SUBJECT: Dubuque Police Remodeling Project - Bid Award
Sealed bids were received for the Dubuque Police Remodeling Project. Chief of Police
Kim Wadding recommends award of the contract to the low bidders, Stumpf
Construction, in the amount of $69,827 for Base Bid #1 and Alternate #1, and that the
contract for Base Bid #2 and Alternate #2 be awarded to All Systems in the amount of
$22,699.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
---1!1Jj~AI{J
Michael C. Van Milligen '--"
MCVM/jh
Attachment
cc: Barry Lindahl, Corporation Counsel
Cindy Steinhauser, Assistant City Manager
Kim B. Wadding, Police Chief
v;
8:)!iC:.
t¡j:S
£-¡mno
D~
~Yk-~
MEMORANDUM
June 1, 2004
FROM:
Michael C, Van Milligen, City Manager
Kim B, Wadding, Police Chief~
Dubuque Police Remodeling Project - Bid Award
TO:
SUBJECT:
INTRODUCTION
The enclosed resolutions provides for the award of the Dubuque Police Remodeling
Project.
DISCUSSION
The Police Remodeling Project remodels the southeast corner of the Dubuque County
Law Enforcement Center 770 Iowa Street. Previously this area housed the Dubuque
Police Investigative Area. With the recently completed jail addition, the investigative
unit has moved to the new addition, The Police Remodeling Project allows needed
expansion for the patrol division. The Police Remodeling creates a new briefing room,
offices for Patrol Captains and Lieutenants, storage areas, and a new operations room
for day-to-day operations, Steve Ulstad Architects designed the remodeling and divided
the project into four components:
Base Bid 1:
This is for the remodeling of the old investigative area into the new Patrol
area.
This is for the outside awning to cover the new doorway that leads to the
south parking lot.
This is for the basic furnishings for the Operations Office and the new
Patrol Briefing Room.
This is for the furnishings for the new Patrol Captain and Lieutenant
Offices and for the furnishings for the new storeroom,
Alternate 1:
Base Bid 2:
Alternate 2:
S
I d b'd
d
M
20 2004 A
f h b'd '
f II
eae I S were opene on av summary 0 t e I s IS as 0 ows:
mimiiilllilllllï!lli!l!œ~mllliiilliiillill l'I'!!!!iii!lii'lílll ~~!;m§ï~h\!!¡¡¡ mi~i!iI!!J~.t!!!~l~b~l¡ml ml¡§I~~¡~¡~I~¡II~illliïiJl_.!iiII~II¡111
11."."...,.1"""
Conlon
Construction Yes $68,806 $17,798 $8,619 $15,187
Gerardy
Construction Yes $66,118 $18,277
Klauer
Construction Yes $58,627 $33,548
Stumpf
Construction Yes $53,273 $16,554
Tricon
Construction Yes $65,600 $17,100
All Svstems Yes $8,731 $13,968
Floor Show
Furnishinas Yes $25,598
Triplett No
Welter FurnishinQs No
'-
RESOLUTION NO. 243-04
ADOPTING PLANS AND SPECIFICATIONS FOR THE DUBUQUE LAW
ENFORCEMENT CENTER REMODELING PROJECT
Whereas, on the 19th day of April 2004, plans, specifications, form of contract
and estimated cost were filed with the City Clerk of Dubuque, Iowa for the Dubuque Law
Enforcement Center Remodeling Project.
Whereas, notice of hearing on plans, specifications, form of contract, and
estimated cost for the Project was published as required by law.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF DUBUQUE, IOWA:
That the said plans, specifications, form of contract and estimated cost are
hereby approved as the plans, specifications, form of contract and estimated cost for
said improvements for said Project.
Passed, adopted and approved this 7th day of June, 2004.
