Consent Decree Semi Annual Report_March 2012Masterpiece on the Mississippi TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager SUBJECT: Consent Decree Semiannual Report DATE: March 12, 2012 Dubuque bierd All-America City 1 2007 City Engineer Gus Psihoyos is submitting the EPA Consent Decree March 5, 2012, Semiannual Report. Michael C. Van Milligen MCVM:sv Attachment cc: Barry Lindahl, City Attorney Cindy Steinhauser, Assistant City Manager Gus Psihoyos, City Engineer THE CITY OF Dui Masterpiece on the Mississippi TO Mike Van Milligen, City Manager FROM Gus Psihoyos, City Engineer DATE March8,2012 SUBJECT Consent Decree Semiannual Report Dubuque band All- America City 'I 1 1 I' 2007 INTRODUCTION The purpose of this memo is to seek approval to submit the March 5, 2012 Semiannual Reportto the agencies stated in the Consent Decree BACKGROUND The City of Dubuque, Iowa is under a Consent Decree according to Case 2 11- cv- 01001 -EJM, United States of America and the State of Iowa v the City of Dubuque, IA [N D Iowa), Civil Action Number 2008V00041, DOJ Case Number 90 -5 -1 -1 -09339 effective June 27, 2011 The purpose of this report is to satisfy Section VIII, Paragraph 25 of the Consent Decree, which requires the City to submit a semiannual report by March 31, 2012 DISCUSSION The purpose of this semiannual report is to satisfy Section VIII, Paragraph 25 of the Consent Decree Paragraph 25 requires the City to submit semiannual reports by March 31 and September 30 after the Effective Date (June 27, 2011) The report includes summary information regarding events and activities performed in the prior six months Therefore, the "reporting period" refers to the time between September 1, 2011 and including February 29, 2012 RECOMMENDATION I recommend that the City Council authorize the City Managerto certify the March 5, 2012 Semiannual Report PROJECT COST- BUDGET IMPACT The recommended actions do not impact the City's budget ACTION TO BE TAKEN I request authorization for the Engineering Department to submit the March 5, 2012 Semiannual Report to the agencies stated in the Consent Decree Prepared by Todd Shoemaker, Environmental Engineer cc Barry Lindahl, City Attorney Don Vogt, Public Works Director John Klostermann, Street &Sewer Maintenance Supervisor Jonathan Brown, Water Plant Manager Steve Brown, Project Manager Deron Muehring, Civil Engineer Todd Shoemaker, Environmental Engineer Prepared for: UNITED STATES ENVIRONMENTAL PROTECTION AGENCY, UNITED STATES DEPARTMENT OF JUSTICE AND IOWA DEPARTMENT OF NATURAL RESOURCES Prepared by: CITY OF DUBUQUE, IA 50 W 13th Street Dubuque, IA 52001 Consent Decree Semiannual Report March 31, 2012 Consent Decree No. 2:11 -cv- 01011 -EJM March 5, 2012 Table of Contents 1.0 CERTIFICATION 1 -1 2.0 INTRODUCTION 2 -1 2.1 Background 2 -1 2.2 Purpose 2 -1 2.3 Report Summary 2 -1 3.0 SANITARY SEWER OVERFLOWS 3 -1 3.1 Sanitary Sewer Overflow Record 3 -1 3.2 SSO's Effect on Public Health and Water Quality 3 -1 3.3 Measures Enacted to Minimize Duration and Impact 3 -1 3.4 Measures Enacted to Stop the Overflow Event 3 -1 3.5 Measures Enacted to Prevent Another Recurrance 3 -1 3.6 Capturing Key Way Overflows 3 -1 3.7 Warning Sign Postings 3 -3 4.0 WATER & RESOURCE RECOVERY CENTER CONSTRUCTION UPGRADE. 4 -1 4.1 Project Planning 4 -1 4.2 Current Project Status 4 -1 4.3 Biosolid Accumulation Prevention at the W &RRC 4 -2 5.0 NATIONAL POLLUTANT DISCHARGE ELIMINATION SYSTEM (NPDES) 5 -1 5.1 Summary of all NPDES Permit Requirement Information 5 -1 5.2 NPDES Violations at the WRRC During The Reporting Period 5 -1 5.2.1 NPDES Violation(s) Log 5 -1 5.2.2 Cause of NPDES Violations 5 -1 6.0 INFLOW & INFILTRATION REDUCTION PROGRAM 6 -1 6.1 Background 6 -1 6.2 Flow Metering 6 -1 6.3 Source Investigations 6 -1 6.3.1 Private Property Inspections 6 -1 6.3.2 Dye Testing 6 -2 6.3.3 Smoke Testing 6 -2 6.3.4 Manholes 6 -3 6.3.5 Sanitary Sewer 6 -3 6.4 Corrective Action Plan 6 -3 6.5 Implementation of Corrective Action Plan 6 -3 i 7.0 CMOM UPDATE 7 -1 7.1 The Clv1Olv1 Program 7 -1 7.2 C1v1O1v1Implementation 7 -1 8.0 ASSESSMENTS AND ENGINEERING ANALYSES 8 -1 9.0 OTHER RELATED ACTIVITIES 9 -1 TABLES Table 2 -1. Organization of information required by the Consent Decree. 