TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: Dog Park Update
DATE: January 10, 2011
Dubuque
bitil
All- AmaicaCity
'
2007
Leisure Services Manager Marie Ware is providing current information regarding the
IDOT property at Dodge and Locust Streets for use as a dog park.
The design of the pet park including fence location, water hydrant location and parking
is in process. The design will then be submitted to IDOT for review and approval. They
have indicated that they will determine if a lease or work in right -of -way permit would
then be issued pending this approval. If approval is received construction would be
spring though summer.
This location would be temporary and would have to be modified or removed when the
new Julien Dubuque Bridge is built.
MCVM:Iw
Attachment
cc: Barry Lindahl, City Attorney
Cindy Steinhauser, Assistant City Manager
Marie Ware, Leisure Service Manager
Michael/C. Van Milligen
4
Masterpiece on the Mississippi
TO:
FROM:
SUBJECT:
DATE:
INTRODUCTION
BACKGROUND
MLW:et
attachment
Michael C. Van Milligen, City Manager
Marie L. Ware, Leisure Services Manage
Dog Park Update
January 7, 2011
Dubuque
kittgi
All-America
''HP®
2007
The purpose of this memorandum is to provide current information regarding the IDOT
property at Dodge and Locust Streets for use as a dog park.
Much research and many discussions led to the choice of the location at Dodge and
Locust for a second dog park. The Fiscal Year 2011 Park Division C.I.P. has the
following project funding for the development of the dog park:
350 1978 73211 Pet Park, Terminal Street $101,000
To request use of this location, IDOT is asking for a plan of the pet park showing all
work proposed, for their review. I met with John Klosterman and Jon Dienst on site to
review the location of utilities and other site issues.
The design of the pet park including fence location, water hydrant location and parking
is in process. This design will then be submitted to IDOT for review and approval. They
have indicated that they will determine if a lease or work in right -of -way permit would
then be issued pending this approval. If approval is received construction would be
spring through summer.
This location would be temporary and would have to be modified or removed when the
new Julien Dubuque Bridge is built.
ACTION REQUESTED
This memo is for informational purposes.