Curb Ramp Install Ph II - CDBG Project D~~~E ~ck~ MEMORANDUM February 13, 2006 TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager SUBJECT: 2006 Curb Ramp Installation - CDBG Project, Phase II (CIP 2601236: ADA Curb Ramp Construction Project) Sealed bids were received for the 2006 Curb Ramp Installation - CDBG Project, Phase II. City Engineer Gus Psihoyos recommends award of the contract to the low bidder, Kluck Construction, Inc., in the amount of $23,843, which is 1.3% under the estimate of probable cost. I concur with the recommendation and respectfully request Mayor and City Council approval. 0J~ML MicHael C. Van Milligen ~.. MCVM/jh Attachment cc: Barry Lindahl, Corporation Counsel Cindy Steinhauser, Assistant City Manager Gus Psi hoyos, City Engineer i5~~~E ~<k~ MEMORANDUM February 10, 2006 FROM: Michael C. Van Milligen, City Manager Gus Psihoyos, City Engineer .V TO: SUBJECT: 2006 Curb Ramp Installation - CDBG Project, Phase II (CIP 2601236: ADA Curb Ramp Construction Project) INTRODUCTION The enclosed resolutions authorize the award of the construction contract for the 2006 Curb Ramp Installation - CDBG Project, Phase II. BACKGROUND The 2006 Curb Ramp Installation - CDBG Project, Phase II will provide for the installation of curb ramps throughout the City and consists of 12 ramps in the areas of Elm Street to Central Avenue and 15th Street to 22nd Street. The proposed ramps for this phase of construction include areas needing small retaining walls, additional sidewalk, curbing, and railings. BID RESULTS Sealed bids were received on the project on February 2, 2006. Kluck Construction, Inc. of Dubuque, Iowa, submitted the low bid in the amount of $23,843.00. This amount is 1.3% under the estimate of probable cost. A summary of the bid proposals received is as follows: Contractor Name Total Bid Kluck Construction, Inc. Skyline Trucking & Storage, Inc. Max Smith Construction Horsfield Construction, Inc. Perry Construction Fondell Excavating Co., Inc. $23,843.00 $25,825.00 $26,324.30 $27,965.28 $28,914.00 $30,221.50 RECOMMENDATION I recommend that the contract be awarded to Kluck Construction, Inc. in the amount of $23,843.00. PROJECT COST - BUDGET IMPACT The estimate of probable costs for the 2006 Curb Ramp Installation - CDBG Project, Phase II is summarized as follows: Cost Estimate Bid Award Construction Contract Contingency Engineering Total Project Cost $24,161.00 2,416.10 3,986.57 $30,563.67 $23,843.00 2,416.10 3,986.57 $30,245.67 The 2006 Curb Ramp Installation - CDBG Project, Phase II will be funded through the Community Development Block Grant Funds for Fiscal Year 2006 that has a balance of $49,699.52. ACTION TO BE TAKEN I recommend that the City Council adopt the attached resolutions awarding the 2006 Curb Ramp Installation - CDBG Project, Phase II to Kluck Construction, Inc. in the amount of $23,843.00. Prepared by Jane Smith, Engineering Assistant cc: Dawn Lang, Budget Director Jon Dienst, PE Aggie Tauke, Housing & Community Development RESOLUTION NO. 60-06 RESOLUTION ADOPTING PLANS AND SPECIFICATIONS Whereas, on the 11th day of January, 2006, plans, specifications, form of contract and estimated cost were filed with the City Clerk of Dubuque, Iowa for the 2006 Curb Ramp Installation - CDBG Project, Phase II. Whereas, notice of hearing on plans, specifications, form of contract, and estimated cost was published as required by law. