Loading...
Consent Decree Semi Annual Report_September 2012 TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager SUBJECT: Consent Decree Semiannual Report DATE: August 29, 2012 City Engineer Gus Psihoyos is recommending submittal of the September 2012 Semiannual Report for the U.S. Environmental Protection Agency Consent Decree. I concur with the recommendation and respectfully request Mayor and City Council approval. / AAh kt1&1 Michael C. Van Milligen MCVM:jh Attachment cc: Barry Lindahl, City Attorney Cindy Steinhauser, Assistant City Manager Teri Goodmann, Assistant City Manager Gus Psihoyos, City Engineer r»e `Emir E` Dubuque DUB E aI -Amer l Masterpiece on the Mississippi 1 I I I I I 2007 TO: Mike Van Milligan, City Manager FROM: Gus Psihoyos, City Engineer DATE: Al 2012 SUBJECT: Consent Decree Semiannual Report INTRODUCFON The purpose of this memo is to request authorization for the City Manager to sign the September 2012 Semiannual Report and to seek approval to submit the document to the agencies stated In the Consent Decree. BACKGROUND The City of Dubuque, Iowa is under a Consent Decree according to Case 211 - up, -01001- EJM,United States of Americo and the State of Iowa v. the City of Dubuque, IS IN D. Iowa), Civil Action Number 2008 W 0041, D0J Case Number 90 51 -1 -03139 affected June 27 2011 The purpose of report is to sassy Second VIII, Paragraph 25 of Consent Decree, which requires the dry to submit semiannual report by September 30, 2012. DISCUSSION The purpose of semiannual report Into satisfy Section VIII Paragraph 25 of Consent Decree. Paragraph 25 requires the City to submit semiannual reports by March 31 and September 30 after the Effective Date (June 27 2011). The report includes summary information regarding events and acteines performed m the pear six months Therefore, the "reporting period" refers to time between March 1,2012 and including August 31 , 2012 RECOMMENDATION endthatthe City Council authorize the City Manager to fairly the September 2812 Semiannual Report and Engineering stafto submit the document to the agencies stated In the Consent Decree. PROJECFCOST- BUOGETIMPACF The recommended actions do not Impact the City's budget ACTION TO BE TAKEN request that the City Council authorize the City Manager to fairly the September 2012 Semiannual Report and Engineering staff to submit the document to the agencies stated in the Consent Decree. Prepared by Todd Shoemaker, Environmental Engineer Barry Gndahl, City Attorney Ban Vogt Pubocwarks Director John Klostermann, Street &Sewer Maintenance Supervisor Jonathan Brown, Water Plant Manager Steve Brown, Project Manager Demn Sharing, Civil Engineer Prepared for: UNITED STATES ENVIRONMENTAL PROTECTION AGENCY, UNITED STATES DEPARTMENT OF JUSTICE 00117 IOWA DEPARTMENT OF NATURAL RESOURCES Prepared by: CITY OF DUBUQUE, IA 50 W I P Street Dubuque, IA 52001 THE CITY OF Dubuque DUB E 11II1-' Masterpiece on the Mississippi' 2012 Consent Decree Semiannual Report September 30, 2012 Consent Decree No. 2:11 -u -01011 -EIM For Period March 1, 2012 through August 31, 2012 Table of Contents 1.0 CERTIFICATION ............................................................................... ............................1 -1 2.0 INTRODUCTION ............................................................................ ............................... 2 -1 2.1 Background .............................................................................. ............................2 -1 2.2 Purpose ..................................................................................... ............................2 -1 2.3 Report Summary ................................................................... ............................... 2 -1 3.0 SANITARY SEWER OVERFLOWS ................................................ ............................3 -1 3.1 Sanitary Sewer Overflow Record ......................................... ............................... 3 -1 3.2 SSO's Effect on Public Health and Water Quality ............... ............................... 3 -1 3.3 Measures Enacted to Minimize Duration and Impact ........... ............................... 3 -2 3.4 Measures Enacted to Stop the Overflow Event .................... ............................... 3 -2 3.5 Measures Enacted to Prevent Another Recurrance ............... ............................... 3 -2 3.6 Capturing Key Way Overflows ............................................ ............................... 3 -2 3.7 Warning Sign Postings .......................................................... ............................... 