2 -2 Table 3 -1. Sanitary sewer overflows during the reporting period. 3 -2 Table 3 -2. Warning sign posting locations. 3 -3 Table 4 -1. Significant deadlines for the Water & Resource Recovery Center. 4 -1 Table 5 -1. Monthly operating reports submitted during the reporting period. 5 -1 FIGURES Figure 6 -1. Map of priority sewersheds for I &I investigation 6 -2 APPENDICES Appendix A: Proposed Sewershed 7. 5. and 10 Flow Meter Locations ii 1.0 Certification I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gather and evaluate the information submitted. Based on my directions and my inquiry of the person or person who manage the system, or those persons directly responsible for gathering the information, the information submitted is, to the best of my knowledge and belief, true, accurate, and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violations. Michael C. Van Milligen City Manager 2.0 Introduction 2.1 BACKGROUND The City of Dubuque, Iowa is under a Consent Decree according to Case 2:11 -cv- 01001 -EJM, United States of America and the State of Iowa v. the City of Dubuque, IA (N.D. Iowa), Civil Action Number 2008V00041, DOJ Case Number 90- 5 -1 -1- 09339. The Consent Decree became effective on June 27, 2011 and requires the City to submit semiannual reports to the Department of Justice (DOJ), Environmental Protection Agency (EPA) and Iowa Department of Natural Resources (DNR). 2.2 PURPOSE The purpose of this report is to satisfy Section VIII, Paragraph 25 of the Consent Decree. Paragraph 25 requires the City to submit semiannual reports on March 31 and September 30 after the Effective Date (June 27, 2011). The report includes summary information regarding events and activities performed in the prior six months. Therefore, the "reporting period" shall refer to the time between September 1, 2011 and February 29, 2012. 2.3 REPORT SUMMARY Paragraph 25 of the Consent Decree requires the semiannual reports to include specific information as well as a summary of the status and progress of all projects and programs required by Sections V and VI of the Consent Decree. Table 2 -1 lists how the required information is organized in this report. Table 2 -1. Orsanization of information required by the Consent Decree. Consent Decree Paragraph Summary of Requirement Report Section 25(a)i Sanitary Sewer Overflow (SSO) locations 3.1 25(a)ii SSO duration of flows Table 3 -1 25(a)iii SSO estimated flow volume Table 3 -1 25(a)iv Waterbody downstream of SSO Table 3 -1 25(a)v Suspected cause of SSO Table 3 -1 25(a)vi SSO effect on public health and water quality 3.2 25(a)vii Measures to minimize SSO 3.3 25(a)viii 'Measures to stop SSO 3.4 25(a)ix Measures to prevent recurrence of SSO and milestones 3.5 25(b)i Construction upgrades 4.0 25(b)ii NPDES permit summary 5.1 25(b)iii NPDES permit violations during reporting period 5.2 8 Assessments and engineering analyses 8.0 9 Disposal ofbiosolids at WPCP 4.3 10(a) Capture of overflow from Key Way Drive manhole 3.6 10(b) Posting of warning signs at SSO locations 3.7 11 Construction upgrade to WPCP 4.2 12(a) North Fork Catfish Creek interceptor placed into service Reported in 9/30/11 Semiannual Report 12(b) I &I flow metering 6.2 12(e) Flow meters installed in first sewershed during 2010 Reported in 9/30/11 Semiannual Report 12(d) I &I source identification 6.3 12(e) I &I corrective action plan 6.4 12(f) Implement I &I corrective actions 6.5 13(a) Collection System Management. Operation, and 'Maintenance plan (CMOM) 7.0 13(b) Implement CMOM 7.2 14 Certify legal authority Completed upon signing of Consent Decree 15 Certify that Section V of Consent Decree has been completed and placed into service To be completed by June 30. 