2000 Resolution No. 418-00RESOLUTION NO.418 -00
FINAL ESTIMATE
Whereas, the contract for the Dubuque Industrial Center West - Phase I Project has
been completed and the City Engineer has submitted his final estimate showing the cost
thereof including the cost of estimates, notices and inspection and all miscellaneous costs;
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
DUBUQUE, IOWA:
Section 1. That the cost of said improvement is hereby determined to be
$5,622,265.19 and the said amount shall be paid from the Alliant loan ($800,000.00), DRA
Distribution and General Fund ($4,236,889.19), Storm Sewer Construction Fund
($137,800.00), and the RISE grant ($447,576.00) of the City of Dubuque, Iowa.
Passed, approved and adopted this 5th day of September, 2000.
Attest:
Jeanne F. Schneider, City Clerk
/4/LL.�..f/ ..�..�/
Fran, Mayor
Terrance M. D