TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: SEP Green Alley between White & Jackson Street from 9th to 10th
(CIP 7102350)
DATE: December 15, 2011
City Engineer Gus Psihoyos is recommending acceptance of the improvements for the
SEP Green Alley Project between White and Jackson Street from 9tn to 10th Street, as
completed by Portzen Construction, Inc, in the final contract amount of $127,155.99.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
Michael C. Van Milligen
MCVM:jh
Attachment
cc: Barry Lindahl, City Attorney
Cindy Steinhauser, Assistant City Manager
Gus Psihoyos, City Engineer
Masterpiece on the Mississippi
Dubuque
knerd
All-America City
hill!
2007
TO: Michael C. Van Milligen, City Manager
FROM: Gus Psihoyos, City Engineer
DATE: December 15, 2009
SUBJECT: SEP Green Alley between White & Jackson Street from 9th to 10th
(CIP 7102350)
INTRODUCTION
The enclosed resolution provides for the acceptance of the improvements for the Green
Alley between White and Jackson Street from 9th to 10th Streets. This is the first of four
green alleys completed to satisfy the June 27, 2011 Environmental Protection Agency
(EPA) Consent Decree.
BACKGROUND
Section X of Case 2:11 -cv- 01001 -EJM, United States of America and the State of Iowa
v. the City of Dubuque, IA (N.D. Iowa), Civil Action Number 2008V00041, DOJ Case
Number 90 -5 -1 -1 -09339 requires the City of Dubuque (City) to implement a
Supplemental Engineering Project (SEP), which has the objective of securing significant
environmental or public health protection and improvements. Under the SEP, the City
has agreed to reconstruct four (4) alleys using permeable interlocking pavers. The four
(4) alleys must be completed by December 31, 2014. In July of 2011 a work plan was
submitted to the EPA that included the alley between White and Jackson Street from
9th to 10th Streets. This alley is in the Historic Millwork District.
Construction of permeable paver alleys will reduce the volume and peak flow of runoff
to the Mississippi River while also reducing the pollutant load associated with
sto rmwate r runoff.
DISCUSSION
Engineering staff discussed the alley reconstruction with the general contractor for the
HMD project, Portzen Construction (Portzen). Since Portzen was already in the
immediate vicinity of the work area, they agreed to do the additional work at HMD
project bid prices. These prices were very favorable compared to recent green alley
projects. Since the HMD project was funded with TIGER funds from the US Department
of Transportation, the SEP alley cannot be included in the HMD project as a change
order as the SEP alley has to be funded completely with City funds.
The Green Alley Project, between White & Jackson Streets, from 9th to 10th Streets, was
completed by Portzen Construction, Inc. of Dubuque, Iowa, in the final contract amount
of $127,155.99.
As provided in Paragraph 43 of the Consent Decree, any public statement, oral or
written, in print, film, or other media, made by the City making reference to the SEP
under the Consent Decree must include the following language:
"This project was undertaken in connection with the settlement of an enforcement
action, United States and State of Iowa v. City of Dubuque, Iowa, taken on behalf
of the U.S. Environmental Protection Agency and the State of Iowa under the
Clean Water Act."
RECOMMENDATION
I recommend that the City Council accept the improvements and authorize payment of
the contract amount of $127,155.99 to Portzen Construction, Inc. of Dubuque, Iowa, for
the Green Alley Project, between White & Jackson Streets, from 9th to 10th Streets.
BUDGET IMPACT
Funding for the SEP Green Alley Project, between White & Jackson Streets, from 9th to
10th Streets is from the FY 12 CIP appropriation for SEP Green Alleys (CIP #7102350).
ACTION TO BE TAKEN
I respectfully request that the City Council adopt the attached resolution accepting the
improvements and authorizing payment of the contract amount of $127,155.99 to
Portzen Construction, Inc. for the SEP Green Alley Project, between White & Jackson
Streets, from 9th to 10th Streets.
Prepared by Jon Dienst, PE
cc: Jenny Larson, Budget Director
Bob Green, Water Department Manager
Don Vogt, Public Works Director
John Klostermann, Street & Sewer Maintenance Supervisor
Deron Muehring, Civil Engineer II
Todd Shoemaker, Environmental Engineer
RESOLUTION NO. 428 -11
ACCEPTING THE SEP GREEN ALLEY PROJECT, BETWEEN WHITE & JACKSON
STREETS, FROM 9TH TO 10TH STREETS, AND AUTHORIZING THE PAYMENT OF
THE CONTRACT AMOUNT TO THE CONTRACTOR
Whereas, the Public Improvement Contract for the SEP Green Alley Project,
between White & Jackson Streets, from 9th to 10th Streets, (the Project) has been
completed and the City Engineer has examined the work and filed a certificate stating
that the Project has been completed according to the terms of the Public Improvement
Contract and that the City Engineer recommends that the Project be accepted; and
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF DUBUQUE, IOWA:
Section 1. The recommendation of the City Engineer is approved and the Project
is hereby accepted.
Section 2. The Finance Director is hereby directed to pay to the Contractor from
the SEP Green Alleys appropriation for the contract amount of $127,155.99 less any
retained percentage provided for therein as provided in Iowa Code chapter 573, and to
pay such retainage only in accordance with the provisions of Iowa Code chapter 573.
Attest:
Passed, approved and adopted this 19th day of December, 2011.
<4,
OP
.1i �✓�
Kevi . Firnstahl, ity erk
i
_ d i_4
Ly V Sutton, Mayor Pro -Tem
CITY ENGINEER'S CERTIFICATE OF FINAL COMPLETION OF THE SEP GREEN
ALLEY PROJECT, BETWEEN WHITE & JACKSON STREETS, FROM 9TH TO 10TH
STREETS
The undersigned City Engineer of the City of Dubuque, Iowa, hereby certifies that
he has inspected the SEP Green Alley Project, between White & Jackson Streets, from
9th to 10th Streets, that the Project has been performed in compliance with the terms of
the Public Improvement Contract, and that the total cost of the completed work is
$128,679.62.
