,381.25
101.84%
8 Tapping Saddle
1.00 EA $ 300.00
1.00 $ 300.00
100.00%
9 Rock Excavation
500.00 CY $ 150.00
500.00 $ 75,000.00
100.00%
10 PCC Pipe Encasement -24" DIP
96.00 LF $ 120.00
116.00 $ 13,920.00
120.83%
11 By -Pass Pumping
1.00 LS $11,200.00
1.00 $ 11,200.00
100.00%
12 Remove and replace storm sewer
80.00 LF $ 70.00
75.00 $ . 5,250.00
93.75%
13 Remove and Replace Water Main
60.00 LF $ 120.00
60.00 $ 7,200.00
100.00%
14 Erosion Control (SWPPP - inspections, maintainence, misc.
1.00 LS $ 2,000.00
1.00 $ 2,000.00
100.00%
15 Silt Fence or Filter Sock - install and remove
550.00 LF $ 2.50
291.00 $ 727.50
52.91%
16 Inlet Protection - install, maintain and remove
6.00 EA $ 100.00
3.00 $ 300.00
50.00%
17 Temporary Construction Entrance - install and remove
2.00 EA $ 1,000.00
2.00 $ 2,000.00
100.00%
18 Temporary Stream Crossing - install and remove
3.00 EA $ 1,500.00
3.00 $ 4,500.00
100.00%
19 Traffic Control
1.00 LS $ 35,000.00
1.00 $ 35,000.00
100.00%
20 Offsite Disposal of Soil (non - contaminated)
4800.00 CY $ 5.50
4800.00 $ 26,400.00
100.00%
21
FEMA Eligible Sanitary Sewer Manhole
Manhole Base for 60" Diameter Manhole
12.00 EA
$ 1,200.00
12.00
$ 14,400.00
100.00%
22
Manhole Base for 108" Diameter Manhole
1.00 EA
$ 2,500.00
1.00
$ 2,500.00
100.00%
23
48" ID Manhole Sidewall
9.00 LF
$ 110.00
9.00
$ 990.00
100.00%
24
60" ID Manhole Sidewall
208.00 LF
$ 185.00
195.00
$ 36,075.00
93.75%
25
108" ID Manhole Sidewall
6.00 LF
$ 550.00
6.00
$ 3,300.00
100.00%
26
Keyed Top Slab for 108" Manhole w/24" Opening
1.00 EA
$ 1,900.00
1.00
$ 1,900.00
100.00%
27
Manhole Cover and Frame
13.00 EA
$ 450.00
13.00
$ 5,850.00
100.00%
28
Internal Manhole Chimney Seal
13.00 EA
$ 400.00
11.00
$ 4,400.00
84.62%
29
Outside Manhole Drop
2.00 EA
$ 3,000.00
2.00
$ 6,000.00
100.00%
30
Temporary Concrete Washout - install and remove
1.00 EA
$ 1,000.00
1.00
$ 1,000.00
100.00%
32
FEMA Eligible Restoration of ROW
HMA Pavement
700.00 TON
$ 80.00
700.00 .
$ 56,000.00
100.00%
33
PCC Curb and Gutter, 30" Width
300.00 LF
$ 22.00
300.00
$ 6,600.00
100.00%
34
Engineering Fabric
300.00 SY
$ 3.00
507.66
$ 1,522.98
169.22%
35
Pavement Markings
1.00 LS
$ 2,648.00
1.00
$ 2,648.00
100.00%
36
PCC Pavement, Class C, T = 8" w/ Intergral Curb
910.00 SY
$ 44.00
909.46
$ 40,016.24
99.94%
37
Stone Base for Pavement
1200.00 TONS
$ 14.40
1332.06
$ 19,181.66
111.01%
38
PCC Sidwalk, T = 4"
360.00 SY
$ 50.00
314.86
$ 15,743.00
87.46%
39
PCC Pavement, Class C, T = 6" (Driveway)
60.00 SY
$ 54.00
70.80
$ 3,823.20
118.00%
THE CRY OF
DUB
Masterpiece on the Mississippi
Contractor Name:
Contractor Address:
City, State, Zip:
Contractor Telephone:
PROJECT CLOSE OUT FORM
Project Name:
CIP Number:
Project Contract Amount:
Project Completion Date:
North Fork Catfish Creek Stormwater &
Sanitary Sewer Improvements - Phase!!
7101802, 7201662, & 7102178
997,168.00
20- Nov -09
Portzen Construction Co.