3 -2 4.0 WATER & RESOURCE RECOVERY CENTER CONSTRUCTION UPGRADE. 4 -1 4.1 Project Planning .................................................................... ............................... 4 -1 4.2 Current Project Status ........................................................... ............................... 4 -1 4.3 Biosolid Accumulation Prevention at the W &RRC ............. ............................... 4 -2 5.0 NATIONAL POLLUTANT DISCHARGE ELIMINATION SYSTEM (NPDES) ... 5-1 5.1 Summary of all NPDES Permit Requirement Information ... ............................... 5 -1 5.2 NPDES Violations at the WRRC During The Reporting Period ......................... 5 -1 5.2.1 NPDES Violation(s) Log ........................................ ............................... 5 -1 5.2.2 Cause of NPDES Violations ...................................... ............................5 -1 6.0 INFLOW & INFILTRATION REDUCTION PROGRAM ............ ............................6 -1 6.1 Background .............................................................................. ............................6 -1 6.2 Flow Metering ....................................................................... ............................... 6 -1 6.3 Source Investigations ............................................................... ............................6 -1 6.3.1 Private Property Inspections ................................... ............................... 6 -1 6.3.2 Dye Testing ............................................................ ............................... 6 -2 6.3.3 Smoke Testing ........................................................ ............................... 6 -2 6.3.4 Manholes ................................................................ ............................... 6 -3 6.3.5 Sanitary Sewer ........................................................ ............................... 6 -3 6.4 Corrective Action Plan .......................................................... ............................... 6 -4 6.5 Implementation of Corrective Action Plan ........................... ............................... 6 -4 i 7.0 CMOM UPDATE ................................................................................ ............................7 -1 7.1 The CMOM Program ............................................................ ............................... 7 -1 7.2 CMOM Implementation ........................................................ ............................... 7 -1 8.0 ASSESSMENTS AND ENGINEERING ANALYSES .................. ............................... 8 -1 9.0 OTHER RELATED ACTIVITIES .................................................... ............................9 -1 TABLES Table 2 -1. Organization of information required by the Consent Decree .... ............................... 2 -2 Table 3 -1. Sanitary sewer overflows during the reporting period . .............................................. 3 -1 Table 3 -2. Warning sign posting locations ................................................... ............................... 3 -2 Table 4 -1. Significant deadlines for the Water & Resource Recovery Center . ........................... 4 -1 Table 5 -1. Monthly operating reports submitted during the reporting period ............................. 5 -1 Table 5 -2. NPDES Violation Log ................................................................. ............................... 5 -1 Table 6 -1. Property inspection progress . ..................................................................................... 6 -1 Table 6 -2. Smoke testing progress ................................................................ ............................... 6 -3 Table 6 -3. Manhole inspection progress ....................................................... ............................... 6 -3 Table 6 -4. Sanitary sewer main televising progress ..................................... ............................... 6 -4 FIGURES Figure 6 -1. Map of priority sewersheds for I &I investigation.... APPENDICES Appendix A: Preliminary Flow Metering Results 11 ............ ............................... 6 -2 1.0 Certification I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gather and evaluate the information submitted. Based on my directions and my inquiry of the person or person who manage the system, or those persons directly responsible for gathering the information, the information submitted is, to the best of my knowledge and belief, true, accurate, and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violations. Michael C. Van Milligen City Manager 1 -1 2.0 Introduction 2.1 BACKGROUND The City of Dubuque, Iowa is under a Consent Decree according to Case 2:11 -cv- 01001 -EJM, United States of America and the State of Iowa v. the City of Dubuque, IA (N.D. Iowa), Civil Action Number 2008V00041. DOJ Case Number 90- 5 -1 -1- 09339. The Consent Decree became effective on June 27, 2011 and requires the City to submit semiannual reports to the Department of Justice (DOJ), Environmental Protection Agency (EPA) and Iowa Department of Natural Resources (DNR). 