Dubuque Industrial Center South_Grading and Utilities 2012 ProjectMasterpiece on the Mississippi
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: Dubuque Industrial Center South
Grading & Utilities - 2012, Phase I
CIP 3602160 - Design, South Siegert Farm
DATE: March 23, 2012
Dubuque
bierd
All- America City
1
2007
City Engineer Gus Psihoyos and Economic Development Director Dave Heiar
recommend City Council approval of the plans, specifications, form of contract and the
estimated cost of $4,744,572 for the Dubuque Industrial Center South Grading and
Utilities — 2012 Project, Phase I.
In 1997, the City acquired approximately 175 acres of farmland known as the South
Siegert Farm. Until March 1, 2012, the property between Highway 20 and Seippel Road
was leased for agricultural purposes until there was an identified need for commercial/
industrial growth.
With more than 10 recent business expansions in the Dubuque Industrial Center West
(DICW), the City of Dubuque has seen unprecedented growth. In less than three years,
the City has sold over 125 acres. The City Council identified the Dubuque Industrial
Center Economic Development District (District) as a high priority for the City's future
commercial /industrial growth. On March 7, 2011, the City Council approved the
inclusion of the South Siegert Farm (Subarea E) within that District.
The Dubuque Industrial Center South — Grading /Expansion of South Siegert Farm will
be completed in phases based on budget and developmental needs. This project would
complete construction of DICW and DICS, which includes grading, road construction, a
bridge, utility extensions, and the development of a recreational area.
The Dubuque Industrial Center South Grading & Utilities — 2012 Project, Phase I
includes the grading of approximately 1,350,000 cubic yards of excavation. The project
includes:
— Temporary and permanent erosion control measures: Sediment basins; detention
basins; vegetated swales; seeding; inlet and outlet projection; and energy
dissipaters.
— Grading: Clearing and grubbing topsoil removal; stockpile and spreading; removal
of unsuitable material; subdrains; excavation; and embankment fill.
— Deconstruction and demolition: Removal of existing structures; well abandonment;
and septic system removal.
— Storm sewer: Approximately 600 lineal feet of storm sewer pipe.
— Sanitary sewer: 2,788 lineal feet of 8- and 12 -inch sanitary sewer pipe.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
Michael C. Van Milligen
MCVM:jh
Attachment
cc: Barry Lindahl, City Attorney
Cindy Steinhauser, Assistant City Manager
Gus Psihoyos, City Engineer
Dave Heiar, Economic Development Director
2
Masterpiece on the Mississippi
TO: Michael C. Van Milligen, City Manager
FROM: Gus Psihoyos, City Engineer
David Heiar, Economic Development Director
SUBJECT: Dubuque Industrial Center South
Grading & Utilities — 2012, Phase I
CIP 3602160 — Design, South Siegert Farm
DATE: March 23, 2012
INTRODUCTION
Dubuque
btrid
All- America City
I II
1
2007
The enclosed resolution is in reference to the public hearing for the Dubuque Industrial
Center South Grading & Utilities — 2012 Project, Phase I.
BACKGROUND
In 1997 the City acquired approximately 175 acres of farmland known as the South
Siegert Farm. Until March 1, 2012, the property between Highway 20 and Seippel Road
was leased for agricultural purposes until there was an identified need for commercial/
industrial growth.
With more than 10 recent business expansions in the Dubuque Industrial Center West
(DICW), the City of Dubuque has seen unprecedented growth. In less than three years,
the City has sold over 125 acres. The City Council identified the Dubuque Industrial
Center Economic Development District (District) as a high priority for the City's future
commercial /industrial growth. In March 7, 2011, the City Council approved (Resolution
87 -11) the inclusion of the South Siegert Farm (Subarea E) within that District.
The Dubuque Industrial Center South — Grading /Expansion of South Siegert Farm will
be completed in phases based on budget and developmental needs. This project would
complete construction of DICW and DICS which includes grading, road construction, a
bridge, utility extensions, and the development of a recreational area.
DISCUSSION
The Dubuque Industrial Center South Grading & Utilities — 2012 Project, Phase I
includes the grading of approximately 1,350,000 cubic yards of excavation. The project
includes:
— Temporary and permanent erosion control measures: Sediment basins; detention
basins; vegetated swales; seeding; inlet and outlet projection; and energy
dissipaters.
