Loading...
Sewershed 11 Corrective Action PlanMasterpiece on the Mississippi TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager SUBJECT: Sewershed 11 Corrective Action Plan DATE: December 12, 2011 Dubuque knerd All-America City hill! 2007 The Sewershed 11 Corrective Action Plan (Plan) proposes corrective actions for the sources of inflow and infiltration (I &I) identified by the City of Dubuque during 2011. I &I sources include but are not limited to sump pumps, driveway drains, brick manholes, and sanitary sewer pipes. The Plan identifies how, when and who is to complete the corrective actions. For example, the City corrective actions include manhole and sanitary sewer improvements and replacement. Private property corrective actions include fixing improperly connected sump pumps, sanitary sewer laterals, and driveway drains. The City of Dubuque, Iowa is under a Consent Decree with the U.S. Environmental Protection Agency effective June 27, 2011. The purpose of this report is to satisfy the Consent Decree, which requires the City to submit a corrective action plan for Sewershed 11 by December 31, 2011 and the other four sewersheds over the next four years. The City's goal is to eliminate and reduce I &I sources before June 30, 2016. The City must demonstrate to the US EPA and Iowa DNR that no sanitary sewer overflows or bypasses occur between July 1, 2016 through June 30, 2017. City inspectors conducted approximately 1,233 private property inspections to identify the roof drain discharge location, the presence of any stairwell or driveway drains, and the presence of a sump pit /pump on site. A failed inspection indicated an improper connection of clear water into the sanitary system. There were 79 properties that needed to take corrective action. Each improper connection observed resulted in a failure notice. The property owner then had 30 days to correct the improper connection, at which point a re- inspection of the property was conducted to verify that the improper connection was eliminated. If the improper connection was not corrected, City inspectors reminded the property owner of the required work; requested a timeline to correct the improper connection; and offered suggestions on how to efficiently and economically correct the connection. If a property owner chooses not to correct an improper connection, the City may pursue legal action against the property owner. The City conducted smoke testing in Sewershed 11 to identify improper clear water connections to the sanitary system and possible cracks, leaks or breaks in a property owner's sanitary lateral. Fifty -three defects were identified by using smoke testing. Sanitary sewer manholes within Sewershed 11 were opened and recorded as concrete or brick. Brick manholes are of the greater I &I concern because they are typically older and deteriorated mortar can be a significant source of infiltration. Of the 278 manholes in Sewershed 11, one hundred and twenty -one are brick. City staff established an asset management system to prioritize the condition and criticality of sanitary sewer pipes. Approximately 1.5 miles of sanitary sewer has subsequently been identified for improvement or replacement. City staff conducted detailed I &I investigations at four large campuses within Sewershed 11: Senior High School, Clarke University, Loras College, Nativity Church and School, and St. Anthony's Church and School. City staff met with campus staff, reviewed utility plans, and conducted dye and smoke testing on each campus. In the end, Senior High School, Clarke University, and St. Anthony's Church and School campuses were found to have improper connections. The Dubuque Community School District responded immediately and is still in the process of addressing improper connections at Senior High School. The improper connection at Clarke University was located in the fall by smoke testing. Since the testing occurred in the fall, the university will be notified and asked to correct the improper connection in early 2012. The St. Anthony Church and School improper connections have been corrected. At this time, the 5 -year CIP Budget appears sufficient to fund the $800,000 in corrective actions identified in the Plan. City Engineer Gus Psihoyos recommends submittal of the Sewershed 11 Corrective Action Plan to the agencies stated in the Consent Decree. I concur with the recommendation and respectfully request Mayor and City Council approval. MCVM:jh Attachment Michael C. Van Milligen 2 cc: Barry Lindahl, City Attorney Cindy Steinhauser, Assistant City Manager Gus Psihoyos, City Engineer 3 THE CITY OF Dui Masterpiece on the Mississippi TO Michael C Van Milligen, City Manager FROM Gus Psihoyos, City Engineer DATE December8,2011 SUBJECT Sewershed 11 Corrective Action Plan Dubuque had All-America City 'I 1 1 I' 2007 INTROD UCTION The Sewerthed 11 Corrective Action Alan (Plan) proposes corrective actions for the sources of inflow and infiltration (I&I) identified by the City of Dubuque during 2011 I &I sources include but are not Invited to sump pumps, driveway drains, brick manholes, and sanitary sewer pipes The Plan identifies how, when and who is to complete the corrective actions For example, the City corrective actions include manhole and sanitary sewer improvements and replacement Prwate property corrective actions include fixing improperly connected sump pumps, sanitary sewer laterals, and driveway drains BACKGROUND The City of Dubuque, Iowa is under a Consent Decree according to Case 2 11 -cv- 01001 -EJM, United States of America and the State of Iowa v the City of Dubuque, IA (N D Iowa), Civil Action Number2008V00041, DOJ Case Number 90- 5 -1 -1- 09339 effectwe June 27, 2011 The purpose of this report is to satisfy Section V, Paragraph 12 of the Consent Decree, which requires the City to submit a corrective action plan for Sewershed 11 by December 31, 2011 Sewershed 11 is the first of five sewersheds identified as receiving elevated flows during and directly after a precipitation event in the 2009 Sanitary Sewer Master Alan Under the Consent Decree, the City has agreed to investigate these five sewersheds Similar correctwe action plans will be drafted and submitted to the US EPA and Iowa DNR over the next four years The City's goal is to eliminate and reduce I&I sources before June 30, 2016 The City must demonstrate to the US EPA and Iowa DNR that no sanitary sewer overflows or bypasses occur between July 1, 2016 through June 30, 2017 DISCUSSION The City employed numerous methods to investigate sources of I &I in 2011 prwate property inspections, smoke testing the sanitary sewer collection system, brick manhole identification, sanitary sewer pipe prioritization, and "campus" inspections Corrective actions specific to each investigation method are listed in the Plan City inspectors conducted approximately 1,233 private property inspections to identify the roof drain discharge location, the presence of any stairwell or driveway drains, and the presence of a sump pit/pump on site Apassing inspection indicated no connections of clear water to the sanitary system A failed inspection indicated an improper connection of clear water into the sanitary system, which could include roof drains connected to the sanitary sewer, a stairwell or driveway drain which is connected to the sanitary sewer, or a sump pump or floor drain plumbed directly to the sanitary sewer Each improper connection observed resulted in a failure notice The property owner then had 30 days to correct the improper connection, at which point a re- inspection of the property was conducted to verify that the improper connection was eliminated If the improper connection was not corrected, City inspectors reminded the property owner of the required work, requested a timeline to correct the improper connection, and offered suggestions on how to efficiently and economically correct the connection If a property owner chooses not to correct an improper connection, the City may pursue legal action against the property owner The City conducted smoke testing in Sewershed 11 to identify improper clear water connections to the sanitary system and possible cracks, leaks or breaks in a property owner's sanitary lateral Fifty -three defects were identified by using smoke testing City staff has classified the results into three categories private repairs, sanitary sewer repairs, and storm sewer repairs Sanitary sewer manholes within Sewershed 11 were opened and recorded as concrete or brick Brick manholes are of the greater I &I concern because they are typically older and deteriorated mortar can be a significant source of infiltration Of the 278 manholes in Sewershed 11, one hundred and twenty -one are brick City staff established an asset management system to prioritize the condition and criticality of sanitary sewer pipes Approximately 1 5 miles of sanitary sewer has subsequently been identified for improvement or replacement City staff conducted detailed I &I investigations at four large campuses within Sewershed 11 Senior High School, Clarke University, Loras College, Nativity Church and School, and St Anthony's Church and School City staff met with campus staff, reviewed utility plans, and conducted dye and smoke testing on each campus In the end, Senior High School, Clarke University, and St Anthony's Church and School campuses were found to have improper connections The Dubuque Community School District responded immediately and is still in the process of addressing improper connections at Senior High School The improper connection at Clarke University was located in the fall by smoke testing Since the testing occurred in the fall, the university will be notified and asked to correct the improper connection in early 2012 The St Anthony Church and School improper connections have been corrected RECOMMENDATION I recommend certification of the Sewershed 11 Corrective Action Plan by the City Manager PROJECT COST - BUDGET IMPACT The corrective actions identified in the Plan amount to approximately $800,000 of repairs or improvements to the City's sanitary sewer collection system This amount does not include any expenses necessary to repair private sump pumps, driveway drains, or sanitary sewer laterals At this time, the 5 -year CIP Budget appears sufficient to fund the corrective actions identified in the Plan However, further investigation and future I &I- related priorities in the other four sewersheds may require the City to add, adjust or remove corrective actions from this Plan ACTION TO BE TAKEN I request authorization for the Engineering Department to submit the Sewershed 11 Corrective Action Plan to the agencies stated in the Consent Decree Prepared by Todd Shoemaker, P E , Environmental Engineer Masterpiece on the Mississippi December 8, 2011 City Hall 50 W. 13th Street Dubuque, Iowa 52001 563.589.4110 563.589.0890 (fax) www.cityofdubuque.org Individuals Listed in Section XVII (Notices) of the Consent Decree: Enclosed is the City of Dubuque Sewershed 11 Corrective Action Plan as required by Case 2:11 -cv- 01001 -EJM, United States of America and the State of Iowa v. the City of Dubuque, IA (N.D. Iowa), Civil Action Number 2008V00041, DOJ Case Number 90 -5 -1 -1 -09339 effective June 27, 2011. Please contact me if additional information is required. Sincerely, Michael C. Van Milligen City Manager Prepared for: UNITED STATES ENVIRONMENTAL PROTECTION AGENCY, UNITED STATES DEPARTMENT OF JUSTICE AND IOWA DEPARTMENT OF NATURAL RESOURCES Prepared by: CITY OF DUBUQUE, IA 50 W 13th Street Dubuque, IA 52001 Sewershed 11 Corrective Action Plan Consent Decree No. 2: 11 -cv -Q 1Q 11 -EJ M December 8, 2011 Table of Contents 1.0 CERTIFICATION 1 -1 2.0 INTRODUCTION 2 -1 2.1 Background 2 -1 2.2 Purpose 2 -1 2.3 Corrective Actions 2 -1 3.0 PRIVATE PROPERTY INSPECTIONS 3 -1 3.1 Inspections 3 -1 3.2 Corrective Actions 3 -1 4.0 SMOKE TESTING 4 -1 4.1 Investigation 4 -1 4.2 Corrective Actions 4 -1 4.2.1 Private Actions 4 -1 4.2.2 Sanitary Sewer Improvements 4 -1 4.2.3 Storm Sewer Improvements 4 -2 5.0 BRICK MANHOLES 5 -1 5.1 Investigation 5 -1 5.2 Corrective Actions 5 -1 6.0 SANITARY SEWER PRIORITY GRADING SYSTEM 6 -1 6.1 Criticality Grade 6 -1 6.2 Condition Grade 6 -3 6.3 Priority Grade 6 -3 6.4 Corrective Actions 6 -4 7.0 CAMPUS INVESTIGATIONS 7 -1 7.1 Sewershed 11 Campuses 7 -1 7.2 Corrective Actions 7 -1 7.2.1 Clarke University 7 -1 7.2.2 St. Anthony's Church and School 7 -1 7.2.3 Senior High School 7 -1 i 8.0 PLAN SUMMARY 8 -1 8.1 Funding 8 -1 8.2 Corrective Action Summary 8 -1 TABLES Table 3 -1. Failed private property inspections. 3 -2 Table 4 -1. Private property defects identified by smoke testing. 4 -2 Table 4 -2. Sanitary sewer defects identified by smoke testing. 4 -3 Table 4 -3. Storm sewer defects identified by smoke testing. 4 -3 Table 5 -1. Brick manholes identified for improvement or replacement 5 -2 Table 6 -1. Weighted percent values for the Probability of Failure factors. 6 -2 Table 6 -2. Weighted percent values for the Consequence of Failure factors 6 -2 Table 6 -3. Guidelines for condition assessment and rehabilitation for Sewershed 11 6 -4 Table 6 -4. Grade 4 pipes identified for improvement or replacement. 6 -6 Table 6 -5. Grade 5 pipes identified for improvement or replacement. 6 -6 Table 8 -1. Summary of corrective actions for Sewershed 11 8 -2 FIGURES Figure 2 -1. Map of priority sewersheds for I &I investigation 2 -2 Figure 6 -1. Criticality Grade Color Matrix 6 -3 Figure 6 -2. Priority grade color matrix 6 -4 Figure 6 -3. Priority grades and brick manholes. 6 -5 APPENDICES Appendix A. Inflow & Infiltration Program Financial Assistance Application Appendix B. City letter to Dubuque Community School District regarding Senior High School Appendix C. Response from Dubuque Community School District Appendix D. December letter to Dubuque Community School District ii 1.0 Certification I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gather and evaluate the information submitted. Based on my directions and my inquiry of the person or person who manage the system, or those persons directly responsible for gathering the information, the information submitted is, to the best of my knowledge and belief, true, accurate, and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violations. Michael C. Van Milligen City Manager 2.0 Introduction 2.1 BACKGROUND The City of Dubuque, Iowa is under a Consent Decree according to Case 2 :11 -cv- 01001 -EJM, United States of America and the State of Iowa v. the City of Dubuque, IA (N.D. Iowa), Civil Action Number 2008V00041, DOJ Case Number 90 -5 -1 -1 -09339 effective June 27, 2011. 2.2 PURPOSE The purpose of this report is to satisfy Section V, Paragraph 12 of the Consent Decree. Paragraph 12 requires the City to submit a corrective action plan for Sewershed 11 by December 31, 2011. Prior to June 27, 2011, the City experienced several discharges of untreated or partially treated wastewater. These events were caused by sharp increases in flow within the sanitary sewer system during and immediately after a rainstorm. To better locate the sources of this issue, the City placed flow meters throughout the city. Depending on location, the meters measured the flow of water from each sewershed over a one to eleven month period of time. Five of the twelve sewersheds were identified as receiving elevated flows during and directly after a precipitation event. Under the Consent Decree, the City has agreed to investigate five sewersheds over the next five years (Figure 2 -1). 