Schmitt Harbor Boat Ramp Proj.RESOLUTION NO. 123-00
ACCEPTING IMPROVEMENT
Whereas, the contract for the Schmitt Harbor Boat Ramp Project has been
completed and the City Manager has examined the work and filed his certificate stating that
the same has been completed according to the terms of the contract, plans and
specifications and recommends its acceptance.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
DUBUQUE, IOWA:
Section 1. That the recommendation of the City Manager be approved and that said
improvement be and the same is hereby accepted.
BE IT FURTHER RESOLVED that the City Treasurer be and he is hereby directed
to pay to the contractor from the Marine Fuel Tax Grant and the Local Option Sales Tax
Fund in amount equal to the amount of this contract, less any retained percentage
provided for therein.
Passed, approved and adopted this ~ day of
Apri 1
,2000.
Attest:
RESOLUTION NO. 123-00
FINAL ESTIMATE
Whereas, the contract for the Schmitt Harbor Boat Ramp Project has been
completed and the City Engineer has submitted his final estimate showing the cost thereof
including the cost of estimates, notices and inspection and all miscellaneous costs;
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
DUBUQUE, IOWA:
Section 1. That the cost of said improvement is hereby determined to be
$96,681.46 and the said amount shall be paid from the Marine Fuel Tax Grant and the
Local Option Sales Tax Fund of the City of Dubuque, Iowa.
Passed, approved and adopted this ~ day of Apri 1
n¿
Attest:
~ ~. /j .
:/4'/%4?~ +'dW¿ þ~".-/
/jeanne F. Schneider, City Clerk