1999 Curb Ramp Installation - CDBGRESOLUTION NO. 196-00
ACCEPTING IMPROVEMENT
Whereas, the contract for the 1999 Curb Ramp Installation - CDBG Project has
been completed and the City Manager has examined the work and filed his certificate
stating that the same has been completed according to the terms ofthe contract, plans and
specifications and recommends its acceptance.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
DUBUQUE, IOWA:
Section 1. That the recommendation of the City Manager be approved and that said
improvement be and the same is hereby accepted.
BE IT FURTHER RESOLVED that the City Treasurer be and he is hereby directed
to pay to the contractor from the CDBG FY2000 Funds in amount equal to the amount of
this contract, less any retained percentage provided for therein.
Passed, approved and adopted this 15th day of Mav
,2000.
Terrance M. Duggan, Mayor
Attest:
Jeanne F. Schneider, City Clerk
.
RESOLUTION NO. 197-00
FINAL ESTIMATE
Whereas, the contract for the 1999 Curb Ramp Installation - CDBG Project has
been completed and the City Engineer has submitted his final estimate showing the cost
thereof including the cost of estimates, notices and inspection and all miscellaneous costs;
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
DUBUQUE, IOWA:
Section 1. That the cost of said improvement is hereby determined to be
$60,761.20 and the said amount shall be paid from the CDBG FY2000 Funds of the City
of Dubuque, Iowa.
Passed, approved and adopted this 15th
Terrance M. Duggan, Mayor
Attest:
Jeanne F. Schneider, City Clerk