2016 16 Demonstrate all SSO and by- passes have been eliminated To be completed by June 30. 2017 17 If SSO or by -pass occurs, submit Remedial Plan and Schedule Only applicable after June 30, 2017 18 If SSO or by -pass occurs due to O &M, submit Remedial Plan and Schedule Only applicable after June 30, 2017 2 -2 3.0 Sanitary Sewer Overflows 3.1 SANITARY SEWER OVERFLOW RECORD Eleven (11) sanitary sewer overflows (SSO, Table 3 -1) occurred in the City of Dubuque during the reporting period. 3.2 SSO'S EFFECT ON PUBLIC HEALTH AND WATER QUALITY No effects on public health were reported. Visual inspection at the downstream waterbody (prior to discharge to the Mississippi River) showed no sign of putrescent, unsightly or harmful bottom deposits; oil, scum and floating debris; unsightly color or turbidity; or offensive odors. 3.3 MEASURES ENACTED TO MINIMIZE DURATION AND IMPACT The City minimized the duration and impact of the SSOs by capturing untreated wastewater and transporting it to the Water and Resources Recovery Center or by setting up a pump and re- routing the flow to a downstream sanitary sewer manhole. 3.4 MEASURES ENACTED TO STOP THE OVERFLOW EVENT For S SO's #3 and #4, the City shut off the lift station pumps and untreated wastewater was transported to the Water & Resources Recovery Center by tankers. Other overflows were stopped by removing the blockage or by setting up a pump and re- routing the flow to a downstream sanitary sewer manhole. 3.5 MEASURES ENACTED TO PREVENT ANOTHER RECURRANCE Increased maintenance will be performed on lines where debris was the cause of the blockage. Increased maintenance along with chemical root foaming will be used on the lines where roots were the cause of the blockage. Following the CMOM, the City continues to implement the Fats, Oils, and Grease (FOG) ordinance to prevent grease- related overflows. 3.6 CAPTURING KEY WAY OVERFLOWS Paragraph 10 of the Consent Decree requires the City to capture all overflows from the manhole located on Key Way Drive between 3500 Keymer Drive and 3507 Keystone Drive. An SSO did not occur at this location during the reporting period, so it was not necessary to capture any overflows. Table 3 -1. Sanitary sewer overflows during the reporting period. SSO # Sewer- shed Street Address Start Date End Date Start Time End Time Overflow Volume Downstream Waterbodv Suspected Cause(s) 1 7 644 Lowell Street 9/19/11 9/19/11 11:00 a.m 11:10 a.m. 25 Mississippi River Defect in the pipe 2 15 Mar Jo Hills Rd Discover Date 9/26/12 9/26/11 Unknown 4:00 p.m. 100 Catfish Creek Bank failure due to heavy rain event on 7/28/2011 3 20 925 Kerper Blvd 10/4/11 10/4/11 10:30 a.m. 11:15 a.m. 1,000 Mississippi River Force Main Break 4 20 509 E 7th St 10/4/11 10/4/11 10:30 a.m. 11:15 a.m. 1,000 Mississippi River Force Main Break 5 14 2700 Dodge St Discover Date 12/9/11 12/9/11 Unknown 5:00 p.m. 200 Catfish Creek Grease 6 8 1855 Greyhound Park Road 1/25/12 1/25/12 2:00 p.m. 3:00 p.m. 200 Mississippi River Grease 7 14 290 Bradley Street on Henderson Street 2/4/12 2/4/12 10:00 a.m. 10:30 a.m. 100 Mississippi River Force Main Break 8 20 820 Mt Loretta Avenue Discover Date 2/14/12 2/14/12 Unknown 3:00 p.m. 50 Mississippi River 9* 8 2460 Lincoln Avenue 1/10/12 1/10/12 8:00 p.m. 10:00 p.m. 20 N/A Roots 10* 10 1990 Amelia Drive 1/21/12 1/21/12 2:15 p.m. 3:00 p.m. 20 N/A Debris 11* 1 3274 Kensington Place g 1/31/12 1/31/12 5:45 p.m. 6:00 p.m. 5 N/A Valve closed by mistake * Basement backup 3 -2 3.7 WARNING SIGN POSTINGS Paragraph 10 of the Consent Decree requires that the City post a warning sign at all SSO sites for at least 6 months after completion of the site cleanup. unless IDNR decides that the sign may be posted for a shorter period of time or not at all. Table 3 -2 lists the current locations where signs are posted. (Postings are not required for basement backups.) Table 3 -2. Warning sign posting locations. SSO # Location Description 1 644 Lowell Street