Michael C. Van Milligen, City Manager
SUBJECT: 2005 Curb Ramp Installation - CDBG Project No.1
(ADA Curb Ramp Construction Project #210-339)
City Engineer Gus Psihoyos recommends initiation of the bidding process for the 2005
Curb Ramp Installation - CDBG Project #1, and further recommends that a public
hearing be set for March 21, 2005. This project provides for construction of curb ramps
at various locations throughout the City in compliance with the American with
Disabilities Act (ADA).
I concur with the recommendation and respectfully request Mayor and City Council
approval.
..i" ;f C . '}7 II'
I li~' id! {I L---
Michael C. Van Milligen
MCVM/jh
Attachment
cc: Barry Lindahl, Corporation Counsel
Cindy Steinhauser, Assistant City Manager
Gus Psi hoyos, City Engineer
Ci
D~~~E
~<k~
MEMORANDUM
February 28, 2005
FROM:
Michael C. Van Milligen, City Managev-----;
Gus Psihoyos, City Engineer Yj~
2005 Curb Ramp Installation - CDBG Project NO.1
(ADA Curb Ramp Construction Project #210-339)
TO:
SUBJECT:
INTRODUCTION
The enclosed resolutions authorize the public bidding procedure for the construction of
curb ramps at various locations throughout the City in compliance with the American
with Disabilities Act.
BACKGROUND
The Americans with Disabilities Act requires that curb ramps be installed at
intersections in all areas of the City. This area is also part of the Housing Department's
Washington Neighborhood Revitalization Area. The City has been installing ramps on
all street resurfacing and reconstruction projects, as well as on all sidewalk inspection
routes.
DISCUSSION
This project continues a systematic program for the installation of curb ramps
throughout the City and consists of 33 ramps in the areas of Elm Street to Central
Avenue and 11th Street to 14th Street.
The schedule for the project will be as follows:
Advertisement for Bids
Notice of Hearing on Plans & Specifications
Receipt of Bids
Public Hearing
Award of Contract
Completion
March 8, 2005
March 11, 2005
March 15, 2005
March 21,2005
March 21,2005
July 1, 2005
"-
'),.<b
---- ----------- -- - '
~
"
"
RESOLUTION NO. 76-05
PRELIMINARY APPROVAL OF PLANS AND SPECIFICATIONS
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF DUBUQUE, IOWA:
That the proposed plans, specifications, form of contract and estimated
cost for the 2005 Curb Ramp Installation - CDBG Project No.1 in the estimated
amount of $28,715.50 are hereby approved and ordered filed in the office of the
City Clerk for public inspection.
Passed, adopted and approved this 7th day of March
Attest:
RESOLUTION NO. 77-05
FIXING DATE OF HEARING ON PLANS AND SPECIFICATIONS
Whereas, the City Council of the City of Dubuque, Iowa has given its
preliminary approval on the proposed plans, specifications, and form of contract
and placed same on file in the office of the City Clerk for public inspection of the
2005 Curb Ramp Installation - CDBG Project No.1.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF DUBUQUE, IOWA:
That a public hearing will be held on the 2151 day of March, 2005, at 6:30
p.m. in the Public Library Auditorium at which time interested persons may
appear and be heard for or against the proposed plans and specifications, form
of contract and cost of said improvement, and the City Clerk be and is hereby
directed to cause a notice of time and place of such hearing to be published in a
newspaper having general circulation in the City of Dubuque, Iowa, which notice
shall be not less than four days nor more than twenty days prior to the day fixed
for its consideration. At the hearing, any interested person may appear and file
objections to the proposed plans, specifications, contract, or estimated cost of
the improvement.
Passed, adopted and approved this 7 th day of
Atte t: J
----- ~ . .'
_~44L/'~ ['~~ /A'li~
eanne F. Schneider, CMC, City Clerk
RESOLUTION NO. 78-05
ORDERING BIDS
NOW THEREFORE, BE IT RESOLVED BY THE COUNCIL OF THE CITY
OF DUBUQUE, IOWA:
That the 2005 Curb Ramp Installation - CDBG Project No.1 is hereby
ordered to be advertised for bids for construction.
BE IT FURTHER RESOLVED, that the amount of the security to
accompany each bid shall be in an amount which shall conform to the provisions
of the Notice to Bidders hereby approved as a part of the plans and
specifications heretofore adopted.
That the City Clerk is hereby directed to advertise for bids for the
construction of the improvements herein provided, to be published in a
newspaper having general circulation in the City of Dubuque, Iowa, which notice
shall not be less than four days nor more than forty-five days prior to the receipt
of said bids at 2:00 p.m. on the 15th day of March, 2005. Bids shall be opened
and read by the City Clerk at said time and will be submitted to the Council for
final action at 6:30 p.m. on the 21st day of March, 2005.
Passed, adopted and approved this 7th day of March
Attest:
_ ~~L~f2/
Jeanne F. Schneider, CMC, City Clerk
RESOLUTION NO.
RESOLUTION ADOPTING PLANS AND SPECIFICATIONS
Whereas, on the 2nd day of March, 2005, plans, specifications, form of
contract and estimated cost were filed with the City Clerk of Dubuque, Iowa for
the 2005 Curb Ramp Installation - CDBG Project NO.1.
Whereas, notice of hearing on plans, specifications, form of contract, and
estimated cost was published as required by law.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF DUBUQUE, IOWA:
That the said plans, specifications, form of contract and estimated cost are
hereby approved as the plans, specifications, form of contract and estimated cost
for said improvements for said project.
Passed, adopted and approved this
day of
,2005.
