Dbq Industrial Ctr West 3rd Add Grading Pro DU~~E ~<k~ MEMORANDUM March 28, 2005 TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager SUBJECT: Dubuque Industrial Center West 3rd Addition/Contract A Mass Grading (CIP: 360359--lndustrial Site Development - Bergfeld Farm, Dubuque Industrial Center West and Chavenelle Drive Extension) Sealed bids were received for the Dubuque Industrial Center West 3rd Addition/ Contract A Mass Grading Project. Subject to concurrence by the Iowa Department of Transportation, City Engineer Gus Psihoyos recommends award of the contract to the low bidder, W.C. Stewart Construction, in the amount of $3,092,815.32, which is 20.56% under the engineer's estimate. I concur with the recommendation and respectfully request Mayor and City Council approval. ,N f( /lit Michael C. Van Milligen '- MCVM/jh Attachment cc: Barry Lindahl, Corporation Counsel Cindy Steinhauser, Assistant City Manager Gus Psihoyos, City Engineer - ,) G_~ ,-.'" ; I ,:1 ,t' D;;B~E ~<k~ MEMORANDUM March 29, 2005 FROM: Michael C. Van Milligen, City Manager Gus Psihoyos, City Engineer ~ TO: SUBJECT: Dubuque Industrial Center West 3rd Addition/Contract A Mass Grading (CIP: 360359--lndustrial Site Development - Bergfeld Farm, Dubuque Industrial Center West and Chavenelle Drive Extension) INTRODUCTION The enclosed resolution authorizes the award of the Dubuque Industrial Center West 3rd Addition/Contract A Mass Grading Project. BACKGROUND This project begins the construction phase of the next expansion of the Dubuque Industrial Center West, including the connection of the east and west sections of Chavenelle Road through the McFadden farm. The 150-acre project area includes the former Bergfeld farm property. IIW has been retained to design and engineer this project for the City. This first bid package allows mass grading of the site to begin as soon as weather permits this spring, earlier than initially anticipated in the budget process. The project is approved in the FY06 Capital Improvement Program. General obligation bond proceeds for the project will be available to fund project expenses incurred prior to July 1, 2005; however, a final FY05 budget amendment will be needed to acknowledge those expenses incurred by the project's early startup. DISCUSSION Sealed bids were received on March 24, 2005. W.C. Stewart Construction submitted the low bid in the amount of $3,085,915.31. This amount is 20.46% under the engineer's estimate. A summary of the bids received is as follows: W.C. Stewart Construction C.J. Moyna & Sons Tom Kueter Construction Scheckel Construction JB Holland Construction McAninch Corporation Steger-Heiderscheit Const. Peterson Contractors Fischer Excavating $ 3, 085,915.31 $ 3, 252,934.30 $ 3, 351,965.75 $ 3, 801,490.01 $ 3, 804,765.54 $ 3, 871,355.20 $ 3, 950,066.06 $ 4, 227,990.30 $ 5, 761,834.69 RECOMMENDATION Four alternates were bid on the project. It is recommended that only one alternate be selected. This alternate would be Alternate A-46-A, which is a 2-foot high by 3-foot wide compost berm to replace a silt fence that was a base item. This alternate would result in at $6,900 increase in the bid award. It should be noted that the low bidder would be W. C. Stewart Construction regardless of which alternates would have been selected. Attached you will find a letter from IIW Engineers & Surveyors, PC recommending the award of the project to W.C. Stewart Construction. I also recommend that the contract be awarded to W.C. Stewart Construction in the total amount of $3,092,815.31. BUDGET IMPACT The summary of the project costs is as follows: Bid Estimate Award Construction Contingency Engineering & Inspection $3,878,,895.00 387,889.00 379,275.00 $3,092,815.31 387,889.00 379.275.00 Total Project Cost $4,646,059.00 $3,859,979.31 It should be noted that the March 1, 2005 initiation memo indicated an engineering amount of $271,500; this amount represented inspection services only and did not include any design fees. The figure has been revised to $379,275, which includes $155,210 for design services and $224,065 for inspection services. The project will be funded with TIF-backed general obligation bond proceeds and RISE grant funds: Iowa DOT Cost (Rise Grant Funds) City of Dubuque Cost $ 395,647.40 $3,464,331.91 $3,859,979.31 ACTION TO BE TAKEN I recommend that the City Council adopt the attached resolution awarding the Dubuque Industrial Center West 3rd Addition/Contract A Mass Grading Project to W.C. Stewart Construction, subject to the concurrence by the Iowa Department of Transportation. Prepared by Todd Irwin cc: Pam Myhre, Economic Development Todd Irwin, Engineering I RESOLUTION NO. 150-05 RESOLUTION ADOPTING PLANS AND SPECIFICATIONS Whereas, on the 2nd day of March, 2005, plans, specifications, form of contract and estimated cost were filed with the City Clerk of Dubuque, Iowa for the Dubuque Industrial Center West 3rd Addition/Contract A Mass Grading Project. Whereas, notice of hearing on plans, specifications, form of contract, and estimated cost was published as required by law. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: That the said plans, specifications, form of contract and estimated cost are hereby approved as the plans, specifications, form of contract and estimated cost for said improvements for said project. April Passed, adopted and approved this 4th day of April, 2005. Terrance M. Duggan, Mayor Attest: Jeanne F. Schneider, CMC, City Clerk . RESOLUTION NO. 151-05 AWARDING CONTRACT Whereas, sealed proposals have been submitted by contractors for the Dubuque Industrial Center West 3rd Addition/Contract A Mass Grading Project pursuant to Resolution No. and notice to bidders published in a newspaper published in the City of Dubuque, Iowa on the 8th day of March, 2005. Whereas, said sealed proposals were opened and read on the 24th day of March, 2005, and it has been determined that the bid of W.C. Stewart Construction of Dubuque, Iowa, in the amount of $3,092,815.31 was the lowest bid for the furnishings of all labor and materials and performing the work as provided for in the plans and specifications. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: That the contract for the above improvement be awarded to W.C. Stewart Construction, subject to the concurrence by the Iowa Department of Transportation, and the Manager be and is hereby directed to execute a contract on behalf of the City of Dubuque for the complete performance of the work. BE IT FURTHER RESOLVED: That upon the signing of said contract and the approval of the contractor's bond, the City Treasurer is authorized and instructed to return the bid deposits of the unsuccessful bidders. Passed, approved and adopted this 4th day of April, ,2005. Terrance M. Duggan, Mayor Attest: Jeanne F. Schneider, CMC, City Clerk MAR-29-05 TUE 10:06 AM DUBUQUE CITY CLERK O~/29/200S 09:23 FAX FAX NO. 563 589 0890 ,...------... ... ......--.- Post-It" Fax NotB 7671 0Ila ~.." , I Much2S,:!ODS 'n) 6 inn F,.... MilL ~ CO.lDepl, Co. Pl'lOne I Phona . axil F811 H City of Dubuque Engineeri:l'Jg A'IT: Gus Psihoyo, and Todd hwln SO Wegt 13111 Street D\lbuque1 lA 510014864 Re; Dubuque Industrial Center West 3l>! Addition Conttact A - Mass Grading AwWR~~tion nw Project No~ 04119-02R Dear a~ and Todd; Tn accordance with owner instructions, bids for the Dl.1buque Indul>trial Cen.ter West 3nl. Addition _ Contract A Mass GnI.ding were opened i1ud read at 2:00 p.m. on March 24, 200S. Nine (9) bids wen;: rc~ved tor this project. A tabulation of the bids is enl;losed. After reviewing the bids, it was dctetmined the low bllSe bid 'W1!S subnritted by w.e. Stewart Construction of 221 East gd1 Strcd, Dubuque, Iowa, in the ~ount of $3,085,915.31. The only Illtemate we would suggest ~sidt:rins would be Alternate A-46-A 2' High X 3' Wide CompOSl Berm (5201700) to replace A-46 Silt Fence ($13,800), re..'lulting in a $6,900 increase in the bid. The; low bidder would be W.C. Stewart Construction, r~dl(Ss of the alternates selected. W.C. Stewart Construction has the e~ence, workforc:e and equipment to properly coI1lplete this contract. Therefore, w~ recommend award of ~ Dubuque Indu$trial Center Wes13'" Addition - Contraot A Mass Oradil\g to w.e, Stcwarl Construction in the atn()un~ ofS3,085,915.31 plus anyaltemlltesselected by the City of Dubuquc. The engineers estin'll!te lor this project was $3,819,754.80. The low base bid of 53,085,915.31 is 5793,839.49 or 20.46% below the engineer's estimate. Sincacly, nw ENGINEERS & SURVEVORS. P.C, (]{!9-jJ~lf_ ~ Z;.