Custer - Allison Henderson Sewer Proj
5U~~E
~<k-~
MEMORANDUM
March 24, 2006
TO:
The Honorable Mayor and City Council Members
FROM:
Michael C. Van Milligen, City Manager
SUBJECT: Award of the Custer/Allison-Henderson Sewer and Detention Basin
Project (CIP 7201376)
Sealed bids were received for the Custer/Allison-Henderson Sewer and Detention Basin
Project. City Engineer Gus Psihoyos recommends award of the contract to the low
bidder, McDermott Excavating, in the amount of $208,795.87, which is 5.51 % over the
engineer's estimate.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
. 'IleA ~:1 rl ~{'--
Michael C. Van Milligen
MCVM/jh
Attachment
cc: Barry Lindahl, Corporation Counsel
Cindy Steinhauser, Assistant City Manager
Gus Psihoyos, City Engineer
~" ;,
5~~~E
~ck~
MEMORANDUM
March 24, 2006
TO:
Michael C. Van Milligen, City Manager
Gus Psihoyos, City Engineer yO
SUBJECT: Award of the Custer/Allison-Henderson Sewer and Detention Basin
Project (CIP 7201376)
FROM:
INTRODUCTION
The enclosed resolutions provide for the award of the Custer/Allison-Henderson
Sewer and Detention Basin Project.
DISCUSSION
The project involves grading and installing drain tile in the northeast portion of
Allison-Henderson Park. An additional storm sewer will be constructed across
Loras Boulevard to Adair Street. Finally, it involves the re-construction of storm
sewer from the northwest corner of Allison-Henderson Park to Custer Street and
to University Avenue.
Sealed bids were received on the project on March 23, 2006. McDermott
Excavating of Dubuque, Iowa, submitted the low bid in the amount of
$208,795.87. This amount is 5.51 % over the engineer's estimate. A summary of
the bids received is as follows:
McDermott Excavating
Connolly Construction, Inc.
Tschiggfrie Excavating Co.
Top Grade Excavating, Inc.
WC Stewart Construction, Inc.
McClain Excavating Co., Inc.
$208,795.87
$220,147.46
$233,994.61
$245,199.66
$263,432.47
$324,189.40
RECOMMENDATION
I recommend that the contract be awarded to McDermott Excavating in the
amount of $208,795.87.
BUDGET IMPACT
The summary of the project costs is as follows:
Estimate Award
Construction $201,960.00 $208,795.87
Contingency 20,196.00 20,196.00
Engineering 30.294.00 30.294.00
Total Project Cost $252,450.00 $259,285.87
The project will be funded with the Fiscal Year 2006 Custer/Allison-Henderson
Sewer and Detention Basin Project appropriations in the amount of $200,229 and
the detention basin and storm sewer service fees from the owners of the Finley
Hospital, Hartig Drug, and Dubuque Bank & Trust owners in the amount of
$26,451. Additional funding of $32,605.87 will come from the Fiscal Year 2007
Storm Sewer ImprovemenUExtensions with a current balance of $79,229.
ACTION TO BE TAKEN
I recommend that the City Council adopt the attached resolutions awarding the
Custer/Allison-Henderson Sewer and Detention Basin Project to McDermott
Excavating in the amount of $208,795.87.
Prepared by Deron Muehring
cc: Dawn Lang, Budget Director
Deron Muehring, Civil Engineer II
Todd Irwin, Engineering Assistant II
BUDGET IMPACT
The summary of the project costs is as follows:
Estimate Award
Construction $201,960.00 $208,795.87
Contingency 20,196.00 20,196.00
Engineering 30.294.00 30.294.00
Total Project Cost $252,450.00 $259,285.87
The project will be funded with the Fiscal Year 2006 Custer/Allison-Henderson
Sewer and Detention Basin Project appropriations in the amount of $200,229 and
the detention basin and storm sewer service fees from the owners of the Finley
Hospital, Hartig Drug, and Dubuque Bank & Trust owners in the amount of
$26,451. Additional funding will come from the Fiscal Year 2007 Storm Sewer
Improvement/Extensions with a current balance of $32,605.
ACTION TO BE TAKEN
I recommend that the City Council adopt the attached resolutions awarding the
Custer/Allison-Henderson Sewer and Detention Basin Project to McDermott
Excavating in the amount of $208,795.87.
Prepared by Deron Muehring
cc: Dawn Lang, Budget Director
Deron Muehring, Civil Engineer II
Todd Irwin, Engineering Assistant II
RESOLUTION NO. 125-06
RESOLUTION ADOPTING PLANS AND SPECIFICATIONS
Whereas, on the 1st day of March, 2006, 2006, plans, specifications, form
of contract and estimated cost were filed with the City Clerk of Dubuque, Iowa for
the Custer/Allison-Henderson Sewer and Detention Basin Project.
Whereas, notice of hearing on plans, specifications, form of contract, and
estimated cost was published as required by law.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF DUBUQUE, IOWA:
That the said plans, specifications, form of contract and estimated cost are
hereby approved as the plans, specifications, form of contract and estimated cost
for said improvements for said project.
Passed, adopted and approved this 3rd day of April, 2006.
Roy D. Buol, Mayor.
Attest:
Jeanne F. Schneider, CMC, City Clerk
RESOLUTION NO. 126-06
AWARDING CONSTRUCTION CONTRACT FOR THE
CUSTER/ALLISON-HENDERSON SEWER AND DETENTION BASIN
PROJECT
Whereas, sealed proposals have been submitted by contractors for the
Custer/Allison-Henderson Sewer and Detention Basin Project pursuant to
Resolution No. and notice to bidders published in a newspaper published
in the City of Dubuque, Iowa on the 10th day of March, 2006.
Whereas, said sealed proposals were opened and read on the 23rd day of
March, 2006, and it has been determined that the bid of McDermott Excavating
of Dubuque, Iowa, in the amount of $208,795.87 was the lowest bid for the
furnishings of all labor and materials and performing the work as provided for in
the plans and specifications.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF DUBUQUE, IOWA:
That the contract for the above improvement be awarded to McDermott
Excavating and the Manager be and is hereby directed to execute a contract on
behalf of the City of Dubuque for the complete performance of the work.
BE IT FURTHER RESOLVED:
That upon the signing of said contract and the approval of the contractor's
bond, the City Treasurer is authorized and instructed to return the bid deposits of
the unsuccessful bidders.
Passed, approved and adopted this 3rd day of April, 2006.
Roy D. Buol, Mayor
Attest:
Jeanne F. Schneider, CMC, City Clerk
RESOLUTION NO. 127-06
APPROVING CONSTRUCTION CONTRACT WITH MCDERMOTT
EXCAVATING FOR THE CUSTER/ALLISON-HENDERSON SEWER
AND DETENTION BASIN PROJECT
Whereas the City Council by Resolution No. 126-06 awarded the
construction contract for the Custer/Allison-Henderson Sewer and Detention
Basin Project to McDermott Excavating; and
Whereas McDermott Excavating has submitted the attached executed
contract and bond.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF DUBUQUE, IOWA:
1. The contract and bond attached hereto are hereby approved.
2. The City Manager is hereby authorized and directed to execute the
contract on behalf of the City of Dubuque.
Passed, approved and adopted this 3rd day of April, 2006.
Roy D. Buol, Mayor
Attest:
Jeanne F. Schneider, CMC, City Clerk
CUSTER I ALLISON HENDERSON PHASE II
STORM SEWER CONSTRUCTION PROJECT
CIP NO. 7201376
CONSTRUCTION COST ESTIMATE
23-Mar-D6
BIDDER
Connolly Construction, lnc
UNIT TOTAL
PRICE PRICE
QUANTITY
DESCRIPTION
NO.
,615.00
3,862.00
2,280.00
11,272.50
5,610.00
535.00
2,175.00
6,877.50
1,056.00
608.00
4,500.00
5,730.75
845.00
3,825.00
660.00
3,935.00
65L386.75
t
t
t
t
t
t
t
t
t
t
t
t
t
t
$
t
,615.00
~
~
~
~
535.00
435.00
45.85
3.30
304.00
37.50
42.45
13.00
3,825.00
660.00
$ 3,935.00
Sub Total
t
t
t
t
t
t
t
t
t
t
t
t
t
t
I
,850.00
9,799.00
1,050.00
8,558.75
6,105.00
310.00
1,550.00
5,310.00
1,555.20
1,010.00
2,316.00
6,520.50
1,040.00
2,905.00
250.00
3.570.00
53L699.45
t
t
t
t
1
1
1
t
1
1
1
1
1
1
1
1
$
$ 1,850.00
$ 4.10
$ 1.75
$ 2.05
$ 9.25
$ 310,00
$ 310,00
$ 35.40
$ 4.86
$ 505.00
$ 19.30
$ 48.30
$ 16.00
$ 2,905.00
$ 250.00
$ 3,.570.00
! 500.00
$ 11,950.00
$ 3,600.00
$ 6,680.00
$ 4,422.00
$ 750.00
$ 2,500.00
$ 8,250.00
$ 1,440.00
$ 350.00
$ 2,400.00
$ 5,400.00
$ 650.00
$ 1,500.00
$ 2,500.00
$ 2500.00
$ 55.392.00
500.00
5.00
6.00
1.60
6.70
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
$ 2,500.00
Sub Total
,500.00
2L500.00
LS
CY
Cy
SY
LF
LS
2390
600
4175
660
DETENTION BASIN AND OVERFLOW PIPE
Erosion Control Measures During Construction
Excavation & Off Site Disposal
Topsoil - Strip, Stockpile, and Replace
Terra Seed - 2" Thickness
750.00
500.00
55.00
4.50
75.00
20.00
40.00
0.00
5
50
EA
LF
SF
EA
LF
SY
Too
LS
LS
LS
4" Draintile, Inc.valves, Fittings, Tie in and Chips
Tie into Existing Outlet Structure
Tie into Existing Manhole I Intake
24" RCP CL JJl wI Bedding & Compacted Granular Backfil
PC Concrete Sidewalk, 4M, Construct
320
2
20
35
66
PC Concrete Access Ramp. Detectable
PC Concrete Curb and Gutter. 2.5'. Construct wI ACe Patch
PC Concrete Pavement, (8") wI Curb & Dowels, Class "C"
Crushed Stone Base
2
3
4
5
6
7
8
9
10
Inc. Handhole
Remove & Replace Exist Elec, Conduit & Wiring
Protect Exist. Hydrant
Traffic and Safety Control
12
13
14
15
16
BIDDER
McDermott Excatlng
UNIT TOTAL
PRICE PRICE
Engineer's Estimate
UNiT TOTAL
PRiCE PRICE
BIDDER
Connolly Construction, 'nc
UNIT TOTAL
PRICE PRICE
,930.00
,155.20
4,927.50
880.00
1,202.00
3,997.09
2,036.64
14,294.50
12,056.65
4,842.00
1,522.80
668.15
1,144.00
3,953.43
1,570.00
1,120.00
3,159.61
543.00
1,396.72
1,179.00
2,110,00
3,380.00
600.00
8,220.00
3,168.00
608.00
947.70
6,762.00
7,616.84
13,749.88
4,225.00
4,420.00
4,725.00
10650.00
54J60.71
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
t
t
1
1
1
1
1
1
$
,930.00
~
~
~
,202.00
67.20
44.00
113.00
59,00
67.25
37.60
29.05
572.00
189.25
785.00
560.00
151.25
543.00
79.00
393.00
2,110.00
1,690.00
600.00
120.00
~
304.00
36.45
23.00
~
98.92
~
4,420.00
4L725.00
1
1
1
1
t
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
t
1
1
1
1
1
1
1
1
1
$
4,185,00
1,246.40
3,741.25
750.00
945.00
3,022.88
6,220.80
3,350.24
9,922.56
2L996.64
,229 ~
340.40
990.00
6,165.50
1,573.92
830.00
4,786.10
210,00
2.973.60
1,155.00
2,310.00
3,904,00
553.00
0,309.25
4,560.00
1,130.00
1,619.80
4,924.50
6,537.30
1,801.10
5,200.00
2,905.00
3,120.00
9588.00
55L096.42
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
t
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
$
$ 4,185.00
$ 4.10
$ 2.05
$ 3.75
$ 945.00
$ 62.61
$ 59.20
$ 105.12
$ 48.64
$ 41,62
$ 30.35
$ 14.80
$ 495.00
$ 295.00
$ 786.96
$ 415.00
$ 229.00
$ 210.00
$ 168.00
$ 385.00
$ 2,310.00
$ 1,952.00
$ 553.00
$ 150.50
$ 4.75
$ 565.00
$ 62.30
$ 16.75
$ 84.90
$ 84.90
$ 16.00
$ 2,905.00
$ 3L120.00
! 2,500.00
! 1,824.00
! 2,628.00
! 1,500.00
! 1,000.00
! 6,246.62
$ ,6,960.72
$ 9,487.50
$ 11,239.25
$ 2,520.00
$ 1,215.00
$ 575.00
$ 790.00
$ 5,222.50
$ 1,624.00
$ 700.00
$ 4,700.25
$ 300.00
$ 3,536.00
$ 1,500.00
$ 1,800.00
$ 3,000.00
$ 850.00
$ 6,165.00
$ 4,320.00
$ 350.00
$ 962.00
$ 5,292.00
$ 6,930.00
$ 12,510.00
$ 3,250.00
$ 1,500.00
$ 6,500.00
$ 3000.00
$ 142L497.84
2,500.00
6.00
1.44
7.50
,000.00
78.00
62.00
75.00
55.00
35.00
30,00
25.00
395.00
250.00
812.00
350.00
225.00
300.00
200.00
500.00
,800.00
,500.00
850,00
90.00
4.50
175,00
37.00
18.00
90.00
90.00
10.00
,500.00
6L500.00
1
1
1
1
1
1
1
1
1
1
1
1
t
t
t
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
$
QUANTiTY
72
40.5
23
2
20.89
2
2
20.89
LS
CY
SY
SY
EA
LF
LF
LF
LF
LF
LF
LF
EA
VF
EA
EA
VF
EA
VF
EA
EA
EA
LS
CY
SF
EA
SY
LF
Too
Too
Too
LS
LS
LS
304
825
200
1.00
20829
273.56
126.5
20435
Backfil
Backfil
Backfil
Backfil
DESCRIPTION
STORM SEWER
Erosion Control Measures During Construction
Topsoil- Strip, Stockpile, and Replace
Terra Seed - 2" Thickness
Sodding
Tie into Existing Junction Box
Storm Sewer, 42~ RCP, CL III wI Bedding
Storm Sewer, 30" RCP, CL III wI Bedding
Storm Sewer, 27" RCP, CL III wI Bedding & Compacted Granulal
Storm Sewer, 24" RCP, CL III wI Bedding & Compacted Granulal
Storm Sewer, 18" RCP, CL III wI Bedding & Compacted Granulal
Storm Sewer, 15" RCP, CL III wI Bedding & Compacted Granula'
Storm Sewer, 6" PVC Schedule 40
72" Dia. Manhole Base wI Bedding
72" Dia. Manhole Sidewall
72" Cia. Manhole Flat top wI Casting
60" Dia. Manhole Base wI Bedding
60" Cia. Manhole Sidewall
48" Cia. Manhole Base wI Bedding & Compacted Granular Backfil'
48" Dia, Manhole Sidewall wI Bedding & Compacted Granular Backfil
7.68
3
1
2
Manhole Frame and Cover
Intake 101-C Special wI Bedding & Compacted Granular Backfil
Intake 101-B wi Bedding & Compacted Granular Backfill
Area Drain Complete
Abandon Existing Storm & Structures
PC Concrete Sidewalk, 4M, Construct
68.5
960
2
26
294
77
139
325
PC Concrete Access Ramp, Detectable
PC Concrete Commercial Drive, Type "A", - Construct
PC Concrete Curb and Gutter, 2.5', Construct
HMA 300k, S, 1 f2" (P
1,1/2" I
one Ba
G 70-34)
pG 64-22
Inc. Handhole
HMA 300k,
Remove & Replace Exist. Elec. Conduit & Wiring
Shoring Design & Installation (for Ex. Light'
Traffic and Safety Control
$
$ 10,650.00
Sub Total
1
~ 9,588.00
Sub Totai
$ 3,000.00
Sub Totai
47.46
.25%
BIDDER
McDermott Excating
UNIT TOTAL
PRICE PRiCE
NO.