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: That the said plans, specifications, form of contract and estimated cost are hereby approved as the plans, specifications, form of contract and estimated cost for said improvements for said project. Passed, adopted and approved this 20th day of February, 2006. Roy D. Buol, Mayor Attest: Jeanne F. Schneider, City Clerk ill RESOLUTION NO. 61-06 AWARDING CONSTRUCTON CONTRACT FOR THE 2006 CURB RAMP INSTAllATION - CDBG PROJECT, PHASE II Whereas, sealed proposals have been submitted by contractors for the 2006 Curb Ramp Installation - CDBG Project, Phase II pursuant to Resolution No. and notice to bidders published in a newspaper published in the City of Dubuque, Iowa on the 20th day of January, 2006. Whereas, said sealed proposals were opened and read on the 2nd day of February, 2006, and it has been determined that the bid of Kluck Construction, Inc. of Dubuque, Iowa, in the amount of $23,843.00 was the lowest bid for the furnishings of all labor and materials and performing the work as provided for in the plans and specifications. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: That the contract for the above improvement be awarded to Kluck Construction, Inc. and the Manager be and is hereby directed to execute a contract on behalf of the City of Dubuque for the complete performance of the work. BE IT FURTHER RESOLVED: That upon the signing of said contract and the approval of the contractor's bond, the City Treasurer is authorized and instructed to return the bid deposits of the unsuccessful bidders. Passed, approved and adopted this 20th day of February, 2006. Roy D. Buol, Mayor Attest: Jeanne F. Schneider, City Clerk ,2006. Attest: .,~~i2J Jeanne F. Schneider, CMC, City Clerk RESOLUTION NO. 62-06 APPROVING CONSTRUCTION CONTRACT WITH KLUCK CONSTRUCTION, INC. FOR THE 2006 CURB RAMP INSTAllATION- CDBG PROJECT, PHASE II Whereas the City Council by Resolution No. 61-06 awarded the construction contract for the 2006 Curb Ramp Installation - CDBG Project, Phase II to Kluck Construction, Inc.; and Whereas Kluck Construction, Inc. has submitted the attached executed contract and bond. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: 1. The contract and bond attached hereto are hereby approved. 2. The City Manager is hereby authorized and directed to execute the contract on behalf of the City of Dubuque. Passed, approved and adopted this 20th day of February, 2006. Roy D. Buol, Mayor Attest: Jeanne F. Schneider, CMC, City Clerk BIDDER: Horsfield Construction BIDDER: Max Smith Construction BIDDER: Skyline Construction BIDDER Kluck Construction Feb 2 2006 DATE: City of Dubuque BID TABULATION FOR: 2006 Curb Ramp Installation BIDDER' Fondell Excavating BIDDER: Perry Construction EST. TOTAL II EST. UNIT UNIT COST COBG Project Phase TOTAL UNIT CO~T TOTAL UNIT COST TOTAL UNIT COST TOTAL UNIT COST TOTAL UNIT COST TOTAL UNIT COST QIT, ITEM $4,775,00 25.00 $5,539.00 $29.00 $5,730,00 $30.00 $5,730,00 $30.00 $6,303,00 $33.00 $5,730.00 $30.00 $5,730,00 $3,168,00 $30.00 $6,00 LF 91.00 PCC Curb & Gutter, Remove, Replace, Complete $13,200,00 25,00 $7,656.00 $14.50 $8,585.28 $16.26 $4,857,60 $9.20 $4,224.00 $8.00 $5,016.00 $9.50 L.F. 528.00 2. 6" PCC Wall, Complete 3. 4" PCC Concrete Sidewalk, Remove, Replace, Complete $949.50 4,50 $1,055,00 $5.00 07.75 $1 $5.25 $1,076,10 $5.10 $1,055,00 $5,00 $1,055.00 $5.00 $1,055,00 $5.00 S.F .00 2 4. 6" pec Concrete Sidewalk, Remove, Replace, Complete $7,060.00 5.00 $9,178.00 $6.50 $7,907.20 $5.60 $9,248.60 $6.55 78.00 $9 $6.50 $8,472.00 $6.00 $9,884.00 $7.00 S.F. 1412.00 $1,03700 61.00 $2,890.00 $170.00 $3,020.05 $177,65 $2,142.00 $126.00 $765.00 $45.00 $1,530.00 $90.00 $2,074.00 $2,050.00 $200.00 $122.00 Units 17.00 Placement of Detectable Warning Area (2x4) 5 $2,870,00 70.00 $2,296.00 56.00 $1,025.00 25.00 $2,870.00 70.00 $4,100,00 00,00 $1,640.00 40.00 $50.00 L.F. 41.00 6. Handrailing, Complete $330.00 65.00 $300.00 150,00 $590.00 295.00 $400.00 200.00 $200,00 100.00 $400.00 200.00 $100.00 No. of 2.00 7. Steps $30,221.50 25,1% $28,914.00 TOTAL BID 9.7% TOTAL BID $27,965.28 5.7% TOTAL BID $26,324.30 9.0% $25,825.00 TOTAL BID 6.9% $23,843.00 TOTAL BID 3% -1 TOTAL BID 00 $24,16 TOTAL ESTIMATE % OVER I UNDER D~~~E ~ck~ -rt35 ;} Jc;o/O r; MEMORANDUM January 3, 2006 TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen,City Manager SUBJECT: 2006 Curb Ramp Installation - CDBG Project Phase II (CIP 2601236: ADA Curb Ramp Construction Project) City Engineer Gus Psihoyos recommends initiation of the bidding process for the 2006 Curb Ramp Installation - CDBG Project Phase II, and further recommends that a public hearing be set for February 20, 2006. I concur with the recommendation and respectfully request Mayor and City Council approval. (lilt! ~J11JL Mich~el C. Van Milligen MCVM/jh Attachment cc: Barry Lindahl, Corporation Counsel Cindy Steinhauser, Assistant City Manager Gus Psihoyos, City Engineer D~~%duE ~Y4-~ MEMORANDUM December 29, 2005 FROM: Michael C. Van Milligen, City Manager Gus Psihoyos, City Engineer ~Q TO: SUBJECT: 2006 Curb Ramp Installation - CDBG Project Phase II (CIP 2601236: ADA Curb Ramp Construction Project) INTRODUCTION The enclosed resolutions authorize the public bidding procedure for the construction of curb ramps at various locations throughout the City in compliance with the American with Disabilities Act. BACKGROUND The Americans with Disabilities Act requires that curb ramps be installed at intersections in all areas of the City. This area is also part of the Housing Department's Washington Neighborhood Revitalization Area. The City has been installing ramps on all street resurfacing and reconstruction projects, as well as on all sidewalk inspection routes. DISCUSSION This project continues a systematic program for the installation of curb ramps throughout the City and consists of 12 ramps in the areas of Elm Street to Central Avenue and 15th Street to 22nd Street. The schedule for the project will be as follows: Advertisement for Bids Notice of Hearing on Plans & Specifications Receipt of Bids Public Hearing Award of Contract Completion January 20, 2006 February 10, 2006 February 2, 2006 February 20, 2006 February 20, 2006 July 1, 2006 RECOMMENDATION It is recommended that the City Clerk establish the date for the public hearing and authorize the City Clerk to advertise for proposals. BUDGET IMPACT The estimate for the project is as follows: Total Project Cost $24,161.00 2,416.10 3,986.57 $30.563.67 Construction Contract Contingency Engineering The proposed ramps for this phase of construction iQclude areas needing small retaining walls, additional walk and curbing reconstruction, as well as possible switchbacks constructed with footings, walls and railings. The project will be funded through the Community Development Block Grant Funds for Fiscal Year 2006 that has a balance of $49,699.52. ACTION TO BE TAKEN The City Council is requested to establish the date for the public hearing and authorize the City Clerk to advertise for proposals through adoption of the enclosed resolutions. Prepared by Jane Smith cc: Jon Dienst, PE Aggie Tauke, Housing & Community Development CDBG CURB RAMP INSTALLATION PROJECT LOCATION RESOLUTION NO. PRELIMINARY APPROVAL OF PLANS AND SPECIFICATIONS NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: That the proposed plans, specifications, form of contract and estimated cost for the 2006 Curb Ramp Installation - CDBG Project Phase II, in the estimated amount of $30,563.67 are hereby approved and ordered filed in the office of the City Clerk for public inspection. Passed, adopted and approved this day of ,2006. Roy D. Buol, Mayor Attest: Jearine F. Schneider, CMC, City Clerk RESOLUTION NO. FIXING DATE OF HEARING ON PLANS AND SPECIFICATIONS Whereas, the City Council of the City of Dubuque, Iowa has given its preliminary approval on the proposed plans, specifications, and form of contract and placed same on file in the office of the City Clerk for public inspection of the 2006 Curb Ramp Installation - CDBG Project Phase II. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: That a public hearing will be held on the 20th day of February, 2006, at 6:30 p.m. in the Public Library Auditorium at which time interested persons may appear and be heard for or against the proposed plans and specifications, form of contract and cost of said improvement, and the City Clerk be and is hereby directed to cause a notice of time and place of such hearing to be published in a newspaper having general circulation in the City of Dubuque, Iowa, which notice shall be not less than four days nor more than twenty days prior to the day fixed for its consideration. At the hearing, any interested person may appear and file objections to the proposed plans, specifications, contract, or estimated cost of the improvement. Passed, adopted and approved this day of ,2006. Roy D. Buol, Mayor Attest: Jeanne F. Schneider, CMC, City Clerk NOTICE OF HEARING ON PLANS AND SPECIFICATIONS Notice of public hearing on proposed plans and specifications, proposed form of contract and estimate of cost for the 2006 Curb Ramp Installation - CDBG Project Phase II: Installation of 12 ramps in the areas of Elm Street to Central Avenue and 15th Street to 22nd Street. NOTICE IS HEREBY GIVEN: The City Council of Dubuque, Iowa will hold a pub lie hearing on the proposed plans, specifications, form of contract and estimate of cost for the 2006 Curb Ramp Installation - CDBG Project Phase II, in accordance with the provisions of Chapter 384, City Code of Iowa, at 6:30 p.m., on the 20th day of February, 2006, in the Public library Auditorium, 360 West 11th Street, in Dubuque, Iowa. Said proposed plans, specifications, form of contract and estimate of cost are now on file in the office of the City Clerk. At said hearing any interested person may appear and file objections thereto or to the' cost of the improvements. Any visual or hearing-impaired persons needing special assistance or persons with special accessibility needs should contact the City Clerk's office at (563) 589-4120 or TDD at (563) 690-6678 at least 48 hours prior to the meeting. Published by order of the City Council given on the ,2006. day of Jeanne F. Schneider, CMC, City Clerk RESOLUTION NO. ORDERING BIDS NOW THEREFORE, BE IT RESOLVED BY THE COUNCIL OF THE CITY . OF DUBUQUE, IOWA: That the 2006 Curb Ramp Installation - CDBG Project Phase II is hereby orderedJo be advertised for bids for construction. BE IT FURTHER RESOLVED, that the amount of the security to accompany each bid shall be in an amount which shall conform to the provisions of the Notice to Bidders hereby approved as a part of the plans and specifications heretofore adopted. That the City Clerk is hereby directed to advertise for bids for the construction of the improvements herein provided, to be published in a newspaper having general circulation in the City of Dubuque, Iowa, which notice shall not be less than four days nor more than forty-five days prior to the receipt of said bids at 2:00 p.m. on the 2nd day of February, 2006. Bids shall be opened and read by the City Clerk at said time and will be submitted to the Council for final action at 6:30 p.m. on the 20th day of February, 2006. Passed, adopted and approved this _ day of ,2006. Roy D. Buol, Mayor Attest: Jeanne F. Schneider, CMC, City Clerk