Green Alley Project (Washington, Elm, 15th-16th Streets) AcceptanceMasterpiece on the Mississippi Dubuque AII•AmdicaCily 11111! 2007 TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager SUBJECT: Green Alley Project (15th - 16th, between Washington & Elm Streets) (CIPs 2622044, 7401405, 7101335) DATE: November 8, 2010 City Engineer Gus Psihoyos is recommending acceptance of the construction contract for the Green Alley Project (15 — 16 between Washington & Elm Streets), as completed by Connolly Construction, Inc. in the final contract amount of $164,306.81, which is a 6.7% increase from the original contract of $154,046.52. The cost increase was due to additional watermain valve replacement needed to properly shut down the watermain during the project. Also, the storm sewer line in 15 Street had to be repaired. I concur with the recommendation and respectfully request Mayor and City Council approval. MCVM:jh Attachment cc: Barry Lindahl, City Attorney Cindy Steinhauser, Assistant City Manager Gus Psihoyos, City Engineer Mich el C. Van Milligen Masterpiece on the Mississippi TO: Michael C. Van Milligen, City Mana e FROM: Gus Psihoyos, City Engineer SUBJECT: Green Alley Project (15 — 16 between Washington & Elm Streets) (CIPs 2622044, 7401405, 7101335) DATE: November 5, 2010 INTRODUCTION DISCUSSION Dubuque an- Amalcacily 1 2007 The enclosed resolution provides for the acceptance of the construction contract for the Green Alley Project (15 — 16 between Washington & Elm Streets). BACKGROUND The Green Alley Project (15 — 16 between Washington & EIm Streets) included: — Reconstruction of the alley pavement surface with interlocking concrete pavers between Washington & Elm Streets, from 15 Street to 16 Street. — Watermain reconstruction. — Replacement of seven (7) lead water services with copper. — New concrete sanitary manholes in the alley and on 15 and 16 Streets. Since the project was funded utilizing Community Development Block Grant, American Recovery & Reinvestment Act funds (CDBG /ARRA), no assessments were levied for the project. The Green Alley Project (15 — 16 between Washington & EIm Streets) was completed by Connolly Construction, Inc. of Peosta, Iowa, in the final contract amount of $164,306.81, which is a 6.7% increase from the original contract of $154,046.52. The cost increase was due to additional watermain valve replacement needed to properly shut down the watermain during the project. Also the storm sewer line in 15 Street had to be repaired. RECOMMENDATION I recommend that the City Council accept the improvements and establish the final contract at $164,306.81 for the Green Alley Project (15 — 16 between Washington & Elm Streets). BUDGET IMPACT The project cost summary for the Green Alley Project (15 — 16 between Washington & Elm Streets) is as follows: Construction Contract Contingency Construction Engineering & Inspection Total Project Cost The project funding summary is as follows: CIP No. 2622044 7401405 7101335 ACTION TO BE TAKEN Award $154,046.52 13,643.95 15,008.35 $182,698.82 Fund Fund Description Amount Community Development Block Grant Recovery Funds $79,995.28 Water Main Replacement Program 71,825.56 Sanitary Sewer Manhole Replacement Fund 24,161.78 Total Project Funding $175,982.62 The City Council is requested to adopt the attached resolution to accept the improvements and to authorize the payment of the contract amount of $164,306.81 to Connolly Construction, Inc. for the Green Alley Project (15 — 16 between Washington & Elm Streets). Prepared by Jon Dienst, P.E., Civil Engineer II cc: Jenny Larson, Budget