2
3
4
5
6
7
8
9
10
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
11
220
$
Total
208J95.87
5.51%
Engineer's Estimate
UNiT TOTAL
PRICE PRiCE
$
Total
I $ 197,889.64 k
Totai
Unde
Over
%
CUSTER I ALLISON HENDERSON PHASE II
STORM SEWER CONSTRUCTiON PROJECT
CIP NO. 7201376
CONSTRUCTION COST ESTIMATE
23-Mar-De
BIDDER
W.C. Stewart Construct. inc.
UNiT TOTAL
PRICE PRICE
,100.00
19,120.00
1,650.00
17,743.75
5,280.00
300.00
1,500.00
13,008.00
1,440.00
1,000.00
4,020.00
6,075.00
774.80
4,189.00
200.00
3500.00
80,900.55
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
$
$ ",00.00
$ 8.00
$ 2.75
$ 4.25
$ 8.00
$ 300.00
$ 300,00
$ 86,72
$ 4,SO
$ 500.00
$ 33.50
$ 45.00
$ 11.92
U,189.00
$ 200.00
$ 3,500.00
Sub Totai
,800.00
,950.00
,350.00
7,743.75
4,785.00
600.00
3,000.00
6,4S0.00
1,360.00
400.00
2,160.00
5,467.50
1,040,00
2,500.00
3S0.00
7,500.00
68L456.25
1
1
1
1
1
1
1
1
1
1
1
1
1
1
$
$
$ 1,800.00
$ 5.00
$ 2.2S
$ 4.25
$ 7.2S
$ 600.00
$ 600.00
$ 43.00
$ 4.25
$ 200.00
$ 18.00
$ 40.50
$ 16.00
$ 2,500.00
L 350.00
! 7,500.00
Sub Totai
822.00
7,887.00
2,160.00
7,743.75
5,280.00
395.00
3,47S,00
0,147.50
1,104.00
280.00
4,290.00
5,906.25
861.25
3.354.00
612.00
3.500.00
67L817.75
1
1
1
1
1
1
t
1
1
1
1
1
1
1
~
822.00
3.30
3.60
4.25
8.00
$
395.00
695.00
67.65
~
140,00
35,75
43.75
13.25
$ 3,354.00
l. 612.00
~ 3,500.00
Sub Totai
t
1
1
1
1
1
1
1
1
1
1
1
$
QUANTITY
2390
600
4175
660
LS
CY
Cy
SY
LF
LS
EA
5
50
320
2
20
35
65
DESCRIPTION
DETENTiON BASiN AND OVERFLOW PiPE
Erosion Control Measures During Construction
Excavation & Off Site Disposal
Topsoil - Strip, Stockpile, and Replace
Terra Seed - 'Z' Thickness
IncValves, Fittings,
into Existing Outlet Structure
into Existing Manhole I Intake
RCP CL 111 wI Bedding & Compacted Granular Backfil
PC Concrete Sidewalk, 4", Construct
in and Chips
Tie
4" Draintile,
Tie
Tie
24'
LF
SF
EA
LF
SY
Too
LS
LS
LS
PC Concrete Access Ramp, Detectable
PC Concrete Curb and Gutter, 2.5', Construct wi ACC Patch
PC Concrete Pavement, (8") wi Curb & Dowels, Class MC"
Inc. Handhole
& Wiring
Crushed Stone Base
Remove & Replace Exist. Elec. Condui
Protect Exist. Hydrant
Traffic and Safety Control
NO.
2
3
4
5
6
7
6
9
10
11
12
13
14
15
16
BiDDER
Top Grade Excavating. inc
UNIT TOTAL
PRICE PRICE
BIDDER
Tschiggfrie Excavating Co.
UNiT TOTAL
PRICE PRICE
BIDDER
W.C. Stewart Construct, inc.
UNIT TOTAL
PRICE PRICE
500.00
836.00
7,008.00
1,700.00
1,000.00
21,95440
20,82400
25,273,00
12,50112
3,175.20
1,602.18
728.87
1,500.00
4,075.50
1,250.00
1,250,00
3,866,50
419.00
1.57530
792.00
2,250.00
4,000.00
700.00
7,747.35
4,560.00
1,300.00
1,339.00
4,410.00
7,449.75
13,448.25
4,296.50
500.00
8,500.00
10.200.00
82L531.92
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
t
1
1
1
1
1
1
1
1
1
1
1
1
1
$
500.00
2.75
3.84
8.50
,000.00
05.55
76.00
99.00
61.28
44.10
39.56
31.69
750.00
195.00
625.00
625.00
185.00
419.00
89.00
264.00
2,250.00
2,000.00
700.00
650.00
51.50
15.00
96.75
96.75
13.22
500.00
$ 8,500.00
$ 10.200.00
Sub Totai
3.10
4.75
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
t
1
1
1
1
1
1
1
1
1
1
$
,800.00
684.00
9,398.75
1,700.00
500.00
7,91294
4,225,12
23,402.50
9.706,63
3,744.00
1,599.75
1,035.00
3,600.00
3,760.20
1,300.00
3,600.00
2,924,60
1,050.00
1,66192
750.00
-
3,500,00
5,800.00
650.00
8,905.00
4,080.00
400.00
1,053.00
5,292.00
6.776,00
12,232.00
5,200.00
2,500.00
5,000.00
11 000.00
76L743.41
1
1
1
1
1
1
1
t
1
1
1
t
t
t
1
1
t
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
L800.00
2.25
5.15
8.50
500.00
86.00
52.00
185.00
47.50
52.00
39.50
45.00
,800.00
180.00
650,00
,800.00
140.00
,050.00
94.00
250.00
3,500.00
2,900,00
650.00
130.00
~
200.00
40.50
18.00
88.00
88.00
16.00
2,500.00
5,000.00
$11.000.00
Sub Total
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
,750.00
2,097.60
9,398.75
1,700.00
346.00
8,496.15
3,253.98
8,159.08
~ 01.47
2,844.00
,543.05
585.35
,270.00
4,491.35
1,490.00
1,100.00
3,697.53
331,00
2,510.56
795.00
1,935.00
5,750.00
1,060.00
9,179.00
3,312.00
360.00
1,162.20
5,791.80
7,392.00
3,344.00
4,030.00
2,500.00
9400.00
66L176,86
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
t
t
t
1
$
lSO.OO
6.90
5.15
8.50
346.00
88.80
48.45
143.55
73.90
39.50
38.10
25.45
635.00
215.00
745.00
550.00
177.00
331.00
142.00
265.00
,935.00
$ 2,875.00
$ 1,060.00
1 134.00
1 3.45
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
$
$ 180.00
$ 44.70
$ 19.70
$ 96.00
$ 96.00
$ 12.40
$
$ 2,500.00
$ 9,400.00
Sub Totai
EA
VF
EA
VF
EA
EA
EA
LS
CY
SF
EA
SY
LF
Too
Too
Too
LS
LS
LS
LS
CY
SY
SY
EA
LF
LF
LF
LF
LF
LF
LF
EA
VF
EA
QUANTITY
DESCRIPTION
STORM SEWER
Erosion Control Measures During eonstruction
Topsoil- Strip, Stockpile, and Replace
Terra Seed ~ 2" Thickness
304
825
200
.00
2
2
20,89
208.29
273.56
126.5
204.35
72
40.5
23
2
20.89
Backfil
Backfil
Backfil
Backfii
Sodding
Tie into Existing Junction Box
Storm Sewer, 42" RCP, CL II! wI Bedding
Storm Sewer, 30" RCP, CL III wI Bedding
Storm Sewer, 27" RCP, CL II( wI Bedding & Compacted Granulal
Storm Sewer, 24" RCP, CllH wI Bedding & eompacted Granulal
Storm Sewer, 18~ RCP, CllU wI Bedding & Compacted Granulal
Storm Sewer, 15~ RCP, Cllll wI Bedding & Compacted Granulal
Storm Sewer, 6" PVC Schedule 40
72" Dia, Manhole Base wI Bedding
72" Dia. Manhole Sidewall
72" Dia. Manhole Flat top wI Casting
60" Dia. Manhole Base wI Bedding
60" Oia. Manhole Sidewall
48" Oia. Manhole Base wI Bedding & Compacted Granular Backfill
48" Oia. Manhole Sidewall wI Bedding & Compacted Granular Backfil
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
7,68
3
1
2
Manhole Frame and Cover
Intake 101.C Special wi Bedding & Compacted Granula
Intake 101-B wI Bedding & Compacted Granular Backfil'
68.5
960
2
26
294
77
139
325
Backfil
Area Drain Complete
Abandon Existing Storm & Structures
PC Concrete Sidewalk, 4", Construct
PC Concrete Access Ramp, Detectable
PC Concrete Commercial Drive,
PC Concrete Curb and Gutter,
Type "A", . Construct
2,5', Construct
22
23
24
25
26
27
28
29
30
S, 1/2" (PG 70~34)
I, 1/2" (PG 64--22
Crushed Stone Base
300k,
300k,
HMA
HMA
Inc. Handhole
Remove & Replace Exist. Elec. Conduit & Wiring
Shoring Design & Installation (for Ex, Ught
Traffic and Safety Control
31
32
33
34
263L432.47
33,12%
BIDDER
Top Grade Excavating, inc
UNIT TOTAL
PRICE PRICE
NO.
$
Totai
245..199.66
23.91%
BiDDER
Tschlggfrie Excavating Co.
UNIT TOTAL
PRICE PRICE
$
Total
233L994.6
8.24%
$
Totai
Over I Under H
%
BIDDER
McCiain Excavating Co. lnc
UNiT TOTAL
PRiCE PRiCE
000.00
9,717.50
3,450.00
23,380,00
5,445.00
1,200.00
4,250.00
11,700.00
1,280.00
1,200.00
30,000,00
3,375.00
1,300.00
2,850.00
500.00
6,000.00
18L647.50
1
1
1
1
1
1
1
1
1
1
1
1
1
1
I
$
$ 1,000.00
$ 8.25
$ 5.75
$ 5.60
$ 8.25
$ 1,200.00
$ 850.00
$ 78.00
$ 4.00
$ 600.00
$ 250.00
$ 25.00
$ 20.00
$ 2,850.00
1. 500.00
$ 6,000.00
Sub Total
QUANTITY
2390
600
4175
660
LS
CY
Cy
SY
LF
LS
EA
LF
SF
EA
LF
SY
Too
LS
LS
LS
DESCRIPTION
DETENTION BASIN AND OVERFLOW PiPE
Erosion Control Measures During Construction
Excavation &
Off Site Disposal
Topsoi Strip, Stockpile, and Replace
Terra Seed - 2" Thickness
5
50
320
2
20
35
65
4" Draintile, InC.Valves, Fittings, Tie
Tie into Existing Outlet Structure
Tie into Existing Manhole I Intake
24" RCP Clltl wI Bedding & Compacted GranuJa
PC Concrete Sidewalk, 4", Construct
in and Chips
NO.
2
3
4
5
6
7
8
9
Backfil
pe Concrete Access Ramp, Detectable
pe Concrete Curb and Gutter, 2.5', Construct wI ACC Patch
PC Concrete Pavement, Wl wi Curb & Dowels, Class "C"
Crushed Stone Base
Inc. HandhoJe
& Wiring
Elec. Condui
Remove & Replace Exist.
Protect Exist. Hydrant
Traffic and Safety Control
12
13
14
15
16
o
1
BIDDER
McCialn excavating Co. Inc
UNIT TOTAL
PRICE PRICE
.
2,000.00
3,040.00
7,300.00
2,100.00
1,500.00
6,328,00
4.179.50
9,685.00
9,584.00
3,960.00
3,442.50
1,012.00
7,040.00
3.657,50
1,400.00
5,600.00
2,508.00
5,900.00
4,814.40
720.00
500.00
6,850.00
3,840.00
1,200.00
1,430.00
4,410.00
7,700.00
3,900.00
5,850.00
--LQQ
9,500.00
7400.00
207L541.90
2,650.00
6L540,00
1
1
1
t
1
t
t
1
1
1
1
t
1
t
1
1
t
1
t
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
$
$ 2,000.00
$ 10,00
$ 4.00
$ 1050
$ 1,500.00
$ 78.50
$ 51.75
$ 155.00
$ 96.00
$ 55.00
$ 85.00
$ 44.00
$ 3,520.00
$ 175.00
$ 700,00
$ 2,800.00
$ 120.00
$ 5,900.00
$ 272 00
$ 240.00
$ 2,650.00
$ 3,270.00
!. 500.00
! 100.00
! 4.00
!. 600.00
1 55.00
1 15.00
!. 100,00
! 100.00
! 8.00
$ .00
QUANTITY
LS
CY
SY
SY
EA
LF
LF
LF
LF
LF
LF
LF
EA
VF
304
825
200
1.00
208.29
273.56
126,5
20435
72
40.5
23
2
20.89
DESCRIPTION
STORM SEWER
Erosion Control Measures During Construction
Topsoil. Strip, Stockpile, and Replace
Terra Seed - 2" Thickness
$ 9,500.00
$ 17,400.00
Sub Totai
2
2
20,89
EA
EA
VF
EA
VF
EA
EA
EA
LS
CY
SF
EA
SY
LF
Too
Too
Too
LS
LS
LS
72" Dia. Manhole Base wI Bedding
72" Dia. Manhole Sidewall
72" Dia. Manhole Flat top wI Casting
60" Dia. Manhole Base wI Bedding
60" Dia. Manhole Sidewall
48" Dia. Manhole Base wi Bedding & Compacted Granular Backfil
48" Dia. Manhole Sidewall wi Bedding & Compacted Granular Backfil
7.68
3
Manhole Frame and Covel
Intake 101-C Special wI Bedding & Compacted Granular Backfil
Intake 101-B wI Bedding & Compacted Granular Backfill
2
Area Drain Complete
Abandon Existing Storm & Structures
PC Concrete Sidewalk, 4", Construct
68.5
960
2
26
294
77
139
325
Type "A", - Construct
2.5', eonstruct
PC Concrete Access Ramp, Detectable
PC Concrete Commercial Drive,
PC Concrete Curb and Gutter.