~dsnide1'> P.E. ~~ ---. Ene. . Copy~ Pamela Myhre, City of Dubuque, Economic Development w.e. S1cwart cortStruction IIW Engineers &Surveyors. P.C. l)ubllI.lU~. fA H~.~l (-.-n. WI INTEGRITY. EX~ERTJSE. SOLUTIONS. P. 01 1ll00l/001 IIVI D~I\II11 F. W~~:;k, prJRF. C:b~il~J A. c....... PIT C~1l D. S".lkol'\l. re: M.ch...l A. Jana<:n. PElS!:! Ilnn;ll~ ^. ll~hn~I'. rer.le. Jobu M. Tt.lnJ\~.I't.s Timolhy ,I. Tr~ncl. PE Jghn F. Wnnd,,.,;.l. r. 1"1> lu1i~ P. Nt"ol~~r. 1'1, J."I~A P. K:llm~.I'U Th~.nu~J. O;.rcr. PLS Wrny A. Child<l\'<., rf.'; G~(''''I') T. Bl<lndln.l't M~I'k C. Jl)ll;:cn. PI.; "'1..11i'lI",,1HI Ardlil..,1 JI . ""'I. MN. ~~ Civil '..nr.iftu.-rinK !ilf\l<IUr'dll.!nll,moo';OK En~lronmenlill t'.n.~I"".rill~ Munl~lpall:ln~nCl:rilll: T''''l'P<'ll:uiOll En~i.....,.{nJ: I'II'l:hin:o:tIlral En:;;iflCll'nn; wd Survc:)'lnl: QI,"li\~ C:~O"II'O' TCRdng (kot~clll\lo;:llll'.n~.I"lIIIlillll 4155 r.:nn".IV".nill Av~n\lC D\Jblllj.u~. Iuwa :'11001-1613 ~ri.\.~~li.~~ S~:M~il."R II fux WVo'w.liwant.r,l:.9t" city of Dubuque, Iowa Dubuque Industrial Center West 3rd Addition Contract A - Mass Grading BID TABULATION March 24, 2005 IIW Project No. 04119-02R Engin....r.s Estimate W.C. Stewart Construction C.J. Moyna & Sons Tom Kueter Construction Scheckel Construction UNIT TOTAL UNIT TOTAL % UNIT TOTAL UNIT TOTAL UNIT TOTAL NO. DESCRIPTION QUANTITY PRICE PRICE PRICE PRICE PRICE PRICE PRICE PRICE PRICE PRICE SITE AND ROADWAY A-l Demolrtion 1 LS $50,000.00 $50,000.00 $5,000.00 $5,000.00 -90% $25,000.00 $25,000.00 $15,000.00 $15,000.00 $20,000.00 $20,000.00 A-2 Wall Abandonment 2EA $1,000.00 $2,000.00 $1,200.00 $2,400.00 20% $1,000.00 $2,000.00 $2,500.00 $5,000.00 $1,000.00 $2,000.00 A-3 Clearing & Grubbing 1 LS $10,000.00 $10,000.00 $4,500.00 $4,500.00 -55% $22,000.00 $22,000.00 $11,000.00 $11,000.00 $10,000.00 $10,000.00 A-4 Excavation, Class 10 1,612,263 CY $1.60 $2,579,620.60 $1.44 $2,321,658.72 -10% $1.40 $2,257,168.20 $1.40 $2,257,168.20 $1.73 $2,789,214.99 A-5 Excavation, Class 12 33,600 CY $3.00 $100,600.00 $1.65 $55,440.00 -45% $4.00 $134,400.00 $4.40 $147,840.00 $4.00 $134,400.00 A-6 Topsoil - Strip, Salvage, Stockpile and Spread 41,600 CY $2.50 $104,000.00 $175 $72,600.00 -30% $2.00 $83,200.00 $4.20 $174,720.00 $3.00 $124,600.00 A-7 Intercaplor Drain Line, 4" 6,100 LF $5.00 $30,500.00 $3.75 $22,875.00 -25% $4.50 $27,450.00 $8.00 $48,600.00 $3.80 $23,160.00 A.a Reinforced Conaete Retaining Wall 1 LS $10,000.00 $10,000.00 $5,910.00 $5,910.00 -41% $7,500.00 $7,500.00 $7,700.00 $7,700.00 $19,441.00 $19,441.00 A-9 3" Crushed Stena Surface 4,100 TON $8.00 $32,600.00 $9.25 $37,925.00 16% $10.00 $41,000.00 $11.50 $47,150.00 $10.70 $43,870.00 SUBTOTAL $2,919,720.80 $2,528,50872 -13% $2,599,718.20 $2,714,378.20 $3,166,905.99 DRAINAGE AND STORM WATER MANAGEMENT A-l0 18" RCP, Class III, Class C Bedding 66 LF $37.00 $2,442.00 $24.70 $1,630.20 -33% $25.00 $1,650.00 $30.00 $1,960.00 $27.40 $1,808.40 A-ll 18" RCP, Class IV, Class B Bedding 138 LF $45.00 $6,210.00 $26.40 $3,643.20 -41% $25.00 $3,450.00 $34.00 $4,692.00 $31.70 $4,374.60 A-12 21" RCP, Class III, Class C Bedding 118 LF $44.00 $5,192.00 $28.16 $3,322.88 -36% $34.00 $4,012.00 $35.00 $4,130.00 $31.35 $3,699.30 A-13 24" RCP, Class III, Class C Bedding 167 LF $53.00 $8,851.00 $31.35 $5,235.45 -41% $34.00 $5,678.00 $36.00 $6,012.00 $34.70 $5,794.90 A-14 30" RCP, Class III, Class C Bedding 37 LF $65.00 $2,405.00 $40.97 $1,515.89 -37% $40.00 $1,460.00 $45.00 $1,665.00 $47.55 $1,759.35 A-15 30" RCP, Class IV, Class B Bedding 174 LF $75.00 $13,050.00 $45.76 $7,962.24 -39% $43.00 $7,482.00 $52.00 $9,048.00 $50.85 $8,847.90 A-16 36" RCP, Class III, Class C Bedding 32 LF $70.00 $2,240.00 $42.05 $1,345.60 -40% $55.00 $1,760.00 $60.00 $1,920.00 $60.30 $1,929.60 A-17 36" RCP, Class IV, Class C Bedding 208 LF $76.00 $15,808.00 $44.55 $9,266.40 -41% $55.00 $11,440.00 $66.00 $13,728.00 $67.95 $14,133.60 A-18 42" RCP, Class IV, Class C Bedding 172 LF $95.00 $16,340.00 $57.05 $9,812.60 -40% $70.00 $12,040.00 $78.00 $13,416.00 $88.70 $15,256.40 A-19 42" RCP, Class III, Class C Bedding 95 LF $85.00 $8,075.00 $67.76 $6,437.20 -20% $62.00 $5,890.00 $72.00 $6,840.00 $78.15 $7,424.25 A-20 48" RCP, Class III, Class C Bedding 68 LF $110.00 $7,460.00 $83.90 $5,705.20 -24% $74.00 $5,032.00 $83.00 $5,644.00 $94.90 $6,453.20 A-21 60" RCP, Class V, Class B Bedding 463 LF $190.00 $87,970.00 $143.03 $66,222.89 -25% $157.00 $72,691.00 $176.00 $81,488.00 $194.00 $89,822.00 A-22 66" RCP, Class V, Class C Bedding 134 LF $210.00 $28,140.00 $172.60 $23,128.40 -18% $195.00 $26,130.00 $205.00 $27,470.00 $223.45 $29,942.30 A-23 18" RCP FES 4 EA $510.00 $2,040.00 $413.80 $1,655.20 -19% $650.00 $2,600.00 $482.55 $1,930.20 $383.00 $1,532.00 A-24 24" RCP FES 3EA $560.00 $1,660.00 $438.10 $1,314.30 -22% $700.00 $2,100.00 $533.55 $1,600.65 $430.00 $1,290.00 A-25 30" RCP FES 3EA $600.00 $1,600.00 $510.10 $1,530.30 -15% $750.00 $2,250.00 $627.90 $1,883.70 $492.00 $1,476.00 A-26 36" RCP FES 2 EA $821.00 $1,642.00 $655.60 $1,311.20 -20% $900.00 $1,600.00 $794.45 $1,588.90 $618.00 $1,236.00 A-27 42" RCP FES 3 EA $1,044.00 $3,132.00 $760.80 $2,282.40 -27% $1,100.00 $3,300.00 $925.40 $2,776.20 $712.00 $2,136.00 A-28 48" RCP FES 1 EA $1,128.00 $1,128.00 $886.00 $886.00 -21% $1,200.00 $1,200.00 $1,052.50 $1,052.50 $874.00 $874.00 A-29 60" RCP FES 1 EA $1,564.00 $1,564.00 $1,200.90 $1,200.90 -23% $1,700.00 $1,700.00 $1,430.90 $1,430.90 $1,214.00 $1,214.00 A-30 66" RCP FES 1 EA $1,691.00 $1,691.00 $1,435.80 $1,435.60 -15% $2,600.00 $2,600.00 $1,772.60 $1,772.60 $1,429.00 $1,429.00 A-31 60" MH Tee 1 EA $2,000.00 $2,000.00 $731.80 $731.80 -63% $2,800.00 $2,800.00 $1,200.00 $1,200.00 $953.00 $953.00 A-32 60" MH Sidewall 35 VF $150.00 $5,250.00 $113.50 $3,972.50 -24% $110.00 $3,850.00 $160.00 $5,600.00 $274.00 $9,590.00 Engineer's Esllmata W.C. St_art Construction C.J. Moyna & Sons Tom Kueter Construction Scheckel Construction UNIT TOTAL UNIT TOTAL % UNIT TOTAL UNIT TOTAL UNIT TOTAL NO. DESCRIPTION QUANTITY PRICE PRICE PRICE PRICE PRICE PRICE PRICE PRICE PRICE PRICE A-33 60" MH Top w/Casting 1 EA $1,000.00 $1,00000 $442.90 $442.90 -56% $650.00 $650.00 $717.00 $717.00 $715.00 $715.00 A-34 Type 104B Catch Basin 2 EA $2,000.00 $4,000.00 $2,387.52 $4,775.04 19% $3,500.00 $7,000.00 $2,500.00 $5,000.00 $3,027.00 $6,054.00 A-3~ Type 104G Getcl1 B.si" 1 EA $2,000 00 $2,000 00 $2,960 00 $2.98000 49% $3,500 on $3,500 on $4.000 00 $4,000 00 $3,77800 $3,77800 A-36 Storm water Control Structura A 1 LS $15,00000 $15,000.00 $9,505.00 $9,505.00 -37% $6,000.00 $6,000.00 $8,00000 $8,000.00 $6,626.00 $6,626.00 A-37 Stormwater Control Strudure B 1 LS $10,000.00 $10,000.00 $10,265.00 $10,265.00 3% $8,500.00 $8,500.00 $9,500.00 $9,500.00 $8,991 00 $8,991.00 A-3B RA-61 Drtch Drain 2 EA $2,000.00 $4,000.00 $1,154.00 $2,308.00 -42% $1,600.00 $3,200.00 $1,750.00 $3,500.00 $2,308.00 $4,616.00 A-39 Drop Inlet Strudura 1 LS $15,000.00 $15,000.00 $8,600.00 $8,600.00 -43% $8,200.00 $8,200.00 $9,000.00 $9,000.00 $7,422.00 $7,422.00 A-40 T ranch Stabilization Stone, wlExcavation 500 TON $13.00 $6,500.00 $9.25 $4,625.00 -29% $12.00 $6,000.00 $13.00 $6,500.00 $13.55 $6,775.00 SUBTOTAL $283,630.00 $205,049.49 -28% $225,985.00 $245,085.65 $257,952.60 EROSION AND SEDIMENTATION CONTROL A-41 Riprap Stilling Basin, Complete 1 LS $15,00000 $15,000.00 $5,000.00 $5,000.00 -67% $24,000.00 $24,000.00 $14,000.00 $14,000.00 $5,000.00 $5,000.00 A-42 Riprap, Class A 1,130 SY $25.00 $28,250.00 $25.00 $28,250.00 0% $35.00 $39,550.00 $20.00 $22,600.00 $20.00 $22,600.00 A-43 Riprap, Class A, Grouted 