Terrance M. Duggan, Mayor
Attest:
Jeanne F. Schneider, City Clerk
RESOLUTION NO. 244-04
AWARDING CONTRACTS FOR THE DUBUQUE LAW ENFORCEMENT
CENTER REMODELING PROJECT
Whereas, sealed proposals have been submitted for the Dubuque Law
Enforcement Center Remodeling Project pursuant to Resolution No. 169-04 and
notice to bidders was published in the Telegraph Herald in the City of Dubuque,
Iowa on the 23rd day of April 2004; and
Whereas, said sealed proposals were opened and read on the 20th day of
May, 2004; and
Whereas, the bid from Stumpf Construction of Dubuque, Iowa, in the
amount of $69,827 was the lowest bid for Base Bid #1 and Alternate #1 for the
construction remodeling for all labor and materials and performing the work as
provided for in the plans and specifications; and
I
Whereas, the bid from All Systems of Dubuque, Iowa, in the. amount of
$22,699 was the lowest bid for Base Bid #2 and Alternate #2 for the furnishings
and all labor and materials for performing the work as provided for in the plans
and specifications.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF DUBUQUE, IOWA:
1. The contract is hereby awarded to Stumpf Construction for Base Bid #1
and Alternate #1.
2. The contract is hereby awarded to All Systems of Dubuque, Iowa for
Base Bid #2 and Alternate #2.
3. The City Manager is hereby directed to execute the foregoing contracts
on behalf of the City of Dubuque for the complete performance of the work.
4.Upon the execution of the foregoing contracts and the approval of the
contractor's bond, the City Treasurer is authorized and directed to return the bid
deposits of the unsuccessful bidders.
Passed, approved and adopted this 7th day of June, 2004.
Terrance M. Duggan, Mayor
Attest:
Jeanne F. Schneider, CMC, City Clerk
Stumpf Construction of Dubuque, Iowa, submitted the low bid for Base Bid #1 ($53,273)
and Alternate #1 ($16,554) for a total of $69,827, All Systems of Dubuque, Iowa
submitted the low bid for Base Bid #2 ($8,731) and Alternate #2 ($13,968) for a total of
$22,699, The low bids are 25% under Steven Ulstad Architects original estimate,
Steven Ulstad Architects has reviewed the bids with the low bidders and each bid
appears to be in order and Steven Ulstad Architects recommends award of the
contracts to the low bidders,
RECOMMENDATION
I recommend that the contract be awarded for Base Bid #1 and Alternate #1 to Stumpf
Construction in the amount of $69,827 and the contract be awarded for Base Bid #2 and
Alternate #2 to All Systems in the amount of $22,699,
Base Bid #1
Alternate #1
Base Bid #2
Alternate #2
SUBTOTAL
Contin enc
Professional Fees
Ex enses
TOTAL PROJECT COST
$69,824
$15,543
$15,352
$26,335
$127,054
$12,825
$ 8,900
$ 2,000
$150,779
$53,273
$16,554
$ 8,731
$13,968
$92,526
$ 9,253
$ 8,900
$ 2,000
$112,679
The project funds would be provided in the following manner:
ill ~mm¡I!I!I¡¡lli1¡¡¡m¡mfi¡Îf¡lì1ïïl~~!IJ~I.P,41~ll"'MtI~.~J0.~I!E!¡ !if:1I¡¡¡§li~m!¡ it ¡mlilliii; ii! [i WI Ii i ¡ il ¡lillilli!1 IlillJiYì~llilll¡'
DLEC New Addition Construction and Remodeling - 010-869 & 010-789 $71,766
FY2005 Mobile Data Terminal Project - No CIP Number Assigned
NOTE: Recently the Dubuque County Sheriff's Office, who is also upgrading
their mobile data terminals, received quotes placing each mobile data terminal at
a cost of $5,500, We would anticipate receiving the same or equal quote for our $33,000
oroiect, This results in a oroiected savinas of $33,000 ($154,000 - $121,000),
Emeraitech Computer Project - Unspent Balance - 010-638 $7,913
TOTAL $112,679
ACTION TO BE TAKEN
The City Council is requested to adopt the attached resolutions awarding the Dubuque
Police Remodeling Project to Stumpf Construction for Base Bid #1 and Alternate #1 and
to All Systems for Base Bid #2 and Alternate #2.
cc:
Cindy Steinhauser, Assistant City Manager
Dawn Lang, Budget Director
Jeanne Schneider, City Clerk
Barry Lindahl, Corporation Attorney
DU~~E
~Yk-~
-rßs g
ç;/ 7 /at¡
MEMORANDUM
April 12,2004
TO:
The Honorable Mayor and City Council Members
FROM:
Michael C, Van Milligen, City Manager
SUBJECT: Initiation of Bid Regarding the Police Department Remodeling
(CIP 010-789 & LEC Expansion 010-869)
Chief of Police Kim Wadding recommends initiation of the bidding process for the Police
Department Remodeling Project, and further recommends that a public hearing be set
for June 7, 2004.