HMA 300k, S, 112M (P
300k,I, 112ft'
led Stone Sa
G 70-34)
pG 64-22)
Inc. Handhole
NO.
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
HMA
32 Remove & Replace Exist. Elec. Conduit & Wiring
33 Shoring Design & Installation (for Ex. Light
34 Traffic and Safety Control
wI Bedding
wi Bedding
wI Bedding & Compacted Granular Backfil
wI Bedding & Compacted Granular Backfil
wI Bedding & Compacted Granular Backfil
wI Bedding & Compacted Granular Sackfil
RCP, CL I
RCP, CL I
27' RCP, CL I
24" RCP, CL I
18" RCP, CL I
15" RCP, CL I
6" PVC Schedule 40
Sodding
Tie into Existing Junction Box
42"
Storm Sewer,
Storm Sewer, 30"
Storm Sewer,
Storm Sewer,
Storm S<
Storm S
Storm S
~wer,
ewer,
ewer,
324,189.40
63.82%
$
Total
H
Unde
~.Over
,.
5~~~E
~ck~
MEMORANDUM
February 28, 2006
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: Initiation of the Custer/Allison-Henderson Sewer and Detention Basin
Project (CIP 7201376)
City Engineer Gus Psihoyos recommends initiation of the bidding process for the
Custer/Allison-Henderson Sewer and Detention Basin Project, and further recommends
that a public hearing be set for April 3, 2006.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
//ll.{ ~~"/12~ j _
Michael C. Van Milligen
MCVM/jh
Attachment
cc: Barry Lindahl, Corporation Counsel
Cindy Steinhauser, Assistant City Manager
Gus Psihoyos, City Engineer
D'G~~E
~<k~
MEMORANDUM
February 27, 2006
FROM:
Michael C. Van Milligen, City Man;~~
Gus Psihoyos, City Engineer ~~
TO:
SUBJECT:
Initiation of the Custer/Allison-Henderson Sewer and Detention Basin
Project (CIP 7201376)
INTRODUCTION
The enclosed resolutions authorize the public bidding procedure for the Custer/Allison-
Henderson Sewer and Detention Basin Project.
BACKGROUND
In 1999, intense rains caused thousands of dollars in property damage throughout
Dubuque, prompting a Presidential Disaster declaration. Figure 1 is a photo of the
flooding that occurred to one of the homes just west of the N. Grandview and Custer
intersection. Pictured is a basement with three feet of black water almost reaching the
piano keys.
Subsequently, funds were established in the Capital Improvement Program Budget to
improve the drainage from the sump on Custer to the lower portion of Allison-
Henderson Park. The objective was to design a system that if surcharged would flood
the lower portion of the park instead of homes. The lower portion of the park was prone
to flooding prior to its use as a detention basin. As proposed, park drainage will improve
with the addition of an outlet structure and drain tile. Figure 2 shows the park flooded
prior to any modifications associated with the detention basin improvements.
DISCUSSION
Some of the improvements associated with the detention basin have been completed.
Within the park, the outlet structure and storm sewer was constructed during the
summer of 2004. At that time, it was discovered that the existing 24-inch clay storm
sewer that runs along N. Grandview from the park to University Ave. was in poor
condition. Funds were established to reconstruct the storm sewer in the following
Capital Improvement Program Budget (FY06).
Figure 1. Basement flooding that occurred in 1999. The black water nearly reached the piano keys.
Project initiation was postponed because of the reconstruction of Nowata Street this
past summer. The Custer/Allison-Henderson Sewer and Detention Basin Project
involves closing N. Grandview to install storm sewer.
A private development was started at the intersection of University Ave. and N.
Grandview by the development group of Finley Hospital, Hartig Drug, and Dubuque
Bank & Trust this past summer. To meet detention basin requirements, the
development group asked City Engineering about the possibility of utilizing the City's
proposed Allison-Henderson detention basin instead of constructing a new detention
basin of their own. The City has already entered into two other Stormwater Detention
Services agreements for the NW Arterial and Carter Road detention basins.
II
i1
~- '
Figure 2. Photo of a flooded Allison-Henderson Park prior to construction of the hockey rink or
stormwater improvements. An outlet structure has already been installed and drain tile will be
added to better drain the park.
Engineering's hydrologic and hydraulic analysis indicates that the proposed Allison-
Henderson Detention Basin can provide the detention required for the Finley, Hartig,
DB&T development. Therefore, a recommendation to enter into a service agreement
with the development group of Finley Hospital, Hartig Drug, and Dubuque Bank and
Trust has been presented to the City Council for consideration. Per the terms of the
agreement, the City will receive a payment of $26,451.00 and beginning in 2007, the
City will receive an annual payment of $300 to increase by 2.5% each year thereafter.
The schedule for the project will be as follows:
Advertisement for Bids
Notice of Hearing on Plans & Specifications
Receipt of Bids
Public Hearing
Award of Contract
Final Completion Date
March 10, 2006
March 17, 2006
March 23, 2006
April 3, 2006
April 3, 2006
August 11, 2006
RECOMMENDATION
I recommend that the City Council establish the date for the public hearing, and
authorize the City Clerk to advertise for bids for the Custer/Allison-Henderson Sewer
and Detention Basin Project.
BUDGET IMPACT
The construction cost estimate for the Custer/Allison-Henderson Sewer and Detention
Basin Project is:
Construction
Contingency
Engineering
$201,960.00
20,196.00
30,294.00
$252,450.00
Total Project Estimate
The project will be funded with the Fiscal Year 2006 Custer/Allison-Henderson Sewer
and Detention Basin Project appropriations in the amount of $200,229 and the detention
basin and storm sewer service fees from the owners of the Finley Hospital, Hartig Drug,
and Dubuque Bank & Trust owners in the amount of $26,451. Additional funding will
come from the Fiscal Year 2007 Storm Sewer Improvement/Extensions in the amount of
$79,229.
ACTION TO BE TAKEN
The City Council is requested to establish the date for the public hearing and to
authorize the City Clerk to advertise for proposals through adoption of the attached
resolutions.
attachments
Prepared by Deron Muehring
cc: Cindy Steinhauser, Assistant City Manager
Dawn Lang, Budget Director
Bill Baum, Economic Development Director
Pam Myhre, Associate Planner
Deron Muehring, Civil Engineer II
----1
---~ ~-
-----: 1.'/MOWAlA ----
_---~ '\-~,- '_ ="~_ --=.;c~.cc:::::::~,
'-----7 ,
'\ I \ t'.
~ ," ! ~. ---.--- )\ {W> WARMING HOUSE
----~__.', ; ~.;r-;-~ETEN:N A:EA :,'
--- \ I'
'I : I I
\ \ \ ,\ '\. - ~,/
" j '\ ~ : \ ! "'-, INLlNE RINK
----- .::; \ \ I "'-
----r~~l\ I:: - - '
, : ~ t----- ~
\ DO\\S:
PJ=__J I M. GI\AMD'4'~
----.~ \ rc=-J' '~'\ 'I" 'I '
'T.-SI "I' _--.a-1, ,\ ::" "
~-\ ~O___L-.J-- -__~
_.ll..D It- -,hr-~:.::;::~-~mr " _~\
.-.---, , \,' I 11
__ \ 0 ,\ "
SITE LOCATION MAP J~
NOT TO SCALE .., ~
z--_~____
-----
---~:-:'::::?
--------
---- ----
I
PROPOSED STORM SEWER:
I
,
I
,
,
I
,
,
I
I ~
: CC
I ~
: ;;;
=
...
>
z
=
ALLISON - HENDERSON PARK
-~
.
n ,~,~~,+ "ORM 1wm
3ROST
VICINITY MAP
....n1I1IIIIIin
NORTH
DUBWuE
S'--9 fk Spi'Ut
EXHIBIT D
RESOLUTION NO.
PRELIMINARY APPROVAL OF PLANS AND SPECIFICATIONS
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF DUBUQUE, IOWA:
That the proposed plans, specifications, form of contract and estimated cost for
the Custer/Allison-Henderson Sewer and Detention Basin Project in the estimated
amount of $252,450.00 are hereby approved and ordered filed in the office of the City
Clerk for public inspection.
Passed, adopted and approved this
day of
2006.
Roy D. Buol, Mayor
Attest:
Jeanne F. Schneider, CMC, City Clerk
RESOLUTION NO.
FIXING DATE OF HEARING ON PLANS AND SPECIFICATIONS
Whereas, the City Council of the City of Dubuque, Iowa has given its preliminary
approval on the proposed plans, specifications, and form of contract and placed same
on file in the office of the City Clerk for public inspection of the Custer/Allison-
Henderson Sewer and Detention Basin Project.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF DUBUQUE, IOWA:
That a public hearing will be held on the 3rd day of April, 2006, at 6:30 p.m. in the
Public Library Auditorium at which time interested persons may appear and be heard for
or against the proposed plans and specifications, form of contract and cost of said
improvement, and the City Clerk be and is hereby directed to cause a notice of time and
place of such hearing to be published in a newspaper having general circulation in the
City of Dubuque, Iowa, which notice shall be not less than four days nor more than
twenty days prior to the day fixed for its consideration. At the hearing, any interested
person may appear and file objections to the proposed plans, specifications, contract, or
estimated cost of the improvement.
Passed, adopted and approved this
day of
,2006.
Roy D. Buol, Mayor
Attest:
Jeanne F. Schneider, CMC, City Clerk
NOTICE OF HEARING ON PLANS AND SPECIFICATIONS
Notice of public hearing on proposed plans and specifications, proposed form of
contract and estimate of cost for the Custer/Allison-Henderson Sewer and Detention
Basin Project Project.
Proiect Description: The storm sewer project consists of two parts with
separate deadlines. The first part of the project will consist of creating a detention basin
adjacent to the hockey rink and constructing an overflow pipe across Loras Boulevard to
outlet in an existing structure on Adair Street. This portion of the project will have a
completion deadline of May 12, 2006 due to the need to have that area of the park
available for summer activities. The second part of the project will consist of extending
a new storm sewer, to the South, from an existing junction box located between the
North end of the hockey rink and Grandview Avenue. The new storm sewer will serve
the Custer Street area and the University/Grandview intersection and will replace an
existing smaller storm sewer in Grandview Avenue which will be abandoned in place.
The deadline for this portion of the project will be August 11, 2006.
NOTICE IS HEREBY GIVEN: The City Council of Dubuque, Iowa will hold a
public hearing on the proposed plans, specifications, form of contract and estimate of
cost for the Custer/Allison Henderson Sewer and Detention Basin Project in accordance
with the provisions of Chapter 384, City Code of Iowa, at 6:30 p.m., on the 3rd day of
April, 2006, in the Public Library Auditorium, 360 West 11th Street, in Dubuque, Iowa.
Said proposed plans, specifications, form of contract and estimate of cost are now on
file in the office of the City Clerk. At said hearing any interested person may appear and
file objections thereto or to the cost of the improvements.
Any visual or hearing-impaired persons needing special assistance or persons
with special accessibility needs should contact the City Clerk's office at (563) 589-4120
or TDD at (563) 690-6678 at least 48 hours prior to the meeting.
Published by order of the City Council given on the
,2006.
day of
Jeanne F. Schneider, CMC, City Clerk
RESOLUTION NO.
ORDERING BIDS
NOW THEREFORE, BE IT RESOLVED BY THE COUNCIL OF THE CITY OF
DUBUQUE, IOWA:
That the Custer/Allison-Henderson Sewer and Detention Basin Project is hereby
ordered to be advertised for bids for construction.
BE IT FURTHER RESOLVED, that the amount of the security to accompany
each bid shall be in an amount which shall conform to the provisions of the Notice to
Bidders hereby approved as a part of the plans and specifications heretofore adopted.
That the City Clerk is hereby directed to advertise for bids for the construction of
the improvements herein provided, to be published in a newspaper having general
circulation in the City of Dubuque, Iowa, which notice shall not be less than four days
nor more than forty-five days prior to the receipt of said bids at 2:00 p.m. on the 23rd day
of March, 2006. Bids shall be opened and read by the City Clerk at said time and will
be submitted to the Council for final action at 6:30 p.m. on the 3rd day of April, 2006.
Passed, adopted and approved this _ day of
,2006.
Roy D. Buol, Mayor
Attest:
Jeanne F. Schneider, CMC, City Clerk
'J
,
~
.
BID PROPOSAL
The bidder hereby certifies that they are the only person or persons interested in this
proposal as principals; that an examination has been made of the plans, specifications, and
contract form, including the special provision contained herein, and of the site of the work,
and the bidder understands that the quantities of work shown herein are approximate only
and are subject to increase or decrease; and further understand that all quantities of work,
whether increased or decreased, are to be performed at the unit price as stipulated herein;
the bidder proposes to furnish all necessary machinery, equipment, tools, labor and other
means of construction, and to furnish all materials specified in the manner and time
prescribed and to do the work at the prices herein set out.
Accompanying this proposal in a separate envelope is a cashier's or certified check
payable to the City Treasurer, City of Dubuque, drawn on a bank in Iowa or a bank chartered
under the laws of the United States, in the amount of ten percent (10%) of the bid submitted;
or a bid bond in the penal sum of ten percent (10%) of the bid submitted executed by the
bidder and an acceptable Corporate Surety. It is understood that this proposal guarantee will
be retained in the event the formal contract or bond is not executed, if award is made to the
undersigned.
The bidder further agrees to execute a formal contract and bond, if required by the
contract documents, within seven (7) days of the award of the contract by the City Council,
and that they will commence work on or about ten (10) days after the date of the contract,
and will complete the work within the specified contract period or pay the liquidated damages
stipulated in the contract documents.
The bidder acknowledges receipt of the following addendum:
Addendum No.1
Dated: March 71, 2006
Dated:
Dated:
PRINCIPAL:
Connolly Construction Inc
Contractor
18409 N Cascade Rd
Address
Individual ( ) Partnership ( ) Corporation (x)
Peost8,
City
.fA 52068
By: ('~ I /~ JQ
Sign~-.
IO"18
State
520';8
Zip
Vice Presif'ient
Title
March 23, 2006
Date
Note: To be completed by out of State bidders.
The State of does ( ) / does not ( ) utilize a percentage preference
for in-state bidders. The amount of preference is percent.