735 SY $30.00 $22,050.00 $35.00 $25,725.00 17% $50.00 $36,750.00 $45.00 $33,075.00 $25.00 $18,375.00 A-44 Riprap, Class C 60SY $27.00 $1,620.00 $25.00 $1,500.00 -7% $60.00 $3,600.00 $28.00 $1,660.00 $20.00 $1,200.00 A-45 Diversion Berm 5,000 LF $5.00 $25,000.00 $0.50 $2,500.00 -90% $2.00 $10,000.00 $1.50 $7,500.00 $2.00 $10,000.00 A-46 Sin Fence 9,200 LF $2.00 $18,400.00 $1.50 $13,600.00 -25% $1.50 $13,800.00 $1.50 $13,600.00 $150 $13,800.00 A-47 Temporary Seed 180AC $275.00 $49,500.00 $50.00 $9,000.00 .02% $50.00 $9,000.00 $50.00 $9,000.00 $50.00 $9,000.00 A-48 Seed and Fertilize, Dubuque Rural 135AC $900.00 $121,500.00 $290.00 $39,150.00 -68% $290.00 $39,150.00 $290.00 $39,150.00 $290.00 $39,150.00 A-49 Seed and Fertilize, Dubuque Urban 10AG $1,200.00 $12,000.00 $550.00 $5,500.00 -54% $550.00 $5,500.00 $550.00 $5,500.00 $550.00 $5,500.00 A-50 Seed and Fertilize, Prairiagrass, Slopes 26AC $1,500.00 $39,000.00 $300.00 $7,600.00 .00% $300.00 $7,800.00 $300.00 $7,600.00 $300.00 $7,800.00 A-51 Mulching, Slopes 52AC $800.00 $41,600.00 $350.00 $18,200.00 -56% $350.00 $18,200.00 $350.00 $18,200.00 $350.00 $18,200.00 A-52 Erosion and Sediment Control, Earthwork Staging 1 LS $50,000.00 $50,000.00 $5,000.00 $5,000.00 -90% $5,000.00 $5,000.00 $7,500.00 $7,500.00 $1.00 $1.00 SUBTOTAL $423,920.00 $161,425.00 -62% $212,350.00 $179,805.00 $150,626.00 ENVIRONMENTAL MITIGATION A-53 Wetland Seed-Mix OBL, WI Compost (Pool Areas) 4.1 AC $2,500.00 $10,250.00 $3,927.00 $16,100.70 57% $3,927.00 $16,100.70 $3,927.00 $16,100.70 $3,927 00 $16,100.70 A-54 Meadow Seed-Mix FACW, WI Compost (Slopes and Islands) 2.7 AC $2,500.00 $6,750.00 $3,762.00 $10,157.40 50% $3,762.00 $10,157.40 $3,762.00 $10,157.40 $3,762.00 $10,157.40 A-55 Silver Maple, 1.7S-;nch Caliper or 15 Gal. (Size) 5EA $200.00 $1,000.00 $152.00 $760.00 -24% $152.00 $760.00 $152.00 $760.00 $152.00 $760.00 A-56 River Birch, 1.75-inch Caliper or 15 Gal. 11 EA $200.00 $2,200.00 $160.00 $1,980.00 -10% $180.00 $1,980.00 $160.00 $1,980.00 $160.00 $1,960.00 A-57 Red Twig Dogwood, 3 Gal. 15 EA $100.00 $1,500.00 $22.00 $330.00 -78% $22.00 $330.00 $22.00 $330.00 $22.00 $330.00 A-58 Istant Red Dogwood, 3 Gal. 6 EA $100.00 $600.00 $22.00 $132.00 -78% $22.00 $132.00 $22.00 $132.00 $22.00 $132.00 A-59 Striped Eulalie Grass, 5 Gal. 51 EA $100.00 $5,100.00 $38.00 $1,938.00 -62% $38.00 $1,938.00 $38.00 $1,938.00 $38.00 $1,938.00 A-60 Swamp \M1rte Oak, 1.75-inch Caliper or 15 Gal. 5 EA $200.00 $1,000.00 $220.00 $1,100.00 10% $220.00 $1,100.00 $220.00 $1,100.00 $220.00 $1,100.00 A-61 Giant Pussy Willow, 5 Gal. 23 EA $100.00 $2,300.00 $50.00 $1,150.00 -50% $50.00 $1,150.00 $50.00 $1,150.00 $50.00 $1,150.00 A-62 Arctic Blue Willow, 5 Gal. 13 EA $100.00 $1,300.00 $50.00 $650.00 -50% $50.00 $650.00 $50.00 $650.00 $50.00 $650.00 A-63 Arrow-wood Viburnum, 5 Gal. 15 EA $100.00 $1,500.00 $40.00 $600.00 -60% $40.00 $600.00 $40.00 $600.00 $40.00 $600.00 A-04 Dwarf American Crenbe!Ty, 5 Gal. 9 EA $100.00 $900.00 $40.00 $360.00 -60% $40.00 $360.00 $40.00 $360.00 $40.00 $360.00 A-65 Swamp Azalea, 3 Gal. 14 EA $100.00 $1,400.00 $40.00 $560.00 -00% $40.00 $560.00 $40.00 $560.00 $40.00 $560.00 A-06 Back Ash, 1.7S-;nch Caliper or 15 Gal. 3 EA $200.00 $600.00 $210.00 $630.00 5% $210.00 $630.00 $210.00 $630.00 $210.00 $630.00 A-67 Harry Garnett, 3 Gal. 16EA $100.00 $1,600.00 $34.50 $552.00 -06% $34.50 $552.00 $34.50 $552.00 $34.50 $552.00 SUBTOTAL $38,000.00 $37,000.10 -3% $37,000.10 $37,000.10 $37,000.10 Engineer's Estimate W.C. St_arl Construction C.J. Moyna & Sons Tom Kuetar Construction Scheckel Construction UNIT TOTAL UNiT TOTAL % UNIT TOTAL UNIT TOTAL UNIT TOTAL NO. DESCRIPTION QUANTITY PRICE PRICE PRICE PRICE PRICE PRICE PRICE PRICE PRICE PRICE MISCELLANEOUS A-68 30" Steel C.si"g R~1 6 I.F $65 00 $42,4R.4 on $120 on $7R,43200 85% $135 on $8R.23R on $131l on $90,196 80 $122 95 $80,360 12 A-69 Traffic Control 1 LS $2,000.00 $2,00000 $500.00 $500.00 -75% $1,000.00 $1,00000 $2,500.00 $2,500.00 $5,000.00 $5,000.00 A-70 Construction Survey 1 LS $50,000.00 $50,000.00 $45,000.00 $45,000.00 -10% $53,645.00 $53,645.00 $48,000.00 $48,000.00 $53,645.00 $53,645.00 A-71 Mobilization & Miscellaneous 1 LS $120,000.00 $120,000.00 $30,000 00 $30,000.00 -75% $35,000.00 $35,000.00 $35,000.00 $35,000.00 $50,000.00 $50,000.00 SUBTOTAL $214,484.00 $153,932.00 -28% $177,881.00 $175,696.60 $189,005.12 TOTAL BASE BID $3,879,754.80 $3,085,915.31 -20% $3,252,934.30 $3,351,965.75 $3,801,490.01 ALTERNATES A-46-A 2' High x 3' Wide Compost Berm 9,200 LF $2.00 $18,400.00 $2.25 $20,700.00 13% $2.25 $20,700.00 $2.25 $20,700.00 $2.25 $20,700.00 A-47-A 1/4" Compost Blanket 180AC $275.00 $49,500.00 $600.00 $108,000.00 118% $600.00 $108,000.00 $600.00 $108,000.00 $600.00 $108,000.00 A-51-A Compost Blanket, Slopes 26AC $1,600.00 $41,600.00 $2,720.00 $70,720.00 70% $2,720.00 $70,720.00 $2,720.00 $70,720.00 $2,720.00 $70,720.00 A-51-B Excelsior Mat, Slopes (lOOT RC-14) 26AC $1,600.00 $41,600.00 $6,000.00 $156,000.00 275% $6,000.00 $156,000.00 $6,000.00 $156,000.00 $6,000.00 $156,000.00 Contractor's Continued JB Holland Construction McAninch Corporation Steger-Helderscheit Const. Peterson Contractors Fischer Excavating UNIT TOTAL UNIT TOTAL UNIT TOTAL UNIT TOTAL UNIT TOTAL NO. DESCRIPTION QUANTITY PRICE PRICE PRICE PRICE PRICE PRICE PRICE PRICE PRICE PRICE SITE AND ROADWAY A-l Demol~ion 1 LS $25,000.00 $25,000.00 $46,650.00 $46,65000 $22,000.00 $22,000.00 $30,000.00 $30,000.00 $53,809.88 $53,609.88 A-2 Wall Abandonment 2 EA $1,200.00 $2,400.00 $1,000.00 $2,000.00 $1,300.00 $2,600.00 $1,500.00 $3,000.00 $750.00 $1,500.00 A-3 Clearing & Grubbing 1 LS $10,000.00 $10,000.00 $15,000.00 $15,000.00 $22,000.00 $22,000.00 $17,000.00 $17,000.00 $12,748.97 $12,748.97 A-4 Excavation, Class 10 1,612,263 CY $1.68 $2,708,601.84 $1.70 $2,740,84710 $1.72 $2,773,09236 $1.90 $3,063,299.70 $2.59 $4,175,761.17 A-5 Excavation, Class 12 33,600 CY $2.85 $95,760.00 $3.70 $124,320.00 $3.50 $117,600.00 $5.65 $189,840.00 $5.98 $200,928.00 A-6 Topsoil - Strip, Salvage, Stockpile end Spread 41,600 CY $3.50 $145,600.00 $3.12 $129,792 00 $3.20 $133,120.00 $4.00 $166,400.00 $3.74 $155,584.00 A-7 Interceptor Drain Line, 4" 6,100 LF $8.50 $51,850.00 $8.50 $51,850.00 $4.50 $27,450.00 $8.50 $51,850.00 $16.90 $103,090.00 A.o Reinforced Concrete Retaining Wall 1 LS $7,500.00 $7,500.00 $7,500.00 $7,500.00 $9,000.00 $9,000.00 $7,500.00 $7,500.00 $8,964.89 $8,96489 A-9 3" Crushed Stona Surface 4,100 TON $12.00 $49,200.00 $12.95 $53,095.00 $11.00 $45,100.00 $12.30 $50,430.00 $15.23 $62,443.00 SUBTOTAL $3,095,911.84 $3,171,054.10 $3,151,962.36 $3,579,319.70 $4,774,829.91 DRAINAGE AND STORM WATER MANAGEMENT A-l0 18" RCP, Class III, Class C Bedding 66 LF $25.00 $1,650.00 $25.00 $1,650.00 $34.00 $2,244.00 $25.00 $1,650.00 $27.97 $1,846.02 A-ll 18" RCP, Class IV, Class B Bedding 138 LF $25.00 $3,450.00 $25.00 $3,450.00 $35.00 $4,830.00 $25.00 $3,450.00 $26.37 $3,639.06 A-12 21" RCP, Class III, Class C Bedding 118 LF $34.00 $4,012.00 $34.00 $4,012.00 $48.00 $5,664.00 $34.00 $4,012.00 $50.34 $5,940.12 A-13 24" RCP, Class III, Class C Bedding 167 LF $34.00 $5,678.00 $34.00 $5,678.00 $41.00 $6,847.00 $34.00 $5,678.00 $30.40 $5,076.60 A-14 30" RCP, Class III, Class C Bedding 37 LF $40.00 $1,460.00 $40.00 $1,480.00 $49.00 $1,813.00 $40.00 $1,480.00 $38.88 $1,437.82 A-15 30" RCP, Class IV, Class B Bedding 174 LF $43.00 $7,482.00 $43.00 $7,482.00 $54.00 $9,396.00 $43.00 $7,482.00 $42.48 $7,391.52 A-16 36" RCP, Class III, Class C Bedding 32 LF $55.00 $1,760.00 $55.00 $1,760.00 $59.00 $1,888.00 $55.00 $1,760.00 $49.63 $1,588.16 A-17 36" RCP, Class IV, Class C Bedding 208 LF $55.00 $11,440.00 $55.00 $11,440.00 $65.00 $13,520.00 $55.00 $11,440.00 $51.90 $10,795.20 A-18 42" RCP, Class IV, Class C Bedding 172 LF $70.00 $12,040.00 $70.00 $12,040.00 $77.00 $13,244.00 $70.00 $12,040.00 $77.34 $13,302.48 A-19 42" RCP, Class III, Class C Bedding 95 LF $62.00 $5,890.00 $62.00 $5,890.00 $68.00 $6,460.00 $62.00 $5,890.00 $58.09 $5,518.55 A-20 48" RCP, Class III, Class C Bedding 68 LF $74.00 $5,032.00 $74.00 $5,03200 $84.00 $5,712.00 $74.00 $5,032.00 $83.09 $5,650.12 A-21 60" RCP, Class V, Class B Bedding 463 LF $157.00 $72,691.00 $157.00 $72,691.00 $173.00 $80,099.00 $157.00 $72,691.00 $179.10 $82,923.30 A-22 66" RCP, Class V, Class C Bedding 134 LF $195.00 $26,130.00 $195.00 $26,130.00 $210.00 $28,140.00 $195.00 $26,130.00 $183.59 $24,601.06 A-23 18" RCP FES 4EA $650.00 $2,600.00 $650.00 $2,600.00 $459.00 $1,836.00 $650.00 $2,600.00 $549.60 $2,198.40 A-24 24" RCP FES 3EA $700.00 $2,100.00 $700.00 $2,100.00 $520.00 $1,560.00 $700.00 $2,100.00 $623.93 $1,871.79 A-25 30" RCP FES 3EA $750.00 $2,250.00 $750.00 $2,25000 $570.00 $1,710.00 $750.00 $2,250.00 $757.46 $2,272.38 A-26 36" RCP FES 2EA $900.00 $1,800.00 $900.00 $1,800.00 $767.00 $1,534.00 $900.00 $1,800.00 $979.96 $1,959.92 A-27 42" RCP FES 3EA $1,100.00 $3,300.00 $1,100.00 $3,300.00 $889.00 $2,667.00 $1,100.00 $3,300.00 $1,142.93 $3,428.79 A-28 48" RCP FES 1 EA $1,200.00 $1,200.00 $1,200.00 $1,200.00 $968.00 $968.00 $1,200.00 $1,200.00 $1,336.91 $1,336.91 A-29 60" RCP FES 1 EA $1,700.00 $1,700.00 $1,700.00 $1,700.00 $1,395.00 $1,395.00 $1,700.00 $1,700.00 $1,810.41 $1,810.41 A-30 66" RCP FES 1 EA $2,600.00 $2,600.00 $2,600.00 $2,600.00 $1,791.00 $1,791.00 $2,600.00 $2,600.00 $2,18789 $2,187.89 A-31 60" MH Tee 1 EA $2,800.00 $2,800.00 $2,800.00 $2,60000 $2,420.00 $2,42000 $2,600.00 $2,800.00 $2,842.39 $2,842.39 A-32 60" MH Sidewall 35 VF $110.00 $3,850.00 $110.00 $3,850.00 $126.00 $4,41000 $110.00 $3,850.00 $185.03 $6,476.05 A-33 60" MH Top w/Casting 1 EA $650.00 $650.00 $650.00 $650.00 $725.00 $725.00 $650.00 $650.00 $1,018.20 $1,018.20 A-34 Type 104B Catch Basin 2EA $3,500.00 $7,000.00 $3,500.00 $7,000.00 $2,688.00 $5,376.00 $3,500.00 $7,000.00 $2,659.13 $5,318.26 JB HoIllIIld Construction McAninch Corporation Slager.Heiderschelt Consl. Peterson Contractors F1echer Excavating UNIT TOTAL UNIT TOTAL UNIT TOTAL UNIT TOTAL UNIT TOTAL NO. DESCRIPTION QUANTITY PRICE PRICE PRICE PRICE PRICE PRICE PRICE PRICE PRICE PRICE A-35 Type 104C Catch Basin 1 EA $3,500.00 $3,500.00 $3,500.00 $3,500.00 $3,486.00 $3,486.00 $3,500.00 $3,500.00 $3,432.50 $3,432.50 A-36 Storm water Control Structure A 1 LS $6,000.00 $6,00000 $6,00000 $6,000.00 $11,480.00 $11,48000 $6,000.00 $6,000.00 $10,361.28 $10,361.28 A.37 Stormwat~ Cnntml Strur:h lNll I::t 11.8 $8,500 00 $R 500 on $8,500 00 $8.500 00 $11,92500 $11.'l25nn $R,5OO on $8,500 00 $11,1258R $11,12588 A-38 RA-61 Drtch Drain 2 EA $1,60000 $3,200.00 $1,600.00 $3,200.00 $1,524.00 $3,04800 $1,600.00 $3,200.00 $3,747.35 $7,494.70 A-39 Drop Inlet Strudure 1 LS $8,200.00 $8,200.00 $8,200.00 $8,200.00 $4,532.00 $4,532.00 $8,200.00 $8,200.00 $4,330.88 $4,330.88 A-40 Trench Stabilization Stone, wlExcavation 500 TON $12.00 $6,000.00 $12.00 $6,000.00 $11.00 $5,500.00 $12.00 $6,000.00 $20.46 $10,230.00 SUBTOTAL $225,985.00 $225,985.00 $246,220.00 $225,985.00 $249,406.84 EROSION AND SEDIMENTATION CONTROL A-41 Riprap Stilling Basin, Complete 1 LS $22,423.00 $22,423.00 $14,010.00 $14,010.00 $18,000.00 $18,00000 $15,000.00 $15,000.00 $21,457.73 $21,457.73 A-42 Riprap, Class A 1,130SY $37.67 $42,567.10 $29.65 $33,504.50 $35.00 $39,550.00 $17.40 $19,662.00 $31.84 $35,979.20 A-43 Riprap, Class A, Grouted 735 SY $40.50 $29,76750 $73.50 $54,022.50 $60.00 $44,100.00 $48.50 $35,647.50 $50.29 $36,963.15 A-44 Riprap, Class C 60 SY $38.00 $2,260.00 $62.75 $3,765.00 $40.00 $2,400.00 $24.00 $1,440.00 $31.83 $1,909.80 A-45 Diversion Berm 5,000 LF $1.00 $5,000.00 $1.00 $5,000.00 $3.00 $15,000.00 $1.25 $6,250.00 $1.38 $6,900.00 A-46 Sin Fence 9,200 LF $1.50 $13,800.00 $1.50 $13,600.00 $2.00 $18,400.00 $1.50 $13,600.00 $1.50 $13,600.00 A-47 Temporary Seed 180AC $50.00 $9,000.00 $50.00 $9,000.00 $50.00 $9,000.00 $50.00 $9,000.00 $50.00 $9,000.00 A-48 Seed and Fertilize, Dubuque Rural 135AC $290.00 $39,150.00 $290.00 $39,150.00 $290.00 $39,150.00 $290.00 $39,150.00 $290.00 $39,150.00 A-49 Seed and Fertilize, Dubuque Urnan 10AC $550.00 $5,500.00 $550.00 $5,500.00 $550.00 $5,500.00 $550.00 $5,500.00 $550.00 $5,500.00 A-50 