The estimated cost of the project is $109,295, . Current dedicated monies for the
remodel includes $40,551 and $31,215 of carryover monies originally dedicated to the
new addition for a total of $71 ,766, a difference of $37,529, Due to the re-estimate
requiring additional funds, we reviewed our current and future capital improvement
projects and proposals. Currently our capital improvement projects include the
Integrated Software Project (Emergitech) and our proposed FY2005 Mobile Data
TerminalsProject. The Emergitech Project has a balance of$94, 112, some ofwhich
will be needed to complete the project and new estimates on the Mobile Data Terminal
Project indicate a savings of approximately $33,000,
I concur with the recommendation and respectfully request Mayor and City Council
approval.
(Y1 uJA {in ¡J1Ku
Michael C, Van Milligen
MCVM/jh
Attachment
cc: Barry Lindahl, Corporation Counsel
Cindy Steinhauser, Assistant City Manager
Kim B, Wadding, Chief of Police
Dawn Lang, Budget Director
.'
¡.
D~~~E
~<k~
MEMORANDUM
Date: April 9, 2004
To: Michael C, Van Milligen
City Manager
From: Kim 8, Wadding At 1",
Police Chief 1'P--'
Re: j Initiation to Bid regarding the Police Department Remodeling (CIP 010-789 &
LEC Expansion 010-869)
INTRODUCTION:
The purpose of this memorandum is to authorize the public bidding process for the
remodel of the police department's former investigative area into a patrol seryices area,
BACKGROUND:
During November 2000, the voters of Dubuque County approved the expansion of the
Dubuque County Law Enforcement Center at our current location. Approved with the
expansion was the development of a new investigative and records area for use by both
the sheriff and city police, With its recent completion, the investigative and records units
have relocated to the new addition allowing the old investigative and records area to be
vacated permitting the remodeling to begin,
The remodeling of the old investigative and records area maximizes this areafor use by
the patrol division for shift briefings and expanded patrol uses, The remodeling
relocates the patrol superyisors to the old investigative area allowing the 911
Communications Superyisor to relocate to the old patrol superyisor location, The
relocation of the 911 Communications Superyisor allows for the expansion of the 911
Communication Dispatch Center to add an additional fourth dispatch console,
The remodeling coincides with the jail expansion where a new south entrance doorway
was added allowing direct access by patrol officers to the new patrol area without
having to enter from the main entrance on the west and east sides of the building, The
remodeling project includes a small canopy over this new south entrance,
DISCUSSION:
Originally the remodeling was budgeted for FY2003 with Portzen Construction
estimating the project at $40,529, With the investigative and records move complete,
'.
our first remodeling step was the selection of Steven Ulstad Architects as the project
architect Steven Ulstad Architects responsibilities include the creation of the remodel
design, creation of the construction documents, receive and review the submitted
remodel bids and oversee the construction administration, Once Steven Ulstad
Architects was selected, design work was begun working through a number of design
meetings with the Police Department Senior Management Staff, From these design
meetings, a re-estimation of the project was completed with the re-estimate costs of
$109,295, The re-estimate includes:
,".'.,rc'."'}'i"¡1,,;;g!~.1~11iI__-
Remodelin Area 1206 S. Ft. $75 $90,450
SUBTOTAL $90,450
10% $9,450
NTE $8,900
$900
$109,295
Contin enc
Professional Fees
Estimated Expenses
PROJECT TOTAL
Current dedicated monies for the remodel includes $40,551 and $31,215 of carryover
monies originally dedicated to the new addition for a total of $71,766, a difference of
$37,529, Due to the re-estimate requiring additional funds, we reviewed our current and
future capital improvement projects and proposals. Currently our capital improvements
projects include the Integrated Software Project (Emergitech) and our proposed FY2005
Mobile Data Terminals Project. The FY2005 Mobile Data Terminal Project contains
$154,000 and the Emergitech project has a balance of $94,112,
To offset the funds needed for the projected re-estimate, we proposed the following:
1)
To use remaining funds designated for the FY2005 Mobile Data Terminal
Project once all budgeted terminals are purchased and installed,
NOTE: Recently the Dubuque County Sheriff's Office, who is also upgrading their
mobile data terminals, received quotes placing each mobile data terminal at a cost
of $5,500, We wOuld anticipate receiving the same or equal quote for our project.