Director Don Vogt, Public Works Director John Klostermann, Street & Sewer Maintenance Supervisor David Harris, Housing & Community Development Director Bob Green, Water Department Manager Bob Schiesl, Assistant City Engineer Aggie Tauke, Community Development Final $164,306.81 0.00 11,675.81 $175,982.62 RESOLUTION NO. 437-10 ACCEPTING THE GREEN ALLEY PROJECT (15 — 16 BETWEEN WASHINGTON & ELM STREETS) AND AUTHORIZING THE PAYMENT OF THE CONTRACT AMOUNT TO THE CONTRACTOR Whereas, the Public Improvement Contract for the Green Alley Project (15th — 16 between Washington & Elm Streets) (the Project) has been completed and the City Engineer has examined the work and filed a certificate stating that the Project has been completed according to the terms of the Public Improvement Contract and that the City Engineer recommends that the Project be accepted; and NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: Section 1. The recommendation of the City Engineer is approved and the Project is hereby accepted. Section 2. The Finance Director is hereby directed to pay to the Contractor from the Community Development Block Grant Recovery Funds, Water Main Replacement Program, and Sanitary Sewer Manhole Replacement Fund appropriations for the contract amount of $164,306.81 Tess any retained percentage provided for therein as provided in Iowa Code chapter 573, and to pay such retainage only in accordance with the provisions of Iowa Code chapter 573. Attest: Jeanne F. Schneider, CMC, City Clerk Passed, approved and adopted this 15th day of No vember 2010. Roy D. uol, Mayor CITY ENGINEER'S CERTIFICATE OF FINAL COMPLETION OF THE GREEN ALLEY PROJECT (15 —16 BETWEEN WASHINGTON & ELM STREETS) The undersigned City Engineer of the City of Dubuque, Iowa, hereby certifies that he has inspected the Green Alley Project (15 — 16 between Washington & Elm Streets), that the Project has been performed in compliance with the terms of the Public Improvement Contract, and that the total cost of the completed work is $175,982.62. Dated this 4th day of November, 2010. City Engineer Filed in the office of the City Clerk on the 9th day of November, 2010. eanne F. Schneider, CMC, City Clerk PARTIAL PAYMENT NO: COUNCIL FINAL PROJECT NAME: CONTRACTOR: Green Alley Pilot Project Connelly Construction, Inc. City of Dubuque - Engineering Division FINAL PAYMENT FORM BID ITEM DESCRIPTION EXCAVATION & STONE 1 Remove Pavement SY 2 Remove Existing Manhole Each 3 Excavation, Unclassified CY 4 Select Backfill Ton 5 Bedding and Void Opening Aggregates (ASTM #8 Washed stone) Ton 6 Porous Aggregate (ASTM #57 washed stone) Ton 7 Porous Aggregate (ASTM #2 washed stone) Ton 8 Backfill, Topsoil SY 9 Existing Curb & Gutter Removal (as indicated /approved by City Engineer) LF 10 Subbase Granular Material (6" Thick) Ton PAVEMENT 11 PCC Concrete Collar - Standard Concrete 12 Permeable Concrete Block Pavers 13 HMA 300k Headers & Streets, 1/2" (PG 64 -22) 14 HMA 300k Driveways, 1/2" (PG 64 -22) 15 PC Concrete Sidewalk, 4 ", Remove & Construct 16 PC Concrete Sidewalk, 6 ", Remove & Construct 17 PC Concrete Curb, 2.5', Construct 18 Geotechnical Fabric 19 Furnish & Install Green Alley Identifier Panel 20 PC Concrete Access Ramp, Detectable 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 WATER MAIN 10" DIP, Class 52 w. /Polywrap & Tracer Wire 3/4" Copper Service Line TYPE K 1" Copper Service Line TYPE K 3/4" Tap & Curb Box/Stop Box W/ installation 1" Tap & Curb Box/Stop Box W/ installation 10" RS Gate Valve & Box 6" RS Gate Valve & Box 10" x 10" Tee MJ 10 "x6" TeeMJ 10" 90 Degree Bend 10" Solid