— Grading: Clearing and grubbing topsoil removal; stockpile and spreading; removal
of unsuitable material; subdrains; excavation; and embankment fill.
— Deconstruction and demolition: Removal of existing structures; well abandonment;
and septic system removal.
— Storm sewer: Approximately 600 lineal feet of storm sewer pipe.
— Sanitary sewer: 2,788 lineal feet of 8- and 12 -inch sanitary sewer pipe.
Since this project will be funded by a bond sale, the project's schedule has been revised
to reflect a June, 2012 bond completion:
Initiate Public Bidding Process
Publish Public Hearing Notice on Plans & Specifications
Public Hearing on Plans & Specifications
Publish Notice to Bidders, Advertise for Bids
Pre -Bid Conference
Receipt of Bid Proposals (Bid- Letting)
Award Construction Contract
Roadway Subgrade Areas Completed
Final Project Completion Date
March 19, 2012
March 23, 2012
April 2, 2012
April 6, 2012
April 24, 2012
May 10, 2012
June 4, 2012
July 1,2013
November 1, 2013
The project specifications provide for a $1,000 /day cost mutually agreed between the
City and contractor if the roadway subgrade areas are not completed by July 1, 2013,
and /or the total project is not completed by November 1, 2013.
The specifications also provide for an incentive of $1,000 per day for early completion of
the subgrading for the streets and /or the total project. The total incentive for the
completed project cannot exceed $50,000. The incentive for the street subgrading area
cannot exceed $25,000 of this total incentive available for the overall grading project.
RECOMMENDATION
I recommend that the City Council approve the plans, specifications, form of contract
and the estimated cost for the Dubuque Industrial Center South Grading & Utilities —
2012 Project, Phase I.
BUDGET IMPACT
The estimate of probable cost for Dubuque Industrial Center South Grading & Utilities —
2012 Project, Phase I is summarized as follows:
Estimate
Phase I: Construction Contract - Base $3,518,967
Phase I: Construction Contract - Alternates 405,080
Contingency 392,405
Consultant Services: Engineering Design, Administration & Inspection 428,120
Total Project Cost $4,744,572
The funding summary for the Dubuque Industrial Center South Project is as follows:
CIP No. Fund Description
3602160 General Obligation (GO) Bonds (TIF Abated)
Transfer from Unused Portion of North Siegert G.O. Bond Sale
Total Project Funding
Fund Amount
$4,585,004
1,000,000
$5,585,004
The maximum budget for the project is $5,585,004 including preliminary and final
design, environmental review and construction of public infrastructure (Phase II). The
estimate of probable cost of Phase I includes a 10% contingency and will also include
several alternate bid items to allow for flexibility when reviewing bid proposals to ensure
that the project remains within budget.
The initial CIP had shown $990,548 in funding coming from land sales. With the savings
from the North Siegert project, this funding source is not needed. Land sales revenue
can now be used for other purposes including the annual contribution to the Greater
Dubuque Development Corporation.
Budget Director Jenny Larson intends to initiate a bond sale to finance this project in
early April, with the actual award of a bond sale scheduled for the June 4 meeting.
ACTION TO BE TAKEN
The City Council is requested to approve the plans, specifications, form of contract and
the estimated cost for the Dubuque Industrial Center South Grading & Utilities — 2012
Project, Phase I.
Prepared by David Heiar, Economic Development Director
cc: Jenny Larson, Budget Director
Bob Green, Water Department Manager
Gus Psihoyos, City Engineer
Deron Muehring, Civil Engineer
Todd Irwin, Engineering Technician
RESOLUTION NO. 87 -12
APPROVAL OF PLANS, SPECIFICATIONS, FORM OF CONTRACT, AND
ESTIMATED COST FOR THE DUBUQUE INDUSTRIAL CENTER SOUTH GRADING
& UTILITIES - 2012 PROJECT, PHASE
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF DUBUQUE, IOWA:
That the proposed plans, specifications, form of contract and estimated cost for
the Dubuque Industrial Center South Grading & Utilities - 2012 Project, Phase I, in the
estimated amount $4,744,572, are hereby approved.
Passed, adopted and approved this 2nd day of Apr i 1 , 2012.