This results in a projected savings o.f $33,000 ($154,000 - $121,000), By approving
the transfer of these savings, the remodel project secures $104,766, a significant
portion of the re-estimate costs.
2)
To use remaining funds originally designated for the Emergitech Project
once all Emergitech project costs are completed,
NOTE: Once the remodel bids are prepared, distributed and received, the project
costs are confirmed and if additional funds were needed we would look to the
remaining Emergitech funds to offset any difference.
RECOMMENDATION:
Based upon the above funding formula, I recommend the City Council adoption of the
three attached resolutions: Preliminary Approval of Plans and Specifications, Fixing
Dateof Hearing on Plans and Specifications, and Notice of Hearing on Plans and
Specifications for the remodeling of certain areas of the City of Dubuque Police
Department at the Dubuque Law Enforcement Center.
NOTICE OF HEARING ON PLANS AND SPECIFICATIONS
Notice of public hearing on proposed plans and specifications, proposed form of
contract and estimate of cost for the Remodeling of Certain Areas of the City of
Dubuque Police Department at the Dubuque Law Enforcement Center.
NOTICE IS HEREBY GIVEN: The City Council of Dubuque, Iowa will hold a
public hearing on the proposed plans, specifications, form of contract and estimate of
cost for the Remodeling of Certain Areas of the City of Dubuque Police Department at
the Dubuque Law Enforcement Center in accordance with the provisions of Chapter
384, Code of Iowa, at 6:30 p.m" on the 7th day of June, 2004, in the Public Library
Auditorium, 11th & Locust, Dubuque, Iowa, Said proposed plans, specifications, form of
contract and estimate of cost are now on file in the Office of the City Clerk, At said
hearing any interested person may appear and file objections thereto or to the costs of
the improvements,
I Any visual or hearing-impaired persons needing special assistance or persons
with special accessibility needs should contact the City Clerk's office at (563) 589-4120
or TDD at (563) 690-6678 at least 48 hours prior to the meeting,
Published by order of the City Council given on the - day of -' 2004,
Jeanne F. Schneider, CMC, City Clerk
RESOLUTION NO.
PRELIMINARY APPROVAL OF PLANS AND SPECIFICATIONS FOR THE
REMODELING OF CERTAIN AREAS OF THE CITY OF DUBUQUE POLICE
DEPARTMENT AT THE DUBUQUE LAW ENFORCEMENT CENTER
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF DUBUQUE, IOWA:
That the proposed plans, specifications, form of contract and estimated cost for
the police remodeling for the investigative area of the City of Dubuque police
department at the Dubuque Law Enforcement Center in the estimated amount of
$109,295 are hereby approved and ordered filed in the office of the City Clerk for public
inspection.
Passed, adopted and approved this - day of - 2004,
Terrance M. Duggan, Mayor
Attest:
Jeanne F. Schneider, CMC, City Clerk
RESOLUTION NO.
FIXING DATE OF HEARING ON PLANS AND SPECIFICATIONS FOR THE
REMODELING OF CERTAIN AREAS OF THE CITY OF DUBUQUE POLICE
DEPARTMENT AT THE DUBUQUE LAW ENFORCEMENT CENTER
Whereas, the City Council of the City of Dubuque, Iowa has given its preliminary
approval to the proposed plans, specifications, and form of contract and placed same
on file in the office of the City Clerk for public inspection for the Remodeling of Certain
Areas of the City of Dubuque Police Department at the Dubuque Law Enforcement
Center.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF DUBUQUE, IOWA: .
That a public hearing be held on the 7th day of June, 2004, at 6:30 p.m, in the
Publlc Library Auditorium, 11th & Locust, Dubuque, Iowa, at which time interested
persons may appear and be heard for or against the proposed plans and specifications,
form of contract and cost of said improvement, and the City Clerk be and is hereby
directed to cause a notice of time and place of such hearing to be published in a
newspaper having general circulation in the City of Dubuque, Iowa, which notice shall
be not less than four days nor more than twenty days prior to the day fixed for its
consideration, At the hearing, any interested person may appear and file objections to
the proposed plans, specifications, contract, or estimated cost of the improvement.
Passed, adopted and approved this - day of - 2004.
Terrance M, Duggan, Mayor
Attest:
Jeanne F. Schneider, CMC, City Clerk