205 Stone Valley Drive
Dubuque, IA 52003
563 -557 -7642
TOTAL CONTRACT WORK
Sub Total 1 $ 722,226.72
City of Dubuque
Engineering
50. W. 13th Street
Dubuque, IA 52001
(563) 589-4270
Sub Total 1 $ 76,415.00
Sub Total 1 $ 145,535.08
Sub Total
$ 20,731.07
I $ 964,907.87
NON -FEMA Eligible Items
31
Riprap
300.00 TONS
$ 20.20
357.33
$ 7,218.07
119.11%
40
Seeding (Turf Grass)
2.00 AC
$ 1,500.00
1.55
$ 2,325.00
77.50%
41
Structural Concrete (Headwall Collar)
15.00 CY
$ 500.00
0.00
$ -
0.00%
42
Offsite Disposal of Soil (petroleum contaminated)
4800.00 CY
$ 8.00
336.00
$ 2,688.00
7.00%
43
Catch Basin, Type 104 -B
2.00 EA
$ 2,500.00
2.00
$ 5,000.00
100.00%
44
Catch Basin, Type 105 -B
1.00 EA
$ 3,000.00
1.00
$ 3,000.00
100.00%
45
Reinforcing Steel
815.00 LBS
$ 1.00
500.00
$ 500.00
61.35%
THE CRY OF
DUB
Masterpiece on the Mississippi
Contractor Name:
Contractor Address:
City, State, Zip:
Contractor Telephone:
PROJECT CLOSE OUT FORM
Project Name:
CIP Number:
Project Contract Amount:
Project Completion Date:
North Fork Catfish Creek Stormwater &
Sanitary Sewer Improvements - Phase!!
7101802, 7201662, & 7102178
997,168.00
20- Nov -09
Portzen Construction Co.
205 Stone Valley Drive
Dubuque, IA 52003
563 -557 -7642
TOTAL CONTRACT WORK
Sub Total 1 $ 722,226.72
City of Dubuque
Engineering
50. W. 13th Street
Dubuque, IA 52001
(563) 589-4270
Sub Total 1 $ 76,415.00
Sub Total 1 $ 145,535.08
Sub Total
$ 20,731.07
I $ 964,907.87
NO.
DATE
TOTAL
CHANGE ORDER
CHANGE ORDER DESCRIPTION
TOTAL
CHANGE ORDER
AMOUNT
1.00
10- Aug -09
Offsite Disposal of Soil (non - contaminated), 4,464 CY @ $5.50
$
24,552.00
1.00
10- Aug -09
Offsite Disposal of Soil (petroleum contaminated), Change from 4800CY to 325CY
2.00
10- Aug-09
Reconnect 4" lateral (3280 Pennsylvania)
$
2,910.00
3.00
12- Aug-09
Reconnect 12" lateral (1690 Kennedy Road)
$
5,040.00
4.00
23- Sep -09
Add C -D Baskets & additional 1/2" depth of concrete for PCC Pavement
$
5,311.25
5.00
23-Sep-09
Additonal cost to convert Catch Basin, 105 -B to Catch Basin, Type 105 -B Special
$
600.00
6.00
22- Oct -09
Sawcutting & Asphalt Removal Associated with Sidewalk Replacement, NW Corner of JFK/Penn
$
446.64
7.00
22- Oct -09
Re- adjustment of MH222 due to modifed grade
$
628.00
8.00
22- Oct -09
Tie in additional sewer service (Arby's from JFK)
$
728.00
9.00
22- Oct -09
Sod & Seeding associated with restoring temporary business access on JFK
$
1,788.50
10.00
22- Oct -09
Detectable warning for curb ramps (8 EA @ $125.00)
$
1,000.00
11.00
22- Oct -09
Adjustment of water main fixtures added during construction & MH adjustments due to grade change
$
1,575.00
12.00
22- Oct -09
Additional asphalt (402.81 Tons) required on Sherwin Williams parking lot
$
32,224.80
13.00
22- Oct-09
Additional PCC Curb & Gutter (154.41 LF) required on Sherwin Williams parking lot
$
3,397.02
14.00
22- Oct -09
Additional PCC Pavement (60.04 SY) required for Sherwin Williams JFK driveway
$
3,242.16
15.00
14- Apr -10
Repair Slope & rip -rap drop -down at rear of Sherwin Williams
$
3,957.23
Total Contract Work Performed to Date:
Total Change Order Work Performed to Date:
Total Due Contractor: $ 1,052,308.47
Total miscellaneous Project Costs: $
Total Engineering Work Performed: $ 157,864.94
Total Land Acquisition and /or Easement Costs: $ 5,643.83
TOTAL PROJECT COST: $ 1,215,817.24
I hereby certify that the above statement shows, in detail, the correct
amount of all work required to complete the above improvement.
APPROVED:
Michael Van Milligen,
City of Dubuque, to
Gus Psihoyos, City Engineer
City of Dubuque, Iowa
Total Change Order Work Performed to Date:
PROJECT COST SUMMARY
The Undersigned, Portzen Construction, Inc., contractor for the above
improvement, does hereby accept the above "Total Due Contractor", as
full settlement for all claims for said improvement.
APPROVED:
BY:
964,907.87
87,400.60
$ 87,400.60
Pr y