2.2 PURPOSE The purpose of this report is to satisfy Section VIII, Paragraph 25 of the Consent Decree. Paragraph 25 requires the City to submit semiannual reports on March 31 and September 30 after the Effective Date (June 27, 2011). The report includes summary information regarding events and activities performed in the prior six months. Therefore, the "reporting period" shall refer to the time between March 1, 2012 and August 31, 2012. 2.3 REPORT SUMMARY Paragraph 25 of the Consent Decree requires the semiannual reports to include specific information as well as a summary of the status and progress of all projects and programs required by Sections V and VI of the Consent Decree. Table 2 -1 lists how the required information is organized in this report. 2 -1 Table 2 -1. Organization of information required by the Consent Decree. Consent Decree Paragraph Summary of Requirement Report Section 25 a i Sanitary Sewer Overflow SSO locations 3.1 25(a)ii SSO duration of flows Table 3 -1 25(a)iii SSO estimated flow volume Table 3 -1 25(a)iv Waterbody downstream of SSO Table 3 -1 25 a v Suspected cause of SSO Table 3 -1 25(a)vi SSO effect on public health and water quality 3.2 25(a)vii Measures to minimize SSO 3.3 25(a)viii Measures to stop SSO 3.4 25(a)ix Measures to prevent recurrence of SSO and milestones 3.5 25 b i Construction upgrades 4.0 25(b)ii NPDES permit summary 5.1 25(b)iii NPDES permit violations during reporting eriod 5.2 8 Assessments and engineering analyses 8.0 9 Disposal of biosolids at WPCP 4.3 10(a) Capture of overflow from Key Way Drive manhole 3.6 10(b) Posting of warning signs at SSO locations 3.7 11 Construction upgrade to WPCP 4.2 12(a) North Fork Catfish Creek interceptor placed into service Requirement completed 12(b) I &I flow metering 6.2 12(c) Flow meters installed in first sewershed during 2010 Requirement completed 12(d) I &I source identification 6.3 12(e) I &I corrective action plan 6.4 12 Implement I &I corrective actions 6.5 Collection System Management, Operation, and 13(a) Maintenance plan CMOM 7.0 13(b) Implement CMOM 7.2 Requirement completed upon 14 Certify legal authority signing of Consent Decree Certify that Section V of Consent Decree has been To be completed 15 completed and placed into service by June 30, 2016 Demonstrate all SSO and by -passes have been To be completed 16 eliminated by June 30, 2017 If SSO or by -pass occurs, submit Remedial Plan and Only applicable 17 Schedule after June 30, 2017 If SSO or by -pass occurs due to O &M, submit Remedial Only applicable 18 Plan and Schedule after June 30, 2017 2 -2 3.0 Sanitary Sewer Overflows 3.1 SANITARY SEWER OVERFLOW RECORD Four (4) sanitary sewer overflows (SSO, Table 3 -1) occurred in the City of Dubuque during the reporting period. Table 3 -1. Sanitary sewer overflows during the reoortim period. SSO # 1' 2 ' 3 4 Sewershed 8 8 15 14 3011 Shiras 3021 Shiras 1495 Southern Street Address 290 Bradley Street Avenue Avenue Avenue Start Date 3/3/12 3/3/12 3/6/12 5/11/12 End Date 3/3/12 3/3/12 3/6/12 5/11/12 Start Time 2:30 p.m. unknown 2:00 p.m. 5:00 p.m. End Time 3:45 p.m. unknown 2:30 p.m. 10:00 P.M. o al 100 unknown 100 2003 VoOver Downstream Mississippi River Mississippi River Catfish Creek Mississippi River W ater bod Suspected d Broken Force Roots Roots Roots/Debris Cause(s) � Basement backup z SSO # 1 and #2 are due to the same blockage event on 3/3/12. Approximately 100 gallons of untreated wastewater was pumped into the storm system by the fire department while providing aid to the resident at 3011 Shiras. SSO #2 was reported to the Public Works Department by the homeowner on Monday, March 5h after the blockage had been removed, so it was not possible to obtain the start and end time and the overflow volume. 3 Volume estimate based on observation. 3.2 SSO'S EFFECT ON PUBLIC HEALTH AND WATER QUALITY No effects on public health were reported for any of the SSOs. For SSO #1, the fire department pumped an estimated 100 gallons of untreated wastewater into the storm sewer to aid the resident. No water quality issues were noted because of this pumping. Limited information is available for SSO #2 because it was reported to the Public Works Department by the homeowner after the SSO #1 blockage had been removed. SSOs #3 and #4 were limited to areas around each manhole. The areas were cleaned and SSO signs were posted. The SSOs did not enter any downstream body of water. 