2.3 CORRECTIVE ACTIONS The City employed numerous methods to investigate sources of I &I: private property inspections; smoke testing the sanitary sewer collection system; brick manhole identification; sanitary sewer pipe prioritization; and "campus" inspections. Corrective actions specific to each investigation method are provided in subsequent sections of this plan. Inflow & Infiltration Progra Sanitary Sewersheds To Be Inspected DLeN.pmrm ux Nissis, , RD DE o Y GRANGE OLYMPIC We" W 32ND 51 BERY.Lt.'PL RRRO NAVE RkI1 rsI LOW£LL DAGIS Figure 2 -1. Map of priority sewersheds for I &I investigation. 2 -2 3.0 Private Property Inspections 3.1 INSPECTIONS City inspectors conducted 1,233 private property inspections to identify the roof drain discharge location, the presence of any stairwell or driveway drains, and the presence of a sump pit /pump on site. A passing inspection indicated no connections of clear water to the sanitary system. A failed inspection indicated an improper connection of clear water into the sanitary system, which could include roof drains connected to the sanitary sewer; a stairwell or driveway drain which is connected to the sanitary sewer; or a sump pump or floor drain plumbed directly to the sanitary sewer. 3.2 CORRECTIVE ACTIONS Each improper connection observed during a private property inspection resulted in a failure notice. The property owner then had 30 days to correct the improper connection, at which point a re- inspection of the property was conducted to verify that the improper connection was eliminated. If the improper connection was not corrected, City inspectors reminded the property owner of the required work; requested a timeline to correct the improper connection; and offered suggestions on how to efficiently and economically correct the connection. If a property owner chooses not to correct an improper connection, the City may pursue legal action against the property owner. The 79 failed private property inspections are listed in Table 3 -1. (More than half have been corrected.) Some improper connections, such as driveway drains, can require complex and costly corrections for property owners. To better understand the cost to property owners, the City obtained three estimates ranging from $4,800 to $6,500 to correct improper driveway drain connections. The City is sensitive to the economic hardship these corrections may cause and the need to eliminate these significant connections to the sanitary sewer. Therefore, a cost -share program has been established for the City to partner with property owners. The application form is provided in Appendix A. City staff will continue using the cost -share program to balance property owner costs and Consent Decree requirements. (The City retains the right to rescind cost -share program at any time for good cause including funding availability.) The City has notified property owners of improper connections by mail, and City staff will continue to work with property owners to address the improper connections by June 30, 2016. Table 3 -1. Failed private property inspections. GIS ID House Number Street Defect Corrective Action Completed? 353620 1350 Nowata St Exterior dram to sanitary sewer Constructed enclosure around stairway Ves 335523 1775 Alta PI Exterior dram to sanitary sewer Constructed enclosure around stairway Ves 358381 2010 Alta Vista St Roof dram to sanitary sewer Disconnected from sanitary sewer Ves 340790 975 W Locust St Sump pump discharges to sanitary sewer New sump pit installed to separate storm and sanitary Ves 335405 2340 Green St Sump pump discharges to sanitary sewer New sump pit installed to separate storm and sanitary Ves 335404 2360 Green St Sump pump discharges to sanitary sewer New sump pit installed to separate storm and sanitary Ves 353600 1340 Auburn St Sump pit without PUMP Pump installed in sump pit and plumbed properly Ves 332904 1365 Loras Blvd Sump pit without pump Pump installed in sump pit and plumbed properly Ves 324692 1919 Asbury Rd Sump pit without pump Pump installed in sump pit and plumbed properly Ves 321778 1511 Adair St Roof dram to sanitary sewer Roof dram disconnected from sanitary sewer Ves 332994 1596 Wood St Roof dram to sanitary sewer Roof drain disconnected from sanitary sewer Ves 320500 1970 St Ambrose St Roof dram to sanitary sewer Roof drain disconnected from sanitary sewer Ves 357918 1340 Wood St Sump pump discharges to sanitary sewer Sump pit disconnected from sanitary sewer Ves 353597 1451 Atlantic St Sump pump discharges to sanitary sewer Sump pit disconnected from sanitary sewer Ves 356767 1670 N Grandview Ave Sump pump discharges to sanitary sewer Sump pit disconnected from sanitary sewer Ves 335505 1845 Atlantic St Sump pump discharges to sanitary sewer Sump pit disconnected from sanitary sewer Ves 331782 1885 Wood St Sump pump discharges to sanitary sewer Sump pit disconnected from sanitary sewer Ves 341949 2396 University Ave Sump pump discharges to sanitary sewer Sump pit disconnected from sanitary sewer Ves 340944 770 Angella St Sump pump discharges through flexible hose Sump pump discharges through rigid pipe Ves 359395 995 Kirkwood Ave Sump pump discharges through flexible hose Sump pump discharges through rigid pipe Ves 318957 1050 Loras Blvd Sump pump discharges through flexible hose Sump pump discharges through rigid pipe Ves 335432 1085 Wood St Sump pump discharges through flexible hose Sump pump discharges through rigid pipe Ves 359325 1111 Rosedale Ave Sump pump discharges through flexible hose Sump pump discharges through rigid pipe Ves 332384 1205 N Booth St Sump pump discharges through flexible hose Sump pump discharges through rigid pipe Ves 357923 1212 Wood St Sump pump discharges through flexible hose Sump pump discharges through rigid pipe Ves 356793 1458 Mt Pleasant St Sump pump discharges through flexible hose Sump pump discharges through rigid pipe Ves 356903 1480 Glen Oak St Sump pump discharges through flexible hose Sump pump discharges through rigid pipe Ves 342248 1490 N Grandview Ave Sump pump discharges through flexible hose Sump pump discharges through rigid pipe Ves 343593 1590 Ashton PI Sump pump discharges through flexible hose Sump pump discharges through rigid pipe Ves 356659 1610 Ashton PI Sump pump discharges through flexible hose Sump pump discharges through rigid pipe Ves 332653 1645 Atlantic St Sump pump discharges through flexible hose Sump pump discharges through rigid pipe Ves 333159 1665 Asbury Rd Sump pump discharges through flexible hose Sump pump discharges through rigid pipe Ves 353591 1693 Loras Blvd Sump pump discharges through flexible hose Sump pump discharges through rigid pipe Ves 333157 1695 Asbury Rd Sump pump discharges through flexible hose Sump pump discharges through rigid pipe Ves 339756 1715 Asbury Rd Sump pump discharges through flexible hose Sump pump discharges through rigid pipe Ves 339763 1726 Asbury Rd Sump pump discharges through flexible hose Sump pump discharges through rigid pipe Ves 335515 1730 Avoca St Sump pump discharges through flexible hose Sump pump discharges through rigid pipe Ves 331788 1755 Wood St Sump pump discharges through flexible hose Sump pump discharges through rigid pipe Ves 315480 1900 Lawndale St Sump pump discharges through flexible hose Sump pump discharges through rigid pipe Ves 331765 1910 Adair St Sump pump discharges through flexible hose Sump pump discharges through rigid pipe Ves 320494 1845 Asbury Rd Sump pump discharges through flexible hose Sump pump discharges through rigid pipe Ves 324699 1950 Asbury Rd Sump pump discharges through flexible hose Sump pump discharges through rigid pipe Ves 324696 1855 Clarke Dr Sump pump discharges through flexible hose Sump pump discharges through rigid pipe Ves 324699 1960 St Ambrose St Sump pump discharges through flexible hose Sump pump discharges through rigid pipe Ves 338791 1921 N Grandview Ave Sump pump discharges through flexible hose Sump pump discharges through rigid pipe Ves 319187 1995 N Grandview Ave Sump pump discharges through flexible hose Sump pump discharges through rigid pipe Ves 319182 2175 Rosedale Ave Sump pump discharges through flexible hose Sump pump discharges through rigid pipe Ves 335394 2215 Green St Sump pump discharges through flexible hose Sump pump discharges through rigid pipe Ves 359305 1049 W Locust St Exterior drain to sanitary sewer Corrective action to be completed by property owner 336599 1065 Auburn St Exterior drain to sanitary sewer Corrective action to be completed by property owner 357922 1222 Wood St Sump pump discharges through flexible hose Corrective action to be completed by property owner 331425 1275 Mt Pleasant St Sump pump discharges to sanitary sewer Corrective action to be completed by property owner 332906 1325 Loras Blvd Sump pump discharges to sanitary sewer Corrective action to be completed by property owner 318969 1339 Alta Vista St Roof dram to sanitary sewer Corrective action to be completed by property owner 353599 1390 Auburn St Exterior drain to sanitary sewer Corrective action to be completed by property owner 353606 1392 Atlantic St Roof dram to sanitary sewer Corrective action to be completed by property owner 331365 1435 Mt Pleasant St Sump pump discharges through flexible hose Corrective action to be completed by property owner 335437 1475 University Ave Exterior drain to sanitary sewer Corrective action to be completed by property owner 335436 1485 University Ave Exterior drain to sanitary sewer Corrective action to be completed by property owner 331362 1491 Mt Pleasant St Sump pump discharges to sanitary sewer Corrective action to be completed by property owner 342277 1529 Mt Pleasant St Roof dram to sanitary sewer, sump pump Corrective action to be completed by property owner 332667 1540 N Algona St Exterior drain to sanitary sewer Corrective action to be completed by property owner 345563 1640 Lawndale St SUMP pump discharges to sanitary sewer Corrective action to be completed by property owner 356655 1660 Ashton PI Sump pit without PUMP Corrective action to be completed by property owner 338781 1671 Avoca St Roof dram to sanitary sewer Corrective action to be completed by property owner 353592 1675 Loras Blvd Sump pump discharges through flexible hose Corrective action to be completed by property owner 356643 1715 Atlantic St Exterior drain to sanitary sewer Corrective action to be completed by property owner 356763 1795 Adair St Exterior drain to sanitary sewer Corrective action to be completed by property owner 343914 1795 Auburn St Roof dram to sanitary sewer Corrective action to be completed by property owner 357992 1815 Loras Blvd Sump pit without PUMP Corrective action to be completed by property owner 325932 1885 St Ambrose St Sump pump discharges through flexible hose Corrective action to be completed by property owner 340697 1911 St Ambrose St Sump pump discharges to sanitary sewer Corrective action to be completed by property owner 340681 1993 St Ambrose St Sump pump discharges to sanitary sewer Corrective action to be completed by property owner 344813 1985 Alta Vista St Roof dram to sanitary sewer Corrective action to be completed by property owner 335529 2025 Delaware St SUMP pump discharges through flexible hose Corrective action to be completed by property owner 319171 2033 Clarke Dr Sump pit without pump Corrective action to be completed by property owner 323944 2215 University Ave Sump pump discharges through flexible hose Corrective action to be completed by property owner 324693 2275 Green St Sump pump discharges through flexible hose Corrective action to be completed by property owner 341948 2396 University Ave Sumo PUMP discharges to sanitary sewer Corrective action to be completed by property owner 3 -2 4.0 Smoke Testing 4.1 INVESTIGATION The City conducted smoke testing in Sewershed 11 to identify improper clear water connections to the sanitary system and possible cracks, leaks or breaks in a property owner's sanitary lateral. Smoke testing has also been used for large commercial or educational buildings where dye testing would not an efficient method of investigation. 4.2 CORRECTIVE ACTIONS Fifty -three defects were identified within Sewershed 11. Photos were taken of each and mapped in the City's GIS. City staff has classified the results into three categories; private repairs; sanitary sewer repairs; and storm sewer repairs. 4.2.1 Private Actions Table 4 -1 lists 27 private property repairs identified by smoke testing and the corrective action required of the property owners by the City. Of the 27 repairs, sixteen are likely related to the sanitary sewer lateral. Identifying the source of I &I in a sanitary sewer lateral can be especially difficult and expensive for an individual property owner. Therefore, City staff has requested a new Capital Improvement Project (CIP) for Fiscal Year 2013 (July 2012 — June 2013) to televise private laterals. If this CIP is approved, the sixteen laterals will be televised to provide the property owner with more definitive information on how to repair the improper connection. If it is not approved, the City will require the property owners to investigate at their cost. According to State Law, the City Council must adopt and certify the budget by March 15, 2013. The City will consider the private repairs listed in Table 4 -1 similar to the failed private property inspections — property owners will be notified by letter in 2012, asked to correct the connection, and City staff will continue to work with property owners to address the improper connections by June 30, 2016. Reinspections will be conducted to ensure the repair was done correctly. 4.2.2 Sanitary Sewer Improvements Smoke testing revealed 21 defects related to the sanitary sewer collection system. The defects consisted of vented manhole covers, brick manholes, and broken or cracked pipes (Table 4 -2). The vented manhole covers will be replaced by the City. As will be discussed in Section 5.2, the brick manholes will be improved or replaced. The pipes will be improved or replaced as will be discussed in Section 6.4. The sanitary sewer improvements identified by smoke testing will cost the City approximately $34,000. 