Along north curb 2 Mar Jo Hills Road Under the highway overpass along Mar Jo Hills Road 3 925 Kerper Boulevard Along 9th and 11th Streets and at the storm sewer outlet at 12th Street 4 509 E 7th Street At the 8th Street storm sewer outlet 5 2700 Dodge Street At the manhole edge of parking lot 6 1855 Greyhound Park Road At storm sewer outlet along Greyhound Park Road 7 290 Bradley Street On Henderson Street at Bradley Street 8 820 Nil. Loretta Avenue At manhole between Mt. Loretta and Southern Avenues 3 -3 4.0 Water & Resource Recovery Center Construction Upgrade 4.1 PROJECT PLANNING During its Fiscal Year 2006 goal setting process, the City Council listed the Water Pollution Control Plant (WPCP) as one of its high priorities. City staff subsequently applied for a State Revolving Fund (SRF) planning and design loan during the summer of 2006, and plant upgrades were placed on the DNR Intended Use Plan schedule. Following public hearings and bidding requirements, the Facility Plan was developed and approved by DNR. The facility's name was also changed to the Water & Resource Recovery Center (W &RRC). In October 2008, the team of Strand Associates /IIW Engineers was approved by the City Council to proceed with the design of the W &RRC upgrades. The NPDES permit was issued by DNR staff on April 1, 2010, and the plant construction permit was signed by DNR staff on April 5, 2010. Following public bidding requirements, the City Council approved a contract, and the notice to proceed was issued August 19, 2010. Table Table 4 -1 lists significant deadlines for the project. Table 4 -1. Sienificant deadlines for the Water & Resource Recovery Center. Deadline Target Date Digester Startup 8/24/2012 Excess Flow Equalization 6/20/2012 Sludge Processing Startup 12/12/2012 Aeration Tank Completion 6/04/2013 Final Clarifiers 8/15/2013 Substantial Completion 9/9/2013 Final Completion 2/14/2014 4.2 CURRENT PROJECT STATUS On July 11, 2011 at approximately 6:10 A.M., a thunderstorm with winds of approximately 74 mph caused damage to two of the four digesters under construction. On July 28, 2011, the City received more than 14 inches of rain in approximately twelve hours which caused considerable damage to the W &RRC construction site. The damage caused by each event and the City's response were documented in separate reports to the EPA, DOJ, and DNR dated July 15, 2011 and August 4, 2011. The City had estimated a project delay of approximately three to four months beyond the final 4 -1 completion date given of October 1, 2013. The City has since granted a 120 working day extension to the two major milestones of digester startup and sludge processing startup. The City and its general contractor are working out details of a revised project completion schedule required by the weather related delays. Factoring in the delays, the City will still meet the startup deadline (April 26. 2014) as prescribed in the Consent Decree barring any further major uncontrollable delays. Through February 29. 2012, the project is in its 18th month of constriction and work has been started on all aspects of the project. At this point. City staff estimates the project is close to 50 °0 complete with an expenditure of approximately $31.000.000 to date. The ultraviolet disinfection system was started in March 2011 and continues to be operational. Work continues on the digesters and sludge processing complex. The construction of the fourth primary clarifier concrete work is completed with the mechanisms beginning to be installed. The reconstruction of primary clarifier number 1 is complete with a few minor mechanical details to finish prior to starting the clarifier. When this clarifier is on -line, work will begin on the reconstruction of the remaining clarifiers. A minimum of two clarifiers will remain in service during construction. In addition to the digester structures, work is progressing on the piping associated with the digester operation along with