Terrance M. Duggan, Mayor
Attest:
Jeanne F. Schneider, CMC, City Clerk
RESOLUTION NO.
ORDERING BIDS
NOW THEREFORE, BE IT RESOLVED BY THE COUNCIL OF THE CITY
OF DUBUQUE, IOWA:
That the 2005 Curb Ramp Installation - CDBG Project No. 1 is hereby
ordered to be advertised for bids for construction.
BE IT FURTHER RESOLVED, that the amount of the security to
accompany each bid shall be in an amount which shall conform to the provisions
of the Notice to Bidders hereby approved as a part of the plans and
specifications heretofore adopted.
That the City Clerk is hereby directed to advertise for bids for the
construction of the improvements herein provided, to be published in a
newspaper having general circulation in the City of Dubuque, Iowa, which notice
shall not be less than four days nor more than forty-five days prior to the receipt
of said bids at 2:00 p.m. on the 15th day of March, 2005. Bids shall be opened
and read by the City Clerk at said time and will be submitted to the Council for
final action at 6:30 p.m. on the 21st day of March, 2005.
Passed, adopted and approved this _ day of
,2005.
Terrance M. Duggan, Mayor
Attest:
Jeanne F. Schneider, CMC, City Clerk
NOTICE TO BIDDERS OF THE RECEIPT OF BIDS
FOR THE 2005 CURB RAMP INSTALLATION
CDBG PROJECT NO.1
Sealed proposals will be received by the City Clerk of the City of Dubuque, Iowa,
at the Office of City Clerk in City Hall no later than 2:00 o'clock p.m. on the 15th day of
March, 2005, for the 2005 Curb Ramp Installation - CDBG Project NO.1.
Copies of the plans and specifications may be obtained in the City Engineer's
office at City Hall. No plan deposit is required.
Payment to the contractor will be made from funds as may be legally used for
such purposes.
All work herein provided for shall be commenced within ten (10) days after the
Notice To Proceed has been issued, and shall be fully completed by the 1st day of July,
2005.
All bids must be submitted on the Bid Form bound in the specifications. Each bid
shall be accompanied by a satisfactory Bid Bond executed by the Bidder and an
acceptable surety; or a cashier's or certified check payable to the City Treasurer, City of
Dubuque, drawn on a bank in Iowa or a bank chartered under the laws of the United
States, in the amount of ten percent (10%) of the bids submitted as security that the
bidder will enter into a contract for doing the work and will give bond with proper
securities for the faithful performance of the contract in the form attached to the
specifications.
The successful bidder will be required to furnish a performance bond in an
amount equal to one hundred percent (100%) of the contract price. Said bond is to be
issued by a responsible surety company approved and acceptable to the City Council,
and shall guarantee the faithful performance of the contract and terms and conditions
therein contained, and shall guarantee the prompt payment of all materials and labor
and protect and save harmless the City of Dubuque, Iowa, from claims and damages of
any kind caused by the operations of the Contractor. Said Bond shall also guarantee
the material and the maintenance of the improvement(s) constructed for a minimum
period of two (2) years from and after its completion and acceptance by the City
Council.
No bid submitted by any Contractor which contains a condition or qualification
s~all be recognized or accepted by the City Council and any letter or communication
accompanying the bid which contains a condition or qualification upon the bid which has
the effect of qualifying or modifying any provision of the specifications in any manner will
be construed as a non-qualifying bid and will be rejected by the City Council as not
responsive.
All proposals must be made on blanks furnished by the City Engineer and each
bidder will be required to state his prices for doing all the items in each section on which
he makes a bid and for all things necessary to make a complete job.
The Bidder's attention is directed to the City of Dubuque's Affirmative Action
Program which is included in the Contract Specifications and the provisions thereof and
hereby made a part of the Contract Documents by reference and incorporated therein.
,: J,.)
The Contractor, when requested by the City of Dubuque, will furnish a statement
of his financial and practical qualifications as provided for in the General Requirements
of the Specifications.
By virtue of statutory authority, a preference will be given to products and
provisions grown and coal produced within the State of Iowa and to Iowa Domestic
Labor.
The City Council reserves the right to reject any and all bids or to waive any
technical ties and irregularities.
All bids will be publicly opened and read by the City Clerk at 2:00 o'clock p.m. on
the 15th day of March, 2005, and will be submitted to the City Council for final action at a
meeting to be held in the Public Library Auditorium, 360 West 11th Street, at said City at
6:30 p.m. on the 21st day of March, 2005. A contract will be awarded at that time or
$U6h subsequent time as the City may determine.
Published by order of the City Council of the City of Dubuque, Iowa and dated
this of , 2005.
Jeanne F. Schneider, CMC, City Clerk
~i ~ I ~
CONSTRUCTION SCHEDULE AND LIQUIDATED DAMAGES
Work herein provided for shall be commenced within the (10) days after notice to
proceed has been issued and shall be fully completed by July 1, 2005.
For each calendar day that any work shall remain uncompleted beyond the
completion schedule, $500.00 per calendar day will be assessed, not as a
. penalty but as predetermined and agreed liquidated damages. The contractor
will be separately invoiced for this amount, and final payment will be withheld
until payment has been made of this invoice.
The assessment of liquidated damages shall not constitute a waiver of the City's
right to collect any additional damages which the City may sustain by failure of
the contractor to carry out the terms of his contract.
An extension of the contract period may be granted by the City for any of the
following reasons:
1. Additional work resulting from a modification of the plans.
2. Delays caused by the City.
3. Other reasons beyond the control of the Contractor, which in the City's
opinion, would justify such extension.