4 -1 4.2.3 Storm Sewer Improvements Smoke was observed from five storm sewer catchbasins during smoke testing (Table 4 -3). City staff investigated each of these immediately, but no direct "cross- connections" to the sanitary sewer were found. Two of the five smoking catchbasins may be due to a nearby sanitary sewer lateral; as discussed above in Section 4.2.1, the City will televise these sanitary laterals if the CIP is approved. The City will further investigate the other three smoking catchbasins in 2012. Public Works staff will flood the storm sewer with dyed water while simultaneously televising the sanitary sewer to locate any possible cross - connections. The storm sewer improvements identified by smoke testing will cost the City approximately $15,000. Table 4 -1. Private property defects identified by smoke testing. G15 ID House Number Street Defect Corrective Action Completed> NA 1744 NGianMiem Ave Smoke fr om Niater Access Televise lateral notify property owner of any necessary epair NA 1669 Adair St Smokefr om Behind Curb Televise lateral notify property owner of any necessary repair NA 1450 Wood St Severed Sanitary 0eanout Property owner repair with water tight seal NA 1951 Lora: Blvd Smoked om ground near gas meter Televise lateral notify property owner of any necessary repair NA 1280 Glen Oak St Smokefr om ground and water access Televise lateral notify property owner of any necessary epair NA X00 55Locust St ;mewalFOmwater vane at corner of Bair: and Televise lateral tit of notify property owner any necessary repair NA 1537 Irving St Smoke nom boner :nip between sidewalk and back of curb Televise lateral notify property owner of any necessary epair NA 1890 Audubon St Smoke from retammg wall. steps and concrete m front ohouse Televise lateral notify property ownero ran any necessary NA 990 Booth St Smokes om water valve across :neet Televise lateral notify property owner of any necessary repair NA 1871 Glen Oak St Smokefr om driveway Property owner to disconnect driveway dr an NA 1575 Irving St Smokefr ominck: near driveway Televise lateral notify property owner of any necessary epair NA 1671 Avoca St Smokefr om r ear downspout Property owner disconnect ownspout from sanitary sewer NA 1660 Ashton PI Smokefr om :hut -of valve Televise lateral notify property owner of any necessary repair NA 1657 Ashton PI Smokefr om:idwalk/valve Televise lateral notify property owner of any necessary repair NA 1905 Lora: Blvd Smokes om rear door Televise lateral notify property owner of any necessary repair NA 1065 Auburn St Smokefr om crack near driveway Property owner to disconnect driveway dr an NA 1339 Mt Pleasant St Smokefr om valve Property owner to install water tight cap NA 730 Kirkwood St Smoket om ground behind curb Televise lateral notify property owner of any necessary repair NA 1985 Clarke Dr Smokefr om hole ingr ound by down spout Property owner disconnect downspout from sanitary sewer NA 1550 Clarke Dr Smoke fr om hole in gr ound Property owner to install water tight cap NA 1570 Mt Pleasant St Smokefr om uneven curb Televise lateral notify property owner of any necessary repair NA 1556 Mt Pleasant St Smokefr om driveway drain Property owner to disconnect driveway drain NA 1350 Nowata St Smokes om stairway dram Acton complete awningm4alled to prevent ram from entering dram (es NA 1200 Glen Oak St Smoke by water shut-of Televise lateral notify property owner of any necessary epair NA 615 Angella St Smoke by water shut-off Lateral wastelevised by licensed plumber noconectve act on needed (es NA 1065 Auburn St Smoket om MH /n :tern intontyard Property owner repair NA 1800 Clarke Dr CSHS softball field, Smoket om ground near MH Property owner repair 4 -2 Table 4 -2. Sanitary sewer defects identified by smoke testing. GIS ID House Number Street Defect Corrective Action Completed? SAN P 05590 1302 Atlantic Street Smoke from Ground, longitudinal crack in pipe Improve or replace pipe SAN 505395 1537 Irving St Vented MH Cover Replace cover SAN 505335 NA Irving St &Decorah St Smoke at MH Diamond Improve or replace manhole SAN 505331 NA Loras Blvd & Nowata St Vented MH Cover Replace cover SAN 506343 1419 Loras Blvd Smoke from ground around MH, Vented Cover Improve or replace manhole SAN 505574 1371 Glen Oak St Smoke from ground around MH Improve or replace manhole SAN 505530 NA Woods N of Lawndale St Smoke from ground around MH Improve or replace manhole SAN 505343 NA St Ambrose St & Rosedale Ave Smoke around MH Improve or replace manhole SAN 505409 NA Custer St & Atlantic St Smoke around MH Improve or replace manhole SAN 505394 1324 N Grandview Ave Smoke from MH, driveway and curb Improve or replace manhole SAN 5 05657 NA Martha St and Nevada St Smoke around MH and catch basin at SE Corner of Intersection Improve or replace pipe to northeast (SAN P 05553) SAN 506739 1331 Glen Oak St Manhole in low spot in front yard Improve or replace manhole SAN 505573 1371 Glen Oak St Smokefrom Ground near MH Improve or replace manhole SAN 505436 NA W Locust St & Clarke Dr Smoke from crack in pavement Improve or replace pipe (Grade 4 pipe, SAN P 06063) SAN 504703 1234 Rosedale Ave Smoke from MH in yard Improve or replace manhole SAN 505320 or 05395 2155 University Vented MH Cover Replace cover SAN P 05622 1340 Auburn St Multiple fractures, hole, lateral intruding Improve or replace pipe SAN P05621 1330 Custer St Multiple fractures, hole in pipe Improve or replace pipe SAN P05619 1790 Custer St Multiple fractures, Joint separated, cicumferential crack rep Im prove or lace pipe SAN P05615 1734 Custer St Multiple fractures Improve or replace pipe SAN P05620 NA Custer St Multiple fractures, longitudinal crack, Joint offset prove or rep pipe Improve ace Table 4 -3. Storm sewer defects identified by smoke testing. GIS ID House Number Street Defect Corrective Action Completed? STO 5 04272 1355 Wood St Smoke from catch basin Flood & dye storm sewer, televise sanitary, improve as needed 40504376 995 Nevada St Smoke from catch basin Protruding lateral tap, property owner to repair STO 5 04340 1371 Glen Oak St Smoke from catch basin Possibly lateral from 1325 Glen Oak, property owner to repair STO 5 04231 1795 Adair Smoke from catch basin Flood & dye storm sewer, televise sanitary, improve as needed STO 5 04310 NA Delaware St &Grandview Ave Smoke from catch basin Flood & dye storm sewer, televise sanitary, improve as needed 4 -3 5.0 Brick Manholes 5.1 INVESTIGATION Sanitary sewer manholes within Sewershed 11 were opened and recorded as concrete or brick. Brick manholes are of the greater I &I concern because they are typically older and deteriorated mortar can be a significant source of infiltration. Of the 278 manholes in Sewershed 11, one hundred and twenty -one are brick. 5.2 CORRECTIVE ACTIONS The City will begin improvement or replacement of the 121 brick manholes (Table 5 -1) during 2012 and will continue as needed until June 30, 2016. Sixty -one of the brick manholes are rated in either "poor" or "repair" condition by City staff and will be addressed first. The remaining brick manholes will be improved or repaired in subsequent years based on age (i.e. the older manholes will be replaced first). The expense of improving or replacing all brick manholes listed is approximately $612,000. Table 5 -1. Brick manholes identified for improvement or replacement. GIS ID House Number Street Defect Corrective Action Completed? SAN 504710 1893 Wood St Brick manhole Improve or replace manhole SAN 505394 1321 N Grandview Ave Brick manhole Improve or replace manhole SAN 505580 1800 Lawndale St Brick manhole Improve or replace manhole SAN 505751 1939 Wood St Brick manhole Improve or replace manhole SAN 505610 1675 Glen Oak St Brick manhole Improve or replace manhole SAN 505385 NA Decorah St & Irving St Brick manhole Improve or replace manhole SAN 505344 1911 N Grandview Ave Brick manhole Improve or replace manhole SAN 505601 1700 Glen Oak St Brick manhole Improve or replace manhole SAN 505331 NA Atlantic St & Delaware St Brick manhole Improve or replace manhole SAN 505585 1800 Glen Oak St Brick manhole Improve or replace manhole SAN 505391 1445 Auburn St Brick manhole Improve or replace manhole SAN 505383 NA Fillmore St & Auburn St Brick manhole Improve or replace manhole SAN 505341 1845 Avoca St Brick manhole Improve or replace manhole SAN 505626 1045 Vernon St Brick manhole Improve or replace manhole SAN 505653 1210 Loras Blvd Brick manhole Improve or replace manhole SAN S 05367 NA Decorah St & Auburn St Brick manhole Improve or replace manhole SAN S 05357 NA Delaware St & Auburn St Brick manhole Improve or replace manhole SAN 505392 NA Loras Blvd & Atlantic St Brick manhole Improve or replace manhole SAN 505612 1686 Lawndale St Brick manhole Improve or replace manhole SAN 505379 1633 Avoca St Brick manhole Improve or replace manhole SAN 505730 950 Wood St Brick manhole Improve or replace manhole SAN 505628 1450 Alta Vista St Brick manhole Improve or replace manhole SAN 505598 1760 Lawndale St Brick manhole Improve or replace manhole SAN 505624 1608 Lawndale St Brick manhole Improve or replace manhole SAN S 07329 NA Alley behind 1789 Univ Ave Brick manhole Improve or replace manhole SAN 505605 1040 Edina St Brick manhole Improve or replace manhole SAN 505615 1098 Edina St Brick manhole Improve or replace manhole SAN 504720 NA N Grandview Ave Brick manhole Improve or replace manhole SAN 505574 1871 Glen Oak St Brick manhole Improve or replace manhole SAN 505654 1430 Glen Oak St Brick manhole Improve or replace manhole SAN 506789 1881 Glen Oak St Brick manhole Improve or replace manhole SAN 505405 1302 Atlantic St Brick manhole Improve or replace manhole SAN 505345 1945 N Grandview St Brick manhole Improve or replace manhole SAN 505384 1460 Atlantic St Brick manhole Improve or replace manhole SAN 505368 NA Delaware St & Ashton PI Brick manhole Improve or replace manhole SAN 501947 1795 Asbury Rd Brick manhole Improve or replace manhole SAN S 07012 NA N Booth St & Martha St Brick manhole Improve or replace manhole SAN 506848 1419 Loras Blvd Brick manhole Improve or replace manhole SAN 505458 NA Clarke Dr & N Grandview Ave Brick manhole Improve or replace manhole SAN 505625 1576 Glen Oak St Brick manhole Improve or replace manhole SAN 505752 1086 Wood St Brick manhole Improve or replace manhole SAN 504703 1234 Rosedale Ave (on Glen Oak St) Brick manhole Improve or replace manhole SAN 501939 1881 Asbury Rd Brick manhole Improve or replace manhole SAN 505579 NA Glen Oak St Brick manhole Improve or replace manhole SAN S 05647 NA Mt Pleasant St & Loras Blvd Brick manhole Improve or replace manhole SAN 505731 935 Nevada St Brick manhole Improve or replace manhole SAN 505648 1050 Loras Blvd Brick manhole Improve or replace manhole SAN 505833 1550 University Ave (behind building) Brick manhole Improve or replace manhole SAN 505404 NA Abandoned alley behind 1875 Custer St Brick manhole Improve or replace manhole SAN 505622 1695 Mt Pleasant St Brick manhole Improve or replace manhole SAN 505378 1555 N Algona St Brick manhole Improve or replace manhole SAN 504715 1875 Audobon St Brick manhole Improve or replace manhole SAN 505356 1709 N Algona St Brick manhole Improve or replace manhole SAN 506803 1585 Wood St Brick manhole Improve or replace manhole SAN 505387 NA Fillmore St & Algona St Brick manhole Improve or replace manhole SAN 505355 NA Dexter St (alley E of Algona St) Brick manhole Improve or replace manhole SAN 504721 NA N Grandview Ave & Auburn St Brick manhole Improve or replace manhole SAN 505393 1421 N Algona St Brick manhole Improve or replace manhole 5 -2 Table 5 -1 (continued). Brick manholes identified for improvement or replacement. SAN 505397 NA Alley behind 1334 Atlantic St Brick manhole Improve or replace manhole SAN 506939 1755 Wood St Brick manhole Improve or replace manhole SAN 505366 1650 N Algona St Brick manhole Improve or replace manhole SAN 505350 2135 Green St Brick manhole Improve or replace manhole SAN 505637 1195 Vernon St Brick manhole Improve or replace manhole SAN 505327 2020 Green St Brick manhole Improve or replace manhole SAN 505541 615 Angella St Brick manhole Improve or replace manhole SAN 505544 1819 Pierce St Brick manhole Improve or replace manhole SAN 505536 595 Angella St Brick manhole Improve or replace manhole SAN 505464 1893 Wood St Brick manhole Improve or replace manhole SAN 505549 NA Angella St & Pierce St Brick manhole Improve or replace manhole SAN 505539 1903 Pierce St Brick manhole Improve or replace manhole SAN 505560 NA Loras property near Kirkwood & Blake Sts Brick manhole Improve or replace manhole SAN 505640 NA Vernon St & Glen Oak St Brick manhole Improve or replace manhole SAN 505559 NA Cox St & Angella St Brick manhole Improve or replace manhole SAN 505540 601 Angella St Brick manhole Improve or replace manhole SAN 505642 1265 Vernon St Brick manhole Improve or replace manhole SAN 505411 1790 Custer St Brick manhole Improve or replace manhole SAN 505562 1037 Kirkwood St Brick manhole Improve or replace manhole SAN 505553 NA Kirkwood St Brick manhole Improve or replace manhole SAN 505402 1375 Auburn St Brick manhole Improve or replace manhole SAN 505415 NA Auburn St (alley between Custer & Univ) Brick manhole Improve or replace manhole SAN S 05724 1081 N Booth St Brick manhole Improve or replace manhole SAN 505364 NA Decorah St & Atlantic St Brick manhole Improve or replace manhole SAN 505413 NA Atlantic St (alley between Custer & Univ) Brick manhole Improve or replace manhole SAN 505359 1645 Atlantic St Brick manhole Improve or replace manhole SAN 505543 890 Kirkwood St Brick manhole Improve or replace manhole SAN 505652 1380 N Booth St Brick manhole Improve or replace manhole SAN S 05725 935 N Booth St Brick manhole Improve or replace manhole SAN S 05721 1319 Mt Pleasant St Brick manhole Improve or replace manhole SAN S 05722 1145 Mt Pleasant St Brick manhole Improve or replace manhole SAN 501941 1850 N Grandview Ave Brick manhole Improve or replace manhole SAN 505646 1435 Mt Pleasant St Brick manhole Improve or replace manhole SAN S 05723 940 Mt Pleasant St Brick manhole Improve or replace manhole SAN 506961 1445 Wood St Brick manhole Improve or replace manhole SAN 505335 1775 Wood St Brick manhole Improve or replace manhole SAN S 01782 1715 Asbury Rd Brick manhole Improve or replace manhole SAN 505319 1655 Asbury Rd Brick manhole Improve or replace manhole SAN 505636 1555 Mt Pleasant St Brick manhole Improve or replace manhole SAN 505343 1937 St Ambrose St Brick manhole Improve or replace manhole SAN 505336 1905 Asbury Rd Brick manhole Improve or replace manhole SAN 507363 1925 Pierce St Brick manhole Improve or replace manhole SAN 505320 1535 Irving St Brick manhole Improve or replace manhole SAN 505395 1537 Irving St Brick manhole Improve or replace manhole SAN S 05534 1978 Cox St Brick manhole Improve or replace manhole SAN 507013 1715 Glen Oak St Brick manhole Improve or replace manhole SAN 505732 995 Nevada St Brick manhole Improve or replace manhole SAN S 05412 1060 Auburn St (at Custer St) Brick manhole Improve or replace manhole SAN 505589 1790 Glen Oak St Brick manhole Improve or replace manhole SAN 507328 1760 Custer St Brick manhole Improve or replace manhole SAN 505362 1735 Avoca St Brick manhole Improve or replace manhole SAN 505634 1100 Vernon St Brick manhole Improve or replace manhole SAN 505340 NA Atlantic St & Dexter St Brick manhole Improve or replace manhole SAN 505334 1795 Adair St Brick manhole Improve or replace manhole SAN 505326 1669 Adair St Brick manhole Improve or replace manhole SAN 505372 1475 Adair St Brick manhole Improve or replace manhole SAN 505588 1799 Lawndale St Brick manhole Improve or replace manhole SAN 505421 1420 Loras Blvd Brick manhole Improve or replace manhole SAN 504711 1865 Adair St Brick manhole Improve or replace manhole SAN 505349 1910 Asbury Rd Brick manhole Improve or replace manhole SAN S 05330 NA Algona St & Dexter St Brick manhole Improve or replace manhole SAN S 05374 NA Decorah St & N Algona St Brick manhole Improve or replace manhole SAN 505380 1425 Adair St Brick manhole Improve or replace manhole 5 -3 6.0 Sanitary Sewer Priority Grading System A sanitary sewer priority grading system offers the City a proactive approach to eliminating sanitary sewer overflows (SSOs). The system allows City staff to pinpoint areas within the gravity sanitary sewer pipes that need a more thorough investigation due to the critical nature of the location, physical attributes of a pipe section, the structural integrity of the pipe, and operation and maintenance needs of the pipe. The general formulas in the priority grading system are listed below and explained further in this section: > Priority Grade = Criticality Grade & Condition Grade Where, • Criticality Grade = Probability of Failure & Consequence of Failure and • Condition Grade = Structural Grade & Operations and Maintenance Grade The EPA report "Rehabilitation of Wastewater Collection and Water Distribution Systems" (May 2009) states that the major issues leading to sanitary sewer blockages and overflows include, "cracks, internal corrosion, grease build -up (plus grit and debris), root intrusion, joint misalignment separation and leakage, excessive pipe deflection, lateral connection /leakage, grade and alignment." Establishing priority grades ensures that the City's resources are being used to maintain and/or rehabilitate the more critical areas within the system first and allow time to develop a schedule to investigate the less critical areas at a later date. 6.1 CRITICALITY GRADE The criticality grade is split into two categories: "Probability of Failure" and "Consequence of Failure." Specific analysis is performed on each category before they are combined into the criticality grade. Eleven factors are divided among the Probability and Consequence categories: 1. Material 2. Age 3. Pipe slope 4. Maintenance 5. Proximity of the pipe to a recorded SSO 6. Pre - defined road capacity levels 7. Priority locations within the City 8. Proximity of the pipe to rivers and water bodies 9. Proximity of the pipe to railroad tracks 6 -1 10. Pipe diameter 11. Pipe is located under a building. Probability of failure factors focus on the physical condition of the pipe while consequence of failure factors focus on the impact a pipe failure will have on the surrounding area. The probability of failure and consequence of failure grades were determined using a weighted percent of the factor grades. The weighted percent allows the City to determine the emphasis placed on each criticality factor. By separating the factors into two categories (Table 6 -1 and Table 6 -2), the weighted percent has a greater effect than if the factors were combined. Table 6 -1. Weighted percent values for the Probability of Failure factors. Probability of Failure Criticality Factor Weighted Percentage Material 25 Age 26 Slope 10 Maintenance 20 Proximity to SSO 19 Sum 100 Table 6 -2. Weighted percent values for the Consequence of Failure factors. Consequence of Failure Criticality Factor Weighted Percentage Road Capacity Levels 18 Priority Location 16 Proximity to Water 15 Proximity to Railroad 10 Diameter 22 Pipe Under Building 19 Sum 100 City staff developed a color matrix to determine an overall criticality grade (Figure 6 -1) for each pipe. The color matrix is based off of the color matrix from the Pierce County, Washington Sewer Utility Asset Management Implementation Criticality Model. Each pipe was assigned a grade for the eleven factors mentioned above ranging from 0 to 10 — the higher the grade, the more critical the pipe is to the system. Probability of failure was assigned a greater emphasis because the City wants to locate pipes with the greatest risk of failure due to the pipe's physical features. The grades associated with the color matrix are as follows: Red = 5 Orange = 4 Yellow = 3 Blue = 2 Green = 1. 6 -2 Figure 6-1 Cobra Iity g ra de color neat nx 62 CONDITIONGRADE The condition grade of a pipe is determined using structural and operation and maintenance (O &M) grades acquired by dosed circuit television (CCTV) evaluation of the pipe As a pipe is televised, Gty staff uses the National Assoaation of Sewer Service Companies (NASSCO) Pipeline Assessment and Certification Program (PACP) to code the pipe Any structural and O &M deficienaes in the pipe are noted by certified PACP operators Since 2010, the condition coding for any pipe recorded by CCTV is automatically done by PipeTech° software which uses the PACP condition grading system matrix Any video completed prior to 2010 was coded manually using the PACP condition grading matrix The PACP grading system code matrix can be found in the NASSCO PACP manual and ranges from 0 to 5 A grade of 0 means there is no structural or O &M deficiency noted for the pipe The condition grade is the maximum of the structural and O &M grades assigned to the pipe 6 3 PRIORITY GRADE The priority grade is the final grade for the pipe and determines the order in which the pipes should be investigated further These investigations include but are not limited to further observation of the pipe, repairs, or replacement The priority grade is dependent on both the condition grade and the criticality grade The condition grade has been assigned greater emphasis than the criticality grade because the condition of the pipe provides more information on if the pipe is likely to fail due to structural issues The pipe priority grade follows the recommendation in "Guidelines for Condition Assessment and Rehabilitation of Large Sewers" paper published in 2001 by the National Research Counal of Canada and is shown in a color matrix (Figure 6 -2) The colors in the color matrix indicate rehabilitation priority 6-3 Probability of Failure Grade 10 Increasing Risk (or pnority) _ 9 8 7 6 S 4 3 2 1 1 2 3 4 5 6 7 8 9 10 Consequence of Failure Grade Figure 6-1 Cobra Iity g ra de color neat nx 62 CONDITIONGRADE The condition grade of a pipe is determined using structural and operation and maintenance (O &M) grades acquired by dosed circuit television (CCTV) evaluation of the pipe As a pipe is televised, Gty staff uses the National Assoaation of Sewer Service Companies (NASSCO) Pipeline Assessment and Certification Program (PACP) to code the pipe Any structural and O &M deficienaes in the pipe are noted by certified PACP operators Since 2010, the condition coding for any pipe recorded by CCTV is automatically done by PipeTech° software which uses the PACP condition grading system matrix Any video completed prior to 2010 was coded manually using the PACP condition grading matrix The PACP grading system code matrix can be found in the NASSCO PACP manual and ranges from 0 to 5 A grade of 0 means there is no structural or O &M deficiency noted for the pipe The condition grade is the maximum of the structural and O &M grades assigned to the pipe 6 3 PRIORITY GRADE The priority grade is the final grade for the pipe and determines the order in which the pipes should be investigated further These investigations include but are not limited to further observation of the pipe, repairs, or replacement The priority grade is dependent on both the condition grade and the criticality grade The condition grade has been assigned greater emphasis than the criticality grade because the condition of the pipe provides more information on if the pipe is likely to fail due to structural issues The pipe priority grade follows the recommendation in "Guidelines for Condition Assessment and Rehabilitation of Large Sewers" paper published in 2001 by the National Research Counal of Canada and is shown in a color matrix (Figure 6 -2) The colors in the color matrix indicate rehabilitation priority 6-3 Red = Immediate Orange = High Yellow = Medium Blue = Low Green = Not Required CONDITION GRADE CRITICALITY GRADE Figure 6 -2 Pnonty grade color matrix Figure 6 -3 shows Sewershed 11 with manhole types and the priority grades identified 6.4 CORRECTIVE ACTIONS The City will improve or replace pipes with priority grades of four and five This follows the recommendation set forth by the National Research Council of Canada in "Guidelines for Condition Assessment and Rehabilitation of Large Sewers" (2001, Table 6 -3) Eleven of the 28 priority grade four pipes are ranked as such due to pipe sags or bends Since these conditions do not necessarily cause I &I, these pipes are excluded from Table 6 -4 as City staff investigates if these pipes warrant improvement or replacement Table6 -3 Gwdebnesfor condrtion assessment and rein bdrtation for Sewershed 11 Rehabilitation and Maintenance Decisions 5 Condition Criticality Count Implication Rehab Priority 4 1 0 or 1 5 Cr Good or Excellent Condition 3 10 1 1-4 141 Not Required 2 2 2 5 D Fair Condtion, Minimal Structural Risk 1 5 2 1-4 57 Low 0 3 3 5 0 Poor Condition, Moderate Risk 1 2 3 4 5 CRITICALITY GRADE Figure 6 -2 Pnonty grade color matrix Figure 6 -3 shows Sewershed 11 with manhole types and the priority grades identified 6.4 CORRECTIVE ACTIONS The City will improve or replace pipes with priority grades of four and five This follows the recommendation set forth by the National Research Council of Canada in "Guidelines for Condition Assessment and Rehabilitation of Large Sewers" (2001, Table 6 -3) Eleven of the 28 priority grade four pipes are ranked as such due to pipe sags or bends Since these conditions do not necessarily cause I &I, these pipes are excluded from Table 6 -4 as City staff investigates if these pipes warrant improvement or replacement Table6 -3 Gwdebnesfor condrtion assessment and rein bdrtation for Sewershed 11 Rehabilitation and Maintenance Decisions Final Grade Condition Criticality Count Implication Rehab Priority Time of Next Inspection (yr) 1 0 or 1 5 Cr Good or Excellent Condition Not Required 10 1 1-4 141 Not Required 15-25 2 2 5 D Fair Condtion, Minimal Structural Risk Low 5 2 1-4 57 Low 10-15 3 3 5 0 Poor Condition, Moderate Risk Medium 3 2 1-4 41 Low 5 -10 5 4 5 0 Very Poor Condition, High Structural Risk Immediate 0 4 1-4 28 High 2 -6 5 5 1 -5 12 Failed or Imminent Failure Immediate 0 Table 6 -4 and Table 6 -5 list the priority grade four and five pipes that have been identified for improvement or replacement The City will begin improvement or replacement of the grade five pipes during 2012 and will continue with grade four pipes as needed until June 30, 2016 The cost to complete this work is approximately $145,000 6 -4 Ti __ Sanita-ry Sew ersl d 11 Grades and Brnck Manholes (Fz ru re 6 -3 i DAGIS,f .V:4e:Alt <:> ... < 110,11. al :I •:11 B E A.:. „f :',aeun kc ktss:sstpin Prnortiy Jai U x ite . m ° o Z dr Z Q m mx s� ..__i Jx1 X O X L4Y c m p c5 HILLCREST RD �O m D r WILBRICHT LN 37 .4 p � QT C9 en en 2UNGSSb .. iu 0 3 3 0 �s co 00 CLARKS DR' O co 4� ID D 91EbtU3't n 1 0 ,Alt 4 �� A t 7yQ Ill 0 O® iryC 7 • * �yy0 P • X�„ �^y $T ®' 9'T i- 6 .1�EpSfl A`�E -0 CC2 b— r I- W 57H S7 x 0 co Z s Q�® ® + & i % o q o N .arerrl 11 1 al ©0 � ® of Q a e�� 'j .y, 9�'' 0 92 * f�c ®* 0� �� N'''om ®® : : * M $I +.�' xO * �s'3 SACS' S- GGC s.Ctijs�0 % Q v 4' GRACE ST St °r:t -C • 4 BENNETT ST Metershed 11 Concrete Manhole° (155) 0 Metershed 11 Bnck Manholes (122) Pnonty Grade 1 [18,631 LF] Prlonty Grade 2 (15,267 LF) Prionty Grade 3 [11,745 LF) — Prlonty Grade 4 (5,034 LF) Prlonty Grade 5 [2,420 LF) rF RIB lV t N n. CIM era 4ye/n utwrwnareen 4V4G1 MYa in4Y aftrWtl 411 MN N. fN of 85' x ���' Page ` LWra..NWGyu Canty 11Y W.rtI iN. 't. M1 nutty erWGyu. .Wtn,SN.2*-0"u D G IN rulunet.aN atuNrltbnWawLOW W4G anJ w rvgnr m na wmox..n..nernnennrx. 1 inch = 1,000 feet W E Iwnwa s Ikb.tSn.an.en JMt wr.lt.mGra >oenaerna weewnwew rn.a..:l l.s.rltn''''' „+� "N �'T" t 1000 500 0 1,000 Feet 3 3 Rip PRP0Rdb51 NPK cryotDIblgle Eg het ag Dllabl lgie Iowa SIM Dotlgle b 9-1271 note 063�S8912DS Fax ei IVJe fled b pleclbl neatw t bed 11 Figure 6-3 Prionty grades and brick manholes 6 -5 Table 6 -4. Grade 4 pipes identified for improvement or replacement. GIS ID House Number Street Defect Corrective Action Completed? SAN P04919 NA W Locust St Sag @ 1913, long crack @235 2, sag @295 6, 3144, joint offset @343 4, sag @436 2 Install pipe liner or replace a portion of the pipe SAN P05553 NA N Booth St Sag @ 155, circumferential crack @275, sag @393,596,320,1133 Install pipe liner or replace a portion of the pipe SAN P05097 NA W Locust St Sag and joint offset in pipe @1330 Install pipe liner or replace a portion of the pipe SAN P 05101 NA W Locust St Sag in pipe @ 23 9, 69 3(questionable), hole @173 3 (plugged, oks) Install pipe liner or replace a portion of the pipe SAN P05112 NA Glen Oak St Circ umferential crack @220, 370 (not id'd on N), sag @459,1253 Install pipe liner or replace a portion of the pipe SAN P05513 NA Glen Oak St Circ umferential crack @323, sag @595, broken pipe @662 -700, long crack @1246 Install pipe liner or replace a portion of the pipe SAN P05319 NA Adair St Joint offset @134 (not id'd on N), Heavy shale (155 -239) Install pipe liner or replace a portion of the pipe SAN P 05436 NA IOrkwood St Joints leaking with dye 220 -223', 232 4', joint offset @310 2 Install pipe liner or replace a portion of the pipe SAN P 05546 NA Glen Oak St Circumferential crack @30 7, chuck out of top of pipe @105 3 Install pipe liner or replace a portion of the pipe SAN P05537 NA Alley behind 1324 Atlantic St Longitudinal crack @ 459, sag in pipe @477, last 25' of pipe not televised Install pipe liner or replace a portion of the pipe SAN P05539 NA N Grandview Ave Oc umferential crack @132, sag @100 - 1146,1579 Install pipe liner or replace a portion of the pipe SAN P05600 NA Wood St Hole @ 431, joint gusher @160 3 (not id'd on N), sag @161 3 Install pipe liner or replace a portion of the pipe SAN P 06113 NA Decorah St Broken pipe @4 0', leaking joint @713 Install pipe liner or replace a portion of the pipe SAN P06117 NA Delaware St Sag in pipe @151 3, holes in pipe @1555(3 to 5 and 7 to 9) Install pipe liner or replace a portion of the pipe SAN P06120 NA Dexter St Tap/ break -in @93 (hole near tap), sag in pipe @291 -620, 1025 (not on TV report) Install pipe liner or replace a portion of the pipe SAN P 06142 NA Clarke Dr Sag in pipe @364,1734, 2119, leaking joint @234 1 Install pipe liner or replace a portion of the pipe SAN P 06127 NA N Algona St Ocumferential crack @65 2, shale buildup 70 -33', 90 -110', sag @140 -150 Install pipe liner or replace a portion of the pipe Table 6 -5. Grade 5 pipes identified for improvement or replacement. GIS ID House Number Street Defect Corrective Action Completed? SAN P 05571 NA Wood St Broken pipe @231, cracked pipe @40 2, broken pipe @53 5, broken pipe @62 2 (into brick MH) Install pipe liner or replace a portion of the pipe SAN P05516 NA Glen Oak St Broken pipe @ 750 (replace 16') Install pipe liner or replace a portion of the pipe SAN P05496 NA Alta Vista St Joints gushing @ 1363 ,1395,1422,1431,1443,1459,1431 Install pipe liner or replace a portion of the pipe SAN P 05525 NA Glen Oak St Pipe located under 4 buildings, pipe broken @ 761 (north edge of house at 1191 Edina) Install pipe liner or replace a portion of the pipe SAN P05532 NA Lawndale St Hole in pipe @577, hole in pipe @605 Install pipe liner or replace a portion of the pipe SAN P 05572 NA Wood St Broken pipe @23 5 Install pipe liner or replace a portion of the pipe SAN P 06071 NA W Locust St Broken pipe @147 7 Install pipe liner or replace a portion of the pipe SAN P06130 NA Delaware St Hole in pipe @34 4 Install pipe liner or replace a portion of the pipe SAN P06136 NA Atlantic St Hole in pipe @17 9, hole in pipe @410 Install pipe liner or replace a portion of the pipe SAN P06174 NA Auburn St Hole in pipe @633 , shale & debris @ 1076, 1354,1463,1653,1351, shale obstruction @133 0 Install pipe liner or replace a portion of the pipe SAN P 06133 NA Avon St Broken pipe @3 0 Install pipe liner or replace a portion of the pipe 6 -6 7.0 Campus Investigations 7.1 SEWERSHED 11 CAMPUSES City staff conducted detailed I &I investigations at four large campuses within Sewershed 11: Senior High School, Clarke University, Loras College, Nativity Church and School, and St. Anthony's Church and School. City staff met with campus staff, reviewed utility plans, and conducted dye and smoke testing on each campus. In the end, Senior High School, Clarke University, and St. Anthony's Church and School campuses were found to have improper connections. 