the installation of the many pumps and motors required for the process. A bio- solids handling contract has been negotiated with Nutri -Ject Systems of Hudson. Iowa and will be on the March 19, 2012 City Council agenda for approval. The laboratory addition of the Administration /Laboratory Building is now estimated to be completed in early to mid -April 2012. Upon completion of the laboratory addition, the existing building will be totally renovated and placed into service. The Administration /Laboratory Building will be a highly energy efficient building using plant effluent to meet heating and cooling needs. The entire structure is highly insulated and will use a minimum of energy for lighting, heating and cooling. -4.3 BIOSOLID ACCUMIULATION PREVENTION AT THE W &RRC The City operates the north incinerator and one of two centrifuges to maintain proper sludge blanket levels in the final clarifiers. In the event that the north incinerator must be shut down for longer than one week, the City would continue to operate the centrifuges and dispose of the sludge at the Dubuque Area Metropolitan Sanitary Landfill. Based on past history, a worst -case complete shutdown, repair and startup of the incinerator can take place in four to six weeks. The supplier of new centrifuges for the plant upgrade is the same firm that has performed major maintenance on the existing centrifuges. This firm has informed W &RRC staff that they would be available to assist should one or both of the operating centrifuges have a major breakdown. At the point one of the centrifuges needs to be removed to proceed with that phase of construction, all critical parts from the removed centrifuge will remain on the site in order to facilitate a rapid repair of the existing centrifuge and return the plant to full operating conditions. Storage space for sludge will remain a challenge until portions of the new plant are brought online. When sections of the reconstructed plant are brought into service, the City will be able to use these areas to assist in W &RRC sludge management. 4 -2 5.0 National Pollutant Discharge Elimination System (NPDES) 5.1 SUMMARY OF ALL NPDES PERMIT REQUIREMENT INFORMATION NPDES Monthly Operating Reports (MOR) for the City of Dubuque W &RRC were submitted to IDNR on the dates listed in Table 5 -1: Table 5 -1. Monthly oneratin6 reports submitted durin the renortin6 period. Report Date Submitted August 2011 9/12/2011 September 2011 10/10/2011 October 2011 11/14/2011 November 2011 12/14/2011 December 2011 1/12/2012 January 2012 2/13/2012 February 2012 To be submitted approximately 3/6/2012 5.2 NPDES VIOLATIONS AT THE WRRC DURING THE REPORTING PERIOD 5.2.1 NPDES Violation(s) Log The City of Dubuque W &RRC had no permit violations during the reporting period. 5.2.2 Cause of NPDES Violations There were no NPDES violations for the reporting period. 6.0 Inflow & Infiltration Reduction Program 6.1 BACKGROUND Prior to the Consent Decree date of lodging, the City experienced several discharges of untreated or partially treated wastewater. These events were caused by sharp increases in flow within the sanitary sewer system during and immediately after a rainstorm. To better locate the sources of this issue, the City placed flow meters throughout the city. Depending on location, the meters measured the flow of water from each sewershed over a one to eleven month period of time. Five of the twelve sewersheds were identified as receiving elevated flows during and directly after a precipitation event. Under the Consent Decree, the City has agreed to investigate these five sewersheds before January 1, 2016. The section below describes the City's progress in identifying I &I sources in the five sewersheds (Figure 6 -1). 6.2 FLOW METERING The City conducted flow metering within Sewershed 12 during 2011. Preliminary flow metering results were reported in the September 30, 2011 Semiannual Report. Flow meter locations have been established for Sewersheds 7, 5, and 10 (Appendix A). 