3 -1 3.3 MEASURES ENACTED TO MINIMIZE DURATION AND IMPACT The City minimized the duration and impact of the SSOs by removing each blockage in the sanitary sewer main. SSO #4 was caused by pipe failure in the force main. The pumps at the station were shut down and the level maintained using a pumping truck which then hauled the sewage to the plant while the pipe was being repaired. 3.4 MEASURES ENACTED TO STOP THE OVERFLOW EVENT SSOs #1, #2, and #3 were stopped by cutting roots in the pipe and removing the blockage. SSO #4 was caused by pipe failure in the force main. The pumps at the station were shut down and the level maintained using a pumping truck which then hauled the sewage to the plant while the pipe was being repaired. 3.5 MEASURES ENACTED TO PREVENT ANOTHER RECURRANCE The locations of SSO #1, #2, and #3 will be added to the City's annual maintenance along with chemical root foaming. The Fire Department has been instructed to discharge untreated wastewater, when possible, to a tanker truck in the future. SSO #4 was caused by pipe failure, and the pipe was repaired. The force main for these stations will be placed in the Fiscal Year 2014 Capital Improvement Project budget to be replaced or lined. 3.6 CAPTURING KEY WAY OVERFLOWS Paragraph 10 of the Consent Decree requires the City to capture all overflows from the manhole located on Key Way Drive between 3500 Keymeer Drive and 3507 Keystone Drive. An SSO did not occur at this location during the reporting period, so it was not necessary to capture any overflows. 3.7 WARNING SIGN POSTINGS Paragraph 10 of the Consent Decree requires that the City post a warning sign at all SSO sites for at least 6 months after completion of the site cleanup, unless IDNR decides that the sign may be posted for a shorter period of time or not at all. Table 3 -2 lists the current locations where signs are posted. (Postings are not required for basement backups.) Table 3 -2. Warning sign posting locations. SSO # Location Description 3 1495 Southern Avenue Sign posted neat to manhole 4 290 Bradley Street Sin posted at the dead end of Henderson Street 3 -2 4.0 Water & Resource Recovery Center Construction Upgrade 4.1 PROJECT PLANNING During its Fiscal Year 2006 goal setting process, the City Council listed the Water Pollution Control Plant (WPCP) as one of its high priorities. City staff subsequently applied for a State Revolving Fund (SRF) planning and design loan during the summer of 2006, and plant upgrades were placed on the DNR Intended Use Plan schedule. Following public hearings and bidding requirements, the Facility Plan was developed and approved by DNR. The facility's name was also changed to the Water & Resource Recovery Center (W &RRC). In October 2008, the team of Strand Associates /IIW Engineers was approved by the City Council to proceed with the design of the W &RRC upgrades. The NPDES permit was issued by DNR staff on April 1, 2010, and the plant construction permit was signed by DNR staff on April 5, 2010. Following public bidding requirements, the City Council approved a contract, and the notice to proceed was issued August 19, 2010. Table Table 4 -1 lists significant deadlines for the project. Table 4 -1. Significant deadlines for the Water & Resource Recovery Center. Deadline Target Date Digester Startup 9/26/2012 Sludge Processing Startup 1/23/2013 Aeration Tank Completion 7/22/2013 Final Clarifiers 8/30/2013 Excess Flow Equalization 10/23/2013 Substantial Completion 10/30/2013 Final Completion 1 4/8/2014 4.2 CURRENT PROJECT STATUS On July 11, 2011 at approximately 6:10 A.M., a thunderstorm with winds of approximately 74 mph caused damage to two of the four digesters under construction. On July 28, 2011, the City received more than 14 inches of rain in approximately twelve hours which caused considerable damage to the W &RRC construction site. The damage caused by each event and the City's response were documented in separate reports to the EPA, DOJ, and DNR dated July 15, 2011 and August 4, 2011. The City had estimated a project delay of approximately three to four months beyond the final completion date given of October 1, 2013. The City has since granted a 120 working day 4 -1 extension to the two major milestones of digester startup and sludge processing startup. The City and its general contractor have worked out details of a revised project