R 95-04 Five-Year Street Construction Program
RESOLUTION NO. 95-04
ADOPTING THE FIVE-YEAR STREET CONSTRUCTION PROGRAM
FOR FISCAL YEARS 2005-2009
Whereas, a recommended Five-Year Street Construction Program for the
Fiscal Years 2005 - 2009 beginning July 1,2004, and ending June 30, 2008, for
the City of Dubuque has been prepared and submitted to the City Council; and
Whereas, the Five-Year Street Construction Program: 1) describes
specific capital improvement projects; 2) provides estimated costs for those
projects; 3) proposed sources of funding; and 4) schedules the fiscal/calendar
year during which each project will be undertaken; and
Whereas, the capital improvement projects for the first year of such five-
year program are included in the Fiscal Year 2005 budget; and
Whereas, the adoption of the Five-Year Street Construction Program is a
prudent measure to provide continuity of programs and is in the best interest of
the City of Dubuque.
NOW THEREFORE, BE IT RESOLVED BY THE COUNCIL OF THE CITY
OF DUBUQUE, IOWA:
Section 1. That the Five-Year Street Construction Program for Fiscal
Years 2005-2009 beginning July 1, 2004, set out in the Fiscal Years 2005-2009
Recommended Capital Improvement Budget, is hereby approved and adopted as
the proposed allocation of City resources for capital improvements as scheduled
in the years shown, subject to annual review and revision.
Attest:
S1CH1
ElJ1m
Heritage Trail Extension
Fremont
Chestnut
Ice Harbor West Road
University
Bell
16th
Dodge
Highland
Spruce
8th
Garfield
Windsor
Stone Ridge
iowa
Locust
Marshall
Burden
Windsor
17th
FY 04 STREET PROGRAM
Projects Currently Under Contract
I!2 l'Js1m§. ~
Heron Pond Bike/Hike Trail 530,000 .
Simpson Reconstruction 712,000
Cox Reconstruction 600,000 .
New Construction 1,800,000
Delhi Reconstruction 1,250,000 .
New Construction 2,200,000
Airhill Resurfacing 50,000
Elm Resurfacing 533,600
Stone Ridge Resurfacing 370,500
End of Public Street Resurfacing 33,000
14th Resurfacing 100,000
Fundina Assís1am::l1
(TEA.21)
(STP 874,000)
(STP 1,500,000)
2/23/2004
Est Como Date
September 30, 2004
October 1,2004
June 30,2004
May 23, 2004
September 30, 2004
May 1, 2004
May 23, 2004
May 23, 2004
May 23,2004
May 23, 2004
May 23, 2004
FY 04 STREET PROGRAM
Projects Currently Under Design
S1rtit Emtn I.Q
University Extension US 20
Port of Dubuque - Market Street Adams 5th
Southwest Arterial Design
US 20 Widening & Intersection Imp. Cedar Cross aid US 20
~
New Construction
New Construction
New Construction
Improvement
02/23/2004
~
Fundlna Assistance
3,085,000' (STP 2,468,000)
858,750 . (DRAlSTP 878,750)
5,000,000 . (IDOT/FHWAIRISE/County/DMATS STP)
275,000 * (U-STEP 275,000)
~
Rosedale
Diagonal
Broadway
Madison
Wacker/Center Grove
Hill
Main
Julien Dubuque Drive
Southwest Arterial
US 20 Intersection Improvements
Port of Dubuque
2/23/2004
STREET CONSTRUCTION PROGRAM FY05-09 SUMMARY
CALENDAR YEAR 2004
Fiscal Year 2005
I!2 ElJ1m l'Js1m§. ~ Fundinr¡ Assistance Last Year's CIP
West Locust Grandview Reconstruction 747,000
Broadway Central Resurfacing 80,000
24th Diagonal Resurfacing 175,000
17th Clarke Resurfacing 78,000
US20 Cedar Cross Resurfacing 150,000
Dodge 9th Resurfacing 500,000
17th 9th Resurfacing 267,000
South Grandvlew Riprow Valley Resurfacing 150,000
New Construction 7,666,000 .
Wacker Cedar Cross New Construction 275,000 .