Attest:
Key',' S. Firnstahl, City Cler
oy D. Buol, Mayor
Masterpiece on the Mississippi
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: Dubuque Industrial Center South
Grading & Utilities -2012, Phase I
CIP 3602160- Design, South Siegert Farm
DATE: March 12, 2012
Dubuque
All America City
2007
Economic Development Director David Heiar and City Engineer Gus Psihoyos are
recommending setting a public hearing for April 2, 2012, and authorizing the public
bidding procedure for the Dubuque Industrial Center South Grading & Utilities — 2012
Project, Phase I.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
Priolf4
Michael C. Van Milligen
MCVM:sv
Attachment
cc: Barry Lindahl, City Attorney
Cindy Steinhauser, Assistant City Manager
Teri Goodmann, Assistant City Manager
Gus Psihoyos, City Engineer
David Heiar, Economic Development Director
Rick Dickinson, President & CEO Greater Dubuque Development Corporation
Masterpiece on the Mississippi
TO: Michael C. Van Milligen, City Manager
FROM: Gus Psihoyos, City Engineer
David Heiar, Economic Development Director
SUBJECT: Dubuque Industrial Center South
Grading & Utilities — 2012, Phase I
CIP 3602160 — Design, South Siegert Farm
DATE: March 15, 2012
INTRODUCTION
Dubuque
katil
*America City
1 ,
2007
The enclosed resolutions authorize the public bidding procedure for the Dubuque
Industrial Center South Grading & Utilities — 2012 Project, Phase I.
BACKGROUND
In 1997 the City acquired approximately 175 acres of farmland known as the South
Siegert Farm. Until March 1, 2012, the property between Highway 20 and Seippel Road
was leased for agricultural purposes until there was an identified need for commercial/
industrial growth.
With more than 10 recent business expansions in the Dubuque Industrial Center West
(DICW), the City of Dubuque has seen unprecedented growth. In less than three years,
the City has sold over 125 acres. The City Council identified the Dubuque Industrial
Center Economic Development District (District) as a high priority for the City's future
commercial /industrial growth. In March 7, 2011, the City Council approved (Resolution
87 -11) the inclusion of the South Siegert Farm (Subarea E) within that District.
The Dubuque Industrial Center West — Grading /Expansion of South Siegert Farm will be
completed in phases based on budget and developmental needs. This project would
complete construction of DICW and DICS which includes grading, road construction, a
bridge, utility extensions, and the development of a recreational area.
DISCUSSION
The Dubuque Industrial Center South Grading & Utilities — 2012 Project, Phase I
includes the grading of approximately 1,350,000 cubic yards of excavation. The project
includes:
— Temporary and permanent erosion control measures: Sediment basins; detention
basins; vegetated swales; seeding; inlet and outlet projection; and energy
dissipaters.
— Grading: Clearing and grubbing topsoil removal; stockpile and spreading; removal
of unsuitable material; subdrains; excavation; and embankment fill.
— Deconstruction and demolition: Removal of existing structures; well abandonment;
and septic system removal.
— Storm sewer: Approximately 600 lineal feet of storm sewer pipe.
— Sanitary sewer: 2,788 lineal feet of 8- and 12 -inch sanitary sewer pipe.
PROJECT SCHEDULE
The schedule for the Dubuque Industrial Center South Grading & Utilities — 2012
Project, Phase I is as follows:
Initiate Public Bidding Process
Publish Notice to Bidders, Advertise for Bids
Publish Public Hearing Notice on Plans & Specifications
Public Hearing on Plans & Specifications
Pre -Bid Conference
Receipt of Bid Proposals (Bid- Letting)
Award Construction Contract
Roadway Subgrade Areas Completed
Final Project Completion Date
March 19, 2012
March 23, 2012
March 23, 2012
April 2, 2012
April 17, 2012
May 1,2012
May 21, 2012
July 1,2013
November 1, 2013
The project specifications also provide for a $750 /day cost mutually agreed between the
City and contractor if the roadway subgrade areas are not completed by July 1, 2013,
and /or the total project is not complete by November 1, 2013.
The specifications also provide for an incentive of $1,000 per day for early completion of
the subgrading for the streets and /or the total project. The total incentive for the
completed project cannot exceed $50,000. The incentive for the street subgrading area
cannot exceed $25,000 of this total incentive available for the overall grading project.
RECOMMENDATION
It is recommended that the City Council establish the date of the public hearing and
authorize the City Clerk to advertise for proposals for the Dubuque Industrial Center
South Grading & Utilities — 2012 Project, Phase I.