7.2 CORRECTIVE ACTIONS 7.2.1 Clarke University The improper connection at Clarke University was found during smoke testing and will be corrected by the university using the process explained for the private property inspections. 7.2.2 St. Anthony's Church and School Two downspouts were connected to the sanitary sewer at St. Anthony Church and School. These have been corrected using the process explained for private property inspections. 7.2.3 Senior High School During June 2011, City staff walked the Senior High School campus with school district staff and used dye and smoke testing to observe flow directions of the sanitary and storm sewer pipes. The inspectors observed: 1) Roof drains improperly connected to the City's sanitary sewer system; 2) Sanitary laterals in West Locust Street that are directed to the Senior campus but appear to be abandoned; and 3) Pavement and sidewalk cracks and joints that provide an indirect connection of rainfall into the sanitary system (infiltration). The City requested the school district to submit a work plan further to investigate, identify, and recommend corrective actions for improper connections at Senior High School (Appendix B). The school district promptly responded by engaging an engineering consultant and conducting their own dye testing. As the school district located improper connections, they were immediately corrected. A summary letter from the school district's engineering consultant is provided in Appendix C. The City conducted smoke testing on November 1, 2011 to verify all work had been properly completed. Unfortunately, City and school district staff continued to observe smoke from roof 7 -1 drains and pavement cracks. The City issued a second letter (Appendix D) to request that the school district correct the defects observed on November 1, 2011. 7 -2 8.0 Plan Summary This plan fully addresses work to be conducted by the City and private property owners within Sewershed 11. The plan is subject to approval by the US EPA and Iowa DNR. 8.1 FUNDING The Capital Improvement Program (CIP) Budget represents the City of Dubuque's five year physical development effort, attempts to address a variety of needs, which the City must meet if it is to maintain its physical facilities, meet its service commitments and provide for its future development. The CIP Budget reflects the City's comprehensive plan and the goals and priorities established by the City Council. The first year of the five -year CIP Budget goes into the budget for the next year and deserves the most attention. The CIP Budget is updated each year so that City Council has the opportunity to change the next four years and add a new year. At this time, the CIP Budget is sufficient to fund the corrective actions identified in this plan. However, the City reserves the right to adjust or remove corrective actions from this plan based upon funding, further investigation, and future I &I- related priorities in other sewersheds. 8.2 CORRECTIVE ACTION SUMMARY The City employed numerous methods to investigate sources of I &I: private property inspections; smoke testing the sanitary sewer collection system; brick manhole identification; sanitary sewer pipe prioritization; and "campus" inspections. Sections 3 through 7 of this plan detailed the proposed corrective actions based upon each investigation method. Table 8 -1 lists all of the corrective actions identified in this plan in one table. The total cost to the City for all proposed corrective actions is approximately $806,000. Table 1 summary of corrective ectmon_ identified for Sewei hed11 GIS ID House Number Street Defed Corrective Action Complete' Pnvete Property Inspection_ 353520 1.'56 Nowata St Exterior dram to sanitary sewer - Drub ucted enclosurearound stainaray Ves 335523 1775 Alta PI Exterior dram to sanitary sewer -mss ucted enclosure around stairway Ves 350301 2010 Alta Vista St Root dr am to sanitary sewer Disconnected tr om sanitary sewer Ves 340790 875 W Locust St Sump pump discharges to sanitary sewer New sump pt installed to separ ate storm and sanitary Ves ::5415 2341 Green St Sump pump discharges to sanitary sewer New sump pt installed to separ ate storm and sanitary Ves '35414 2350 - een St Sump pump discharges to sanitary sewer New sump pt installed to separ ate storm and sanitary Ves 353500 L'41 Aubur n St Sump pit without pump pump installed in sump pit and plumped proper l} Ves '32404 1.'55 Lor as Bbd Sump pit without pump pump installed in sump pit and plumped proper l} Ves 324542 1818 Asbury Rd Sump pit without pump pump installed in sump pit and plumped proper l} Ves 321778 1511 Adair St Root dr am to sanitary sewer Root dr am disconnected tr om sanitary sewer Ves '32804 1505 Wood St Root dr an to s nitary sewer Root dr an disconnected fr om sanitary sewer Ves 320500 1870 StAmhr ose St Root dr am to sanitary sewer Root dr am disconnected tr om sanitary sewer Ves 357018 1.'41 Wood St Sump pump discharges to sanitary sewer Sump pit disconnected tr om sanitary sewer Ves 353587 1451 Amirante St Sump pump discharges to sanitary sewer Sump pit disconnected tr om sanitary sewer Ves 355757 1570 N 'sr andrriew A■re Sump pump discharges to sanitary sewer Sump pit disconnected tr om sanitary sewer Ves 335505 1845 Amirante St Sump pump discharges to sanitary sewer Sump pit disconnected tr om sanitary sewer Ves 881782 1885 Wood St Sump pump discharges to sanitary sewer Sump pit disconnected tr om sanitary sewer Ves 341040 2385 tinnier sity Aire Sump pump discharges to sanitary sewer Sump pit disconnected tr om sanitary sewe r Ves 340444 770 Argella St Sump pump discharges thr ough flexible hose r Sump pump discharges thr ough gid pipe Ves 358385 805 Kirkwood Aire Sump pump discharges thr ough flexible hose Sump pump discharges thr ough rigid pipe Ves 818957 1050 Lor as Bbd Sump pump discharges thr ough flexible hose Sump pump discharges thr ough rigid pipe Ves 885432 1005 Wood St Sump pump discharges thr ough flexible hose Sump pump discharges thr ough rigid pipe Ves 858325 1111 Rosedale Aire Sump pump discharges thr ough flexible hose Sump pump discharges thr ough rigid pipe Ves 882384 1205 N Booth St Sump pump discharges thr ough flexible hose Sump pump discharges thr ough rigid pipe Ves 357423 1212 Wood St Sump pump discharges thr ough flexible hose Sump pump discharges thr ough rigid pipe Ves 355743 1458 Mt Pleasant St Sump pump discharges thr ough flexible hose Sump pump discharges thr ough rigid pipe Ves 8558Eg 1480 Galen Dal: St Sump pump discharges thr ough flexible hose Sump pump discharges thr ough rigid pipe Ves 342248 1490 N 'sr andrriew A■re Sump pump dm scharges thr ough flexible hose Sump pump dm scharges thr ough rigid pipe Ves 34543 1580 Ashton PI Sump pump discharges thr ough flexible hose Sump pump discharges thr ough rigid pipe Ves 355558 1510 Ashton PI Sump pump discharges thr ough flexible hose Sump pump discharges thr ough rigid pipe Ves 882553 1545 Atlantc St Sump pump discharges thr ough flexible hose Sump pump discharges thr ough rigid pipe Ves 33159 1555 Asbury Rd Sump pump discharges thr ough flexible hose Sump pump discharges thr ough rigid pipe Ves 353541 1543 Lor as Bbd Sump pump discharges thr ough flexible hose Sump pump discharges thr ough rigid pipe Ves 33157 1595 Asbury Rd Sump pump discharges thr ough flexible hose Sump pump discharges thr ough rigid pipe Ves 888755 1715 Ashury Rd Sump pump discharges thr ough flexible hose Sump pump discharges thr ough rigid pipe Ves 38753 1725 Ashury Rd Sump pump discharges thr ough flexible hose Sump pump discharges thr ough rigid pipe Ves 335515 1730 Avoca St Sump pump discharges thr ough flexible hose Sump pump discharges thr ough rigid pipe Ves 881788 1755 Wood St Sump pump discharges thr ough flexible hose Sump pump discharges thr ough rigid pipe Ves 315480 1800 Lawn dale St Sump pump discharges thr ough flexible hose Sump pump discharges thr ough rigid pipe Ves 881755 1810 Adair St Sump pump discharges thr ough flexible hose Sump pump discharges thr ough rigid pipe Ves 320494 1845 Ashury Rd Sump pump dm scharges thr ough flexible hose Sump pump dm scharges thr ough rigid pipe Ves 32480 1850 Ashury Rd Sump pump dm scharges thr ough flexible hose Sump pump dm scharges thr ough rigid pipe Ves 32485 1855 Clad:e Err Sump pump discharges thr ough flexible hose Sump pump discharges thr ough rigid pipe Ves 324688 1850 StAmhr ose St Sump pump dm scharges thr ough flexible hose Sump pump dm scharges thr ough rigid pipe Ves 38741 1421 N '3r andrriew Aire Sump pump discharges thr ough flexible hose Sump pump discharges thr ough rigid pipe Ves 319187 1985 N '3r andrriew Aire Sump pump discharges thr ough flexible hose Sump pump discharges thr ough rigid pipe Ves 319182 2175 Rosedale Aire Sump pump discharges thr ough flexible hose Sump pump discharges thr ough rigid pipe Ves 885384 2215 Green St Sump pump discharges thr ough flexible hose Sump pump discharges thr ough rigid pipe Ves 358805 1049 W Locust St Exter or drain to sanitary sewer Cor r ectnre action to be completed by pr oper ty owner 35580 1055 Aubur n St Exterior drain to sanitary sewer _ ectnre action to he completed by pr oper ty owner 357022 1222 Wood St Sump pump discharges thr ough flexible hose _ ectnre action to he completed by pr oper ty owner 881425 1275 Mt pleasant St Sump pump discharges to sanitary sewer o ectnre action to be completed by pr oper ty owner 882005 1825 Lor as Bbd Sump pump discharges to sanitary sewer Cor r ectnre action to be completed by pr oper ty owner 818559 1339 Alta Vista St Root dr an to s nitary sewer Cor r ectnre action to be completed by pr oper ty owner 353544 1880 Aubur n St Exter or dram to sanitary sewer _ ectnre action to be completed by pr oper ty owner 353505 1852 Atlantc St Root dr an to nitary sewer Cor r ectnre action to be completed by pr oper ty owner 881855 1435 Mt Pleasant St Sump pump discharges thr ough flexible hose _ ectnre action to be completed by pr oper ty owner 885437 1475 tinnier sity Aire Exter or dram to sanitary sewer Cor r ectnre action to be completed by pr oper ty owner 88545 1485 tinnier sity Aire Exter or dram to sanitary sewer Cor r ectnre action to be completed by pr oper ty owner 331352 1401 Mt Pleasant St Sump pump discharges to sanitary sewer _ ectnre action to be completed by pr oper ty owner 342277 1528 Mt pleasant St Root dr an to s nitary sewer sump pump discharges thr ough flexible host _ ectnre action to be completed by pr oper ty owner 882557 1541 N Algona St Exterior drain to sanitary sewer Correctnre action to be completed by pr oper ty owner GIS ID House Number Street Defed Corrective Action Complete' :4555: 1549 Lawn dale St Sump pump discharges to sanitary sewer _c ectnre action to be completed by pr oper ty owner :55555 1550 Ashton PI Sump pit without pump _c ectnre action to be completed by pr oper ty owner :8781 1571 Aac a St Roof dran to nitary sewer Cor r ectnre action to be completed by pr oper ty owner 353592 1575 Lor as B■rd Sump pump discharges thr ough flexible hose _c ectnre action to be completed by pr oper ty owner 35554 1715 Atlantic St Exter or drain to sanitary sewer Cor r ectnre action to be completed by pr oper ty owner 355753 1795 Adair St Exterior drain to sanitary sewer _c ectnre action to he completed by pr oper ty owner 34414 1745 Aubur n St Roof dran to sanitary sewer _c ectnre action to be completed by pr oper ty owner 357892 1815 Lor as Bhrd Sump pit without pump _c ectnre action to be completed by pr oper ty owner 325932 1885 StAmhr ose St Sump pump discharges thr ough flexible hose _c ectnre action to be completed by pr oper ty owner 340507 1911 StAmhr ose St Sump pump discharges to sanitary sewer oectnre action to be completed by pr oper ty owner 340501 1983 StAmhr ose St Sump pump discharges to sanitary sewer Cor ectnre action to be completed by pr oper ty owner 34481,' 1985 Alta Vista St Roof dr a n to nitary sewer Cor r ectnre action to be completed by pr oper ty owner 335528 2025 Delawar e St Sump pump discharges thr ough flexible hose _ ectnre action to be completed by pr oper ty owner 319171 gig. Clar l:e Dr Sump pit without pump _c ectnre action to be completed by pr oper ty owner 323944 2215 Llnnrer smty Are Sump pump discharges thr ough flexible hose _c ectnre action to be completed by pr oper ty owner 32493 2275 Green St Sump pump discharges thr ough flexible hose C catnre action to be completed by pr oper ty owner 341948 2395 unimer smty Are Sump pump discharges to sanitary sewer Cor r ectnre action to becompleted by pr oper ty owner Smoke TeTine - Pnvete Property Detect_ NA 1700 NGrendview Ave Smoke fronm Water Acce__ Televise Ieter el, notify property owner o fenynece__eryrepemr NA 1669 Adeur St Smoke fronm Behind Curb Televise Ieter el, notify pr operty owner o fenynece__eryrepeir NA 1050 Wood St Severed Sennery Cleenout Property ownerrepemr with water tight eel NA 1951 Lore :Blvd Smoke fronm ground n e e r e 3 _ meter Televise Ieter el, notify pr operty owner o fenynece__eryrepeir NA 1230 Glen C,ek St Smoke fronm ground end waterec , = TelevLTeleviseIeter el, notify pr operty owner o fenynece__eryrepeir NA 300 WLocust St Smoke fronmweterveive et corner of Teir_ end sidewelk Televise Ieter el, notify property owner o fenynece__eryrepeir NA 1537 Irving St Smoke fronm butter Trip between sidewelk end beck of curb Televise Ieter el, notify property owner o fenynece__eryrepeir NA 1390 Audubon St Smoke fronmretemmmne well.Tep: end concrete in front of hone Televise Ieter el, notify property owner o fenynece__eryrepeir NA 990 Booth St Smoke fronmwe tervelveecro__Treet TelevL a Ieter el, notify property owner ofeny nece__eryrepeir NA 1371 Glen 09 St Smoke fronm tlnvewey Property owner to disconnect tlnvewey drem NA 1575 Irving St Smoke fronm rock_ neer drmvevey Televise Ieter el, notify property owner o fenynece__eryrepeir NA 1671 Avoca St Smoke fronmreer downspout Property owner disconnect downspout fr onm sent 3ry ewer NA 1660 Ashton P I Smoke fron9 hut- ottvelve Televise Ieter el, notify property owner o fenynece__eryrepemr NA 1657 Ashton P I Smoke fron9 sidwelkivelve Televise Ieter el, notify property owner o fenynece__eryrepemr NA 1905 Lore :Blvd Smoke fronmreer door Televise Ieter el, notify pr operty owner o fenynece__eryrepemr NA 1065 Auburn St Smoke fronmcreck ner tlnvewey Property owner to disconnect tlnvewey drem NA 1339 Mt PIe_ent St Smoke fronmvelve Property owner tom Tellweter tight cep NA 730 Kirkwood St Smoke fronm ground behind cur b TelevL a Ieter el, notify property owner ofeny nece__eryrepeir NA 1935 Clerke Dr Smoke fronm hole in eround by down spout Property owner disconnect downspout troom sent 3ry ewer NA 1550 Clerke Dr Smoke fronm hole in eround Property owner tom Tellweter tight cep NA 1570 Mt PIe_ent St Smoke fronm uneven curb Televise Ieter el, notify property owner o fenynece__eryrepeir NA 1556 Mt PIe_ent St Smoke fronm tlnvewey drem Property owner to disconnect tlnvewey drem NA 1350 Now3t3 St Smoke fronm T3mrwey drem Action complete, ewnine mrt elled to prevent rem from entering drem Yes NA 1200 Glen 09 St Smoke byweter but -off Televise Ieter el, notify prroperty owner o fenynece__eryrepemr NA 615 Aneelle St Smoke byweter but -off Leter el we_telev9 ed by licensed plumber, no correctiveectmon needed Yes NA 1065 Auburn St Smoke fronm MH /cmnern in frontyertl Property owner repair NA 1300 Clerke Dr (SHS oftbell field) Smoke fronm ground ner MH Property owner repair Smoke TeTine - Sen'tery Sewer Detect: SAN P 05590 1302 Atlentic Street Smoke fronm Ground, lonenutlmelcreck