Adams 5th New Construction 858,750' (DRA Dist)
TOTAL 10,946,750
Annual Street Program
2,147,000
Budget
$2,096,000
S1CH1
Bonson
5th
Nowata
9th
Carlotta
Alta Vista
Bluff
South Grandview
Mt. Pleasant
11th
Carter
Carmel
Southwest Arterial
02/23/2004
STREET CONSTRUCTION PROGRAM FY05.09 SUMMARY
CALENDAR YEAR 2005
Fiscal Year 2006
I!2 ElJ1m l'Js1m§. ~ Fundinr¡ Assistance Last Year's CIP
Asbury End Reconstruction 440,000 Cal. Yr. 2004
Central Bluff Reconstruction 302,000
University Loras Reconstruction 276,000
Bluff Alta Vista Dowel Bar RetrofiUProfiling 110,000
Alia Vista Alpine Reconstruction 102,000
5th University Reconstruction 445,000
9th 14th Repair/Resurfacing 185,000
Southern Carmel Resurfacing 180,000
University End Resurfacing 220,000
White Bluff Resurfacing 177,000
Hillcrest West 32nd Resurfacing 550,000
South Grandview End Resurfacing 39,000 (RISE 160,000)
New Construction 10,000,000 .
TOTAL 13,026,000
Annual Street Program 3,026,000 .
Budget $2,809,500
. Less Separately Funded Projects
~
Foye/MerchanUGold
Needham
Mt Carmel
5th
Summit
Iowa
14th
15th
Pennsylvania
Almond
Ellis
Locust
Chavenelle Rd. Extension
Southwest Arterial
I!2
West Locust
5th
South Grandview
Hill
5th
4th
White
Locust
tenox
Ellis
West Locust
5th
Dub. Ind. Ctr.
02/23/2004
STREET CONSTRUCTION PROGRAM FY05.09 SUMMARY
CALENDAR YEAR 2006
Fiscal Year 2007
E1JHn l'Js1m§. ~ Fundina Assistance
Napier Reconstruction 579,000
7th Reconstruction 160,000
Pump House Reconstruction 200,000
Delhi Reconstruction 715,000
3rd Reconstruction 175,200
9th Resurfacing 250,000
Elm Resurfacing 120,000
Central Resurfacing 159,000
John F. Kennedy Resurfacing 194,000
Faye Resurfacing 47,000
Almond Resurfacing 45,000
17th Resurfacing 432,500
Dub. Ind. Ctr. . West New Construction 320,000 .
New Construction 15,666,000 .
Last Year's cœ
New. Tied to Sanitary Proj
New. Tied to Sanitary Proj
TOTAL
19,062,700
Annual Street Program
3,076,700
. Less Separately Funded Projects
Budget
$2,991,500
02/23/2004
STREET CONSTRUCTION PROGRAM FY05.09 SUMMARY
CALENDAR YEAR 2007
Fiscal Year 2008
S1CH1
E1JHn .II! /':JQt¡¡§. ~ Fundina Assistance
Bryant End Reconstruction 1,600,000
St. Ambrose Clarke Reconstruction 170,000
Central Locust Reconstruction 191,000
John F. Kennedy Clarke Resurfacing 500,000
St. Ambrose University Resurfacing 161,000
5th Locust Connector Resurfacing 135,000
New Construction 20,168,000'
Last Year's CIP
Rush
Asbury
10th
New - Replace Hamilton
New. Replace Hamilton
Asbury
Asbury
Main
New. Replace Hamilton
Southwest Arterial
TOTAL
22,925,000
Annual Street Program
22,925,000
Budget
$2,643,000
. Less Separately Funded Projects
Cedar Cross
Jackson
Kaufmann
Chavenelle
~
Port of Dubuque - Charter Street Extension
Town Clock Plaza - Phase IV
Southwest Arterial
STREET CONSTRUCTION PROGRAM FY05-09 SUMMARY
CALENDAR YEAR 2008
Fiscal Year 2009
.II!
Emm
Starlite Cedar Cross Court
6th 11th
Quarry Bonson
Northwest Arterial Radford
6th-7th
5th
Main to Locust
TOTAL
Annual Street Program
Budget
. Less Separately Funded Projects
l'!111ä
Reconstruction
Reconstruction
Resurfacing
Dowel Bar Retrofit
New Construction
Design
New Construction
~
1,502,000
660,000
535,000
121,000 .
975,000 .
500,000 .
12,384,000 .