BUDGET IMPACT
The estimate of probable cost for Dubuque Industrial Center South Grading & Utilities —
2012 Project, Phase I is summarized as follows:
Estimate
Phase I: Construction Contract - Base $3,518,967
Phase I: Construction Contract - Alternates 405,080
Contingency 392,405
Consultant Services: Engineering Design, Administration & Inspection 428,120
Total Project Cost $4,744,572
The funding summary for the Dubuque Industrial Center South Project is as follows:
CIP No. Fund Description
3602160 General Obligation (GO) Bonds (TIF Abated)
Transfer from Unused Portion of North Siegert G.O. Bond Sale
Total Project Funding
Fund Amount
$4,585,004
1,000,000
$5,585,004
The maximum budget for the project is $5,585,004 including preliminary and final
design, environmental review and construction of public infrastructure (Phase II). The
estimate of probable cost of Phase I includes a 10% contingency and will also include
several alternate bid items to allow for flexibility when reviewing bid proposals to ensure
that the project remains within budget.
The initial CIP had shown $990,548 in funding coming from land sales. With the savings
from the North Siegert project, this funding source is not needed. Land sales revenue
can now be used for other purposes including the annual contribution to the Greater
Dubuque Development Corporation.
Budget Director Jenny Larson intends to initiate a bond sale to finance this project in
early April, with the actual award of a bond sale scheduled for the May 21 meeting.
ACTION TO BE TAKEN
The City Council is requested to establish the date of the public hearing and authorize
the City Clerk to advertise for proposals for the Dubuque Industrial Center South
Grading & Utilities — 2012 Project, Phase I.
Prepared by David Heiar, Economic Development Director
cc: Jenny Larson, Budget Director
Bob Green, Water Department Manager
Gus Psihoyos, City Engineer
Deron Muehring, Civil Engineer
Todd Irwin, Engineering Technician
RESOLUTION NO.
DUBUQUE INDUSTRIAL CENTER SOUTH
GRADING & UTILITIES — 2012 PROJECT, PHASE I
PRELIMINARY APPROVAL OF PLANS, SPECIFICATIONS, FORM OF
CONTRACT, AND ESTIMATED COST; SETTING DATE OF PUBLIC HEARING
ON PLANS, SPECIFICATIONS, FORM OF CONTRACT, AND ESTIMATED
COST; AND ORDERING THE ADVERTISEMENT FOR BIDS
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF DUBUQUE, IOWA:
The proposed plans, specifications, form of contract and estimated cost
for the Dubuque Industrial Center South Grading & Utilities — 2012 Project,
Phase I, in the estimated amount $4,744,572, are hereby preliminarily approved
and ordered filed in the office of the City Clerk for public inspection.
A public hearing will be held on 2nd day of April, 2012, at 6:30 p.m. in the
Historic Federal Building Council Chambers at which time interested persons
may appear and be heard for or against the proposed plans and specifications,
form of contract and estimated cost of said Project, and the City Clerk be and is
hereby directed to cause the attached notice of the time and place of such
hearing to be published in a newspaper having general circulation in the City of
Dubuque, Iowa, which notice shall be published not less than four days nor more
than twenty days prior to the date of such hearing. At the hearing, any interested
person may appear and file objections to the proposed plans, specifications, form
of contract, or estimated cost of the Project.
The Dubuque Industrial Center South Grading & Utilities — 2012 Project,
Phase I is hereby ordered to be advertised for bids for construction.
The amount of the security to accompany each bid shall be in an amount
which shall conform to the provisions of the Notice to Bidders hereby approved.
The City Clerk is hereby directed to advertise for bids for the construction
of the improvements herein provided, by publishing the attached Notice to
Bidders to be published in a newspaper having general circulation in the City of
Dubuque, Iowa, which notice shall be published not less than four but not more
than forty -five days before the date for filing bids before 2:00 p.m. on the 1st day
of May, 2012. Bids shall be opened and read by the City Clerk at said time and
will be submitted to the City Council for final action at 6:30 p.m. on the 21st day of
May, 2012, in the Historic Federal Building Council Chambers (second floor), 350
West 6th Street, Dubuque, Iowa.
Passed, adopted and approved this day of , 2012.