I STORM SEWER
1 Erosion Control Measures During Construction
2 Topsoil - Strip, Stockpile, and Replace
3 Terra Seed - 2" Thickness
4 Sodding
5 Tie into Existing Junction Box
6 Storm Sewer, 42" RCP, CL III wi Bedding
7 Storm Sewer, 30" RCP, CL III wi Bedding
8 Storm Sewer, 27" RCP, CL III wi Bedding & Compacted Granular Backfill
9 Storm Sewer, 24" RCP, CL III wi Bedding & Compacted Granular Backfill
10 Storm Sewer, 18" RCP, CL III wi Bedding & Compacted Granular Backfill
11 Storm Sewer, 15" RCP, CL III wi Bedding & Compacted Granular Backfill
12 Storm Sewer, 6" PVC Schedule 40
13 72" Ola. Manhole Base wi Beddin9
14 72" Oia. Manhole Sidewall
15 72" Oia. Manhole Flat top wi Casting
16 60" Oia. Manhole Base wi Bedding
17 60" Oia. Manhole Sidewall
18 48" Oia. Manhole Base wi Bedding & Compacted Granular Backfill
1948" Oia. Manhole Sidewall wi Bedding & Compacted Granular Backfill
20 Manhole Frame and Cover
21 Intake 101-C Special wi Bedding & Compacted Granular Backfill
22 Intake 1 01-B wi Bedding & Compacted Granular Backfill
23 Area Drain - Complete
24 Abandon Existing Storm & Structures
25 PC Concrete Sidewalk, 4", Construct
26 PC Concrete Access Ramp, Detectable
27 PC Concrete Commercial Drive, Type "A", - Construct
28 PC Concrete Curb and Gutter, 2.5', Construct
29 HMA 300k, S, 1/2" (PG 70-34)
30 HMA 300k, I, 1/2" (PG 64-22)
31 Crushed Stone Base
32 Remove & Replace Exist. Elec, Conduit & Wiring - Inc. Handhole
33 Shoring Design & Installation (for Ex. light)
34 Traffic and Safety Control
1 LS 1930.00
304 CY 3 . 80
1825 SY 7.70
200 SY 4.40
1.00 EA 1202.00
208 LF 67.20
274 LF 44.00
127 LF 113.00
204 LF 59.00
72LF 67.25
40.5 LF 37.60
23 LF 29.05
2 EA 572. DO
20.9 VF 1 89 . 75
2 EA 785.00
2 EA 560.00
20.9 VF 1 5 1 . 25
1 EA 543.00
17.7 VF 79.00
3 EA 393.00
1 EA 21 10.00
2EA1690.00
1 LS 600.00
68.5CY 170.00
960 SF 3.30
2 EA 304. DO
26 SY 36.45
294 LF 73.00
77 Ton 98.97
139 Ton 98.92
325 Ton 13.00
1 LS it420.00
1 LS 4775.00
1 Lsl 0650.00
Sub Total
TOTAL BID
1930.00
1155.20
4927 . 50
880.00
1202.00
13977.liO
12051i.00
14351.00
12036.00
4842.00
1522.80
668.15
1144.00
3955.33
1570.00
1170.00
3161.13
543.00
1398.30
1179. DO
2110.00
3380.00
600.00
8220.00
3168.00
li08.00
947.70
li762.00
7616.84
13749.88
4725.00
4420.00
4775.00
10650.00
[154,801.4)
,
~20, 188.1.
CITY OF DUBUQUE, IOWA
CUSTER I ALLISON HENDERSON PHASE II
STORM SEWER CONSTRUCTION PROJECT
CIP NO. 7201376
BID FORM
NO. DESCRIPTION
UNIT
QUANTITY PRICE
I DETENTION BASIN AND OVERFLOW PIPE
1 Erosion Control Measures During Construction
2 Excavation & Off Site Disposal
3 Topsoil- Strip, Stockpile, and Replace
4 Terra Seed - 2" Thickness
5 4" Draintile, Inc.Valves, Fittings, Tie in and Chips
6 Tie into Existing Outlet Structure
7 Tie into Existing Manhole I Intake
8 24" RCP CL III wI Bedding & Compacted Granular Backfill
g PC Concrete Sidewalk, 4", Construct
10 PC Concrete Access Ramp, Detectable
11 PC Concrete Curb and Gutter, 2.5', Construct wi ACC Patch
12 PC Concrete Pavement, (8") wi Curb & Dowels, Class "C"
13 Crushed Stone Base
14 Remove & Replace Exist. Elec. Conduit & Wiring - Inc. Handhole
15 Protect Exist. Hydrant
16 Traffic and Safety Control
1 LS 1615.00
2390 CY 5.80
600 CY 3.RO
4175 SY 2.70
660 LF 8.50
1 LS 535.00
5 EA 435.00
150 LF 45.85
320 SF 3.30
2 EA 304.00
120 LF 37.50
135 SY 42.45
65 Ton 13.00
1 LS 3825.00
1 LS 660.00
1 LS 3935,00
Sub Total
TOTAL
PRICE
1615.00
13862.00
2280.00
11272.50
5li10.00
535.00
2175.00
liAn.50
10Sh.00
h08.00
4500.00
5730.70
81t5.00
3825.00
6liO.00
3935.00
tli5,381i.75j
BID BOND
KNOWN AlL MEN BY THESE PRESENTS, that we Connolly Construction, Inc.
as Principal (Contractor), !Ind United Fire & Casualty Company , as Surety, are held
and firmly bound unto the unto the City of Dubuque, Iowa (City), In the penal sum of _
Ten Percent of Attached Bid in lawful money of the United States, for the payment of
which sum well and ttuly to be made. we bind ourselves, our heirs, executors,
administrators, and llUCO'lSSOrS, jointly and severally, firmly by these presents. The
condition of this obligation is such that whereas the Principal has submitted the
accompanying bid, dated 23rd day of March , 2006, for the Cusler I
Allison Henderson PhaBe II Storm Sewer Construction Project
NOW, THEREFORE, jf the Principal shali not wiihdraw said bid within the period
specified therein during the opening of same, or If no period specified, within thirty (30)
days after Hid opening, and shall within the period specified therefore, If no period be
specified, within seven (T) days after too prescribed forms are presented to him for
signature, enter Into a written contract with the Municipality, in accordance with the bid
as accepted, and give bond with good and suffICient surety or sureties, as may be
r8QUlrect for the faithful pelformance and proper fulfillment of such contract, then the
above obligation shall be void and of no effect, otherwise to remain in full force and
virtue.
By virtue of statutory authority, the full Bmount of this bid bond shall be forfeited
to the Municipality In liquidations of damages sustained In the event that the afore
de15cribed bidder, Principal, falls to execute the contract end provide the bond as
provided in the specifications or by law.
IN WITNESS WHEREOF, the above bounden parties have executed this
Instrument under their several seals this ? 1 ,t day of March , 2006,
the name and corporate seal of eech corporate party being hereto affIXed and these
presents duly signed by Its undersigned representative pursuant to authority of Its
governing body.
PRINCIPAl.:
SURETY:
Connoliy Construction, Inc.
Contractor
By: ~
S.
Ignature
Unhed Fire & Casualty Comp31:j-
Surety Company
By: ~.', - t.. W~
Signature
Vice President
Tide
Attorney-in-Fact
Trtle
3/72/06
Dete
3/21/06
Date
TOTAL P.1il3
UNITED PlRe &C~UAl;TY.i:()MP.i\NY
HQME OfFICl!r.CEDP,ij RAPlll., IOWA .....
CERTIFIED Copy OF POWER OF ATTORNEY
(Original on file et Home Office 01 Company - See Certification)
.' . -',""".'
. """"" .
-....,..-. ,-.,' -.'-:,' .::."
"--', ,".- "'" ....-
.' ....., ,', . ,- ., . ,
.'- ....... '.
-, " ... "-.'- '"'.''' '. '" ... ,'" .- .". ... " .... -'
KNOW All, MEN 8Y THESe PRI!SENTs, Thatthe UNITED.FIRE & CASUAUY COMPANY, a ~tpor.tion duly orglnlN<! and existing
under the taws 01 the Stale of IoWa, and havil1g ~s principal office In Cedar RapidS, State of Iowa, does make, constitute and appolnt
PATIUCIA A. PRICI<, OR DAVID l'IlITZ, OR D!ANII .k. .HBDRICK, OR idlITB H. $IIIDBI!:llG, CHAIlLES J. AlII)llACCHIO,
OR OLIVIA PHAIl, ALL IIIDIVIDUALLY of DUBUQUE IA
:' ':,':.':' ,:::i .' .:_ ':':, .:', .' ..". .~':_ :,' . " ': ,: ::,:: " . . _ '. > '''_'' ,,0 _: ; _:: .
. llt;trQ!o illJd laWftJ1Aito';"y($).lnCF~ ~Ih power anditu\hority herebyconlarr811to ~Igl), seal.and eXBoute.jnltS lJehellil~ la'l\'fllI#oIldS,
U"d~kln~e~~owerObli!l"ioryi"sIl'tJmentscl simlh!r nelure as follows: . ~~an" . A~.)., J~nds .. ..... .. ..' .. ........ .... ..... ....
and 10 bittdUlollTEO.FU1<I. &'CASUAtTY COMPANYlhereby eS fully arid 10 Ihesamll .extent. as il such Insltumenls were.igflad by !fie. .
duly authOrized officers 01 UNITED FIRE & CASUAl; TY COMPANY and elllhe acts 01 said Attorney, pursuanllo the authority heraby
glv<ln~r.herebYl'!\tifi!ldan4.confirmed. .. .. .... ... .... ..... . .. ... .'
CA$U~~ec~iJ~e~!>y~.~I'j;C~tinuOUSllr:~ shallrema;n in Nil 10rcerdeff~unW;"""kid bYUN!1"gD\IRE &
... .Tl!i.s power ofAItQ~is mIl.de l,~d~Ul.d p~~ua~ttoand byeuihOrlty ?r IhefO~ng~Y.Lawduly ado~bY Boerdol
(}i"l;lmqfll1eCol1)l>8nyi)nAprll.18;:1117~i '.' . '.'. ....... ...., ..... ...... .
., . ". "... "Article V - surety Bonds and undertakings""
Section 2, Appointment 01 Attorney-in-Fact. "The Presidenl or any Vice President, or any olher ollicer 01 the Company may,
frofllllme 10 ~me, appoint by written certlficales attorneys-in-fact to actin behalf ollhe Compal1Y in Ih.e execution q)!,olicie.; o!
. jn.s,ur8nl'8,b(\n~'Hnderta/(lngs and oIher obllgalory Instruments 01 like nature. The slgnalure o(any officer euihori~herebY, ......
. jjrnHllecC\tporote.sasl,Il1JIY be affixed by lacsimilelo any power of attorney or special power ofattol1ley otce!tlfic8tJon Of . .
!lltherauthorizeo h~ebY; S~ch signature and seal, when so usad, being edopted by Ihe ComJl"nYas.theoriQinal signalflrepf
.u.9~<'ffieer.andlh..otigin.oJ seal 01 Ihe Company, 10 be valid and binding upon the Company wnh thesamB foroeande!fecfas ...
l.hq99h)'tlanijI,IIY affl~ad. . Such attorneys-in fect, subjecllo the IImllations set lorth in Ihelr resp~rvec..rtificat~ Of.~orll>'. . .
shalltiave !uli power to bind Ihe Company by thalr signature and llX8CU!ion 01 any such instrumenlt; and to atlaehthe seel 01
the Company thereto. The President or any Vice President, the Board 01 Directors or any other officer 01 Ihe Company may at
. ery lime.rBUJlke allpt1Wer.and authority previously given to any attomey-In-fact. . .
(I IN WiTNeSS WHEREOF, the UNITED FIRE & CASUALTY COMPANY has causetl thesa presenlslo be signed by
ftS vice preSident end ~s corporale seal to be hereto affixed this 11th <lay of FeIlruary, 2005
1m UNITED FIRE & CASUALTY COMPANY
Z By 4?f ({ ~ Viee Presld.nt
State ~'~,901!!1tY 01;Liri6, $J: .
"-'. ..
". '.'" --'. ... . ..'..... .'
"'.o'n.': l.i;~li."~'y,'-ot-::~~tuai:,),::~pps, before me p.rsonal.~y came Ran~y A. ilalll.o'- __':" '.. :::, "';,
to me~, W\'9 tl"'nll by me dUly sworn, did deposa end say; Ihat he resides in Cedar Rapids, SIele'lf io;va: Ihel hl!".aVIC" ..
. President anhil UNITEO FIRE & .CASUAL TY COMPANY, the corporation described in and which execuledthe abo1/8 InStrument that
he knows Ihe seal 01 said corporalion; that the seal affixed to.'~e said insltumenl is such corporale seal; th~ it was so affiXed pursuant
I.'t.aulhO. .,.r.. ity... given.~.y li1..... 80....". rd...ql.D. if. e..l1I...ors....... 9...f.. S81.... d co......rp.o.....rat.io.. "... a.hd that h~.Si9"ed....;.nis..".....m. ..~.I~ ,.,1.' ..e.rr~~~~.. ~ ...UU...f$ TS.....tu. ant..tloO..II.~.. ...a auih;>utho....... .~ riity. ,and'
acknOwledgeS same 19 be lhe .ctan~d~of said corpC~rQn. .... vYYi"\~~. . .
. .1'.' MrptELLE~~N.. .. ... ...... .. . .. ... .
....." c~""" j".....~ 704?4J "Nolary P\,bll~ . .. .... .
~. .. MYCOY!ilIS"ONIX~I.Et My ""mml3slon expJres:07/14/2C1QS
ow. 7-/4-(>1."
I, I~" ul\il~gn~dofflcerof{"e I;JNiTEP FIRE & CASUAUY COMPANY(d9herllbyil'8r1ifythall havecornpareil the f9rll9OibllcpPYOI
lt1eP9""eror Allprne,. .~d aflldi/vll,anlt tll~ "uPY oftll.. S\lCtiol1 pf 1I1e py.I.~ oh.i~ C9mpany.s setforfti in..I,d Po",,' of ~o::n.y,
with Iha qRIGINALSClNflLji; IN THE}-tOME Of;F1CE OF SA1DCO,,1I'ANY, anfllhlit lj1es.ma are COITectJTllnScripls tl>!'re9liandJlf
llle whOle aUhe s'.idoriginals, and thatlhe said.Pow.rof Attorney hss.n.61 baen Fell<)kedandis now in fUll lorce andelfect.. .
, -,,, '. '_"'::":'. ,--c' ~. ....... ......,... -c, . ',.'''.'' "..: -'. .': ,:, ..' .:. .." "".'." _.C "'''-.', ..... ..._", -.........._<.:., .'....
In t"iitimonyWhereof I have hereLihtb subscribetl my name and affixed the corporale seal ollhe said Company
this. 21 5t day 01 March 20 ..!l2-.
fJ~ // %;/ $ecr~a~
ilOr,tPOO19Cl1l9+01
, ..
BID PROPOSAL
The bidder hereby certifies that they are the only person or persons interested in this
proposal as principals; that an examination has been made of the plans, specifications, and
contract form, including the special provision contained herein, and of the site of the work,
and the bidder understands that the quantities of work shown herein are approximate only
and are subject to increase or decrease; and further understand that all quantities of work,
whether increased or decreased, are to be performed at the unit price as stipulated herein;
the bidder proposes to furnish all necessary machinery, equipment, tools, labor and other
means of construction, and to furnish all materials specified in the manner and time
prescribed and to do the work at the prices herein set out.
Accompanying this proposal in a separate envelope is a cashier's or certified check
payable to the City Treasurer, City of Dubuque, drawn on a bank in Iowa or a bank chartered
under the laws of the United States, in the amount of ten percent (10%) of the bid submitted;
or a bid bond in the penal sum of ten percent (10%) of the bid submitted executed by the
bidder and an acceptable Corporate Surety. It is understood that this proposal guarantee will
be retained in the event the formal contract or bond is not executed, if award is made to the
undersigned.
The bidder further agrees to execute a formal contract and bond, if required by the
contract documents, within seven (7) days of the award of the contract by the City Council,
and that they will commence work on or about ten (10) days after the date of the contract,
and will complete the work within the specified contract period or pay the liquidated damages
stipulated in the contract documents.
