Southwest Arterial North Cascade Road Bridge Construction ProjectMasterpiece on the Mississippi
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: Southwest Arterial Project
North Cascade Road Bridge Construction Project
Iowa DOT Project No. HDP -2100 (661)- -71 -31
DATE: January 10, 2011
Dubuque
kiftil
AN-America City
'
2007
City Engineer Gus Psihoyos is recommending to set February 7, 2011 as the date for a
public hearing on the North Cascade Road Bridge Construction Project (Phase II of the
Southwest Arterial Project).
The preliminary engineering design phase was completed in March, 2008 and the
Southwest Arterial project is now proceeding with the final engineering design phase,
right -of -way property acquisition and archaeological and cultural resource phase III
mitigation work.
On August 16, 2010 the City Council approved the award of the North Cascade Road
Reconstruction Project (phase I of the Southwest Arterial) to C.J. Moyna & Sons, Inc. of
Elkader, Iowa in the amount of $1,591,521.32. This phase of construction provides for
the reconstruction (grading & paving) and realignment of North Cascade Road from
about 0.6 miles south of the Storybook Hill Children's Zoo to 0.1 miles north of the zoo.
The stage I grading (Bridge abutments) was completed in November which will allow
the new bridge construction to begin in April 2011. Following completion of the bridge
work, stage II grading & paving will resume and is anticipated to be completed by early
fall of 2011.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
MCVM:Iw
Michael C. Van Milligen
Attachment
cc: Barry Lindahl, City Attorney
Cindy Steinhauser, Assistant City Manager
Gus Psihoyos, City Engineer
Masterpiece on the Mississippi
TO: Michael C. Van Milligen, City Manager
FROM: Gus Psihoyos, City Engineer
SUBJECT: Southwest Arterial Project
North Cascade Road Bridge Construction Project
Iowa DOT Project No. HDP -2100 (661)- -71 -31
DATE: January 10, 2011
INTRODUCTION
The purpose of this memorandum is to provide the City Council with information related to
the North Cascade Road Bridge Construction Project (Phase II of the Southwest Arterial
project) and request that a date for the public hearing be established.
BACKGROUND
Dubuque
kittil
AU- Amaica City
111111
2007
The preliminary engineering design phase was completed in March, 2008 and the
Southwest Arterial project is now proceeding with the final engineering design phase, right -
of -way property acquisition and archaeological and cultural resource phase III mitigation
work.
Additionally, the City is evaluating construction phasing alternatives for completing
components of the project with currently available federal, state and local funding. To
maximize available funding, the City is preparing to move forward with several side road
construction projects that would allow for Southwest Arterial improvements to be made that
would provide immediate public benefit and would provide significant efficiencies and cost
savings on the future grading and paving of the four -lane Southwest Arterial corridor
between Highway 151/61 to Highway 20.
On August 16, 2010, the City Council approved the award of the North Cascade Road
Reconstruction Project (Phase I of the Southwest Arterial) to C.J. Moyna & Sons, Inc. of
Elkader, Iowa, in the amount of $1,591,521.32. This phase of construction provides for the
reconstruction (grading & paving) and realignment of North Cascade Road from about 0.6
miles south of the Storybook Hill Children's Zoo to 0.1 miles north of the zoo. The stage
grading (bridge abutments) was completed in November which will allow the new bridge
construction to begin in April 2011. Following the completion of the bridge work, stage II
grading & paving will resume and is anticipated to be completed by early fall of 2011.
Other side road construction projects that are currently in the design stages are the
English Mill Road reconstruction and the Military Road reconstruction projects. Both the
English Mill and Military Road reconstruction projects will include the construction of new
bridges which will allow the future Southwest Arterial to cross under each of those side
roads.
DISCUSSION
The realigned section of North Cascade Road will have a new bridge constructed which
will allow the future Southwest Arterial to cross under North Cascade Road. The new
bridge project will provide for the construction of a 272 ft. x 44 ft. pretensioned prestressed
concrete beam bridge which will include a 10 -foot wide paved shoulder that would
accommodate bicycle and pedestrian use. The new bridge will also include architectural
enhancement treatments that will include native Dubuque limestone textured piers, pier
caps, abutment walls and barrier rails. The bridge will also have architectural piers that
extend above the bridge deck, along with decorative LED roadway lighting and decorative
bridge railing. Attached is a graphic rendering of the North Cascade Road Bridge and the
proposed architectural enhancement treatments which will be a consistent design theme
for the future English Mill and Military Road bridges.
Once the North Cascade Road, English Mill and Military Road projects are completed and
construction of the Southwest Arterial begins, citizens and vehicular traffic using those side
roads will not be impacted while construction work occurs under each of those side roads.