6.3 SOURCE INVESTIGATIONS 6.3.1 Private Property Inspections As of February 29, 2012, over 97% of all properties in Sewershed 11 and 69% of all properties in Sewershed 12 have been inspected. Private property inspections identify the roof drain discharge location, the presence of any stairwell or driveway drains, and the presence of a sump pit /pump on site. A passing inspection indicates no connections of clear water to the sanitary system. A failed inspection indicates a connection of clear water directly into the sanitary system, which may include roof drains connected to the sanitary sewer; a stairwell or driveway drain which is connected to the building floor drain; or a sump pump which is plumbed directly to the sanitary lateral or a floor drain within the building. Each improper connection observed during a private property inspection results in a failure notice. The property owner then has 30 days to correct the improper connection, at which point a re- inspection of the property conducted to verify that the improper connection has been eliminated. If the improper connection has not been corrected, the City may pursue legal action against the property owner to complete the necessary work. Inflow & Infiltration Progra Sanatary Sewersheds To Be Inspected rsl LOWELL Mf Figure 6-1. Map of priori sewersheds for I &I investigation. 6.3.2 Dye Testing Dye testing has been performed m conjunction with private property inspections If the discharge location of a downspout, exterior stairwell drain, or dnveway dram is unknown, the City will use dye to identify the discharge location(s) If the dye is found in the sanitary sewer, the property owner receives notice consistent with the private property inspection process described in Section 6 3 1 6.3.3 Smoke Testing The City conducted smoke testing in Sewersheds 12 and 20 during September and October 2011, respectively Although Sewershed 20 is not one of the priority sewersheds identified in the Consent Decree, City staff felt it was necessary to identify stormwater inflow that has been observed at a nearby wastewater pumpmg station The City expects to conduct additional smoke testmg in 2012 in Sewershed 7 and possibly Sewersheds 5 and 10 6 -2 6.3.4 manholes As discussed in the Sewershed 11 Corrective Action Plan, each sanitary manhole in Sewershed 11 has been opened and recorded as concrete or brick and rated based on its structural integrity in order to prioritize its improvement or replacement. A similar process will be completed for Sewershed 12 during 2012. 6.3.5 Sanitary Sewer Approximately 99 °o of the public sanitary sewer within Sewershed 11 has been inspected using a closed circuit television system. Any cracks, leaky joints, illegal lateral connections, and damaged or broken pipes have been recorded. The severity of the structural degradation of each pipe section will be rated based on severity. This rating system will be used to prioritize which pipe sections are in need of immediate improvement. 6.4 CORRECTIVE ACTION PLAN As stated in Paragraph 12 of the Consent Decree, the Sewershed 11 Corrective Action Plan was submitted prior to December 31, 2011. A similar report will be submitted by December 31, 2012 for Sewershed 12. 6.5 InMPLEnMENTATION OF CORRECTIVE ACTION PLAN The City is awaiting approval of the Sewershed 11 Corrective Action Plan submitted to EPA in December 2011. Due to schedule requirements, however, work has already begun where necessary. City staff continues to work with property owners to correct improper private connections. The City is preparing plans and specifications to improve brick manholes and sanitary sewer pipes. 