The bidder acknowledges receipt of the following addendum:
Addendum I
Dated:
Dated:
Dated:
03-22-06
PRINCIPAL:
McDermott Excavating
Contractor
14407 Hwy 20 West
Address
Individual ( ) Partnership ( ) Corporation h)
By: ~~-'Mc~
Signature
14407 Hwy 20 West
City
Iowa
State
52003-9709
Zip
Supervisor
Title
03-23-06
Date
Note: To be completed by out of State bidders.
The State of does ( ) I does not ( ) utilize a percentage preference
for in-state bidders. The amount of preference is percent.
,. . ,
CITY OF DUBUQUE, IOWA
CUSTER I ALLISON HENDERSON PHASE II
STORM SEWER CONSTRUCTION PROJECT
CIP NO. 7201376
BID FORM
NO. DESCRIPTION
QUANTITY
I DETENTION BASIN AND OVERFLOW PIPE
1 Erosion Control Measures During Construction
2 Excavation & Off Site Disposal
3 Topsoil- Strip, Stockpile, and Replace
4 Terra Seed - 2" Thickness
S 4" Draintile, Inc.Valves, Fittings, Tie in and Chips
6 Tie into Existing Outlet Structure
7 Tie into Existing Manhole I Intake
8 24" RCP CL III wi Bedding & Compacted Granular Backfill
9 PC Concrete Sidewalk, 4", Construct
10 PC Concrete Access Ramp, Detectable
11 PC Concrete Curb and Gutter, 2.5', Construct wi ACC Patch
12 PC Concrete Pavement, (8") wi Curb & Dowels, Class "C"
13 Crushed Stone Base
14 Remove & Replace Exist. Elec. Conduit & Wiring - Inc. Handhole
15 Protect Exist. Hydrant
16 Traffic and Safety Control
1 LS
2390 CY
600 CY
4175 SY
660 LF
1 LS
5 EA
150 LF
320 SF
2 EA
120 LF
135 SY
65 Ton
1 LS
1 LS
1 LS
UNIT
PRICE
i
i
I,
I,
I
r
TOTAL
PRICE
850.00 $ 1 850.00
4.10 9 799.00
1.75 1 050.00
2.05 8 558.75
q.?S h 10S.00
310.00 310.00
310.00 1 550.00
35.40 5 310.00
4.86 1 555.20
505.00 1 010.00
19.30 2 316.00
48.30 6 520.50
16.00 1 040.00
2 905.00 2 905.00
250.00 250.00
3 570.00 3 570.00
Sub Total l~53 699.45'
1
I'
"
"
'I
I
1
,
I'
,
1.
I
i
r
, ..
-~---~-,.. -_._.._~.~..-
-~--- _ _'_'.n___'.
I STORM SEWER
1 Erosion Control Measures During Construction 1 Ls4 185.00 $ 4 185.00
2 Topsoil- Strip, Stockpile, and Replace 304 CY 4.10 1 246.4U
3 Terra Seed - 2" Thickness 1825 SY 2.05 3 741.25
4 Sodding 200 SY 3.75 750.00
5 Tie into Existing Junction Box 1.00 EA 945.00 945.00
6 Storm Sewer, 42" RCP, CL III wi Bedding 208 LF 62.61 13 022.88
7 Storm Sewer, 30" RCP, CL 111 wi Bedding 274 LF 59.20 16 220.80
8 Storm Sewer, 27" RCP, CL III wi Bedding & Compacted Granular Backfill 127 LF 105.12 13 350.24
9 Storm Sewer, 24" RCP, CL 111 wi Bedding & Compacted Granular Backfill 204 LF 48.64 9 922.56
10 Storm Sewer, 18" RCP, CL III wi Bedding & Compacted Granular Backfill 72 LF 41.62 2 996.64
11 Storm Sewer, 15" RCP, CL 111 wi Bedding & Compacted Granular Backfill 40.5 LF 30 35 1 229.18
12 Storm Sewer, 6" PVC Schedule 40 23 LF 14.80 340.40
13 72" Dia. Manhote Base wi Bedding 2 EA 495.00 990.00
14 72" Dia. Manhole Sidewall 20.9 VF 295.00 6 165.50
15 72" Dia. Manhole Flat top wi Casting 2 EA 786.96 1 573.92
16 50" Dia. Manhole Base wi Bedding 2 EA 415.00 830.00
17 60" Dia. Manhole Sidewall 20.9 VF ??Q 00 II 7RF, 10
18 48" Dia. Manhoie Base wi Bedding & Compacted Granular Backfill 1 EA ?10 00 ?10.00
19 48" Dia. Manhole Sidewall wi Bedding & Compacted Granular Backfill 17.7 VF 168.00 2 973.60
20 Manhole Frame and Cover 3 EA 385.00 1 155.00
21 Intake 101-C Special wi Bedding & Compacted Granular Backfill 1 EA2 310.00 2 310.00
22 Intake 101-B wi Bedding & Compacted Granular Backfill 2 EA 1 952.00 3 904.00
23 Area Drain - Complete 1 LS 553.00 ')')3.00
24 Abandon Existing Storm & Structures 68.5 CY 150.50 10309.25'
25 PC Concrete Sidewalk, 4". Construct 960 SF 4.75 4 ')F,O 00
26 PC Concrete Access Ramp, Detectable 2 EA 565.00 1 130.00
27 PC Concrete Commercial Drive, Type "A", ~ Construct 26 SY 62.30 1 619.80
28 PC Concrete Curt> and Gutter, 2.5', Construct 294 LF 16.75 4 924.50
29 HMA 300k, S, 1/2" (PG 70-34) 77 Ton 84.90 6 ')37.30'
30 HMA 300k, t, 1/2" (PG 64-22) 139 Ton 84.90 11 R01 10
31 Crushed Stone Base 325 Ton 16.00 S ?OO 00
32 Remove & Replace Exist. Elec. Conduit & Wiring - Inc. Handhole 1 LS 2 905.00 7 90S 00
33 Shoring Design & Installation (for Ex. Light) 1 LS 3 120.00 3 1 70 00
34 Traffic and Safety Control 1 LS 9 588.00 ~15~ ~~~.~~
Sub Total
TOTAL BID $g08 795.87
....
."
BID BOND
KNOWN ALL MEN BY THESE PRESENTS, that we, McDermott Excavating
Dubuque. IA , as Principal, and Merchants Bonding Company (Mutual)
as Surety, are held and firmly bound unto the City of Dubuque hereinafter
called "Municipality", in the penal sum of 10% of Total Bid in lawful money of
the United States, for the payment of which sum well and truly to be made, we bind
ourselves, our heirs, executors, administrators, and successors, jointly and severally,
firmly by these presents. The condition of this obligation is such that whereas the
Principal has submitted the accompanying bid, dated 3/23 , 2006, for the
Custer Allison Henderson Phase II Storm Sewer and Grading for Detention
Basin
NOW, THEREFORE, if the Principal shall not withdraw said bid within the period
specified therein during the opening of same, or if no period specified, within thirty
(30) days after said opening, and shall within the period specified therefor, or, if no
period be specified, within seven (7) days after the prescribed forms are presented to
him for signature, enter into a written contract with the Municipality, in accordance
with the bid as accepted, and give bond with good and SJ,!fficient surety or sureties,
as may be required for the faithful performance and proper fulfillment of such contract,
then the above obligation shall be void and of no effect, otherwise to remain in full
force and virtue.
By virtue of statutory authority, the full amount of this bid bond shall be
forfeited to the Municipality in liquidations of damages sustained in the event that the
aforedescribed bidder, Principal, fails to execute the contract and provide the bond as
provided in the specifications or by law.
IN WITNESS WHEREOF, the above bounden parties have executed this
instrument under their several seals this 23rd day of March , 2006
the name and corporate seal of each corporate party being hereto affixed and these
presents duly signed by its undersigned representative pursuant to authority of its
governing body.
Date:
3/23/06
McDermott Excavating
Principal ..!4.--
By ~ c:. 1'Yzjl ~j
Date:
1/21/06
Merchants Bonding SOmpany (Mutual)
./' I
SuretV ! ~
By _;eeA>~ ~ ~
Attorney-In-Fact
,
Merchants Bonding Company
(Mutual)
POWER OF ATTORNEY Bond No.
Know AU Persons By These Presents, that the MERCHANTS BONDING COMPANY (MUTUAL), a corporation duly organized under
the laws of the State of Iowa, and having its principal office in the City of Des Moines, County of Polk, State of Iowa, hath made,
constituted and appointed, and does by these presents make, constitute and appoint
J. Allen Wallis III, Fred 1. Kunnert, Jerry L Price
of Dubuque and State of Iowa its true and lawful Attorney.in-Fact, with full power
and authority hereby conferred in its name, place and stead, to sign, execute, acknowledge and deliver in its behalf as surety any
and all bonds, undertakings, recognizances or other written obligations in the nature thereof, subject to the limitation that any such
instrument shall not exceed the amount of:
THREE MILLION ($3,000,000.00) DOLLARS
and to bind the MERCHANTS BONDING COMPANY (MUTUAL) thereby as fully and to the same extent as if such bond or
undertaking was signed by the duly authorized officers of the MERCHANTS BONDING COMPANY (MUTUAL), and all the acts of
said Attorney-in-Fact, pursuant to the authority herein given, are hereby ratified and confirmed.
This Power-of-Attorney is made and executed pursuant to and by authority of the following Amended Substituted and Restated By-
Laws adopted by the Board of Directors of the MERCHANTS BONDING COMPANY (MUTUAL) on November 16, 2002.
ARTICLE 11, SECTION 8 - The Chainnan of the Board or President or any Vice President or Secretary shall have power and
authority to appoint Attorneys.in-Fact, and to authorize them to execute on behalf of the Company, and attach the Seal of the
Company thereto, bonds and undertakings, recognizances, contracts of indemnity and other writings obligatory in the nature
thereof.
ARTICLE II, SECTION 9 - The signature of any authorized officer and the Seal of the Company may be affixed by facsimile
to any Power of Attorney or Certification thereof authorizing the execution and delivery of any bond, undertaking,
recognizance, or other suretyship obligations of the Company, and such signature and seal when so used shall have the
same force and effect as though manually fixed.
In Witness Whereof, MERCHANTS BONDING COMPANY (MUTUAL) has caused these presents to be signed by its President and
its corporate seal to be hereto affIxed, this 1st day of January, 2003.
.........
.. "G CO..
...~~~.......~.I>...
. ...~..~\\PO<9..;...,,-S-..
..C,,:j ...,.......~.
.c.,..;;e: tf\.
.t-:_ -0- 0:-.
.%' '3:
.4'.. 1933 .::
....._. .c::.
.-......... '::"Y.
.v~. .:,.~.
... :lit..... "'\:\~..
.. {::{ .
.......
STATE OF IOWA
COUNTY OF POLK 55.
MERCHANTS BONDING COMPANY (MUTUAL)
~~7~
President
On this 1st day of January, 2003, before me appeared Larry Taylor, to me personally known, who being by me duly sworn did say that
he is President of the MERCHANTS BONDING COMPANY (MUTUAL), the COI'pOration described in the foregoing instrument, and that the
Seal affixed to the said instrument is the Corporate Seal of the said Corporation and that the said instrument was signed and sealed in behalf
of said Corporation by authority of its Board of Directors.
In Testimony Whereof, I have hereunto set my hand and affixed my Official Seal at the City of Des Moines, Iowa, the day and year first
above written.
@
CINDY SMYTH
Q:nnissicn~~
1Io\'0nnis!iaI Elq:i....
Mln:h 16, 2006
STATE OF IOWA
COUNTY OF POLK S5.
01,~w.
I, William Warner, Jr., Secretary of the MERCHANTS BONDING COMPANY (MUTUAL), do hereby certify that the above and foregoing
is a true and correct copy of the POWER-OF-ATTORNEY executed by s.aid MERCHANTS BONDING COMPANY (MUTUAL), which is
still in full force and effect and has not been amended or revoked.
In Witness Whereof, I have hereunto set my hand and affixed the seal of the Company on this 23rc1day of March, 2006
MSC 0814 (2/03)
.......
.. \\G CO..
..~()\...... '41,;.
.....~..~"v.POti:;..~..;..
:c.,.:~ ~;'.~~
:~:_ -0- 0:-.
. ""'. 1933 :~:
.~_. .c::::-.
.-'7;1:'. .'~.
. ~. .~~.
.. :lij,........~ ..
... * ...
......
..v~~~,
Secretary
.
/'
BID PROPOSAL
The bidder hereby certifies that they are the only person or persons interested in this
proposal as principals; that an examination has been made of the plans, specifications, and
contract form, including the special provision contained herein, and of the site of the work,
and the bidder understands that the quantities of work shown herein are approximate only
and are subject to increase or decrease; and further understand that all quantities of work,
whether increased or decreased, are to be performed at the unit price as stipulated herein;
the bidder proposes to furnish all necessary machinery, equipment, tools, labor and other
means of construction, and to furnish all materials specified in the manner and time
prescribed and to do the work at the prices herein set out.
Accompanying this proposal in a separate envelope is a cashier's or certified check
payable to the City Treasurer, City of Dubuque, drawn on a bank in Iowa or a bank chartered
under the laws of the United States, in the amount of ten percent (10%) of the bid submitted;
or a bid bond in the penal sum of ten percent (10%) of the bid submitted executed by the
bidder and an acceptable Corporate Surety. It is understood that this proposal guarantee will
be retained in the event the formal contract or bond is not executed, if award is made to the
undersigned.
The bidder further agrees to execute a formal contract and bond, if required by the
contract documents, within seven (7) days of the award of the contract by the City Council,
and that they will commence work on or about ten (10) days after the date of the contract,
and will complete the work within the specified contract period or pay the liquidated damages
stipulated in the contract documents.
The bidder acknowledges receipt of the following addendum:
Addendum #1
Dated:
Dated:
Dated:
3/21/06
PRINCIPAL:
Tschiggfrie Excavating Co
Contractor
425 Julien Dubuque
Address
c
Dubuque
City
By:
) Partnership ( ) Corporation (x)
Iowa
State
52003
Zip
General Superinr.'nnpnt
Title
1/:n/Oh
Date
Note: To be completed by out of State bidders.
The State of does ( ) I does not ( ) utilize a percentage preference
for in-state bidders. The amount of preference is percent.