in pipe Inmprove orrapiece pipe SAN 505395 1537 Irvine St Vented MH Cover Replete cover SAN 505335 NA Irvine St& Decor eh St Smoke et MH Dien,ontl Inmpr ove or r apiece nmenhole SAN 505331 NA Lore :Blvd & NOw3t3 St Vented MH Cover Replete cover SAN 506303 1019 Lore :Blvd Smoke fron, ground eround MH. Vented Cover Inmpr OVe Or replete nmenhole SAN 505570 1371 Glen 09 St Smoke fron, ground eround MH Inmpr OVe Or replete nmenhole SAN 505530 NA Woods N of Lewndele St Smoke fron, ground eround MH Inmpr OVe Or ,apiece nmenhole SAN 505303 NA St An,brO a St& RO edele Ave Snmokeeround MH Inmpr OVe Or replete nmenhole SAN 505009 NA Curter St &Atlentic St Snmokeeround MH Inmpr OVe Or r apiece nmenhole SAN 505390 1320 N Grendview AVe Smoke tton,MH. tlrivewey end cur b Inmpr OVe Or r apiece nmenhole SAN 505657 NA Merthe St end Nevede St Snmokeeround MH end etch ben et SE Corner oflnterect9Or Inmprove or apiece pipe tonorthest (SAN P 05553; SAN 506739 1331 Glen 09 St Menhole in low spot in frontyertl Inmpr OVe Or replete nmenhole SAN 505573 1371 Glen 09 St Snmoketronm Ground ner MH Inmpr OVe Or replete nmenhole SAN 505036 NA W Locust St& CIerke Dr Smoke fronmcreck in pevenment Inmprove orrapiece pipe (Grede 0 pipe. SAN P 05053; SAN 500703 1230 Ro edeleAVe Smoke fron, MH in yertl Improve Or replete nmenhole SAN 505320 Or 05395 2155 University Vented NlH Cover Replete cover SAN P 05622 1300 Auburn St Multiple f r e c t u r e_. hole. Ieter el intrutlme Inmprove orrapiece pipe SAN P 05621 1330 Curter St Multiple frectur e_. hole in pipe Inm pr ove or raplece pipe SAN P 05619 1790 Curter St Multiple frectur e_. pint epereted. cmcunmferentmelcreck Inmprove orrapiece pipe SAN P 05615 1730 Curter St Multiple frectur es Improve orrapiece pipe SAN P05620 NA Cuter St Multiple frectur e_. lone9[utlmel creck.'cunt ottet Inmprove or apiece pipe GIS ID House Number Street Defed Corrective Action Complete' Smoke TeTine Storni Sewer Detect: 5TO 5 00272 1155 Wood 5f Smoke froni[etch bs in Flood & dye Torni ewer televL e_3ni[3ry, improve 3_ needed 5TO 5 0035 ee5 Neved3 St Smoke froni[etch bs in Profrudinelsfer 3lfsp, property owner to r ep3ir 5TO 5 00300 1371 uIen uek St Smoke froni[etch b3 in Possibly lifer 3l from 1925 ulen ask, property owner to r ep3ir 5TO500231 1795 Adsir 5f Smoke froni[etch bsin Flood & dye Torni ewer, televLe_3ni[3ry, improve 3_ needed 5TO500310 NA Delswsre St &Grsntlwev Ave Smoke from [etch bsin Flood &dye Torm ewer, televLe_3ni[ 3ry, improve 3_ needed Brick M enhole= SAN 500710 1193 Wood St Brick m3nbole Improve or repl3[e m3nbole SAN 505390 1331 N Gr endview Ave Brick m3nbole Improve or repl3[e m3nbole SAN 50550 1100 L3wntl3le St Brick m3nbole Improve or repl3[e m3nbole SAN 505751 1939 Wood St Brick m3nbole Improve or repl3[e m3nbole SAN 505610 1675 Glen Gsk St Brick m3nbole Improve or repl3[e m3nbole SAN 50535 NA Decor eh St &Irvine St Brick m3nbole Improve or repl3[e m3nbole SAN 505300 1911 N Gr endview Ave Brick m3nbole Improve or repl3[e m3nbole SAN 505601 1700 GIenGsk St Brick m3nbole Improve or repl3[e m3nbole SAN 505331 NA AtI3nfi[ St & DeI3wsre St Brick m3nbole Improve or repl3[e m3nbole SAN 50555 1100 GIenGsk St Brick m3nbole Improve or repl3[e m3nbole SAN 505391 1005 Auburn St Brick m3nbole Improve or repl3[e m3nbole SAN 50533 NA Fillmore St & Auburn St Brick m3nbole Improve or repl3[e m3nbole SAN 505301 1305 Avo[3 St Brick m3nbole Improve or repl3[e m3nbole SAN 505626 1005 Vernon St Brick m3nbole Improve or repl3[e m3nbole SAN 505653 1210 Lor3_Blvd Brick m3nbole Improve or repl3[e m3nbole SAN 505567 NA Decor eh St& Auburn St Brick m3nbole Improve or repl3[e m3nbole SAN 505357 NA DeI3wsre St & Auburn St Brick m3nbole Improve or repl3[e m3nbole SAN 505393 NA Lor3_Blvd & Aflsnfi[ St Brick m3nbole Improve or repl3[e m3nbole SAN 505612 1616 L3wntl3le St Brick m3nbole Improve or repl3[e m3nbole SAN 505379 1633 Avo[3 St Brick m3nbole Improve or repl3[e m3nbole SAN 505730 950 Wood St Brick m 3nbole Impr ove or repl3[e m 3nbole SAN 505621 1050 AIf3 ViT3 St Brick m3nbole Improve or repl3[e m3nbole SAN 505591 1760 L3wntl3le St Brick m3nbole Improve or repl3[e m3nbole SAN 505620 1501 L3wntl3le St Brick m3nbole Improve or repl3[e m3nbole SAN 507339 NA Alley behind 1739 unn Ave Brick m3nbole Improve or repl3[e m3nbole SAN 505605 1000 Edina St Brick m3nbole Improve or repl3[e m3nbole SAN 505615 1091 Edina St Brick m3nbole Improve or repl3[e m3nbole SAN 500730 NA N Gr endview Ave Brick m3nbole Improve or repl3[e m3nbole SAN 505570 1371 GIenGsk St Brick m3nbole Improve or repl3[e m3nbole SAN 505650 1030 Glen Gsk St Brick m3nbole Improve or repl3[e m3nbole SAN 505719 1331 GIenGsk St Brick m3nbole Improve or repl3[e m3nbole SAN 505005 1303 AtI3nfi[ St Brick m3nbole Improve or repl3[e m3nbole SAN 505305 1905 N Gr endview St Brick m3nbole Improve or repl3[e m3nbole SAN 50530 1060 AtI3nfi[ St Brick m3nbole Improve or repl3[e m3nbole SAN 505363 NA Delaware St & Ashton PI Brick m3nbole Improve or repl3[e m3nbole SAN 501907 1795 Asbury Rd Brick m3nbole Improve or repl3[e m3nbole SAN 507013 NA N Booth St &M3rthe St Brick m3nbole Improve or repl3[e m3nbole SAN 506303 1019 Lor3_5lv6 Brick m3nbole Improve or repl3[e m3nbole SAN 505051 NA EI3rSe Dr & N Grsntlwev Ave Brick m3nbole Improve or repl3[e m3nbole SAN 505625 1576 GIenGsk St Brick m3nbole Improve or repl3[e m3nbole SAN 505753 1016 Wootl 5f Brick m3nbole Improve or repl3[e m3nbole SAN 500703 1330 Ro edsle Ave (on GIenGsk St) Brick m3nbole Improve or repl3[e m3nbole SAN 501939 1111 Asbury Rd Brick m3nbole Improve or repl3[e m3nbole SAN 505579 NA GIenGsk St Brick m3nbole Improve or repl3[e m3nbole SAN 505607 NA Mt Ple_3no St& Lor3_555tl Brick m3nbole Improve or repl3[e m3nbole SAN 505731 935 Ne'3d3 St Brick m3nbole Improve or repl3[e m3nbole SAN 505503 1050 Lor3_5lv6 Brick m3nbole Improve or repl3[e m3nbole SAN 505333 1550 University AVe(behind building) Brick m3nbole Improve or repl3[e m3nbole SAN 505000 NA Absndonedslley behind 1375 Curter St Brick m3nbole Improve or repl3[e m3nbole SAN 505622 1695 Mt Ple_3nf St Brick m3nbole Improve or repl3[e m3nbole SAN 505371 1555 N Aleon3 St Brick m3nbole Improve or repl3[e m3nbole SAN 500715 1175 Audobon St Brick m3nbole Improve or repl3[e m3nbole SAN 505356 1709 N Aleon3 St Brick m3nbole Improve or repl3[e m3nbole SAN 506103 1515 Wootl 5f Brick m3nbole Improve or repl3[e m3nbole SAN 50537 NA Fillmore St & Aleon3 St Brick m3nbole Improve or repl3[e m3nbole SAN 505355 NA Geyer St (alley E of Aleon3 St) Brick m3nbole Impr ove or repl3[e m 3nbole SAN 500731 NA NGssndview Ave &Auburn St Brick m3nbole Impr ove or repl3[e m 3nbole SAN 505393 1031 N Aleon3 St Brick m3nbole Improve or repl3[e m3nbole SAN 505397 NA Alley behind 1330AtI3nfi[ St Brick m3nbole Improve or repl3[e m3nbole SAN 506939 1755 Wood St Brick m3nbole Improve or repl3[e m3nbole SAN 5 05966 1650 N Aleon3 St Brick m3nbole Improve or repl3[e m3nbole GIS ID House Number Street Defed Corrective Action Complete' Br'ck Nlenhole= SAN 505350 2135 G en S1 Brick ni3nbole Inipr ove or replace ni3nbole SAN 505697 1195 Vernon St Brick ni3nbole Inipr ove or replace ni3nbole SAN 905327 2020 GT eon S1 Brick ni3nbole Inipr ove or replace ni3nbole SAN 905501 615 Aneelle St Brick ni3nbole Inipr ove or replace ni3nbole SAN 505500 1119 Pierce S1 Brick ni3nbole Inipr ove or replace ni3nbole SAN 505596 595 Anee113 St Brick ni3nbole Inipr ove or replace ni3nbole SAN 505060 1193 Wood St Brick ni3nbole Inipr ove or replace ni3nbole SAN 505509 NA Aneelle St& Pierce S1 Brick ni3nbole Inipr ove or replace ni3nbole SAN 905539 1903 Pierce S1 Brick ni3nbole Inipr ove or replace ni3nbole SAN 905560 NA Lor a_ property near Kirkwood & B13Ye S1_ Brick nienhole Inipr ove or replace ni3nbole SAN 905600 NA Vernon St &Glen G9k St Brick ni3nbole Inipr ove or replace ni3nbole SAN S05559 NA Co. St & Anee113 St Brick ni3nbole Inipr ove or replace ni3nbole SAN 505500 601 Anee113 St Brick ni3nbole Inipr ove or replace ni3nbole SAN 505602 1265 Vernon St Brick ni3nbole Inipr ove or replace ni3nbole SAN 505011 1790 Curter St Brick ni3nbole Inipr ove or replace ni3nbole SAN S05562 1037 Kirkwood S1 Brick ni3nbole Inipr ove or replace ni3nbole SAN 505553 NA Kirkwood S1 Brick ni3nbole Inipr ove or replace ni3nbole SAN 505003 1375 Auburn St Brick ni3nbole Inipr ove or replace ni3nbole SAN 505015 NA Auburn St(311ey between Curter & unrv) Brick ni3nbole Improve or replace ni3nbole SAN 505720 1011 N Booth St Brick ni3nbole Inipr ove or replace ni3nbole SAN 505360 NA Decorah St& AtIentic St Brick manhole Inipr ove or replace manhole SAN 505013 NA AtIentic St (elley between curter & univ) Brick manhole Inipr ove or replace manhole SAN 505359 1605 AtIentic St Brick manhole Inipr ove or replace manhole SAN 505503 190 Kirkwood St Brick manhole Inipr ove or replace manhole SAN S05652 1330 N Booth St Brick manhole Inipr ove or replace manhole SAN S05725 935 N Booth St Brick manhole Inipr ove or replace manhole SAN S05721 1319 MtP1e_3n1 St Brick manhole Inipr ove or replace manhole SAN S05722 1105 MtP1e_3n1 St Brick manhole Inipr ove or replace manhole SAN 501901 1150 NGrendview Ave Brick manhole Inipr ove or replace manhole SAN 505606 1035 MtP1e_3n1 St Brick manhole Inipr ove or replace manhole SAN 505729 900 MtP1e_3n1 St Brick manhole Inipr ove or replace manhole SAN S06961 1005 Wootl 5t Brick manhole Inipr ove or replace manhole SAN 505335 1775 Wood St Brick manhole Inipr ove or replace manhole SAN S01733 1715 Asbury Rd Brick manhole Inipr ove or replace manhole SAN 505319 1655 Asbury Rd Brick manhole Inipr ove or replace manhole SAN 505696 1555 Mt PIe_3nt St Brick manhole Inipr ove or replace manhole SAN 505303 1937 St Anibrore St Brick manhole Inipr ove or replace manhole SAN 505336 1905 Asbury Rd Brick manhole Inipr ove or replace manhole SAN 507969 1925 Pierce St Brick manhole Inipr ove or replace manhole SAN 505330 1535 Irvine St Brick manhole Inipr ove or replace manhole SAN 505395 1537 Irvine St Brick manhole Inipr ove or replace manhole SAN 505530 1971 Co. St Brick manhole Inipr ove or replace manhole SAN 507013 1715 Glen Oek St Brick manhole Inipr ove or replace manhole SAN 505792 995 Ne13d3 St Brick manhole Inipr ove or replace manhole SAN 505012 1060 Auburn St (et Curter St) Brick manhole Inipr ove or replace manhole SAN 505539 1790 Glen Oek St Brick manhole Inipr ove or replace manhole SAN 507323 1760 Curter St Brick manhole Inipr ove or replace manhole SAN 505962 1735 Avoca St Brick manhole Inipr ove or replace manhole SAN 505630 1100 Vernon St Brick manhole Inipr ove or replace manhole SAN 505300 NA AtIentic St & Deeer St Brick manhole Inipr ove or replace manhole SAN 505330 1795 A69ir St Brick manhole Inipr ove or replace manhole SAN 505926 1669 A69ir St Brick manhole Inipr ove or replace manhole SAN 505972 1075 A69ir St Brick manhole Inipr ove or replace manhole SAN 505511 1799 L3wndeIe St Brick manhole Inipr ove or replace manhole SAN 505031 1030 Lor a_ Blvd Brick manhole Inipr ove or replace manhole SAN 500711 1165 A69ir St Brick manhole Inipr ove or replace manhole SAN 505309 1910 Asbury Rd Brick manhole Inipr ove or replace manhole SAN 505330 NA Aleon3 St & De.ter St Brick manhole Inipr ove or replace manhole SAN 505370 NA Decorah St& N Aleon3 St Brick manhole Inipr ove or replace manhole SAN 50530 1025 A69ir St Brick manhole Inipr ove or replace manhole GIS ID House Number Street Defed Corrective Action Complete' Senitery Sewer Pr for i[y SyTeni -Ge ede 0 Pipe: SAN P00919 NA NILocurt St 53e ■w 1913,1on0csck ko235 2. E3g ko2956. 3100, loin off=e[ ko303 0. zee ko0362 Improve or replace 3 portion of the pipe SAN P05553 NA NBooth St 53¢42155, c ' un!erenti 3 l c r s c k s o27 5. zee kv 3e 1. 59 b. u 3 0 . 1 1 1 1 Iniprove or replace 3 portion of the pipe SAN P05097 NA NILocurt St Sae end l o l n t o f f = e t i n pipe kt, 1 3 3 0 Iniprove orreplsce 3 portion of the pipe SAN P05101 NA NILocurt St See I n pipe @2219.693(que11loeble), hole X21733(plueeed.ok0; Iniprove orreplsce 3 portion of the pipe 5ANP05112 NA G I e n O 3 k St Elrcln!erentlslcrsck X2330. 370 (notltl'tl on TV). zee X2459,135_ Iniprove orreplsce 3 portion of the pipe SAN P05513 NA G I e n O 3 k St Elrcln!erentlsIcrsckooa333, zee 0o555, broken pipe s663- 700,Ione[sckooa1345 Improve orreplsce 3 portion of the pipe SAN P05319 NA Atl31r 5t I o l n t ottet 41130 (not l tl ' tl on TV), HesvyFele(155 -339) Improve orreplsce 3 portion of the pipe SAN P05416 NA Kirkwood S[ loints Iesklne with dye 330 -333'. 3 3 3 0 ' , I o l n t offset k23102 Iniprove or replace 3 portion of the pipe SAN P05506 NA G l e n O 3 k St E unmerentlslcrosck ko307. chuck out of top of pipe X21053 Improve or replace 3 portion of the pipe SAN P05517 NA Alley behind 1320AtI3nt'c St Lonenutllnslcr 3[k X2459,= I n pipe k2477, 1 s T 35' o f pipe not televised Iniprove or replace 3 portion of the pipe SAN P05539 NA N�5rsntivlew Ave E unmerentl 3lcr 3[k kol32.P kol00- 114eo1579 Improve or replace 3 portion of the pipe SAN P05600 NA Wood St Hole o2431, J o i n t gusher s21603 (notltl'tl on TV). zee k21613 Improve or replace 3 portion of the pipe SAN P06113 NA Decor eh St Broken pipe k240'. leklnelolnt X2]11 Improve or replace 3 portion of the pipe SAN P06117 NA Delswsre St S3eln pipe o21513,ho le_ In pipe X21555(3 to 53567 to 9) Improve or replace 3 portion of the pipe SAN P06120 NA DeAer 5t Tap /br ek- Inol93(hole ner tep). zee In pipe k2391E30. 1035 (not on TV report) Improve or replace 3 portion of the pipe SAN P06102 NA Clarke D r S 3 e l n pipe k236 4. 1710. 