16,677,000
2,697,000
$2,643,000
Fundina Assistance
435,000
02/23/2004
Last Year's CIP
Gal. Yr. 2005
Gal. Yr. 2007
Cal. Yr. 2007
Estimate Base on 2010 15%
DEFERRED LIST
S1rtit Emtn Is1. ~ Estimate BASE Estimate CURRENT Fiscal Year
4th 6th East Reconstruction 800,000 920,000
8th Airhill Roberts Reconstruction 400,000 460,000 Cal. Yr. 2006
Atlantic University Grandview Reconstruction 770,000 886,000 FY06
Auburn Grace Grandview Reconstruction 725,000 834,000 FY06
Bennett Grandview McCormick Reconstruction 760,000 874,000 FY06
Bies Daniel Asbury Reconstruction 512,500 589,000 FY07
Booth 5th Loras Reconstruction 722,000 830,000
Century US20 Sylvan Reconstruction 790,000 909,000
Cleveland Bryant End Reconstruction 1,600,000 1,840,000
Commercial 7th East End Reconstruction 667,000 767,000 FY04
Cox Loras Kirkwood Resurfacing 190,000 219,000 FY05
Custer North Grandview Algona Reconstruction 320,000 368,000 FY06
Dell 11th Arlington Reconstruction 200,000 230,000 FY04
Grace Grandview McCormick Reconstruction 700,000 805,000 FY06
Penn/Middle Radford City Limits Reconstruction
Nevada 3rd Martha Reconstruction 132,000 152,000
Railroad Main Harrison Reconstruction
Rockdale Key West Marco Reconstruction 0
Picket Henion Fairview Reconstruction
Sylvan Century Pennsylvania Reconstruction 525,000 604,000 FY08
Southern Arrowhead Rockdale Reconstruction 1,335,000 1,535,000 FY06
0
13th Main Locust Resurfacing/Brick 55,000 63,000 FY06
16th Locust Main Resurfacing 40,000 46,000
24th Central Windsor Resurfacing 50,500 58,000 FY06
27th Central Jackson Resurfacing 72,500 83,000 FY06
2nd Bluff Main Resurfacing (Downtown Improvements) 0
W 32nd Jackson Fink Resurfacing
7th Central Jackson Resurfacing 66,700 77,000
Concord Marion End Resurfacing 88,000 101,000
Grove Terrace 11th Wilbur Resurfacing 56,000 64,000
Marion Fremont End Resurfacing 141,000 162,000
Main 4th Locust Connector Resurfacing
Main Locust Connector Railroad Resurfacing
Roosevelt Peru Amelia Resurfacing
Tower Drive Rockdale End (Trailer Court) Resurfacing
UNMET NEEDS IN FIVE-YEAR STREET PROGRAM FY 05
S1rtit
EIJm1
I.Q
~
Estimate BASE
Estimate CURRENT
Belmont Loras
Hamilton/Kilgore/Roosevelt
Rose
Reconstruction
Resurfacing
O&M
O&M
Fiscal Year
Cal. Yr 2006
Cal. Yr 2007
D~
~cÆ~
MEMORANDUM
February 23, 2004
TO:
Michael C. Van Milligen, City Manager
Michael A. Koch, Public Works Director %...k
SUBJECT: Five-Year Street Construction Program for Fiscal Years 2005-2009
FROM:
INTRODUCTION
The enclosed resolution provides for the acceptance of the Five-Year Street
Construction Program.
DISCUSSION
At the February 19, 2004 Council budget hearing, the Engineering Division
presented its Five-Year Construction Program for Fiscal Years 2005-2009 to the
City Council. This program, which is part of the Five-Year Capital Improvement
Projects, includes the estimated costs for the construction work and the
anticipated year during which each project will be undertaken. This Five-Year
Street Construction Program is considered annually by the City Council and
appropriately revised.
RECOMMENDATION
I recommend that the City Council accept the Five-Year Construction Program
for Fiscal Years 2005-2009.
ACTION TO BE TAKEN
The City Council is requested to approve this resolution for the acceptance of the
Five-Year Construction Program for Fiscal Years 2005-2009.
cc:
Dawn Lang, Budget Director
Bob Green, Water Plant Manager
Don Vogt, Operations & Maintenance Manager
Mike Felderman, PE
. '
D~
~cÆ~
MEMORANDUM
February 23, 2004
TO:
FROM:
Michael C. Van Milligen, City Manager
Michael A. Koch, Public Works Director j;p~
SUBJECT: Five-Year Street Construction Program for Fiscal Years 2005-2009
INTRODUCTION
The enclosed resolution provides for the acceptance of the Five-Year Street
Construction Program.
DISCUSSION
At the February 19, 2004 Council budget hearing, the Engineering Division
presented its Five-Year Construction Program for Fiscal Years 2005-2009 to the
City Council. This program, which is part of the Five-Year Capital Improvement
Projects, includes the estimated costs for the construction work and the
anticipated year during which each project will be undertaken. This Five-Year
Street Construction Program is considered annually by the City Council and
appropriately revised.
RECOMMENDATION
I recommend that the City Council accept the Five-Year Construction Program
for Fiscal Years 2005-2009.
ACTION TO BE TAKEN
The City Council is requested to approve this resolution for the acceptance of the
Five-Year Construction Program for Fiscal Years 2005-2009.
cc:
Dawn Lang, Budget Director
Bob Green, Water Plant Manager
Don Vogt, Operations & Maintenance Manager
Mike Felderman, PE