Sanitary Sewer Reconstruction Project - Alley between Rhomberg and Garfield - Acceptance
.
.
.
RESOLUTION NO. 546-00
ACCEPTING IMPROVEMENT
Whereas, the contract for the Sanitary Sewer Reconstruction Project - Alley
between Rhomberg and Garfield from Stanton to Shiras has been completed and the City
Manager has examined the work and filed his certificate stating that the same has been
completed according to the terms of the contract, plans and specifications and
recommends its acceptance.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
DUBUQUE, IOWA:
Section 1. That the recommendation of the City Manager be approved and that said
improvement be and the same is hereby accepted.
BE IT FURTHER RESOLVED that the City Treasurer be and he is hereby directed
to pay to the contractor from the Sanitary Sewer Construction Fund in amount equal to the
amount of this contract, less any retained percentage provided for therein.
Passed, approved and adopted this 20th day of November, 2000.
Attest:
.
.
.
RESOLUTION NO. 547-00
FINAL ESTIMATE
Whereas, the contract for the Sanitary Sewer Reconstruction Project - Alley
between Rhomberg and Garfield from Stanton to Shiras has been completed and the City
Engineer has submitted his final estimate showing the cost thereof including the cost of
estimates, notices and inspection and all miscellaneous costs;
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
DUBUQUE, IOWA:
Section 1. That the cost of said improvement is hereby determined to be
$109,137.08 and the said amount shall be paid from Sanitary Sewer Construction Fund
of the City of Dubuque, Iowa.
Passed, approved and adopted this 20th
Attest:
/~'/
Jeanne Schneider, City Clerk