Seed and Fertilize, Prairiagrass, Slopes 26AC $300.00 $7,800.00 $300.00 $7,800.00 $300.00 $7,800.00 $300.00 $7,600.00 $300.00 $7,600.00 A-51 Mulching, Slopes 52AC $350.00 $18,200.00 $350.00 $18,200.00 $350.00 $18,200.00 $350.00 $18,200.00 $350.00 $18,200.00 A-52 Erosion and Sediment Control, Earthwork Staging 1 LS $40,000.00 $40,000.00 $21,000.00 $21,000.00 $15,250.00 $15,250.00 $10,000.00 $10,000.00 $6,000.00 $6,000.00 SUBTOTAL $235,487.60 $224,752.00 $232,350.00 $181,449.50 $202,659.88 ENVIRONMENTAL MITIGATION A-53 Wetland Seed-Mix OBL, WI Compost (Pool Areas) 4.1 AC $3,927.00 $16,100.70 $3,927.00 $16,100.70 $3,927.00 $16,10070 $3,927.00 $16,100.70 $3,927.00 $16,100.70 A-54 Meadow Seed-Mix FACW, WI Compost (Slopes and Islands) 2.7 AC $3,762.00 $10,157.40 $3,762.00 $10,157.40 $3,762.00 $10,157.40 $3,762.00 $10,157.40 $3,762.00 $10,157.40 A-55 Silver Maple, 1.7S-;nch Caliper or 15 Gal. (Size) 5EA $152.00 $760.00 $152.00 $760.00 $152.00 $760.00 $152.00 $760.00 $152.00 $760.00 A-56 River Birch, 1 75-inch Caliper or 15 Gal. 11 EA $180.00 $1,980.00 $180.00 $1,980.00 $160.00 $1,980.00 $180.00 $1,980.00 $160.00 $1,980.00 A-57 Red Twig Dogwood, 3 Gal. 15EA $22.00 $330.00 $22.00 $330.00 $22.00 $330.00 $22.00 $330.00 $22.00 $330.00 A-58 Istant Red Dogwood, 3 Gal. 6EA $22.00 $132.00 $22.00 $132.00 $22.00 $132.00 $22.00 $132.00 $22.00 $132.00 A-59 Striped Eulalie Grass, 5 Gal. 51 EA $38.00 $1,938.00 $38.00 $1,938.00 $38.00 $1,938.00 $38.00 $1,938.00 $38.00 $1,938.00 A-OO Swamp \M1rte Oak, 1.75-inch Caliper or 15 Gal. 5EA $220.00 $1,10000 $220.00 $1,100.00 $220.00 $1,10000 $220.00 $1,100.00 $220.00 $1,100.00 A-61 Giant Pussy Willow, 5 Gal. 23 EA $50.00 $1,150.00 $50.00 $1,150.00 $50.00 $1,150.00 $50.00 $1,150.00 $50.00 $1,150.00 A-62 Arctic Blue Willow, 5 Gal. 13 EA $50.00 $650.00 $50.00 $650.00 $50.00 $650.00 $50.00 $650.00 $50.00 $650.00 A-03 Arrow-wood Vibumum, 5 Gal. 15EA $40.00 $600.00 $40.00 $600.00 $40.00 $600.00 $40.00 $600.00 $40.00 $600.00 A-04 Dwarf American Cranberry, 5 Gal. 9EA $40.00 $360.00 $40.00 $360.00 $40.00 $360.00 $40.00 $360.00 $40.00 $360.00 A-65 Swamp Azalea, 3 Gal. 14 EA $40.00 $560.00 $40.00 $560.00 $40.00 $560.00 $40.00 $560.00 $40.00 $560.00 A-06 Back Ash, 1.75-inch Caliper or 15 Gal. 3EA $210.00 $630.00 $210.00 $630.00 $210.00 $630.00 $210.00 $630.00 $210.00 $630.00 A-67 Harry Gamett, 3 Gal. 16EA $34.50 $552.00 $34.50 $552.00 $34.50 $552.00 $34.50 $552.00 $34.50 $552.00 SUBTOTAL $37,00010 $37,000.10 $37,00010 $37,000 10 $37,000.10 MISCELLANEOUS JB Holland Construction McAninch Corporation Stsger-Heiderschelt Consl Peterson Contractors Fischer Excavating UNIT TOTAL UNIT TOTAL UNIT TOTAL UNIT TOTAL UNIT TOTAL NO. DESCRIPTION QUANTITY PRICE PRICE PRICE PRICE PRICE PRICE PRICE PRICE PRICE PRICE A-OB 30" Steel Casing 653.6 LF $135.00 $88,236.00 $135.00 $88,236.00 $176.00 $115,033.60 $135.00 $88,236.00 $170.60 $111,504.16 A-69 Traffic Control 1 LS $2,000.00 $2,000.00 $2,500.00 $2,50000 $2,500.00 $2,500.00 $2,500.00 $2,500.00 $600.00 $600.00 A_m Con.,tn.,ct'ion SurvP-y 11.S $~3,R45 on $53,645 on $2~,oon on $25,0110 on $58,000 00 $58,000 00 $55,000 00 $5~,ooO 00 $~~.R45 00 $53,64500 A-71 Mobilization & Miscellaneous 1 LS $66,500.00 $66,500.00 $96,828.00 $96,828.00 $107,000.00 $107,000.00 $58,50000 $58,500.00 $332,188.80 $332,188.80 SUBTOTAL $210,381.00 $212,564.00 $282,533.60 $204,236.00 $497,937.96 TOTAL BASE BID $3,804,765.54 $3,871,355.20 $3,950,066.06 $4,227,990.30 $5,761,834.69 ALTERNATES A-46-A 2' High x 3' Wide Compost Berm 9,200 LF $2.25 $20,700.00 $2.25 $20,700.00 $2.25 $20,700.00 $2.25 $20,700.00 $2.25 $20,700.00 A-47-A 1/4" Compost Blanket 180AC $600.00 $108,000.00 $600.00 $108,000.00 $600.00 $108,000.00 $600.00 $108,000.00 $600.00 $108,000.00 A-51-A Compost Blanket, Slopes 26AC $2,720.00 $70,720.00 $2,720.00 $70,720.00 $2,720.00 $70,720.00 $2,720.00 $70,720.00 $2,720.00 $70,720.00 A-51-B Excelsior Mat, Slopes (lOOT RC-14) 26AC $6,000.00 $156,000.00 $6,000.00 $156,000.00 $6,000.00 $156,000.00 $6,000.00 $156,000.00 $6,000.00 $156,000.00