Iowa 32 Bike/Hike Trail Phase 3 Project AcceptanceMasterpiece on the Mississippi TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager SUBJECT: Iowa 32 Bike /Hike Trail Phase 3 Project, CIP #100 -2273 DATE: October 31, 2011 Dubuque Med AN- AmericaCity I'll, 2007 Leisure Services Manager Marie Ware recommends City Council acceptance of the Iowa 32 Bike /Hike Trail Phase 3 Project (between Plaza Drive and Payton), as completed by Drew Cook & Sons Excavating, in the final contract amount of $136,946, which was $6,654 below the bid amount of $143,600. A change order was processed to add a 24" pipe for drainage and the trail was re- aligned. I concur with the recommendation and respectfully request Mayor and City Council approval. Michael C. Van Milligen MCVM:jh Attachment cc: Barry Lindahl, City Attorney Cindy Steinhauser, Assistant City Manager Marie L. Ware, Leisure Services Manager Masterpiece on the Mississippi TO: FROM: SUBJECT: DATE: Michael C. Van Milligen, City Manager Marie L. Ware, Leisure Services Manager Iowa 32 Bike /Hike Trail Phase 3 Project, CIP #100 -2273 October 31, 2011 INTRODUCTION Dubuque hfril aA- Amedcacily 2007 The purpose of this memorandum is to recommend that the City Council accept the Iowa 32 Bike /Hike Trail Phase 3 Project (between Plaza Drive and Payton). DISCUSSION The Iowa 32 Bike /Hike Trail Phase 3 Project has been completed by Drew Cook & Sons Excavating in the final contract amount of $136,946. A summary of the project costs is as follows: Estimated cost Bid amount Actual cost Construction contract $ 147,000 $ 143,600 $ 136,946 Contingency $ 20,000 Engineering $ 33,000 $ 12,271 TOTAL $ 200,000 $ 143,600 $ 149,217 A change order was processed to add a 24" pipe for drainage. The trail was re- aligned which caused a credit of $9,078 to the project. Engineering costs were reduced for the project as preliminary engineering was completed to apply for other grants. Those costs were paid in previous fiscal years and projects and are not grant eligible. A $200,000 R.E.A.P. grant was received to fund this project. ACTION STEP The action requested is that the City Council adopt the attached resolution accepting the improvement and setting the final cost. MLW:et attachment copy Jon Dienst / Gus Psihoyos / Laura Carstens / Jenny Larson Preparer: Marie L. Ware Address: 2200 Bunker Hill Rd Phone: (563) 589 -4263 RESOLUTION NO. 355 -11 ACCEPTING THE IOWA 32 BIKE /HIKE TRAIL PHASE 3 PROJECT AND AUTHORIZING THE PAYMENT OF THE CONTRACT AMOUNT TO THE CONTRACTOR Whereas, the Public Improvement Contract for the Iowa 32 Bike /Hike Trail Phase 3 Project (the Project) has been completed and the City Engineer has examined the work and filed a certificate stating that the Project has been completed according to the terms of the Public Improvement Contract and that the City Engineer recommends that the Project be accepted; and NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: Section 1. The recommendation of the City Engineer is approved and the Project is hereby accepted. Section 2. The Finance Director is hereby directed to pay to the Contractor from the Iowa 32 Bike /Hike Trail Phase 3 Project appropriation for the contract amount of $136,946 less any retained percentage provided for therein as provided in Iowa Code chapter 573, and to pay such retainage only in accordance with the provisions of Iowa Code chapter 573. Attest: Passed, approved and adopted this 7th day of November Kevin Firnstahl, City Clerk , 2011. D/ Roy D. Buol, Mayor