PROJECT SCHEDULE
The project development schedule for the North Cascade Road Bridge Construction
Project (Phase II) is as follows:
Iowa DOT Advertisement for Bids
Notice of Hearing on Plans & Specifications
Iowa DOT Receipt of Bids (Bid Letting)
City Public Hearing on Plans & Specifications
City Award of Contract (Subject to Iowa DOT Approval)
Iowa DOT Start Date
Contract Completion Date
December 22, 2010
January 18, 2011
January 26, 2011
February 7, 2011
February 7, 2011
April 4, 2011
85 Working Days
Completed Summer 2011
Because this project is bid through the Iowa DOT in Ames, it is acceptable for the City to
hold a public hearing on the North Cascade Road Bridge Construction Project following the
receipt of bids. At the February 7 meeting, following the public hearing, the City Council
will be requested to concur in the award of the Improvement Contract, subject to Iowa DOT
approval.
RECOMMENDATION
I recommend that the City Council set February 7, 2011, as the date for a public hearing
on the North Cascade Road Bridge Construction Project (Phase II of the Southwest
Arterial project).
BUDGET IMPACT
The estimate of probable cost for the North Cascade Road Bridge Construction Project is
as follows:
Description Amount
Construction Contract $1,560,000
Contingency 156,000
Contract Administration / Construction Engineering 171.600
Total Project Cost $1,887,600
The project funding summary is as follows:
CIP Funding Source Amount
3001287 Federal SAFETEA -LU Funding (80 %) $ 438,454
3001287 Omnibus 2009 Appropriations Act (100 %) 950,000
3001287 THUD 2010 Appropriations (100%) 389,533
3001287 Local Funding (20 %) 109,613
Total Project Funding $1,887,600
ACTION TO BE TAKEN
The City Council is requested to set the date for a public hearing on the North Cascade
Road Bridge Construction Project (Phase II of the Southwest Arterial project) through
adoption of the enclosed resolution.
Prepared by Robert Schiesl, Assistant City Engineer
cc: Jenny Larson, Budget Director
RESOLUTION NO. 18 -11
SOUTHWEST ARTERIAL PROJECT
NORTH CASCADE ROAD BRIDGE CONSTRUCTION
IOWA DOT PROJECT NO. HDP -2100 (661)- -71 -31
SETTING DATE OF PUBLIC HEARING ON PLANS, SPECIFICATIONS, FORM OF
CONTRACT, AND ESTIMATED COST
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF DUBUQUE, IOWA:
The proposed plans, specifications, form of contract and estimated cost for the
North Cascade Road Bridge Construction Project (Phase II of the Southwest Arterial
Project), Iowa DOT Project No. HDP -2100 (661)-- 71 -31, in the estimated amount
$1,887,600, are hereby preliminarily approved and ordered filed in the office of the City
Clerk for public inspection.
A public hearing will be held on the 7 day of February, 2011, at 6:30 p.m. in the
Historic Federal Building Council Chambers (second floor), 350 West 6 Street,
Dubuque, Iowa, at which time interested persons may appear and be heard for or
against the proposed plans and specifications, form of contract and estimated cost of
said Project, and the City Clerk be and is hereby directed to cause the attached notice
of the time and place of such hearing to be published in a newspaper having general
circulation in the City of Dubuque, Iowa, which notice shall be published not Tess than
four days nor more than twenty days prior to the date of such hearing. At the hearing,
any interested person may appear and file objections to the proposed plans,
specifications, form of contract, or estimated cost of the Project.
Passed, adopted and approved this 18th day of January, 2011
Roy D. Buol, Mayor
Attest:
Jeanne F. Schneider, CMC, City Clerk
NOTICE OF PUBLIC HEARING ON PLANS, SPECIFICATIONS, FORM OF
CONTRACT, AND ESTIMATED COST FOR NORTH CASCADE ROAD BRIDGE
CONSTRUCTION, IOWA DOT PROJECT NO. HDP -2100 (661)- -71 -31
NOTICE IS HEREBY GIVEN: The City Council of the City of Dubuque, Iowa will
hold a public hearing on the proposed plans, specifications, form of contract and
estimated cost for the North Cascade Road Bridge Construction (Phase II of the
Southwest Arterial Project), Iowa DOT Project No. HDP -2100 (661)-- 71 -31, in
accordance with the provisions of Chapter 26, Code of Iowa, at 6:30 p.m., on the 7 day
of February, 2011, in the Historic Federal Building Council Chambers (second floor),
350 West 6 Street, Dubuque, Iowa. Said proposed plans, specifications, form of
contract and estimated cost are now on file in the office of the City Clerk. At said
hearing any interested person may appear and file objections thereto.
The scope of the Project is as follows:
• The project will provide for the construction of a 272 ft. x 44 ft. pretensioned
prestressed concrete beam bridge.
Any visual or hearing- impaired persons needing special assistance or persons
with special accessibility needs should contact the City Clerk's office at (563) 589 -4120
or TDD at (563) 690 -6678 at least 48 hours prior to the meeting.
Published by order of the City Council given on the day of , 2011.
Jeanne F. Schneider, CMC, City Clerk