2 1 1 9 . leklne J o i n t k23301 Improve or replace 3 portion of the pipe SAN P06127 NA NAleon351 EI[unmerentl 3lcr 3[k ko653, File buildup 70- 11.90- 110',zee k2140 -150 Improve or replace 3 portion of the pipe Senitery Sewer Priority SyTeni -pier 3tle 5 Pipe= SAN PO55]1 NA Wood S[ Broken pipe 02331, cr 3cketl pipe 02403, broken pipe o255broken pipe ko622 (into brick 10H) Improve or replace 3 portion of the pipe SAN P05516 NA Glen Eisk St Broken pipe X2750 (replace 1 6' ) Improve or replace 3 portion of the pipe SAN P05096 NA AIt35111351 Iolnt_euhlne k21353 .1395.1033.1431.1443.1459.141 Improve or replace 3 portion of the pipe SAN P05525 NA Glen Eisk St Pipelo[3tetl under 4 bulltllnee pipe broken o2 761(north edge of hone 3t 1191Etlin3) Improve or replace 3 portion of[he pipe SAN P05532 NA L3wntlsle St Hole I n pipe 025]], hole I n pipe o2605 Improve or replace 3 portion of the pipe SAN P05572 NA Wood 5t Broken pipe 02335 Improve or replace 3 portion of the pipe SAN P06071 NA NILocu11 St Broken pipe 021477 Improve or replace 3 portion of the pipe SAN P06130 NA Delswsre St Hole I n pipe o2l44 Improve or replace 3 portion of the pipe SAN P06136 NA Atlsnt'c 5t Hole I n pipe awl] 9 , hole i n pipe o2410 Improve or replace 3 portion of the pipe SAN P 0617 NA Auburn 5[ Hole In pipe ko63l, Fele& debris kt, 107 6.135 0.10o 1.1651.1151, Feleoblructlon 421110 Improve or replace 3 portion of the pipe SAN P06133 NA Avon St Broken pipe o2l0 Improve or replace 3 portion of the pipe THE CITY OF DThUi Masterpiece on the Mississippi Engineering Department, I &I Program City Hall 50 W 13th Street Dubuque, Iowa 52001 563 690 6113 www cityofdubuque org /i &i FINANCIAL ASSISTANCE APPLICATION (Rev. 12 /6 /11) Program Eligibility and Requirements 1 Applicant must be the owner and resident of the property where code violation occurred 2 All applicants are eligible for 50% assistance on repairs greater than $500 The maximum amount of City assistance is $3,000 unless the applicant qualifies for income -based assistance described below 3 City assistance amounts greater than $1,000 will be 3 -year forgivable loans The City assistance amount shall be due upon the sale of the property if the owner - occupant sells the property within 3 years of financial assistance application approval The assistance amount will not be prorated 4 Applicant must obtain cost estimates from three licensed contractors, and all three estimates must be greater than $500 (Applicant is responsible for paying the first $500 ) 5 The City retains the right to solicit additional cost estimates if it deems the cost estimates obtained by the property owner excessive 6 The three cost estimates must be itemized and accompany this application form Work not related to the code violation is not applicable The City may exclude work if it is not related to code repairs 7 Applicant may choose any of the three contractors but will be reimbursed based on the lowest of the three cost estimates 8 Reimbursement will occur after a Work is completed per City Code, b Work is re- inspected and deemed satisfactory by the City of Dubuque (We suggest having the re- inspection done by the City prior to final payment to the contractor ) 9 Additional assistance is available based on U S Department of Housing and Community Development income guidelines The assistance percentage (75 %, 50 %, or 25 %) is in addition to the 50% assistance amount offered to all applicants See attached "Participant Income Verification Form " 10 Fundino examples Lowest Cost Estimate Amount Not Subject to Cost Share Amount Subject to Cost Share 50% City Cost Share Income -Based Assistance Percentage Income -Based City Cost Share Amount Total Cost to Applicant $4,500 $4,500 $500 $4,000 $2,000 0% $0 - $2,000 $2,500 $4,500 $4,500 $500 $4,000 $2,000 25% $500 $2 000 - $500 $2,000 $4,500 $4,500 $500 $4,000 $2,000 50% $1,000 - $2,000 - $1,000 $1,500 $4,500 $4,500 $500 $4,000 $2,000 75% $1,500 - $2 000 - $1,500 $1,000 " For all eligible costs, as determined by the City 11 If the City finds the work was not done correctly and a violation remains, the City of Dubuque assumes no responsibility 12 The City retains the right to review each application thoroughly Improper connections or connections to the sanitary sewer system made without a City permit may not be eligible for financial assistance 13 The City retains the right to rescind this assistance at any time for good cause including funding availability Page 1 of 4 Applicant — Please Complete This Page Please complete fully and accurately, attach a copies of all income verification information and cost estimates and submit to Office of City Engineering ATTN Todd Shoemaker, Environmental Engineer 50 W 13th Street Dubuque, Iowa 52001 -4864 Phone (563) 589 -4270 Name of Property Owner: Phone #: Property Address: City: State: Zip: Today's Date: Signature: Cost Estimates to Correct Violation: Amount ($) Plumber or Company License Number Cost Estimate #1 Cost Estimate #2 Cost Estimate #3 Are you applying for income -based assistance: YES NO I • If you checked "YES" Verification Form ". • Attach a complete Include a copy of W • If no income tax filing you receive such attaching a copy of • If any of your income and submitted along • Residence Description • Number in Household: • If unemployed, state I authorize the City of Dubuque for purposes of my qualifying hereby certify that the above understand that false statements above, please complete copy of the latest Federal -2 forms. is required, please attach as SOCIAL SECURITY, a statement from the source is through Social Security, with this application OR (check one): Single Family Under Age 18 Between this section and the "Participant Income income tax statement as submitted to the IRS. note stating so and show all sources of income PENSION, INTEREST, CHILD SUPPORT, etc. of income for verification. the attached release form must be completed a copy of the SSA -1099. Rental: (# of units) 18 & 65 — Over _ 65 _ source of income: to contact my employer, or source of income, in order to verify my income for the financial assistance for the Inflow and Infiltration Reduction Program information is true and correct, and that I reside at the location indicated, and or information are grounds for denial of the assistance Signature of Property Owner Home Phone Social Security # Work Phone Signature of Property Owner Home Phone Social Security # Work Phone Unusual circumstance information: Page 2 of 4 PARTICIPANT INCOME VERIFICATION FORM CITY OF DUBUQUE, IOWA The U.S. Department of Housing and Community Development (HUD) requires the following information be collected for using this service. This information is confidential and for reporting purposes only. If you have any questions regarding this form, please contact the Housing and Community Development Department at (563) 589 -4239. 1 Please CIRCLE BELOW THE NUMBER OF RELATED PEOPLE LIVING IN YOUR HOUSEHOLD, UNDER FADHLY SIZE. On that same line to the right of the number you circled, CIRCLE ONE of the four ranges that includes the AMOUNT OF YOUR COMBINED GROSS HOUSEHOLD INCOME (including yourself), as of the date signed below Family Size Extremely Low Income - 75% Assistance Very Low Income - 50% Assistance Low Income - 25 /o Assistance 25% Over Income 1 $0 - $13,400 $13,401- $22,300 $22.301- $35,700 Above $35,700 $0 - $15,300 $15,301 - $25,S00 $25.,01- $40,800 Above $40,800 3 $0 - $17,200 $17,201 - $28,700 $28,701- $45,900 Above $45,900 4 $0- $19,100 $19,101 - $31,850 $31,851- $50,950 Above $50,950 $0 - $20,650 $20,651 - $34,400 $34,401-$55,050 Above $55,050 6 $0 - $22,200 $22 201 - $36,950 $36,951- $59,150 Above $59,150 7 $0- $23,700 $23,701 -$39, 00 $39,501- $63,200 Above $63,200 8 or more $0 - $25,250 $25,250 - $42,050 $42.050- $67,300 Above $67,300 Are you Hispanic ? Yes ❑ No ❑ 3 What is the race of the person you are applying for (please check one)? ❑ White ❑ Asian & White ❑ Black/Afncan American ❑ Asian ❑ American Indian/Alaskan native ❑ Native Hawanan/Other Pacific Islander ❑ American Indian/Alaskan Native & White ❑ Black/Afncan American & White ❑ American Indian/Alaskan Native & Black/Afncan American ❑ Other Multi- Racial ❑ Asian/Pacific Islander ❑ Hispanic 4 Is the participant from a home where there is a female head of household? ❑ Yes ❑ No I certify that the information above is, to the best of my knowledge and belief, true, correct and complete as stated herein I am aware that the information being provided is subject to verification by the local or Federal government Print Name Signature Street Address City, State, Zip Code Telephone Number Date Warning: Whoever knowingly and willingly makes or uses a document or writing containing any false, fictitious or fraudulent statement or entry may be subject to federal prosecution Page 3 of 4 This Page For City Use Only Date of Inspection Reason for Violation ❑ Roof drain discharges to sanitary sewer ❑ Yard / area drain discharges to sanitary sewer ❑ Exterior stairway or driveway drain discharges to sanitary sewer ❑ Sump pit without pump ❑ Sump pump discharges to sanitary sewer ❑ Sump pump discharges to floor drain ❑ Sump pump discharges through flexible hose to exterior ❑ Seepage collection system (foundation drain) discharges to sanitary sewer ❑ Seepage collection system discharges to floor drain Total Repair Cost 50% Assistance Income -based assistance Total Assistance Amount. Application Approved Yes No Amount Approved $ Date Approved _ Page 4 of 4 THE CITY OF Dui E Masterpiece on the Mississippi July 15, 2011 Mr. Jim Brimmer Dubuque Community Schools 2300 Chaney Road Dubuque, IA 52001 -3095 Dear Mr. Brimmer: Engineering Department, I&I Program City Hall 50 W. 13th Street Dubuque, Iowa 52001 563.690.6113 www.cityofdubuque.org/ i&i The City of Dubuque is conducting an Inflow and Infiltration (I &I) Program to eliminate storm water inflow and groundwater infiltration into Dubuque's sanitary sewer collector system. Excessive I &I can cause sanitary sewer back -ups into basements, overflows into creeks and wetlands, and increased operating costs to process the water at the Dubuque Water Pollution Control Plant. The area surrounding and including Senior High School has been identified as a source of high sanitary sewer flows during rainfall events, which indicates excessive I &I. Over the past month, City inspectors have walked the Senior campus with your staff and used dye and smoke testing to observe flow directions of the sanitary and storm sewer pipes. The inspectors have observed: 1) Numerous roof drains that are improperly connected to the City's sanitary sewer system; 2) Numerous sanitary laterals in West Locust Street that are directed to the Senior campus but appear to be abandoned; and 3) Pavement and sidewalk cracks and joints that provide an indirect connection of rainfall into the sanitary system (infiltration). A work plan must be submitted to the City within 30 days of the date of this letter to investigate, identify, and recommend corrective actions for improper connections at the Senior High School and Transportation Center campuses. The investigation and identification tasks of the work plan shall be completed within 60 days of the date of this letter. The recommended corrective actions shall include an estimated completion date. The work plan shall be certified by a licensed engineer in the State of Iowa. Your help and cooperation in addressing these improper connections is greatly appreciated. If you have any questions regarding the work plan, please call me at (563) 690 -6034. Sincerely, te, Todd Shoemaker, PE, CFM Environmental Engineer Cc: Gus Psihoyos, City Engineer October 7, 2011 Mr. James C. Brimmer Manager of Buildings & Grounds Dubuque Community Schools 2300 Chaney Rd. Dubuque, IA 52001 -3095 Re: Report of Testing Results, Corrective Improvements and Future Recommendations I & I Evaluation at Senior High School IIW Project No: 11156-01 INTRODUCTION The City of Dubuque Engineering Department is conducting an Inflow and Infiltration (I & I) Program to eliminate storm water inflow and groundwater infiltration into Dubuque's sanitary sewer system. City officials were concerned that the Senior High School campus was the source of excessive inflow and infiltration present in the City's sanitary sewer collection system during rainfall events. At the request of the Dubuque Community School District, IIW formulated a plan to evaluate the impacts of inflow through cross - connections and infiltration through aged and/or broken sewers or manhole structures that originate on the Senior High School campus and contribute flow to the City of Dubuque's sanitary sewer system. The City of Dubuque had performed a limited amount of smoke and dye testing at the Senior High School campus initially to determine that there likely was some I & I issues that needed to be corrected. As a result of the City's preliminary evaluation, the City Engineering Department instructed the Dubuque Community School District to investigate, identify and recommend corrective actions for improper connections. TESTING PROCEDURE First, IIW conducted interviews of existing Dubuque Community School employees and City employees to obtain additional first hand observation information. Next, available Dubuque Community School and City of Dubuque documentation regarding plumbing as- builts, storm sewer system and sanitary sewer collection system plans and maps were reviewed to formulate a specific plan to investigate, dye test and monitor the existing sewer systems. The testing and investigation procedure began with three consecutive days of dye testing the roof drains of the buildings that comprise the Senior High School campus. The testing involved a coordinated effort between IIW, P.C., Dubuque Community School District's Building and Grounds staff and the City of Dubuque Engineering Department staff to monitor and report results of the testing. After analyzing the results of the dye testing, recommendations for televising and exploratory excavation were made to the Dubuque Community School District to specifically locate and delineate the corrective improvements that needed to be performed. IIW, P.C. www.iiwengr.com ARCHITECTURE CIVIL ENGINEERING CONSTRUCTION SERVICES ENVIRONMENTAL ENGINEERING LAND SURVEYING MUNICIPAL ENGINEERING STRUCTURAL ENGINEERING TRANSPORTATION ENGINEERING Dennis F. Waugh, PE /SE* Charles A. Cate, PE ** Gary D. Sejkora, PE Michael A. Jansen, PE/SE Ronald A. Balmer, PE/SE /AIA John M. Tranmer, PLS Timothy J. Tranel, PE* John F. Wandsnider, PE Julie P. Neebel, PE James P. Kaune, PE Thomas J. Oster, PLS ** Wray A. Childers, PLS Geoffry T. Blandin, PE Mark C. Jobgen, PE Lauren N. Ray, PE/SE* Bradley J. Mootz, PE/SE Cody T. Austin, PE* Marc D. Ruden, PE Mark R. Fassbinder, AIA* Michael A. Ruden, NCARB /AIA* Alice M. Ohrtmann, PE Craig J. Elskamp, AIA Robert W. Blok, PE Eric J. Helminiak, PE /SE* Steven J. Hunn, PE Jeff J. Brandt, PLS * LEED AP ** Retired 4155 Pennsylvania Avenue, Dubuque, IA 52002 -2628 • [P] 563.556.2464/800.556.4491 • [F] 563.556/811 ENGINEERS. ARCHITECTS. SURVEYORS. iiw Dubuque Senior High School I & I Report October 7, 2011 Page 2 of 6 The Dubuque Community School District was very proactive in their approach to correcting the deficiencies discovered over the course of the investigation. The televising recommended was immediately performed by a combination of School District and City resources. The televising was promptly reviewed and recommendations for exploratory excavation were provided to further determine the corrective actions that were suggested. The School District immediately hired a local contractor to make the recommended corrections as the evaluation was progressing. A more specific discussion of the investigation and testing results coupled with the corrective improvements performed are summarized in the following section. The Dubuque Community School District will provide a map to the City of Dubuque Engineering Department that indicates the locations of sanitary and storm sewers on the campus that were able to be determined through a combination of archived plan research and field investigation. The map also highlights the locations of the improper connections and subsequent corrective improvements. INVESTIGATION 1 TESTING RESULTS AND CORRECTIVE IMPROVEMENTS A. 1921 Main Building Dye testing was first conducted on roof drains of the Main Building of Senior High School that was constructed around 1921. This was chosen as a starting point due to the fact that the City found evidence through smoke testing that there was some sort of connection between the sanitary and the storm sewers that serve this building. The results of dye testing revealed that there was some minor cross - connection occurring in the vicinity of storm and sanitary manholes in the southwest quadrant of the Main Building courtyard. It was recommended to the School District that televising in conjunction with dye testing be conducted to determine if there was a direct cross - connection between the separate sanitary and storm sewer systems or if there was damaged pipes or separated joints causing the cross - connection by exfiltration from the storm sewer and infiltration into the sanitary sewer. The televising indicated that the cross - connection was through exfiltration and infiltration occurring between the storm and sanitary sewers due to broken and /or separated joints. The School District immediately hired a contractor to excavate the area around the storm and sanitary structures to further investigate the extent of corrective