Roy D. Buol, Mayor
Attest:
Kevin S. Firnstahl, City Clerk
NOTICE OF PUBLIC HEARING ON PLANS, SPECIFICATIONS, FORM OF
CONTRACT, AND ESTIMATED COST FOR THE DUBUQUE INDUSTRIAL
CENTER SOUTH GRADING & UTILITIES — 2012 PROJECT, PHASE I
NOTICE IS HEREBY GIVEN: The City Council of the City of Dubuque,
Iowa will hold a public hearing on the proposed plans, specifications, form of
contract and estimated cost for the Dubuque Industrial Center South Grading &
Utilities — 2012 Project, Phase I, in accordance with the provisions of Chapter 26,
Code of Iowa, at 6:30 p.m., on the 2nd day of April, 2012, in the Historic Federal
Building Council Chambers (second floor), 350 West 6th Street, Dubuque, Iowa.
Said proposed plans, specifications, form of contract and estimated cost are now
on file in the office of the City Clerk. At said hearing any interested person may
appear and file objections thereto.
The scope of the Project is as follows:
The Dubuque Industrial Center South Grading & Utilities — 2012 Project, Phase I
includes the grading of approximately 1,350,000 cubic yards of excavation. The
project includes:
— Temporary and permanent erosion control measures: Sediment basins;
detention basins; vegetated swales; seeding; inlet and outlet projection; and
energy dissipaters.
Grading: Clearing and grubbing topsoil removal; stockpile and spreading;
removal of unsuitable material; subdrains; excavation; and embankment fill.
— Deconstruction and demolition: Removal of existing structures;
abandonment; and septic system removal.
— Storm sewer: Approximately 600 lineal feet of storm sewer pipe.
— Sanitary sewer: 2,788 lineal feet of 8- and 12 -inch sanitary sewer pipe.
well
Any visual or hearing- impaired persons needing special assistance or
persons with special accessibility needs should contact the City Clerk's office at
(563) 589 -4120 or TDD at (563) 690 -6678 at least 48 hours prior to the meeting.
2012.
Published by order of the City Council given on the day of
Kevin S. Firnstahl, City Clerk
NOTICE TO BIDDERS
CITY OF DUBUQUE PUBLIC IMPROVEMENT PROJECT
DUBUQUE INDUSTRIAL CENTER SOUTH
GRADING & UTILITIES — 2012, PHASE I
Time and Place for Filing Sealed Proposals. Sealed bids for the work comprising
each improvement as stated below must be filed before 2:00 p.m. on May 1, 2012, in
the Office of the City Clerk, City Hall - First Floor, 50 West 13th Street, Dubuque, Iowa.
Time and Place Sealed Proposals Will be Opened and Considered. Sealed
proposals will be opened and bids tabulated at 2:00 p.m. on May 1, 2012, at City Hall -
Conference Room B, 50 West 13th Street, Dubuque, Iowa, for consideration by the City
Council (Council) at its meeting on May 21, 2012. The City of Dubuque, Iowa, reserves
the right to reject any and all bids.
Time for Commencement and Completion of Work. Work on each improvement
shall be commenced within 10 days after the Notice to Proceed has been issued based
on the following schedule: roadway subgrade areas completed by July 1, 2013, and
final completion by November 1, 2013.
Bid Security. Each bidder shall accompany its bid with a bid security as security that
the successful bidder will enter into a contract for the work bid upon and will furnish after
the award of contract a corporate surety bond, acceptable to the governmental entity,
for the faithful performance of the contract, in an amount equal to one hundred percent
of the amount of the contract. The bid security shall be in the amount of ten percent
(10 %) of the amount of the contract and shall be in the form of a cashier's check or
certified check drawn on a state - chartered or federally chartered bank, or a certified
share draft drawn on a state - chartered or federally chartered credit union, or the
governmental entity may provide for a bidder's bond with corporate surety satisfactory
to the governmental entity. The bid bond shall contain no conditions excepted as
provided in this section.
Contract Documents. Copies of the plans and specifications prepared by IIW, PC, are
available from Tri -State Blueprint & Framing Co. /Rapids Reproduction, 696 Central
Avenue, Dubuque, IA 52001. Telephone number: 563 - 556 -3030. No plan deposit is
required.
Copies of the construction documents may be viewed at: the Office of Economic
Development, City Hall - Second Floor, 50 West 13th Street, Dubuque, Iowa; or at the
Office of IIW, P.C., 4155 Pennsylvania Avenue, Dubuque, Iowa. If there are questions
and /or additional information is needed, contact IIW Project Manager John Wandsnider,
PE at j.wandsnider @iiwengr.com or by calling (563) 556 -2464.
Project information will also be posted on the City's website at www.cityofdubuque.org.
