Ice Harbor Pump Aux. Power PMEMORANDUM November 20, 2003 TO: FROM: SUBJECT: The Honorable Mayor and City Council Members Michael C. Van Milligen, City Manager Ice Harbor Pump Auxiliary Power Project Sealed bids were received for the Ice Harbor Pump Auxiliary Power Project. Operations and Maintenance Manager Don Vogt recommends award of the contract to the Iow bidder, Portzen Construction, for the base bid amount of $69,395, which is 2.7% over the engineer's estimate. I concur with the recommendation and respectfully request Mayor and City Council approval. icnael C. Van Milligen MCVM/jh Attachment cc: Barry Lindahl, Corporation Counsel Cindy Steinhauser, Assistant City Manager Don Vogt, Operations& Maintenance Manager CITY OF DUBUQUE, IOWA MEMORANDUM November 20, 2003 TO: FROM: SUBJECT: Michael C. Van Milligen, City Manager .~ Don Vogt, Operations & Maintenance Manage Ice Harbor Pump Auxiliary Power Project INTRODUCTION The enclosed resolutions provide for the final adoption of plans and specifications and the award of a construction contract for the Ice Harbor Pump Auxiliary Power Project. DISCUSSION This project provides for the pumhase and installation of a diesel-fueled, auxiliary power generator, transfer switch, generator enclosure and associated conduit and wire for auxiliary power to run the floodwall pumps located at the Ice Harbor pumping facility. A tabulation of the five sets of bids received accompanies this memorandum, as does a letter of bid award recommendation from our project engineering firm, IIW Engineers and Surveyors P.C.. IIW has recommended contract award to the contractor submitting the lowest bid. RECOMMENDATION I recommend that the contract be awarded to Portzen Construction of Dubuque, Iowa for the base bid of $69,395.00, which is 2.7% over the engineer's estimate. BUDGET IMPACT A tabulation of the project's initial and subsequent recommended budget is as follows: Construction Contract Contingency Engineering TOTAL CONSTRUCTION ESTIMATE $ 67,575.00 7,457.00 7,000.00 $ 82,032.00 PER LOW BID $ 69,395.00 5,637.00 7,000.00 $ 82.032.00 This project will be funded with monies ($82,032.00) budgeted specifically for it in our depadTnent's FY2004 capital improvement budget. ACTION TO BE TAKEN The City Council is requested to adopt the attached resolutions providing for the final adoption of plans and specifications and the award of the construction contract. ATTACHMENTS RESOLUTION NO. 499-03 RESOLUTION ADOPTING PLANS AND SPECIFICAITONS Whereas, on the 20th day of October, 2003, plans, specifications, form of contract and estimated cost were filed with the City Clerk of Dubuque, Iowa for the Ice Harbor Pump Auxiliary Power Project. Whereas, notice of headng on plans, specifications, form of contract, and estimated cost was published as required by law. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: That the said plans, specifications, form of contract and estimated cost are hereby approved as the plans, specifications, form of contract and estimated cost for said improvements for said project. Passed, adopted and approved this 1st day of December, 2003. Terrance M. Duggan, Mayor Attest: Jeanne F. Schneider , City Clerk RESOLUTION NO. 500-03 AWARDING CONTRACT Whereas, sealed proposals have been submitted by contractors for the Ice Harbor Pump Auxiliary Power Project pursuant to pdor resolution and notice to bidders published in a newspaper published in the City of Dubuque, Iowa on the 24th day of October 2003. Whereas, said sealed proposals were opened and read on the 12th day of November, 2003 and it has been determined that the bid of Portzen Construction of Dubuque, Iowa in the amount of $69,395.00 was the lowest bid for providing all labor and materials and performing the work as provided for in the plans and specifications. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: That the contract for the above improvement be awarded to Portzen Construction and the City Manager be and is hereby directed to execute a contract on behalf of the City of Dubuque for the complete performance of the work. BE IT FURTHER RESOLVED: That upon the signing of said contract and the approval of the contractor's bond, the City Treasurer is authorized and instructed to return the bid deposits of the unsuccessful bidders. Passed, approved and adopted this 1st day of December, 2003. Terrance M. Duggan, Mayor Attest: Jeanne F. Schneider City Clerk November 13, 2003 John Klostermann Operations and Maintenance Department City of Dubuque 925 Kerper Boulevard Dubuque, IA 52001-2338 Re: City of Dubuque Ice Harbor Generator and Transfer Switch Project 2003 Award Recommendation IIW Project No. 01184-03 Dear John: In accordance with city instructions, bids for the Ice Harbor Generator and Transfer Switch Project 2003 were opened and read at 2:00 p.m. on November 12, 2003. Five (5) bids were received for this project. A tabulation of the bids received is enclosed. The low bid was submitted by Portzen Construction, 205 Salina Street, Dubuque, Iowa 52003 in the mount of $69,395.00. Portzen Construction has the experience, workforee and equipment to properly complete this project. Therefore, we reconm~end award of Ice Harbor Generator and Transfer Switch Project 2003 to Portzen Construction in the mount of $69,395.00. The eng/neer's estimate for this project was $67,575.00. The low bid of $69,395.00 is $1,820.00 or 2.7% above the engineer's estimate. Sincerely, srawYo ; P.c. Eric: Bid Tabulation Copy: Portzen Construction Jeanne Schneider, City Clerk Dennis E Waugh, PE/SE Charles A. Cate. PE Gary D. Sejkom. PE Michael A. Jansen. PFJSE Ronald A, Bulmer, PE/SE* John M. Tranmer, PLS Timothy J. Tranet, PE John F. Wandsnlder, PE Julie R Neebet, PE James R Kaune, PE Thomas J. Oster, PLS Wray A. Childem. PLS Geoffry T Blandin, PE Steven J. Hunn, PE Civil Engineering Structural Engineering Environmental Engineerkug Municipal En~neering Transportation Eugineering Land Surveying Quality Control Testing I IIW Engineers & Surveyors, P.C. Dubuque, IA Hazel Green, WI INTEGRITY. EXPERTISE. 50LUTION5. 4155 Pennsylvania Avenue Dubuque, Iowa 52002-2628 563.556.2464 563.556.7811 fax www.iiwengr, com CITY OF DUEUQUE~IOWA ICEHAREOR GENERATOR AND TRANSFER SWITCH PROJECT 2003 BID TABULATION NOVEMBER 12, 2003 ENGINEER'S ESTIMATE PORTZEN CONS'T. MARYVILLE CONST. CONLON CONS% TOTA~ TRICON CON$~ TOTAL DRAX, INC. 2.69% 4.26% 7.22~ 12.56% 76,10% MEMORANDUM October 13, 2003 TO: FROM: SUBJECT: The Honorable Mayor and City Council Members Michael C. Van Milligen, City Manager Ice Harbor Pump Auxiliary Power Project Operations and Maintenance Department Manager Don Vogt recommends initiation of the bidding process for the Ice Harbor Pump Auxiliary Power Project, and further recommends that a public hearing be set for December 1, 2003. I concur with the recommendation and respectfully request Mayor and City Council approval. MCVM/jh Attachment cc: Barry Lindahl, Corporation Counsel Cindy Steinhauser, Assistant City Manager Don Vogt, Operations & Maintenance Department Manager CITY OF DUBUQUE, IOWA MEMORANDUM October 1, 2003 TO: FROM: SUBJECT: Michael C. Van Milligen, City Manager Don Vogt, Operations & Maintenance Department Manag Ice Harbor Pump Auxiliary Power Project INTRODUCTION The attached resolutions authorize the public bidding procedure for the Ice Harbor Pump Auxiliary Power Project. DISCUSSION This project provides for the pumhase and installation of a diesel-fueled, auxiliary power generator, transfer switch, generator enclosure, and associated conduit and wiring for auxiliary power to run the floodwall pumps located at the Ice Harbor pumping facility. In the event of a power outage, this generator would provide power to run the Ice Harbor floodwall pumps, reducing the chance of inland flooding dudng Mississippi River high water events. The schedule for this project is proposed as follows: Advertisement of Bids Notice of Public Hearing Receipt of Bids Public Hearing Award of Contract October 24, 2003 November 21, 2003 November 12, 2003 December 1, 2003 December 1, 2003 BUDGET IMPACT The cost estimates for the project are as follows: Construction Contract $ 67,575.00 Contingency $ 7,457.00 Engineering $ 7,000.00 TOTAL $ 82,032.00 This project will be funded with monies ($82,032.00) budgeted