I STORM SEWER
1 Erosion Control Measures During Construction
2 Topsoil- Strip, Stockpile, and Replace
3 Terra Seed - 2" Thickness
4 Sodding
5 Tie into Existing Junction Box
6 Storm Sewer, 42" RCP, CL III wi Bedding
7 Storm Sewer, 30" RCP, CL III wI Bedding
8 Storm Sewer, 27" RCP, CL III wi Bedding & Compacted Granular Backfill
9 Storm Sewer, 24" RCP, CL III wi Bedding & Compacted Granular Backfill
10 Storm Sewer, 1sn Rep, CL III wI Bedding & Compacted Granular 8ackfiU
11 Storm Sewer, 15" RCP, CL III wi Bedding & Compacted Granular Backfill
12 Storm Sewer, 6" PVC Schedule 40
13 72" Dia. Manhole Base wi Bedding
14 72" Dia. Manhole SidewaD
15 72" Dia. Manhole Flat top wi Casting
16 60" Dia. Manhole Base wi Bedding
17 60" Dia. Manhole Sidewall
18 48" Dia. Manhole Base wI Bedding & Compacted Granular Backfill
19 48" Dia. Manhole Sidewall wI Bedding & Compacted Granular Backfill
20 Manhole Frame and Cover
21 Intake 101-C Special wi Bedding & Compacted Granular Backfill
22 Intake 101-B wi Bedding & Compacted Granular Backfill
23 Area Drain - Complete
24 Abandon Existing Storm & Sl1Uctures
25 PC Concrete Sidewalk, 4", Construct
26 PC Concrete Ar;cess Ramp, Detectable
27 PC Concrete Commercial Drive, Type "A", - Construct
28 PC Concrete Curb and Gutter, 2.5', Construct
29 HMA 3001<, S, 112" (PG 70-34)
30 HMA 300k, I, 112" (PG 64-22)
31 Crushed Stone Base
32 Remove & Replace Exist Elec. Conduit & Wiring - Inc. Handhole
33 Shoring Design & Installation (for Ex. Ught)
34 Traffic and Safety Control
~
1 LS
304 CY
1825 SY
200 SY
1.00 EA
208.3 LF
273.6 LF
126.5 LF
204.4 LF
72 LF
40.5 LF
23 LF
2 EA
20.89 VF
2EA
2EA
20.89 VF
1 EA
17.68 VF
3 EA
1 EA
2EA
1 LS
68.5 CY
960 SF
2EA
26 SY
294 LF
77 Ton
139 Ton
325 Ton
1 LS
1 LS
1 LS
TOTAL BID
$1,750.00
$6.90
$5.15
$8.50
$346.00
$88.80
$48.45
$143.55
$73.90
$39.50
$38.10
$25.45
$635.00
$215.00
$745.00
$550.00
$177.00
$331.00
$142.00
$265.00
$1 ,935.00
$2,875.00
$1,060.00
$134.00
$3.45
$180.00
$44.70
$19.70
$96.00
$96.00
$12.40
$0.00
$2,500.00
$9,400.00
SUb Total
$1,750.00
$2,097.60
$9,398.75
$1 ,700.00
$346.00
$18,496.15
$13,253.98
$18,159.08
$15,101.47
$2,844.00
$1,543.05
$585.35
$1,270.00
$4,491.35
$1,490.00
$1,100.00
$3,697.53
$331.00
$2,510.56
$795.00
$1,935.00
$5,750.00
$1,060.00
$9,179.00
$3,312.00
$360.00
$1,162.20
$5,791.80
$7,392.00
$13,344.00
$4,030.00
$0.00
$2,500.00
$9400.00
$166; 176861
... S,~~.3,~~~lJ
CITY OF DUBUQUE, IOWA
CUSTER I AlLISON HENDERSON PHASE II
STORM SEWER CONSTRUCTION PROJECT
CIP NO. 7201376
BID FORM
NO. DESCRIPTION
UNIT
QUANTITY PRICE
I DETENTION BASIN AND OVERFLOW PIPE
1 Erosion Control Measures During Construction
2 Excavation & Off Site Disposal
3 Topsoil- Strip, StDcl<pile, and Replace
4 Terra Seed - 2" Thickness
5 4" Drainlile, Inc. Valves, Fittings, Tie in and Chips
6 Tie into Existing 0uUet S1rudure
7 Tie into Existing Manhole Ilntake
e 24" RCP CL '" wi Bedding & Compacted Granular Backfill
9 PC Concrete Sidewalk, 4", Construct
1 0 PC Concrete Access Ramp, Detectable
11 PC Concrete Curb and Gutter, 2.5', Construct wi ACC Patch
12 PC Concrete Pavement, (8") wi Curb & Dowels, Class "C"
13 Crushed stone Base
14 Remove & Replace Exist EIec. Conduit & Wiring - Inc. HandhoIe
15 Protect Exist Hydrant
16 Traffic and Safety Control
...1
1 LS
2390 CY
600 CY
4175 SY
660 LF
1 LS
5EA
150 LF
320 SF
2EA
120 LF
135 SY
65 Ton
1 LS
1 LS
1 LS
$822.00
$3.30
$3.60
$4.25
$8.00
$395.00
$695.00
$67.65
$3.45
$140.00
$35.75
$43.75
$13.25
$3,354.00
$612.00
$3,500.00
Sub Total
TOTAL
PRICE
$822.00
$7,887.00
$2,160.00
$17,743.75
$5,280.00
$395.00
$3,475.00
$10,147.50
$1,104.00
$280.00
$4,290.00
$5,906.25
$861.25
$3,354.00
$612.00
$3500.00
$67:817.75 .~
.. ~",-' .- ~_.>
"
BID BOND
KNOWN ALL MEN BY THESE PRESENTS, that we Tschi,,,lfrie Excavating Co.
as Principal (Contractor), andFidelity and Deposit Company of Mary,l8scEurety, are held
and firmly bound unto the unto the City of Dubuque, Iowa (City), in the penal sum of -
10% of Amount Bid------- in lawful money of the United States, for the payment of
which sum well and truly to be made, we bind ourselves, our heirs, executors,
administrators, and successors, jointly and severally, firmly by these presents, The
condition of this obligation is such that whereas the Principal has submitted the
accompanying bid, dated 23rd day of March . 2006, for the Custer /
Allison Henderson Phase II Storm Sewer Construction Project.
NOW, THEREFORE, if the Principal shall not withdraw said bid within the period
specified therein during the opening of same, or if no period specified. within thirty (30)
days after said opening, and shall within the period specified therefore, if no period be
specified, within seven (7) days after the prescribed forms are presented to him for
signature, enter into a written contract with the Municipality, in accordance with the bid
as accepted, and give bond with good and sufficient surety or sureties, as may be
required for the faithful performance and proper fulfillment of such contract, then the
above obligation shall be void and of no effect, othel"Nise to remain in full force and
virtue.
By virtue of statutory authority, the full amount of this bid bond shall be forfeited
to the Municipality in liquidations oJ damages sustained in the event that the afore
described bidder, Principal, fails to execute the contract and provide the bond as
provided in the specifications or by law,
IN WITNESS WHEREOF, the above bounden parties have executed this
instrument under their several seals this 23rd day of March , 2006,
the name and corporate seal of each corporate party being hereto affixed and these
presents duly signed by its undersigned representative pursuant to authority of its
governing body,
PRINCIPAL:
SURETY:
Tschiggfrie Excavating Co.
Sy: COp j~~ ()
Signature 4
t/fJ
Title
Fidelity and Deposit Company of
Surety Company Maryland
Sy: , j\"'fdJ--',~dlux"e"
Signature) \ '7
Nancy D. Schwarz
Attorney-in-Fact
Title
March 23, 2006
Date
March 23, 2006
Date
Power of Attorney
FIDELITY AND DEPOSIT COMPANY OF MARYLAND
KNOW ALL MEN BY THESE PRESENTS: Thalthe FIDELITY AND DEPOSIT COMPANY OF MARYLAND, a
corporation of the State of Maryland, by THEODORE G. MARTINEZ, Vice President, and GREGORY E. MURRAY,
Assistant Secretary, in pursuance of authority granted by Article VI, Section 2, of the By-Law' id Company, which are
set forth on the reverse side hereof and arc hereby certified to he in full force and ell ~ 1 'b dJi >reor, docs hereby
nominate, constitute and appoint F, Melvyn HRUBETZ, Joyce O. HE E S, Nancy D.
SCHWARZ and Patrick K. DUFF, all of Des Moines, low ~~ 3 f torney-m-Fact, to
make, execute, seal and delIver, for, and on its bcha 0' ~lS ~~Il and all bonds and
undertakings, and the executIOn orE' uch d{J 10 S r' &lJf\hesc presents, shall be as bindmg upon said
Company, as tully a~d ampl tQ:illt(I{lj ur . t een duly executed and acknowledged by the
regularly elected of - . Cbhi n~1 . f ore, Md., In their own proper persons. This power or attorney
revokes thaI issued '. of ~ . Z, Joyce O. HERBERT, Mark E. KEAIRNES, Nancy D. SCHWARZ,
MelIssa L. EY ANS, ~rF!')~'UilNM' ed AprIl I 1,2003.
The said Assistant ~r~ does hereby certify that the extract set forth on the reverse side hereof is a true copy of Article VI,
Section 2, of the By-Laws of said Company, and is now in force.
IN WITNESS WHEREOF, the said Vice-President and Assistant Secretary have hereunto suhscrihed their names and
affixed Ihe Corporate Seal of the said FIDELITY AND DEPOSIT COMPANY OF MARYLAND, this 24th day of February,
A.D. 2005.
ATTEST:
FIDELITY AND DEPOSIT COMPANY OF MARYLAND
/7. .. C ;;'1
L=f'-?j7;- , '/11-'-6
I -
~/ _/ ~'~
~7?~t(?(? ;;v" I'VJi/ibe..f}/1
I
By:
Grew)!}' E. Murray Assistant Secreta!}'
Theodore G. Martine::.
State of Maryland } s ..
City of Baltimore . s.
On this 24th day of February, A.D. 2005, he fore the suhscriher, a Notary Public of the Slale of Maryland, duly
commissioned and qualified, came THEODORE G. MARTINEZ, Vice President, and GREGORY E. MURRAY, Assistant
Secretary of the FIDELITY AND DEPOSIT COMPANY OF MARYLAND, to me personally known to be the individuals
and officers described in and who executed the preceding instrument, and they each acknowledged the execution or the same,
and heing hy me duly sworn, severally and each for himself deposeth and saith, that they are the said oflicers of the Company
aforesaid, and that the seal affixed to the preceding instrument is the Corporate Seal of said Company, and that the said
Corporate Seal and their signatures as such officers were duly affixed and subscribed to the said instrument hy the authority
and direction of the said Corporation.
IN TESTIMONY WHEREOF, I have hereunto set my hand and affixed my Official Seal the day and year first above
written.
\,\\11.11111/11,
e,;~,i:~6~1
,;,);;:~);:~,:;\""
/' .. /")
1'~.-o-T'-r.,j'JA/^JJ:___ L____L
Constance A. Dunn Nofw}' Puhlic
My Commission Expires: July 14,2007
POA-F 088-6895
"
EXTRACT FROM BY-LAWS OF FIDELITY AND DEPOSIT COMPANY OF MARYLAND
"Article VI, Section 2. The Chairman of the Board, or the President, or any Executive Vice-President, or any of the Senior
Vice-Presidents or Vice-Presidents specially authorized so to do by the Board of Directors or by the Executive Committee,
shall have power, by and with the concurrence of the Secretary or anyone of the Assistant Secretaries, to appoint Resident
Vice-Presidents, Assistant Vice-Presidents and Attorneys-in-Fact as the business of the Company may require. or to
authorize any person Of persons to execute on behalf of the Company any bonds, undertaking, recognizances, stipulations.
policies, contracts, agreements, deeds, and releases and assignments of judgements, decrees, mortgages and instruments in
the nature of mortgages,...and to aftix the seal of the Company thereto."
CERTIFICATE
!, the undersigned, Assistant Secretary of the FIDELITY AND DEPOSIT COMPANY OF MARYLAND, do herehy certify
that the foregoing Power of Attorney is still in full force and effect on the date of this certificate; and I do further certify that
the Vice-President who executed the said Power of Attorney was one of the addilional Vice-Presidents specially authorized
by the Board of Directors to appoint any Attorney-in-Fact as provided in Article VI, Seetion 2, of the By-Laws of the
FIDELITY AND DEPOSIT COMPANY OF MARYLAND.
This Power of Attorney and Certificate may be signed by facsimile under and by authority of the following resolution of the
Board of Directors of the FIDELITY AND DEPOSIT COMPANY OF MARYLAND at a mccting duly callcd and hcld on
the 10th day of May, 1990.
RESOLVED: "That the facsimile or mechanically reproduccd seal of the company and facsimile or mechanically
reproduced signature of any Vice-President, Secretary, or Assistant Secretary of the Company, whether made heretofore or
hereafter, wherever appearing upon a certified copy of any power of attorney issued by the Company, shall bc v<llid and
binding upon the Company with the same force and effect as though manually aftixed."
IN TESTIMONY WHEREOF, I have hereunto suhscribed my name and affixed the corporate seal of the said Company.
this
23rd
day of
March
2006
ASS;S/WIISccr('/(In
BID PROPOSAL
The bidder hereby certifies that they are the only person or persons interested in this
proposal as principals; that an examination has been made of the plans, specifications, and
contract form, including the special provision contained herein, and of the site of the work,
and the bidder understands that the quantities of work shown herein are approximate only
and are subject to increase or decrease; and further understand that all quantities of work,
whether increased or decreased, are to be performed at the unit price as stipulated herein;
the bidder proposes to furnish all necessary machinery, equipment, tools, labor and other
means of construction, and to furnish all materials specified in the manner and time
prescribed and to do the work at the prices herein set out.
Accompanying this proposal in a separate envelope is a cashier's or certified check
payable to the City Treasurer, City of Dubuque, drawn on a bank in Iowa or a bank chartered
under the laws of the United States, in the amount of ten percent (10%) of the bid submitted;
or a bid bond in the penal sum of ten percent (10%) of the bid submitted executed by the
bidder and an acceptable Corporate Surety. It is understood that this proposal guarantee will
be retained in the event the formal contract or bond is not executed, if award is made to the
undersigned.
The bidder further agrees to execute a formal contract and bond, if required by the
contract documents, within seven (7) days of the award of the contract by the City Council,
and that they will commence work on or about ten (10) days after the date of the contract,
and will complete the work within the specified contract period or pay the liquidated damages
stipulated in the contract documents.
The bidder acknowledges receipt of the following addendum:
)JtYi~i IvD...liV\ ;tI.. I
Dated: /L1A>C..cH 2./ 2..-00 <0
Dated:
Dated:
PRINCIPAL:
.\J' . . /
c ->Tl.4Jlt1Z, Ccr'.s J1(~-n . rJ , lAIc.
Contractor .
Indiv,idual (
~)
.) 2 I (4 sT d -rh. -'5veEE-r-
Address
'~JI~~ ,.II...( 0e-'
City
/ (j ,.v /4"
State
S2-00 I
Zip
By:,
8> i' .5 I D~7V"--'
Title
;l.1A:,alf 22", 2.-00~
Date
Note: To be completed by out of State bidders.
The State of does ( ) / does not ( ) utilize a percentage preference
for in-state bidders. The amount of preference is percent.