Preference for Iowa Products and Labor. By virtue of statutory authority, preference
will be given to products and provisions grown and coal produced within the State of
Iowa, and to Iowa domestic labor, to the extent lawfully required under Iowa statutes.
Sales Tax. The bidder should not include sales tax in its bid. A sales tax exemption
certificate will be available for all material purchased for incorporation in the project.
General Nature of Public Improvement.
Dubuque Industrial Center South Grading & Utilities — 2012 Project, Phase I
The Dubuque Industrial Center South Grading & Utilities — 2012 Project, Phase I
includes the grading of approximately 1,350,000 cubic yards of excavation. The project
includes:
— Temporary and permanent erosion control measures: Sediment basins; detention
basins; vegetated swales; seeding; inlet and outlet projection; and energy
dissipaters.
— Grading: Clearing and grubbing topsoil removal; stockpile and spreading; removal
of unsuitable material; subdrains; excavation; and embankment fill.
— Deconstruction and demolition: Removal of existing structures; well abandonment;
and septic system removal.
— Storm sewer: Approximately 600 lineal feet of storm sewer pipe.
— Sanitary sewer: 2,788 lineal feet of 8- and 12 -inch sanitary sewer pipe.
Pre -Bid Conference. Each prospective bidder is encouraged to attend the Pre -Bid
Construction Conference to be held at 1 PM Central Time on April 17, 2012, at the
Historic Federal Building Council Chambers (second floor), 350 West 6th Street,
Dubuque, Iowa. Attendance by all prospective bidders is not mandatory but highly
recommended.
Published in the Telegraph Herald, March 23, 2012.
NOTICE TO BIDDERS
CITY OF DUBUQUE PUBLIC IMPROVEMENT PROJECT
DUBUQUE INDUSTRIAL CENTER SOUTH
GRADING & UTILITIES — 2012, PHASE I
Time and Place for Filing Sealed Proposals. Sealed bids for the work comprising
each improvement as stated below must be filed before 2:00 p.m. on May 10, 2012, in
the Office of the City Clerk, City Hall - First Floor, 50 West 13th Street, Dubuque, Iowa.
Time and Place Sealed Proposals Will be Opened and Considered. Sealed
proposals will be opened and bids tabulated at 2:00 p.m. on May 10, 2012, at City Hall -
Conference Room B, 50 West 13th Street, Dubuque, Iowa, for consideration by the City
Council (Council) at its meeting on June 4, 2012. The City of Dubuque, Iowa, reserves
the right to reject any and all bids.
Time for Commencement and Completion of Work. Work on each improvement
shall be commenced within 10 days after the Notice to Proceed has been issued based
on the following schedule: roadway subgrade areas completed by July 1, 2013, and
final completion by November 1, 2013.
Bid Security. Each bidder shall accompany its bid with a bid security as security that
the successful bidder will enter into a contract for the work bid upon and will furnish after
the award of contract a corporate surety bond, acceptable to the governmental entity,
for the faithful performance of the contract, in an amount equal to one hundred percent
of the amount of the contract. The bid security shall be in the amount of ten percent
(10 %) of the amount of the contract and shall be in the form of a cashier's check or
certified check drawn on a state - chartered or federally chartered bank, or a certified
share draft drawn on a state - chartered or federally chartered credit union, or the
governmental entity may provide for a bidder's bond with corporate surety satisfactory
to the governmental entity. The bid bond shall contain no conditions excepted as
provided in this section.
Contract Documents. Copies of the plans and specifications prepared by IIW, PC, are
available from Tri -State Blueprint & Framing Co. /Rapids Reproduction, 696 Central
Avenue, Dubuque, IA 52001. Telephone number: 563 - 556 -3030. No plan deposit is
required.
Copies of the construction documents may be viewed at: the Office of Economic
Development, City Hall - Second Floor, 50 West 13th Street, Dubuque, Iowa; or at the
Office of IIW, P.C., 4155 Pennsylvania Avenue, Dubuque, Iowa. If there are questions
and /or additional information is needed, contact IIW Project Manager John Wandsnider,
PE at j.wandsnider @iiwengr.com or by calling (563) 556 -2464.
Project information will also be posted on the City's website at www.cityofdubuque.org.
Preference for Iowa Products and Labor. By virtue of statutory authority, preference
will be given to products and provisions grown and coal produced within the State of
Iowa, and to Iowa domestic labor, to the extent lawfully required under Iowa statutes.