6 -3 7.0 CMOM Update 7.1 THE CMOM PROGRAM The City of Dubuque's Capacity, Management, Operation and Maintenance Plan (CMOM) provides a summary of its policies, procedures, practices, and responsibilities associated with its sanitary sewer collection system. It is the blueprint for the City's managers and field workers to better manage, operate, and maintain Dubuque's sanitary sewer collection system, investigate capacity- constrained area, prevent SSOs, respond to SSOs that may occur, and plan for future system expansion. In compliance with the Consent Decree, the City submitted the CMOM to EPA, DOJ, and DNR on September 22, 2011. 7.2 CMOM IMPLEMENTATION As required by Paragraph 13 of the Consent Decree, the CMOM must be fully implemented within two calendar months after receiving formal approval by EPA. In actuality, the City continues to implement many of the provisions of CMOM because they were already in effect at time of CD. The City developed the CMOM to serve as a "living" document. As the City reviews its current procedures and codes, the CMOM will be updated and new procedures implemented as needed. Any revisions to the CMOM will be submitted to EPA, DOJ, and DNR for review and approval as required under the Consent Decree. 8.0 Assessments and Engineering Analyses The City's engineering department, public works department and W &RRC staff continue to evaluate and analyze the sewer collection system and W &RRC to ensure compliance with all legal requirements. However, no specific study was undertaken during the reporting period. 9.0 Other Related Activities • Submitted semiannual report on September 21, 2011. Awaiting approval by EPA. • Submitted CMOM on September 22, 2011. Awaiting approval from EPA. • Submitted Supplemental Engineering Project (SEP) Work Plan on September 26, 2011. Awaiting approval by EPA. • Submitted Sewershed 11 Corrective Action Plan on December 21, 2011. Awaiting approval by EPA. • At request of Department of Justice (email dated October 3, 2011), removed Mr. Benjamin Fisherow from the list of persons to receive email notice regarding Force Majeure events. • Noted new address of Kate Loyd, Department of Justice is 999 18h Street, Suite 370 Denver, CO 80203 -2413 Annendix A Proposed Sewershed 7, 5, and 10 Flow Meter Locations Sewonhed 7 Subwatershed E)en aeon W o,I` ,S qv DTs 5 Teti O4 /' 'ks, W 28 T4 ST is �BUE A VIS7 ST BERKLEY PL 0 �W 0 .y� Fir 0 FAIRWAY DR SEWARD c h c m Q A O PUTNAM ST 7 -3 m t. o v m in C % r m NA �% u) , 2 pIZ It 0' � LL It IL Q Ca T MER EAGLE S 7 -2 ov v . 00r. ST G OP 'S DIAGONAL ST ‹� 1�G 02 1- t.s� Qv P fig'( 3R Co In NAPIER ST 7 -1 CLARKE DR Q eLLi~VV -cn I r 1R O: 4 1S NOOOOOH ALMOND ST W LOCUST ST n d) V Legend SEWKRSHFD ID 7 -1 7 -2 7 -3 7 -4 METER LOCATION S ewers l� l d b : 8 u Jvvat ARROWWVOD LN DERBY GRANGE RD _ 0 r r z z i Z fy` BARONY DR N HQ NHOr M3 - W J U J w BITTERSWEET LN 5 -2 OR�T0� oR pV 5 -5 DAVID i= m r SUNSET PARK RAVEN OAKS DR 1 - - - f \ ( °o MEGGAN ST ti -4 r -1 lcd TIFFANY CT ARBOR HILLS DR GI' HUNTINGTON SPRING VALLEY RD m 0 5 -1 CASTLE WOODS LN 0'4KV/Ew CT WALLER ST MARYWOOD DR U w LfSA CT m b i FOOTHILL, RD FOOTHILLI }CT 0 W KAREN ST ce Z 0) ct q ..V ,_2 '� U r Z. O = KATRINA CIR KANE CT r WESTMORE DR L/NDALE ST KAUFMANN AVE c LORI ST �SaRaH STST i _ CORTEZ o -4 MA DERA ST 4 KANE ST 3 AI-TURA DR DCERRO DR RENAISSANCE DR \AIRWAY DR R k co e Z or( k 2 N =1 r Legend SEUUERSFILD ID 5 -1 5 -2 5 -3 5 -4 5 -5 METER LOCATION • Sewershed C)❑ bwa r r� e ��� NHS V1P �� OLYMPIC HTS ROYER KANE ST '-\ ��om z -1 Oq F tu co '���s' y�O�P 5 0 >. P. P� , ` S� KEOKUK C T + ,c,' � p p5 BERKLEY PL Q Pa 3\14 PEE \ SWAN DR I J FLAMINGO DR to � m v« -p G) ' �tf m o .p LANCHE AVE RIDGEWAY AVE o s1 o`P�,o e�5� 5� � p tro- \i.. � co co 44 OW 10 -3 aTH ST/ PUT$IAM a� I RKE r�' -- SEWARD MONT REST S'. WALKER ST 'EDITH ST O'NEILL ST LIBERTY AVE op G2 i)Si- 055 5 LINK ST rON • RIDGk' HOGREFE ST DAVIS ST BURDEN ST 021 NVOY?I3HS NAPIER ST 10 -2 5�.0 IS VIVA VN3179 CLINTON ST i1' 3 ®HENN ST �`L vpo E }IN 3 W 210SON1M 10 -4 5'i S.A 0 �cn R►ES ST r 10 -1 4 MEiI4 OR ti 1- a BARRY ST LUCREITIA ST JANSEN T JUSTIN LN 10 -5 GREYHOUND PARK RD /rg0F� gNN4L s SREEH DR i Legend SEWERSHED ID 10 -5 10 -4 10 -3 10 -2 10 -1 10 METER LOCATION •