completion schedule required by the weather related delays. Factoring in the delays, the City will still meet the startup deadline (April 26, 2014) as prescribed in the Consent Decree barring any further major uncontrollable delays. As of August 2012 the project is in its 24th month of construction and work has been started on all aspects of the project. City staff estimates the project is close to 66% complete. The ultraviolet disinfection system was started in March 2011 and continues to be operational. The Anaerobic Digestion complex began the startup process August 9, 2012. This process was continued until August 20, 2012 when seed sludge was added to the digesters, with solids from the Dubuque plant added to the digesters shortly thereafter. Depending on the speed of the startup full solids loading into the digesters will be completed in 30 to 45 days. Upon successful startup of the digesters work can begin on the installation of new solids handling equipment. The bio- solids handling equipment is expected to be online by February 2013. There will be sufficient storage in the digesters to accommodate solids storage until the new centrifuges are online. A bio -solid handling contract has been negotiated and signed with Nutri -Ject Systems of Hudson, Iowa. The laboratory addition of the Administration/Laboratory Building is complete and work has begun on the rebuilding of the existing Administration/Laboratory building. The Administration/Laboratory Building will be a highly energy efficient building using plant effluent to meet heating and cooling needs. The entire structure is highly insulated and will use a minimum of energy for lighting, heating and cooling. 4.3 BIOSOLID ACCUMULATION PREVENTION AT THE W &RRC On April 5, 2012 there was an explosion at the W &RRC which destroyed the main blower for the North incinerator and severely damaged the recuperator. Because the digesters would be online sooner than the incinerator could be repaired the decision was made to not repair the incinerator and begin hauling solids to the Dubuque Area Metropolitan Sanitary Landfill. Arrangements have also been made with Waste Management Inc. to haul solids to its landfill facility in East Moline, Illinois. The supplier of new centrifuges for the plant upgrade is the same firm that has performed major maintenance on the existing centrifuges. This firm has informed W &RRC staff that they would be available to assist should one or both of the operating centrifuges have a major breakdown. At the point one of the centrifuges needs to be removed to proceed with that phase of construction all critical parts from the removed centrifuge will remain on the plant site in order to facilitate a rapid repair of the existing centrifuge and return the plant to full operating conditions. Storage space for sludge will remain a challenge until portions of the new plant are brought online. When sections of the reconstructed plant are brought into service, the City will be able to use these areas to assist in W &RRC sludge management. 4 -2 5.0 National Pollutant Discharge Elimination System (NPDES) 5.1 SUMMARY OF ALL NPDES PERMIT REQUIREMENT INFORMATION NPDES Monthly Operating Reports (MOR) for the City of Dubuque W &RRC were submitted to IDNR on the dates listed in Table 5 -1: Table 5 -1. Monthly o eratin reports submitted during the reporting period. Report Date Submitted February 2012 3/06/2012 March 2012 4/12/2012 April 2012 5/15/2012 May 2012 6/15/2012 June 2012 7/13/2012 July 2012 8/14/2012 August 2012 To be submitted approximately 9/7/2012 5.2 NPDES VIOLATIONS AT THE WRRC DURING THE REPORTING PERIOD The W &RRC had permit violations in April and May of 2012 following the explosion which caused major damage to the then - operating incinerator used for solids disposal. 5.2.1 NPDES Violation(s) Log Table 5 -2. NPDES Violation Log TSS Seven Day Average Maximum Allowed by Permit (mg/L Reported m /L April 22-28 45 49 May 1 -7 45 46 May 8 -14 45 144 TSS Monthly Average May 2012 30 1 49 CBOD Seven Day Average May 8 -14 25 1 62 5.2.2 Cause of NPDES Violations As reported in section 1.3 The W &RRC lost the use of its only operating incinerator on April 5, 2012. It was necessary to make some piping adjustments to the sludge delivery system prior to 5 -1 being able to haul sludge to the landfill. This work took the remainder of that week in April to complete. During this period, the City was unable to remove solids from the system which contributed to a buildup of excess solids in the plant. In addition to the solids handling difficulties the existing flow - meters where removed from the existing SCADA system and new flow meters installed for the new SCADA system. The existing recycle pumps were controlled from the old SCADA system, and it took a few days to coordinate the proper pumping rate using both the new and old systems. 