Sales Tax. The bidder should not include sales tax in its bid. A sales tax exemption
certificate will be available for all material purchased for incorporation in the project.
General Nature of Public Improvement.
Dubuque Industrial Center South Grading & Utilities — 2012 Project, Phase I
The Dubuque Industrial Center South Grading & Utilities — 2012 Project, Phase I
includes the grading of approximately 1,350,000 cubic yards of excavation. The project
includes:
— Temporary and permanent erosion control measures: Sediment basins; detention
basins; vegetated swales; seeding; inlet and outlet projection; and energy
dissipaters.
— Grading: Clearing and grubbing topsoil removal; stockpile and spreading; removal
of unsuitable material; subdrains; excavation; and embankment fill.
— Deconstruction and demolition: Removal of existing structures; well abandonment;
and septic system removal.
— Storm sewer: Approximately 600 lineal feet of storm sewer pipe.
Sanitary sewer: 2,788 lineal feet of 8- and 12 -inch sanitary sewer pipe.
Pre -Bid Conference. Each prospective bidder is encouraged to attend the Pre -Bid
Construction Conference to be held at 10 AM Central Time on April 24, 2012, at the
Historic Federal Building Council Chambers (second floor), 350 West 6th Street,
Dubuque, Iowa. Attendance by all prospective bidders is not mandatory but highly
recommended.
Published in the Telegraph Herald, March 23, 2012.
NOTICE OF PUBLIC
HEARING ON PLANS,
SPECIFICATIONS,
FORM OF CONTRACT,
AND ESTIMATED
COST FOR THE
DUBUQUE
INDUSTRIAL CENTER
SOUTH GRADING &
UTILITIES - 2012
PROJECT, PHASE I
NOTICE IS HEREBY
GIVEN: The City
Council of the City of
Dubuque, Iowa will
hold a public hearing
on the proposed plans,
specifications, form of
contract and estimated
cost for the Dubuque
Industrial Center South
Grading & Utilities -
2012 Project, Phase I,
in accordance with the
provisions of Chapter
26, Code of Iowa, at
6:30 p.m., on the 2nd
day of April, 2012, in
the Historic Federal
Building Council Cham-
bers (second floor),
350 West 6th Street,
Dubuque, Iowa. Said
proposed plans,
specifications, form of
contract and estimated
cost are now on file in
the office of the City
Clerk. At said hearing
any interested person
may appear and file
objections thereto.
The scope of the
Project is as follows:
The Dubuque
Industrial Center South
Grading & Utilities -
2012 Project, Phase I
includes the grading of
approximately
1,350,000 cubic yards
of excavation. The
project includes:
- Temporary and
permanent erosion
control measures:
Sediment basins;
detention basins;
vegetated swales;
seeding; inlet and
outlet projection; and
energy dissipaters.
- Grading: Clearing
and grubbing topsoil
removal; stockpile and
spreading; removal of
unsuitable material;
subdrains; excavation;
and embankment fill.
- Deconstruction and
demolition: Removal of
existing structures;
well abandonment; and
septic system removal.
- Storm sewer:
Approximately 600
lineal feet of storm
sewer pipe.
- Sanitary sewer:
2,788 lineal feet of B-
and 12 -inch sanitary
sewer pipe.
Any visual or hearing -
impaired persons need-
ing special assistance
or persons with special
accessibility needs
should contact the City
Clerk's office at (563)
589 -4120 or TDD at
(563) 690 -6678 at least
48 hours prior to the
meeting.
Published by order of
the City Council given
on the 19th day of
March, 2012.
Kevin S. Firnstahl,
City Clerk
It 3/23
STATE OF IOWA {SS:
DUBUQUE COUNTY
CERTIFICATION OF PUBLICATION
I, Suzanne Pike, a Billing Clerk for Woodward Communications, Inc., an Iowa
corporation, publisher of the Telegraph Herald,a newspaper of general circulation
published in the City of Dubuque, County of Dubuque and State of Iowa; hereby
certify that the attached notice was published in said newspaper on the following
dates: March 23, 2012, and for which the charge is $27.60.
Subscribed to before me, Notary Public in and for Dubuque County, Iowa,
,200,E .
this 6376 day of
Notary Public in and for Dubuque County, Iowa.
MAriY K WEGTaRMEY R
Omm ioIor7 Novi ar °?ti,yly
grlp