specifically for it in our department's FY2004 capital improvement projects budget. ACTION TO BE TAKEN The City Council is requested to establish the date for the public hearing and authorize the City Clerk to advertise the request-for proposals through the adoption of the attached resolutions. ATTACHMENTS DJV/Iml RESOLUTION NO. -03 FIXING DATE OF THE HEARING ON PLANS AND SPECIFICATIONS Whereas, the City Council of the City of Dubuque, Iowa has given its preliminary approval on the proposed plans, specifications, and form of contract and placed same on file in the office of the City Clerk for public inspection of the Ice Harbor Pump Auxiliary Power Project. NOW THEREFORE BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: That on the 1~t of December, 2003, a public hearing will be held at 6:30 p.m. in the Public Library Auditorium at which time interested persons may appear and be heard for or against the proposed plans and specifications, form of contract and cost of said improvement, and the City Clerk be and is hereby directed to cause a notice of time and place of such hearing to be published in a newspaper having general circulation in the City of Dubuque, Iowa, which notice shall be not less than four days nor more than twenty days prior to the day fixed for its consideration. At the hearing, any interested person may appear and file objections to the proposed plans, specifications, contract, or estimated cost of the improvement. Passed, adopted and approved this 20~h day of October, 2003 Terrance M. Duggan Mayor Attest: Jeanne F. Schneider City Clerk NOTICE OF HEARING ON PLANS AND SPECIFICATIONS Notice of public hearing on proposed plans and specifications, proposed form of contract and estimate of cost for the Ice Harbor Pump Auxiliary Power Project. NOTICE IS HEREBY GIVEN: The City Council of Dubuque, Iowa will hold a public hearing on the proposed plans, specifications, form of contract and estimate of cost for the Ice Harbor Pump Auxiliary Power Project, in accordance with the provisions of Chapter 384, City Code of Iowa, at 6:30 p.m. on the 1~t day of December 2003 in the Public Library Auditorium in Dubuque, Iowa. Said proposed plans, specifications, form of contract and estimate of cost are now on file in the office of the City Clerk. At said hearing any interested person may appear and file objections thereto or to the cost of the improvements. Published by order of the City Council given on the 20t~ day of October, 2003. Jeanne F. Schneider City Clerk RESOLUTION NO. -03 PRELIMINARY APPROVAL OF PLANS AND SPECIFICATIONS NOW THEREFORE, BE IT RESOLVED BY THE CiTY COUNCIL OF THE CITY OF DUBUQUE, IOWA: That the proposed plans, specifications, form of contract and estimated cost for the Ice Harbor Pump Auxiliary Power Project in the estimated amount of $82,032.00, are hereby approved and ordered filed in the office of the City Clerk for public inspection. Passed, adopted and approved this 20th day of October, 2003. Terrance M. Duggan Mayor Attest: Jeanne F. Schneider City Clerk RESOLUTION NO. -03 ORDERING BIDS NOW THEREFORE, BE IT RESOLVED BY THE COUNCIL OF THE CITY OF DUBUQUE, IOWA: That the Ice Harbor Pump Auxiliary Power Project is hereby ordered to be advertised for bids for construction. BE IT FURTHER RESOLVED, that the amount of the security to accompany each bid shall be in an amount which shall conform to the provisions of the notice to bidders hereby approved as a part of the plans and specifications heretofore adopted. That the City Clerk is hereby directed to advertise for bids for the construction of the improvements herein provided, to be published in a newspaper having general circulation in the City of Dubuque, Iowa, which notice shall not be less than four days nor more than twenty days prior to the receipt of said bids at 2:00 p.m. on the 12th day of November, 2003. Bids shall be opened and read by the City Clerk at said time and will be submitted to the Council for final action at 6:30 p.m. on the 1~t day of December, 2003. Passed, adopted and approved this 20~h day of October, 2003. Terrance M. Duggan Mayor Attest: Jeanne F. Schneider City Clerk