CITY OF DUBUQUE, IOWA
CUSTER I AlLISON HENDERSON PHASE II
STORM SEWER CONSTRUCTION PROJECT
CIP NO. 7201376
BID FORM
NO. DESCRIPTION
UNIT
QUANTITY PRICE
I DETENTION BASIN AND OVERFLOW PIPE
1 Erosion Control Measures During Construction
2 Excavation & Off Site Disposal
3 Topsoil- Strip, Stockpile, and Replace
4 Terra Seed - 2" Thickness
5 4" Draintile, Inc.valves, Fittings, Tie In and Chips
6 Tie into Existing Outlet Structure
7 Tie into Existing Manhole I Intake
8 24" RCP CL III wI Bedding & Compacted Granular Backfill
g PC Concrete Sidewalk, 4", Construct
10 PC Concrete Access Ramp, Detectable
11 PC Concrete Curb and Gutter, 2.5', Construct wi ACC Patch
12 PC Concrete Pavement, (8") wI Curb & Dowels, Class "C"
13 Crushed Stone Base
14 Remove & Replace Exist. Elec. Conduit & Wiring - Inc. Handhole
15 Protect Exist. Hydrant
16 Traffic and Safety Control
1 LS /,/00 ~
2390 CY 5, C'"
600 CY Z.7,
4175 SY -"/.l"
660 LF e ,.'
1 LS 3<'0.'"
5 EA 3e0, <:(,
150 LF &."12-
320 SF 1. ",
2 EA SZ1:>""
120 LF 33. so
135 SY 1"5.""
65 Ton 1I,9Z.
1 LS 4,18'1,CO
1 LS .2. 00<'>
1 LS 3. S-OO, ';0
Sub Total
TOTAl
PRICE
iI;, 100. .:.9-
1'1. fl.-a, ,<>
1,6Su,c:"
17. 743 7,
...".J. Zgo, co
Seo,":'(,'
1,:;00, q,
13, Ceo"'
I.~'fo. Co>
i. DO...), ...0
4. Oz.'" ",
L 07.s- <,;0....
'171. '8'-'
4.1 67, '0
.l~c:.J, ~'~)
3500. ~,.,
161'. 900.5"' I
I STORM SEWER
1 Erosion Control Measures During Construction 1 LS aG. c< ...5Z:tJ. c..J
2 Topsoil- Strip, Stockpile, and Replace 304 CY 2.7S' 83",'0
3 Terra Seed - 2" Thickness 1825 SY 3~' 1oc'8 C(J
., , .
4 Sodding 200 SY 8. >-0 I. leo. '"
5 Tie into Existing Junction Box 1.00 EA ~ OeD, 00 I.rOO(':>,oo
6 Storm Sewer, 42" RCP, CL III wi Bedding 208 LF /o.f'.>' 21. "} fJ-1. 4'"
7 Storm Sewer, 30" RCP, CL III wi Bedding 274 LF 70.~ 'oa"1M>
~~ <'->P .
8 Storm Sewer, 27" RCP, CL III wi Bedding & Compacted Granular Backfill 127 LF I 71. c~ 25.z-7, cn
9 Storm Sewer, 24" RCP, CL ill wi Bedding & Compacted Granular Backfill 204 LF ~,1.2~ 12 :-:>-0/. ' 2-
10 Storm Sewer, 18" RCP, CL III wi Bedding & Compacted Granular Backfill 72 LF 4'f. 10 3'/75-' ~
11 Storm Sewer, 15" RCP, CL III wi Bedding & Compacted Granular Backfill 40.5 LF 31.5~ "'6." 2. 18
12 Storm Sewer, 6" PVC Schedule 40 23 LF .31. " 12- fl. &~,.
13 72" Dia. Manhole Base wi Bedding 2 EA 7SlJ,." /'50'.), cc-
14 72" Dia. Manhole Sidewall 20.9 VF IVG. "'" 4. o'1s:,-u
15 72" Dia. Manhole Fiat top wi Casting 2 EA t,25'."" I, 2- S<:. .,.
16 60" Dia. Manhole Base wi Bedding 2 EA hZ-S.- I 2- 5-0. (;'0
17 60" Dia. Manhole Sidewall 20.9 VF 180,:0" 3 {? (-,6. so>
18 48" Dia. Manhole Base wi Bedding & Compacted Granular Backfill 1 EA 1n," 11Q. DO
19 48" Dia. Manhole Sidewall wi Bedding & Compacted Granular Backfill 17.7 VF tifI. DC I, s 7 S'. J"
20 Manhole Frame and Cover 3 EA 21v+' D_ 7"t2.~v
21 Intake 1 01-C Special wi Bedding & Compacted Granular Backfill 1 EA 2 Z <;b..- 2.250,<:1"
22 Intake 101.B wi Bedding & Compacted Granular Backfill 2 EA ...? 0 00 '-u 4. 0 Ci,)~..J.)
23 Area Drain - Complete 1 LS 1 oe, ~.~) '7 0(\ c~'
24 Abandon Existing Storm & Structures 68.5 CY 113,'. 7,'7~7.''''
25 PC Concrete Sidewalk, 4", Construct 960 SF 1. -TS' -1; 5i.o. ,n
26 PC Concrete Access Ramp, Detectable 2 EA c,5C- co 1.3"'0 ,..'
27 PC Concrete Commercial Drive, Type "A", - Construct 26 SY 51.51> I, 337. 0.'
28 PC Concrete Curb and Gutter, 2.5', Construct 294 LF /~(,oC> 1.,4,10. <.,
29 HMA 300k, S, 1/2" (PG 70-34) 77 Ton ''It.1s 'Z 4+'1'S'
30 HMA 300k, I, 1/2" (PG 64-22) 139 Ton 'lL.lS / 3. 441. t,
31 Crushed Stone Base 325 Ton 13. .. 1: Z'it su
32 Remove & Replace Exist. Elec. Conduit & Wiring - Inc. Handhole 1 LS ~."w SC(!'C
33 Shoring Design & Installation (for Ex. Light) 1 LS li. SOO, "" 8 SVo ' ,
34 Traffic and Safety Control 1 LS ID, ZOc...'J, c.O 10 Z oi'. C(J
SubTotal $f18;.S31.9J.-1
TOTAL BID -'2'3.432. 471
BID BOND
I
I
I
I
KNOWN ALL MEN BY THESE PRESENTS, that we W.C. Stewart Construction, Inc.
as Principal (Contractor), and United Fire & Casualty Company , as Surety, are held
and firmly bound unto the unto the City of Dubuque, Iowa (City), in the penal sum of.:}eh
Percent of the Total ,Rid in lawful money of the United States, for the payment of
which sum well and truly to be made, we bind ourselves, our heirs, executors,
administrators, and successors, jointly and severally, firmly by these presents. The
condition of this obligation is such that whereas the Principal has submitted the
accompanying bid, dated 21st day of March , 2006, for the Custer I
Allison Henderson Phase II Storm Sewer Construction Project.
NOW, THEREFORE, if the Principal shall not withdraw said bid within the period
specified therein during the opening of same, or if no period specified, within thirty (30)
days after said opening, and shall within the period specified therefore, if no period be
specified, within seven (7) days after the prescribed forms are presented to him for
signature, enter into a written contract with the Municipality, in accordance with the bid
as accepted, and give bond with good and sufficient surety or sureties, as may be
required for the faithful performance and proper fulfillment of such contract, then the
above obligation shall be void and of no effect, otherwise to remain in full force and
virtue.
By virtue of statutory authority, the full amount of this bid bond shall be forfeited
to the Municipality in liquidations of damages sustained in the event that the afore
described bidder, Principal, fails to execute the contract and provide the bond as
provided in the specifications or by law.
IN WITNESS WHEREOF, the above bounden parties have executed this
instrument under their several seals this 21st day of March , 2006,
the name and corporate seal of each corporate party being hereto affixed and these
presents duly signed by its undersigned representative pursuant to authority of its
governing body.
PRINCIPAL:
SURETY:
J
W.C. Stewart Construction, Inc.
con!r ctor
/)
By: c_l ~
Signat e
t;-),
. ~ l"3: /Dc7V ,-
Title
By:
Company
~
1
Scott A. DeSousa, Attornev-in-Fact
Title
/v1f\7ZU+ 2? 2.;00("
.
Date
3/21/2006
Date
UNITED FIRE & CASUAL TV COMPANY
HOME OFFICE - CEDAR RAPIDS, IOWA
CERTIFIED COPY OF POWER OF ATTORNEY
(Original on file at Home Office of Company - See Certification)
KNPWALL MEN ElY THESE PRESENTS, That the UNITED FIRE & CASUALTY COMPANY, a corporation duly organized and existing
under the laws of the State of Iowa, and having its principal office in Cedar Rapids, State of Iowa, does make, constitute and appoint
ROBERT J. MILLER, OR TERRANCE J. FRIEDMAN,OR SCOTT A. DESOUSA, ALL INDIVIDUALLY of DUBUQU~ IA
its true and lawful Attorney( s}-in-Fact with power and authority hereby conferred to sign, seal and execute in its behalf all lawful bonds,
undertakings and other obligatory instruments of similar nature as follows: Any and All Bonds
and to bind UNITED FIRE 8, cASiJAL TV COMPANY thereby as fully and to the same extent as if such instruments were signed bY the
duly authorized officers of UNITED FIRE & CASUAL TV COMPANY and all the acts of said Attorney, pursuant to the authority hereby
given are hereby ratified and confirmed.
The Authority hereby granted is continuous and shall remain in full force and effect until revoked by UNIT"D FIRE &
CASUALTY COMPANY.
This power of Attorney is made and executed pursuant to and by authority of the following By-Law duly adopted by Board of
Directors of the GompanY on April 18, 197,3-
"Article V - Surely Elonds and Undertakings"
Section 2, AppOintment of Attorney-in-Fact. "The President. or any Vice President, or any ot.her officer of the Company may,
from t.ime to t.ime, appoint by written certificat.es attorneys-in-fact. t.o act in behalf of the Company in the execution of policies of
insYrance, bonds, Undertakings and other obligatory instruments of like nature. The signature of any officer authori;:ed hereby,
and the Gorporate seal, may be affixed by facsimile to any power of attorney or special power of attorney Or certificatio~ of
either authori;:ed hereby; sUch signature and seal, when so used, being adopted by the Company as the original signatyre of
such officer and the original seal of the Company, to be valid and binding upon the Company with the same force and. eff~ct as
though manually affixeq. Such attorneys-in fact, subject to the limitations set forth in their respective certificateS of authority
shall have fyll power to bind the Company by their signature and execution of any such instruments and to attach the seal of
the Company thereto. The President or any Vice President, the Board of Directors or any other officer of the Company may at
any time revoke all power and authority previously given to any attomey-in-fact.
~ IN WITNESS WHEREOF, the UNITED FIRE & CASUALTY COMPANY has caused these presents to be s'gned by
~~~=\ ,ts v,ce president and Its corporate seal to be hereto affixed this 9th day of March, 2005
'; .iu: !J UNITED FIRE & CASUALTY COMPANY
,.~ It.~$ 42
.~"~ ~-1. /J; ~ A
By --. r '1'. ~ Vice PresIdent
state of IOwa, COunty of Linn, ss:
On 9tl1 day of March, 2005, before me personally came Randy A. RamIo
to me known, who being by me duly sworn, did depose and say; that he resides in Cedar Rapids, State of Iowa; that he is a Vice
President. of the UNITED FIRE&CASUAL TY COMPANY, the corporation described in and which executed the above instrument that
he knows the seal of said corporation; that the seal affixed to the said instrument is such corporate seal; that it was so affixed pursuant
to authority given by the Board of Directors of said corporation and that he signed his name thereto pursuant to like authority, and
acknowledges same to b" the act anqdeed of said corporation. ~~ ~ .~
31,.' ,.MICHELl.EWlLSON
i...... ~r. CO",,,..,oNNu,,.e. 70.. 4745 Notary Public
.... .. MY COMM.IS$IQ~ EXPIRES My commission expires: 07/14/20M
0.... "7 P..H::!a
I, the undersignedoffie"'r olthe UNITED FIRE & CASUALTY COMPANY, do hereby certify that I have compared the foregoing copy Of
the Power ofAttorneYandaffidavit,and the copy of the Section of the by;laws o/.aid Company as set .forth in said Power Of AttorneY,
with the ORIGINALS qN FILE INTHE HOM" OFFICE OF SAID COMpANY, and that the same are correct transcript. thereof, and of
the whole of th<:! said originals, and that the said Power of All9r~ey has not !:leen revoked and is now in full force and effect.
~~1l :~i:estTI~nt'llhe~~~f ~tav~~f~hnto sUbscribe~6Y OEmeand affixed the corporate seal of the said Company
",a..AL ~i p
f'~ ...... 4I:....~~
.~,.~ .. tV.#~ Secretary
BONDOO19 0802 01
,
BID PROPOSAL
The bidder hereby certifies that they are the only person or persons interested in this
proposal as principals; that an examination has been made of the plans, specifications, and
contract form, including the special provision contained herein, and of the site of the work,
and the bidder understands that the quantities of work shown herein are approximate only
and are subject to increase or decrease; and further understand that all quantities of work,
whether increased or decreased, are to be performed at the unit price as stipulated herein;
the bidder proposes to furnish all necessary machinery, equipment, tools, labor and other
means of construction, and to furnish all materials specified in the manner and time
prescribed and to do the work at the prices herein set out.
Accompanying this proposal in a separate envelope is a cashier's or certified check
payable to the City Treasurer, City of Dubuque, drawn on a bank in Iowa or a bank chartered
under the laws of the United States, in the amount of ten percent (10%) of the bid submitted;
or a bid bond in the penal sum of ten percent (10%) of the bid submitted executed by the
bidder and an acceptable Corporate Surety. It is understood that this proposal guarantee will
be retained in the event the formal contract or bond is not executed, if award is made to the
undersigned.
The bidder further agrees to execute a formal contract and bond, if required by the
contract documents, within seven (7) days of the award of the contract by the City Council,
and that they will commence work on or about ten (10) days after the date of the contract,
and will complete the work within the specified contract period or pay the liquidated damages
stipulated in the contract documents.
The bidder acknowledges receipt of the following addendum:
~JJI!.t'\du~Y\ J. I
Dated: 3- ?/- 6h
Dated:
Dated:
PRINCIPAL:
~ <Dra.de
Contractor
bY.. (dV4 -i'J J Y\c.
tD. -ArJY... I g/
Address
Individual ( ) Partnership ( ) Corporation <Xi.
-&;f LU Dr ..f.+1
Cit
By ciflrJ Ji.{P
Si nature
pve-5.
Title
TDWA.
State
~dO~S
Zip
3-C{3- ()!P
Date
Note: To be completed by out of State bidders.
The State of does ( ) / does not ( ) utilize a percentage preference
for in-state bidders. The amount of preference is percent.
I
CITY OF DUBUQUE, IOWA
CUSTER I ALLISON HENDERSON PHASE II
STORM SEWER CONSTRUCTION PROJECT
CIP NO. 7201376
BID FORM
NO. DESCRIPTION
UNIT
QUANTITY PRICE
I DETENTION BASIN AND OVERFLOW PIPE
1 Erosion Control Measures During Construction
2 Excavation & Off Site Disposal
3 Topsoil- Strip, Stockpile. and Replace
4 Terra Seed - 2" Thickness
5 4" Draintile, Inc.Valves, Fittings, Tie in and Chips
6 Tie into Existing Outlet Structure
7 Tie into Existing Manhole I Intake
8 24" RCP CL III wI Bedding & Compacted Granular Backfill
9 PC Concrete Sidewalk, 4", Construct
10 PC Concrete Access Ramp, Detectable
11 PC Concrete Curb and Gutter. 2.5', Construct wI ACC Patch
12 PC Concrete Pavement, (8") wI Curb & Dowels, Class "C"
13 Crushed Stone Base
14 Remove & Replace Exist. Elec. Conduit & Wiring - Inc. Handhole
15 Protect Exist. Hydrant
16 Traffic and Safety Control
1 LS /rY60
2390 CY ~ .lFJ
600 CY _ .~~
4175 SY _ Lf ~
660 LF 'I. ~)
1 LS IJrXJM
"'"
5 EA 1,(Jf)-
150LF -43.'"