Sleeve 10" x 6" Reducer 10 "CapMJ 6" DIP w. /Polywrap & Tracer Wire 6" Solid Sleeve 10" Mega Lug 6" Mega Lug Fixture Adjustment, Valves & Manholes SANITARY SEWER 39 18" DIP w. /Bedding 40 48" Diameter Manhole Base 41 48" Diameter Manhole Sidewall 42 Manhole Frame & Cover UNIT SY SF Ton Ton SF SF LF SY Each Each LF Each VF Each MISCELLANEOUS 43 Sawcut, (Regardkess of Pavement Type) LF UNIT COST $3.85 $515.00 $9.15 $17.50 $17.50 $20.95 $26.70 $12.00 $6.85 $19.20 $38.30 $5.15 $106.01 $106.01 $4.35 $5.65 $16.80 $1.25 $155.00 $93.00 $126.00 $965.00 $125.00 $270.00 $3.15 CONTRACT AMOUNT: $154,046.52 QUANTITY TO DATE 703.00 3.00 250.00 992.89 35.68 166.41 256.47 75.00 62.70 128.10 130.70 3136.00 61.90 37.00 50.80 166.25 62.30 809.00 2.00 4.00 LF $55.10 341.30 LF $19.80 139.00 LF $20.90 10.00 Each $585.00 16.00 Each $615.00 1.00 Each $1,490.00 4.00 Each $802.00 4.00 Each $358.00 3.00 Each $287.00 1.00 Each $289.00 1.00 Each $219.00 5.00 Each $171.00 3.00 Each $124.00 3.00 LF $36.80 11.00 Each $120.00 3.00 Each $93.00 34.00 Each $60.00 15.00 Each $396.00 11.00 16.85 2.00 19.50 2.00 DATE: November 2, 2010 AMOUNT EARNED TO DATE $ 2,706.55 $ 1,545.00 $ 2,287.50 $ 17,375.58 $ 624.40 $ 3,486.29 $ 6,847.75 $ 900.00 $ 429.50 $ 2,459.52 $ 5,005.81 $ 16,150.40 $ 6,562.02 $ 3,922.37 $ 220.98 $ 939.31 $ 1,046.64 $ 1,011.25 $ 310.00 $ 372.00 $ 18,805.63 $ 2,752.20 $ 209.00 $ 9,360.00 $ 615.00 $ 5,960.00 $ 3,208.00 $ 1,074.00 $ 287.00 $ 289.00 $ 1,095.00 $ 513.00 $ 372.00 $ 404.80 $ 360.00 $ 3,162.00 $ 900.00 $ 4,356.00 $ 2,123.10 $ 1,930.00 $ 2,437.50 $ 540.00 262.40 $ 826.56 44 6" Subdrain (Perforated Drain Tile) 45 Connect Subdrain to Storm Sewer Pipelines 46 Waterproofing Membrane 47 2" Insulation Board 48 Sod 49 Dust Control Surface Treatment 50 Erosion Control Plan - Operating Procedures 51 Traffic Control & Safety Control 52 Mobilization C1 Connect 18" DIP to 15" Clay & Connect 8" Lateral- Sanitary Sewer C2 Connect 6" Lateral on 15th Street C3 Add 8" Lateral Opening to Manhole Base in 16th St. Manhole C4 Install Gate Valves in Alley between 16th & 17th Street C5 Remove & Replace clay Storm Sewer with 24" RCP C6 6" Macro coupling C7 Saw Manhole Top down 1.5" to 2" C8 Tap 15" DIP C9 Night Work for Water C10 Concrete along Foundations C11 Excavation for wall LF $11.00 313.00 LS $555.00 1.00 SF $5.80 SY $9.50 64.10 SY $6.00 80.81 MGAL $40.00 LS $3,895.00 1.00 LS $3,445.00 1.00 LS $4,040.00 1.00 LS LS LS LS LS LS LS LS LS CY CY TOTAL AMOUNT EARNED TO DATE: 1.00 $ 2,959.82 1.00 $ 419.97 1.00 $ 1,084.25 1.00 $ 150.00 1.00 $ 2,791.71 2.00 $ 147.30 1.00 $ - 1.00 $ 1,340.00 1.00 $ 490.00 10.00 $ 203.00 41.00 $ 12.00 TOTAL AMOUNT EARNED TO DATE - CHANGE ORDERS: TOTAL AMOUNT EARNED TO DATE: $ 3,443.00 $ 555.00 $ 608.95 $ 484.86 $ 3,895.00 $ 3,445.00 $ 4,040.00 152,254.46 $ 2,959.82 $ 419.97 $ 1,084.25 $ 150.00 $ 2,791.71 $ 294.60 $ - $ 1,340.00 $ 490.00 $ 2,030.00 $ 492.00 $ $ 12,052.35 $ 164,306.81 TOTAL DUE CONTRACTOR: 1 $ 164,306.81 1 ENGINEERING: 1 $11,675.81 1 TOTAL CONSTRUCTION COST: 1 $175,982.62 1 CERTIFICATE OF THE CITY MANAGER: I hereby certify that the above statement shows in detail the correct amount of all wQ squired to complete the above improvement. APPROVED: Michael Van Milligen, Cit Manager City of Dubu ue wa APPROVED: Gus Psihoyos, City Engineer City of Dubuque, Iowa CERTIFICATE OF THE CONTRACTOR: The undersigned, contractor for the above improvement, does hereby accept the above "Total Due Contractor ", as full settlement for all claims for said improvement. CONTRACTOR: C0 , r1. 1 ‘ , r1. 1 ‘ • I I ,/ / BY: J:i TITLE: L • P DATE: //:- 2'- PI J4rL