411
Dated this 6 day of emmtick
, 2011.
Filed in the office of the City Clerk on the day o
City Engineer
2011.
Kevin S. irnsta I Clerk
City of Dubuque - Engineering Division
Council Final Payment Form
PARTIAL PAYMENT NO: COUNCIL FINAL
PROJECT NAME: SEP Green Alley between White & Jackson from 9th to 10th
CONTRACTOR: Portzen Construction
BID ITEM DESCRIPTION
UNIT
Masterpiece on the Mississippi
DATE: December 14, 2011
CONTRACT AMOUNT: $107,082.15
CONTRACT
UNIT COST
QUANTITY
TO DATE
AMOUNT EARNED
TO DATE
2 EXCAVATION, CL 10, RDWY +BORROW (INCLUDES WATE CY $12.00 393.00 $ 4,716.00
3 TOPSOIL, FURN +SPREAD CY $35.00 $ -
6 GRANULAR SUBBASE TON $15.00 28.22 $ 423.30
13 HMA COMMERCIAL MIX (INCL ASPH BINDER) TON $95.23 $ -
21 GRANULAR BACKFILL TON $5.00 502.94 $ 2,514.70
33 SUBDRAIN, STD. PERFORATED, 6" LF $7.00 270.00 $ 1,890.00
43 RMVL PAV'T SY $7.00 640.38 $ 4,482.66
44 RMVL OF INTAKE = UTILITY ACCESS EACH $347.75 1.00 $ 347.75
48 SIDEWALK, PCC, 5" SY $47.96 100.00 $ 4,796.00
CONCRETE COLLAR SY $60.00 169.16 $ 10,149.60
71 PIPE LINING, RESIN, CURED IN PLACE, LE 36" LF $64.20 322.60 $ 20,710.92
74 WATERMAIN, TRENCHED, DIP, 6" LF $56.01 29.42 $ 1,647.81
75 WATERMAIN, TRENCHED, DIP, 8" LF $49.86 259.51 $ 12,939.17
85 FITTING BY COUNT, DI, TEE 8 X 6 EACH $620.60 3.00 $ 1,861.80
94 FITTING BY COUNT, DI, 45 DEGREE BEND, 8 IN EACH $739.37 2.00 $ 1,478.74
106 VALVE, GATE, DIP, 6" EACH $1,129.92 3.00 $ 3,389.76
115 WATER SERVICE CONNECTION, 3/4 IN EACH $400.00 4.00 $ 1,600.00
117 WATER SERVICE CONNECTION, 2 IN EACH $1,200.00 3.00 $ 3,600.00
122 CONNECTION TO EXISTING WATER MAIN, 6 IN EACH $390.55 1.00 $ 390.55
123 CONNECTION TO EXISTING WATER MAIN, 8 IN EACH $498.62 2.00 $ 997.24
140 STORM SERVICE, 6" EACH $481.50 2.00 $ 963.00
145 WATER SERVICE, 3/4 IN LF $29.40 47.00 $ 1,381.80
147 WATER SERVICE, 2 IN LF $45.40 24.20 $ 1,098.68
155 INSULATION BOARD, 2 INCH SF $2.14 $ -
162 BRICK PAVERS, TYPE 4 - HERRINGBONE PATTERN SF $5.03 3341.00 $ 16,805.23
168 BEDDING & VIOD AGGREGATES(ASTM #8 WASHED STO TON $19.26 36.74 $ 707.61
169 POROUS AGGREGATE (ASTM #57 WASHED STONE) TON $19.00 166.50 $ 3,163.50
170 POROUS AGGREGATE (ASTM #2 WASHED STONE) TON $35.00 232.68 $ 8,143.80
SUB -TOTAL EARNED TO DATE:
$ 110,199.63
6" 45 Deg Bend EACH $588.50 2.00 $ 1,177.00
6" DIP Cap EACH $190.00 3.00 $ 570.00
Connect to Existing 8" Sanitary Sewer EACH $978.00 1.00 $ 978.00
Watermain Parts Increase from original bid LS $2,089.21 1.00 $ 2,089.21
Inrill of Window Wells LS $6,355.70 1.00 $ 6,355.70
Waterproofing near John While Building LS $512.00 1.00 $ 512.00
Foam Waterproofing Sealing (use same material as used on LS $2,415.00 1.00 $ 2,415.00
6" Fitting By Count, DI,22.5 Degree EACH $588.50 2.00 $ 1,177.00
8" PVC Pipe for connecting Sanitary Sewer in Abandon Manh LS $1,682.45 1.00 $ 1,682.45
SUB -TOTAL EARNED TO DATE:
TOTAL AMOUNT EARNED TO DATE:
TOTAL DUE CONTRACTOR:
ENGINEERING:
TOTAL CONSTRUCTION COST:
$ 16,956.36
$ 127,155.99
$ 127,155.99
$ 1,523.63
$ 128,679.62
CERTIFICATE OF THE CITY MANAGER:
I hereby certify that the above statement shows in detail the correct amount of all work required to
APPROVED:
APPROVED:
c• +fete the above improvement.
Michael Van Mill'. a City Manage
City of D wa /
Gus Psihoyos, City Engineer
City of Dubuque, Iowa
CERTIFICATE OF THE CONTRACTOR
he undersigned, Portzen Construction, Inc.
contractor for the above improvement, does
hereby accept the above 'Tot Due Contractor", as full settlement for all claims for said improvement.
CONTRACTOR:
BY:
TITLE: President
DATE: 14 -Dec -11