5 -2 6.0 Inflow & Infiltration Reduction Program 6.1 BACKGROUND Prior to the Consent Decree date of lodging, the City experienced several discharges of untreated or partially treated wastewater. These events were caused by sharp increases in flow within the sanitary sewer system during and immediately after a rainstorm. To better locate the sources of this issue, the City placed flow meters throughout the city. Depending on location, the meters measured the flow of water from each sewershed over a one to eleven month period of time. Five of the twelve sewersheds were identified as receiving elevated flows during and directly after a precipitation event. Under the Consent Decree, the City has agreed to investigate these five sewersheds before January 1, 2016. The section below describes the City's progress in identifying I &I sources in the five sewersheds (Figure 6 -1). 6.2 FLOW METERING The City conducted flow metering within Sewershed 7 during 2012. Preliminary flow metering results are presented in Appendix A. 6.3 SOURCE INVESTIGATIONS 6.3.1 Private Property Inspections Private property inspection progress is reported in Table 6 -1. Private property inspections identify the roof drain discharge location, the presence of any stairwell or driveway drains, and the presence of a sump pit /pump on site. A passing inspection indicates no connections of clear water to the sanitary system. A failed inspection indicates a connection of clear water directly into the sanitary system, which may include roof drains connected to the sanitary sewer; a stairwell or driveway drain which is connected to the building floor drain; or a sump pump which is plumbed directly to the sanitary lateral or a floor drain within the building. Table 6 -1. Pronertv inspection nroeress. Sewershed Percent of Completed Property Inspections* Consent Decree Deadline to Complete Property Inspections 11 100 9/30/11 12 90.6 6/30/12 7 90.2 6/30/13 5 14.8 6/30/14 10 None 6/30/15 *The Consent Decree does not state that all properties must be inspected. However, it is the City of Dubuque's intent to inspect 100% of the properties in each sewershed. 6 -1 Each improper connection observed during a private property inspection results in a failure notice. The property owner then has 30 days to correct the improper connection, at which point a re- inspection of the property conducted to verify that the improper connection has been eliminated. If the improper connection has not been corrected, the City may pursue legal action against the property owner to complete the necessary work. Inflow & Infiltration Program, & A DUB UE Snnitnry S,.,, W, To B, lnspeeted Aa `m ---0' g 10=N DV RD g o �� DERBY GRANDE m — C� n} — reTS W 32ND 5T S wershetl l0 �� e S w rshetl5 dwo opQ" o µENE Si re reiw.o� ' '9L �asrda' 8 a 01 ; y, g� 1, 61115 KAUFMANN AVE�c Sewr' ' +.tl7 Apr B 9 °'rvse qr mw�s a eeTST IZ�E,re XILLLFEST FO n wrvvmtw �IQ i V "E - n -o rsh 11 N o�FF o o cama+ +sore 0 s, D NN VLVANIAAVE o �T ocH Q v �s ciu V' p �>�' S� a Cc L1 ODGE'n n m /W�E ...cxrPo �e 4 _ NYgure 61. Map of priority sewersheds for I &I investigation. 6.3.2 Dye Testing Dye testing has been performed in conjunction with private property inspections. If the discharge location of a downspout, exterior stairwell drain, or driveway drain is unknown, the City will use dye to identify the discharge location(s). If the dye is found in the sanitary sewer, the property owner receives notice consistent with the private property inspection process described in Section 6.3.1. 6.3.3 Smoke Testing Smoke testing progress is reported in Table 6 -2. The City conducted smoke testing in Sewersheds 7 and 5 during July and August 2012, respectively. Results will be included in the 6 -2 Corrective Action Plan for each sewershed according to the deadline outlined in the Consent Decree. Defects and their locations were recorded and will be processed using the City's GIS. Table 6 -2. Smoke testing progress. Sewershed Percent of Smoke Testing Completed* Consent Decree Deadline to Complete Property Inspections 11 100 9/30/11 12 100 6/30/12 7 100 6/30/13 5 100 6/30/14 10 None 6/30/15 *The Consent Decree does not state that smoke testing must occur within every sanitary sewer main of each sewershed. However, it is the City of Dubuque's intent to smoke -test 100% of the sanitary sewer mains in each sewershed. 