improvements needed. Upon investigation, IIW reported findings to the I & I Program staff from the City Engineering Department and recommended the replacement of damaged storm and sanitary sewer sections in the courtyard. The work was completed immediately while the trench remained open from the exploratory excavation. B. 1964 Addition to Main Building Dye testing was also conducted on roof drains of the 1964 Addition to the Main Building of Senior High School. The City found no evidence through smoke testing that there was connection between the sanitary and the storm sewers that serve this building but, in an effort to investigate thoroughly, testing of the roof drains was performed. The results of dye testing revealed that there was no cross - connection occurring between the sanitary and the storm sewers that serve this building. It was recommended to the School District that televising be conducted on the storm and sanitary sewers that cross beneath this building to determine their condition and better understand the piping configuration that serves the school. A review of the televising reports indicated that the plans for this building that the School District has on file generally agree with the actual configuration of the piping that was able to be confirmed in the field. Minor alterations to the schools under floor plans concerning the piping have been conveyed to school staff. Dubuque Senior High School I & I Report October 7, 2011 Page 3 of 6 C. 1952 Nora Gymnasium The next area where dye testing was conducted was the roof drains at the Nora Gymnasium. The building was constructed around 1952. The City found evidence through smoke testing that there was some sort of cross - connection between the sanitary and the storm sewers that serve this building. The results of dye testing revealed that there was some direct cross - connection between the storm and sanitary sewers that run parallel to each other outside the northwest wall of the gymnasium. More specifically, the roof drain located above the western most entrance to the gymnasium was directly connected to the sanitary sewer. It was recommended to the School District that televising in conjunction with further dye testing be conducted in the storm and sanitary sewers that serve the gymnasium to determine if there are more direct connections and to assess the condition of the sewers. A comparative analysis of the televising report to the original site plan for the gymnasium indicated that it was possible that the sanitary service connections serving the northwest restrooms, concession and drinking fountain facilities in the gymnasium were possibly directly connected to the storm sewer. Dye testing of the facilities confirmed the televising reports. The School District immediately closed all facilities that were improperly connected to the storm sewer until repairs could be made and instructed the contractor they hired to excavate the area along the northwest wall of the gymnasium to further investigate the extents of corrective improvements needed. Upon investigation of the excavated service laterals and main sewers, IIW determined that corrective improvements could be made through reconfiguration of the sanitary service laterals to be routed directly into the sanitary sewer and the cross connected roof drain could also be rerouted to the storm sewer manhole adjacent to the cross - connection location, Additionally, all wye connections in the storm sewer that accepted sanitary flow were removed and repaired. All work was completed immediately while the trench remained open from the exploratory excavation. Subsequent to the findings along the northwest wall of the Nora Gymnasium, further investigation through dye testing of the locker room, restroom, laundry and drinking fountain facilities along the southeast side of the gymnasium were conducted. One apparent cross - connection was found to be occurring between the storm and sanitary sewer systems when the restroom facilities in the Nora Gym lobby were flushed with dye. Corrective improvements that were performed and the correlation of this issue to one discovered beneath the 1988 Addition to Senior High School is described in the following section. D. 1988 Addition Between Nora Gym and Tech Buildings Dye testing was conducted on roof drains of the 1988 Addition between Nora Gym and the Technical Buildings. The City had reportedly found some evidence through smoke testing that the western most roof drain may be connected to the sanitary sewer that serves the 1921 main building and the 1964 addition to the main building. The results of roof drain dye testing revealed that there was no cross - connection occurring between the sanitary and the storm sewers that serve this building. As the School District was conducting televising on the accessible main sanitary and storm sewers near the Nora Gym lobby restroom that was determined through dye testing to have a cross - connection occurring, the televising personnel conducted testing of the storm and sanitary sewers accessible that pass beneath the 1988 Addition. Televising reports indicated that the main VCP storm sewer that channels all of the storm flow that is collected from the Nora Gymnasium roof drains appeared to be 75% obstructed with a mass of concrete. The pipe was also broken at this location. The televising crew was able to provide a distance to the obstruction. The distance indicated that the mass of concrete was very near the location of a drilled concrete pier foundation for a structural column of the 1988 addition. Dubuque Senior High School I & I Report October 7, 2011 Page 4 of 6 The construction plans for the 1988 Addition had called for the clay storm sewer to be abandoned and rerouted away from the location of the dilled piers. The School District scheduled their Contractor to come perform exploratory excavation near the column after verifying with IIW's structural engineers that excavation adjacent to the drilled pier would not jeopardize the structural integrity of the supporting column. The exploratory excavation confirmed a suspicion that during the construction of the 1988 Addition the concrete piers were drilled through the storm sewer and the abandonment and relocation of the storm sewer was never performed. Once the exploratory trench was opened in the mechanical room of the 1988 Addition, the televising of the remainder of the storm sewer was conducted and it was determined that the remaining sewer was in good shape. IIW worked with the School District and the Contractor to develop a corrective improvement plan to construct a concrete structure at the pier that would allow storm water to flow unobstructed around the drilled concrete pier. The concrete structure was subsequently constructed. We believe that the obstruction that was created in the storm sewer at this location was a major cause of infiltration of storm water into the sanitary sewer in an upstream location near the south side of the Nora Gym lobby restroom. This realization came after performing exploratory excavation on the areas of the storm and sanitary sewer immediately upstream of the obstruction that were excavated to further delineate corrective improvements necessary to remedy the cross - connection occurring from the Nora Gym lobby restroom and to fix separated and cracked joints witnessed in reviewing the televising reports. Upon excavation we discovered multiple issues: 1. The sanitary service lateral from the restroom in the Nora Gym lobby was not connected to either the sanitary or storm sewer, the lateral discharged in the soil above the storm sewer. 2. The storm sewer had severe joint separation and some cracked joints. 3. The sanitary sewer had two open wyes adjacent to the location where the storm sewer had the joint separation. (The sanitary sewer and the storm sewer run parallel and in opposite directions to each other approximately 5 feet apart at this location.) The obstruction under the 1988 Addition coupled with the above issues immediately upstream of the obstruction combine to be a very likely source of extensive storm sewer inflow into the sanitary system during substantial rainfall events that likely would cause surcharging in the storm sewer to exfiltrate from the separated joints and inflow into the open wyes of the sanitary sewer located adjacent to the storm sewer. The School District eliminated the separated joints in the storm sewer through replacement of the sewer in the affected areas, eliminated the open wyes in the sanitary sewer, and replaced the sanitary service lateral from the Nora Gym lobby restroom from the building to the sanitary main and properly connected the lateral to the sanitary sewer. E. 1952 Technical Building Dye testing was conducted on roof drains of the 1952 Technical Building of Senior High School. The City found no evidence through smoke testing that there was connection between the sanitary and the storm sewers that serve this building but to investigate thoroughly testing of the roof drains was performed. The results of dye testing revealed that there was no cross- connection occurring between the sanitary and the storm sewers that serve this building. It was recommended to the School District that televising be conducted on the accessible main storm sewer that crosses beneath this building to determine its condition and better understand the piping configuration that serves the school. A review of the televising reports indicated that the plans for this building that the School District has on file generally agree with the actual configuration of the piping that was able to be confirmed in the field. Dubuque Senior High School I &I Report October 7, 2011 Page 5 of 6 F. 1921 Technical Building Finally, dye testing was also conducted on roof drains of the 1921 Technical Building of Senior High School. The City found no evidence through smoke testing that there was connection between the sanitary and the storm sewers that serve this building but to investigate thoroughly, testing of the roof drains and the restroom facilities in the basement was performed. The results of the dye testing revealed that there was no cross - connection occurring between the sanitary and the storm sewers that serve this building. G. Storm and Sanitary Structures on Campus Outside of Buildings The storm and sanitary sewer structures south of the campus generally serve to convey storm and sanitary sewer flow from the campus to the respective storm and sanitary sewer systems of the City of Dubuque. Visual inspection of manholes and inlets coupled with televising was performed on accessible storm and sanitary sewer structures that are located to the south of the buildings that comprise the Senior High School campus. The campus manhole and inlet structures were also monitored during the dye testing operations performed in order to help determine the presence of cross - connections and to confirm the understanding of how the system is connected. The investigative testing procedures conducted did not reveal any cross - connections between the sanitary and storm sewers that convey wastewater and storm water from the buildings that comprise the Senior High School campus to the City of Dubuque sewer systems. TOTAL COST OF CORRECTIVE IMPROVEMENTS The total cost of the corrective improvements to date including the engineering investigation, televising and corrective repair work performed by the Dubuque Community School District's contractor is approximately $90,000. RECOMMENDATIONS FOR FUTURE IMPROVEMENTS The Dubuque Community School District was very proactive in terms of immediately addressing and fixing identified issues with inflow and infiltration occurring between the storm and sanitary sewer systems that serve the Dubuque Senior High School campus. During the investigation that took place as a part of this evaluation it was revealed that the storm sewers and structures that convey storm water from the 1921 Main Building and the 1964 Addition are in very bad condition and are also likely undersized. We do not believe this situation contributes to any cross - connection of the sanitary and storm sewer systems, but it is an issue that should be corrected as the School District has historically had issues with soil erosion on the hillside adjacent to the right field fence of the softball diamond likely associated with storm structures surcharging during heavy rain events. The School District is currently in the process of designing improvements to Dalzell field. It is our understanding that some of these improvements will extend into the area to the west of Dalzell field adjacent to and including a portion of the softball field. It is our recommendation that the School District takes this opportunity to include upgrades to the storm sewer system that conveys flow through this area as part of the Dalzell field project. IIW, P.C. would be pleased to provide engineering services to perform hydraulic analysis and design services in regard to the recommended improvements. Dubuque Senior High School I & I Report October 7, 2011 Page 6 of 6 ATTACHMENTS Attached are hard copies of the televising reports from the Dubuque Community School District's contracted televising company and also the reports from the City of Dubuque's televising crew. Also attached is a map prepared by the Dubuque Community School District that highlights the corrective improvements described in this report and shows how the storm and sanitary sewers are configured on the campus to the extent that we were able to discover through the investigations of this evaluation. �ottiluuunii� P�FeSS /.0,1, �', hereby direct personal engineering nand hattl am a duly licensed en ede or . 4:: . ,� t. 4" MARC D. .0 z: RUDEN • z .. Professional Engineer under the laws of the State of Iowa, FOR IIW, P.C. 3 �m ; v .. 19249 ; to .. i -b 4: ?Lz--t—■ gt/<___-- /4/7/// ,,,�� Marc D. Ruden, P.E. Date „ ►l ►0►1111�1„��0 License Number 19249 My license renewal date is December 31, 2012 SEAL Pages or sheets covered by this seal: Entire Report P: 1111156\156- 011Project Admin\Dubuque Senior 1 & 1 Report 10- 7- 2011.doc Masterpiece on the Mississippi December 8, 2011 Mr Bill Burkhart Dubuque Community Schools 2300 Chaney Road Dubuque, IA 52001 -3095 Dear Mr Burkhart Engineering Department, I &I Program City Hall 50 W 13th Street Dubuque, Iowa 52001 563 690 6113 www cityofdubuque org /i&i The purpose of this letter is to follow -up on the smoke testing conducted at Senior High School on November 1, 2011 The City conducted smoke testing to verify that all improper connections of stromwater into the sanitary sewer system had been completed correctly Unfortunately, City and school district staff continued to observe smoke from roof drains, around two manholes, and from pavement cracks Please submit a work plan to the City within 30 days of the date of this letter to investigate, identify, and recommend corrective actions for improper connections to the sanitary sewer at Senior High School If additional investigation and identification tasks are necessary, they shall be completed by Apnl 30, 2012 The corrective actions shall be completed by June 30, 2012 The work plan shall be certified by an engineer licensed in the State of Iowa Your help and cooperation in addressing these improper connections is greatly appreciated If you have any questions regarding the work plan, please call me at (563) 690 -6034 Sincerely, Todd Shoemaker, PE, CFM Environmental Engineer Cc Gus Psihoyos, City Engineer