6.3.4 Manholes Manhole inspection progress is reported in Table 6 -3. All sanitary manholes in Sewersheds 12, 5, and 7 have been opened and recorded as concrete or brick and rated based on structural integrity in order to prioritize improvement or replacement. Inspection results were recorded and processed using the City's GIS. Table 6 -3. Manhole inspection progress. Sewershed Percent of Manhole Inspections Completed* Consent Decree Deadline to Complete Property Inspections 11 100 9/30/11 12 100 6/30/12 7 100 6/30/13 5 99 6/30/14 10 None 6/30/15 *The Consent Decree does not state that all manholes must be inspected. However, it is the City of Dubuque's intent to inspect 100% of the brick manholes in each sewershed. 6.3.5 Sanitary Sewer Progress of sanitary sewer main televising is reported in Table 6 -4. Any cracks, leaky joints, illegal lateral connections, and damaged or broken pipes have been recorded. The severity of the structural degradation of each pipe section will be rated based on severity. This rating system will be used to prioritize which pipe sections are in need of immediate improvement. 6 -3 Tahle 6 -4. Sanitary sewer main televisinn nrnnress. Sewershed Percent of Televised Sanitary Sewer Mains* Consent Decree Deadline to Complete Property Inspections 11 >95 9/30/11 12 >90 6/30/12 7 >66 6/30/13 5 None 6/30/14 10 None 6/30/15 *The Consent Decree does not state that all sanitary sewer mains must be televised. However, it is the City of Dubuque's intent to televise 100% of the sanitary sewer mains in each sewershed. 6.4 CORRECTIVE ACTION PLAN As stated in Paragraph 12 of the Consent Decree, the Sewershed 11 Corrective Action Plan was submitted prior to December 31, 2011. A similar report will be submitted by December 31, 2012 for Sewershed 12. 6.5 IMPLEMENTATION OF CORRECTIVE ACTION PLAN The City is awaiting approval of the Sewershed 11 Corrective Action Plan submitted to EPA in December 2011. Due to schedule requirements, however, work has already begun where necessary. City staff continues to work with property owners to correct improper private connections. The City is actively rehabilitating brick manholes and sanitary sewer pipes that were identified in the plan to be deficient. 6 -4 7.0 CMOM Update 7.1 THE CMOM PROGRAM The City of Dubuque's Capacity, Management, Operation and Maintenance Plan (CMOM) provides a summary of its policies, procedures, practices, and responsibilities associated with its sanitary sewer collection system. It is the blueprint for the City's managers and field workers to better manage, operate, and maintain Dubuque's sanitary sewer collection system, investigate capacity- constrained area, prevent SSOs, respond to SSOs that may occur, and plan for future system expansion. The City received notice from the EPA that the CMOM had been approved on June 4, 2012. 7.2 CMOM IMPLEMENTATION As required by Paragraph 13 of the Consent Decree, the City has fully implemented the CMOM within two calendar months (August 4, 2012) of approval by the EPA. The City developed the CMOM to serve as a "living" document. As the City reviews its current procedures and codes, the CMOM will be updated and new procedures implemented as needed. Any revisions to the CMOM will be submitted to EPA, DOJ, and DNR for review and approval as required under the Consent Decree. 7 -1 8.0 Assessments and Engineering Analyses The City's engineering department, public works department and W &RRC staff continue to evaluate and analyze the sewer collection system and W &RRC to ensure compliance with all legal requirements. However, no specific study was undertaken during the reporting period. 8 -1 9.0 Other Related Activities • Submitted semiannual report on March 26, 2012. Awaiting approval by EPA. 9 -1 Appendix A Sewershed 7 Preliminary Flow Metering Results SwmhdTSubeehdDelineation \, 74 4s 51 § \& % {® x % 5y \: / > /7 x t ` < . > ���( _ . . � !' , _\ , > , `o .. ` ° ®` Legend Simplified ___ .z =z =, .� __n 140,000 120,000 100,000 40,000 20,000 R 24th & White Streets Flow Montoring Location #1 (2012) 6� IOX 10\10 4,11 4,1 1r =Rainfall Total Flow —DWF iii 1.2 GI3 0.6 i 0.4 0.2 R 250,000 200,000 150,000 100,000 50,000 0 White Street - Next to Fulton School Flow Montoring Location #2 (2012) =Rainfall Total Flow —DWF iv -01 `1 �^� ti`' � 1 � 1.2 GI3 0.6 i 0.4 0.2 R MM 70,000 50,000 40,000 30,000 20,000 10,000 0 4VI 6i° e 41 e 1\�, -%\° 414 1 ^\q" =Rainfall Total Flow DWF 400 Kaufmann Ave Flow Montoring Location #3 (2012) V 1.2 GI3 0.6 i 0.4 0.2 W 40,000 35,000 30,000 25,000 20,000 15,000 10,000 5,000 0 41 41V Rainfall Total Flow —DWF 524 Kaufmann Avenue Flow Monitoring Location #4 (2012) Vi 1.2 GI3 0.6 i 0.4 0.2 W