320 SF ""I. CIS
2 EA (~)('-'
120 LF I '6<><:
135 SY "10.50
I. ""
65 Ton / " """
1 LS ,') ~crt"
1 LS 2{jJ"V
1 LS '7500'"
Sub Total
TOTAL
PRICE
l7U
/ 'ifXJ .
/ I 9:)(). ,~
13.~(). "-'
171"'13.'1r
"17 :?S. <'0
",on. ""'"
;> (JDO. c>tJ
(/150.=
/3(~O."-'
.L/Ol). ,,,-,
02/ u,() <'D
5</t/7. so
/0<-;0."""
.?lsm."'-'
. sS-O ~
SlJo ~
I t,l~5I~.;bf
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
I STORM SEWER
Erosion Control Measures During Construction
Topsoil - Strip, Stockpile, and Replace
Terra Seed - 2" Thickness
Soddin9
Tie into Existing Junction Box
Storm Sewer, 42" RCP, CL III wi Bedding
Storm Sewer, 30" RCP, CL ill wi Bedding
Storm Sewer, 27" RCP, CL III wi Bedding & Compacted Granular Backfill
Storm Sewer, 24" RCP, CL III wi Bedding & Compacted Granular Backfill
Storm Sewer, 18" RCP, CL III wi Bedding & Compacted Granular Backfill
Storm Sewer, 15" RCP, CL III wi Bedding & Compacted Granular Backfill
Storm Sewer, 6" PVC Schedule 40
72" Dia. Manhol~ Base wi Bedding
72" Dia. Manhole Sidewall
72" Dia. Manhole Flat top wi Casting
60" Dia. Manhole Base wi Bedding
60" Dia. Manhole Sidewall
48" Dia. Manhole Base wi Bedding & Compacted Granular Backfill
48" Dia. Manhole Sidewall wi Bedding & Compacted Granular Backfill
Manhole Frame and Cover
Intake 1 01-C Special wi Bedding & Compacted Granular Backfill
Intake 101-B wi Bedding & Compacted Granular Backfill
Area Drain - Complete
Abandon Existing Storm & Structures
PC Concrete Sidewalk, 4", Construct
PC Concrete Access Ramp, Detectable
PC Concrete Commercial Drive, Type "A", - Construct
PC Concrete Curb and Gutter, 2.5', Construct
HMA 300k, S, 1/2" (PG 70-34)
HMA 300k, I, 1/2" (PG 64-22)
Crushed Stone Base
Remove & Replace Exist. Elec. Conduit & Wiring - Inc. Handhole
Shoring Design & Installation (for Ex. Light)
Traffic and Safety Control
C'<>
1 LS 1'1f())
304 CY ;) ,.)5.
1825 SY C:;.I )-
200 SY <g. SD
1.00 EA 50.'). ao
208 LF &~, <><>
274 LF Sd, "'"
127 LF I ifS. ,",
204 LF -</1. 5 ()
72 LF "');).().J
40.5 LF :..s'J. 50
23 LF -'15,0,';'
~
2 EA I!fDO,
CA, ~
20.9 VF I "c>.
2 EA /".$ll. ""
2 EA /8U)~
20.9 VF I q.O, U'tJ
1 EA / (') '>7), ,..,
17.7 VF . 9<1. ""
3 EA C?SO~
d>
1 EA '2,500
2 EA ;)J<j{Jl)-
1 LS I,,'SO.....
68.5 CY /:>D~ ,
960 SF "'-I,~
2 EA ,.;Jill""
26 SY .ljO."~
294 LF ~
77 Ton
139 Ton
325 Ton~
1LS~
1 LS sruo
1 LS II OUO~
Sub Total
TOTAL BID
"""
l80u /
(o8f./.. ~
93qg. '~
~
I 700 "
S()O""
17 9/;). "14
/<ldd5 c"-
c)l:3 -)fCb) . 3,0
q 70(, ~-~
.-? 7 "1'1 'Y
/S'N.7:J
J03J."'"
3<':'00,-
3'7tRO."'-o
I,OD''''''
3("'OO~
;;; 9,)'/, ~,?
~
/ () SO. -
/tr,~/, 9~
7SD"'O'
:;;Sooo:-
5S'CXJ ~
150"'"
(?
if1 05 ~
./.}{) Sb-
-<ov.....
~~~~
tonG" ::
/,~S~:
d S(/)-
5(ij:) ,":"!
J/(}VO. ,K>
In~143,"/1
18-<15 /91. ~(.I
BID BOND
KNOWN ALL MEN BY THESE PRESENTS, that we Top Grade Excavating, Inc.
as Principal (Contractor), and North American Specia'!!y'lnsurance Company, as Surety, are held
and firmly bound unto the unto the City of Dubuque, Iowa (City), in the penal sum of _
Ten Percent of Amount Bid (10%)-- in lawful money of the United States, for the payment of
which sum well and truly to be made, we bind ourseives, our heirs, executors,
administrators, and successors, jointly and severally, firmly by these presents. The
condition of this obligation is such that whereas the Principal has submitted the
accompanying bid, dated 23rd day of March , 2006, for the Custer I
Allison Henderson Phase II Storm Sewer Construction Project.
NOW, THEREFORE, if the Principal shall not withdraw said bid within the period
specified therein during the opening of same, or if no period specified, within thirty (30)
days after said opening, and shall within the period specified therefore, if no period be
specified, within seven (7) days after the prescribed forms are presented to him for
signature, enter into a written contract with the Municipality, in accordance with the bid
as accepted, and give bond with good and sufficient surety or sureties, as may be
required for the faithful performance and proper fulfillment of such contract, then the
above obligation shall be void and of no effect, otherwise to remain in full force and
virtue.
By virtue of statutory authority, the full amount of this bid bond shall be forfeited
to the Municipality in liquidations of damages sustained in the event that the afore
described bidder, Principal, fails to execute the contract and provide the bond as
provided in the specifications or by law,
IN WITNESS WHEREOF, the above bounden parties have executed this
instrument under their several seals this 23rd day of Ma~ch , 2006,
the name and corporate seal of each corporate party being hereto affixed and these
presents duly signed by its undersigned representative pursuant to authority of its
governing body.
PRINCIPAL:
SURETY:
By:
North American Specialty Insuranoe Company
- Sureiy Company ---.
~ c~
By: Signa~U;e -. - -.-. -
Dianne S. Riley, Attorney-in-Fact
Title
March 23, 2006
Date
March 23, 2006
Date -----------
.
.
NAS SURETY GROUP
NORTH AMERICAN SPECIALTY INSURANCE COMPANY
WASHINGTON INTERNATIONAL INSURANCE COMPANY
GENERAL POWER OF A TIORNEY
KNOW ALL MEN BY THESE PRESENTS, THAT North American Specialty Insurance Company, a corporation duly organized and existing under
laws ofthe State of New Hampshire, and having its principal office in the City of Manchester, New Hampshire, and Washington International
Insurance Company, a corporation organized and existing under the laws of the State of Arizona and having its principal office in the City of ltasca,
Ulinais, each does hereby make, constitute and appoint:
JANET AL.ESSIO, JAY D, FREIERMUTH, CRAIG E. HANSEN, CLIFFORD W. AUGSPURGER,
MARTHA LA THRUM, DIANNE S. RIL.EY, BRIAN M. DEIMERL y, CINDY BENNETT,
and ANNE CROWNER. JOINTL. Y OR SEVERALL.Y
Its true and lawful Attomey(s).in.Fact, to make, execute, seal and deliver, for and on its behalf and as its act and deed. bonds or other writings
obligatory in the nature of a bond on behalf of each of said Companies. as surety, on contracts of suretyship as are or may be required or pennitled by
law, regulation, contract or othelWise, provided that no bond or undertaking or COntract or suretyship executed under this authority shall exceed the
amount of;
TEN MILUON (10,000,000,00) DOL.LARS
This Power of Attorney is granted and is signed by facsimile under and by the authority of the following Resolutions adopted by the Boards of
Directors of both North American Specialty Insurance Company and Washington Internationallnsurance Company at meetings duly called and held
on the 241h of March, 2000:
"RESOLVED, that any two of the President, any Executive Vice President, any Vice President, any Assistant Vice President, the Secretary Of any
Assistant Secretary be. and eacll or any of them hereby is authorized to execute a Power of Attorney qualil)ting the attorney named in the given Power
of Attorney to execute on behalf of the Company bonds, undertakings and all contracts of surety, and that each or any of them hereby is authorized to
attest to the execution of any such Power of Attorney and to attach Iherein the seal of the Company; and it is
FURTHER RESOLVED, that ttle signature of such officers and the seal of the Company may be affixed to any such Power of Attorney or to any
certificate relating thereto by facsimile, and any such Power of Attorney or certificate bearing such facsimile signatures or fucsimile seal shall be
binding upon the Company when so affix.ed and in the future with regard to any bond, undertaking or contract of surety to which it is attached,"
1UIll11lUlJ ,d1l1""I<.,
~'~"".un' 1~/e t14a- ~'~....,\OnAt ;:~,~
",-S'.tl'"w'k'~"" '"5'-'''~'''''
..,~~ k ,"
_.'-"..l =.. ~\,~", By 1.i~ CORPORATE\,'1\~;.
tl, "~1 sl....~.P.Arll..n_,r.-..ldlnI..CI&l.r~~~.lInO!l1cllrofW.ulpK'-IIJ..ltrnlllIoelllJnMlJ'.n.C!ComJHIn,,& -
,i~~ 11013 "-1~.'fI1 VlnPrrlh"nll>rN"rlhAm~.I~..Spcrl"t,IIIAlnllC'C'.IImpall' 1; SEAL Ii!
~":\"', ,"~" \:%.. \ "''''./ ~ I
~~~~r.~~ At. : <-4' ,.... ~-,-, ~,.'
~ltrfimll;Il\\I\\,~ By ~P("7~'--- ""..,..,~.."""""
D.vltt M. LlI)'l1l.n. Vkll PrullIeqt olW.blnclolll.tun.tllNlllllu....nu comp.., ..
Vito Prc:Adrnl ofN.I111 Amtncan SpecIally IlIlllnlQl:e C_pan)'
IN WITNESS WHEREOF, North American Specialty Insurance Compan)' and Washington Intem8tionallnsurance Company have caused their
official seals to be hereunto affixed, and these presents to be signed by their authorized officers this 10th day of November ,20Q!..
North American Specialty InsurDnce Company
Washington International Insurance Company
State of Illinois
County of Du Page
ss:
On this JOth day of November . 20~. before me, a Notary Public personally appeared Steven P Anderson . President and CEO of
Washington Intemationallnsurance Company and Vice President of North American Specialty Insurance Company and David M, Lavman ,
Vice President of Washington International Insurance Company and Vice Presidenl of North American Specialty Insurance Company,
personally known to me, who being by me duly sworn, acknowledged Ihat they signed the above Power of Attorney as officers of and
acknowledged said instrument to be the voluntary act ~nd deed of their respective companies,
"OFFIOAL SEAL"
SUSAN ANSEl.
~OlolIYPWic,Sllt1eotmn.
1M Commit... exp...1t012OO1l
J /
L~__t~
Susan Ansel, Notary Public
I, James A Camenter ,the duly elected Assistan-[SecretalV 0 North American Specialty Insurance Company and Washington
International Insurance Company, do hereby certify that the above and foregoing is a true and correct copy of a Power of Attorney given by said North
American Specialty Insurance Company and Washington International Insurance Company, which is still in full force and effect.
IN WITNESS WHEREOF, I have set my hand and affixed the seals of the C'..ompanies this 23rdday of March ,2006 ,
?fl"--'/Jy6~
J_^- ~tt. Vice Prll"dl:Dl4 Auiltonl Sei:maryorWullinJlon Inll'mOllllP~1 la_tl.'COlnpgny "-
Nonll Amerlt.. Spt:doll)' lllill""",C Compaa)'
~
'. J
BID PROPOSAL
The bidder hereby certifies that they are the only person or persons interested in this
proposal as principals; that an examination has been made of the plans, specifications, and
contract form, including the special provision contained herein, and of the site of the work,
and the bidder understands that the quantities of work shown herein are approximate only
and are subject to increase or decrease; and further understand that all quantities of work,
whether increased or decreased, are to be performed at the unit price as stipulated herein;
the bidder proposes to furnish all necessary machinery, equipment, tools, labor and other
means of construction, and to furnish all materials specified in the manner and time
prescribed and to do the work at the prices herein set out.
Accompanying this proposal in a separate envelope is a cashier's or certified check
payable to the City Treasurer, City of Dubuque, drawn on a bank in Iowa or a bank chartered
under the laws of the United States, in the amount of ten percent (10%) of the bid submitted;
or a bid bond in the penal sum of ten percent (10%) of the bid submitted executed by the
bidder and an acceptable Corporate Surety, It is understood that this proposal guarantee will
be retained in the event the formal contract or bond is not executed, if award is made to the
undersigned,
The bidder further agrees to execute a formal contract and bond, if required by the
contract documents, within seven (7) days of the award of the contract by the City Council,
and that they will commence work on or about ten (10) days after the date of the contract,
and will complete the work within the specified contract period or pay the liquidated damages
stipulated in the contract documents,
.&>"
Dated:
Dated:
Dated:
PRINCIPAL:
Signat
Ii' [::IIf) 1':,-./7
itle
(' t!t' j)
_,0.' l6o:",/f
Address
!?z)S:/1- ""ZA
City
SOl
jl} ~L /)1./ ./;~ ~,/A 'f/A){-' f; &/(
, Contractor
Individual ( ) Partnership ( ) Corporation kn
By:
--
LA
State
?/C7 /00
D;;rte /
.;5cl'j& t5'
Zip
Note: To be completed by out of State bidders,
The State of does ( ) / does not ( ) utilize a percentage preference
for in-state bidders, The amount of preference is percent.
,
STORM SEWER
1 Erosion Control M08SUres During Construction
2 Topsoil- Strip, Stockpile, and Replace
3 Terra Seed - 7 Thickness
4 Sodding
5 Tie into Existing Junction Box
6 S1Drm Sewer, 47 RCP, CL III wi Bedding
7 S1Drm Sewer, scr RCP, CL III wi Bedding
B S1Drm Sewer, 'E" RCP, CL III wi Bedding & Compacted Granular Backfill
9 Storm Sewer, 24" RCP, CL III wi Bedding & Compacted Granular Backfill
10 S1Drm Sewer, 18" RCP, CL III wi Bedding & Compacted Granuler Backfill
11 S1Drm Sewer, 15" RCP, CL III wi Bedding & Compacted Granular Backfill
12 Storm SlIWtIr, B" PVC Schedule 40
13 7Z' Die. Manhole Base wi Bedding
14 7Z' Die. Manhole Sidewall
15 77' Die. Manhole Flat top wi Casting
16 60" Dia. Manhole Ba.. wi Bedding
17 60" Dia. Manhole Sidewall
18 48" Dia. Manhole B_ wi Bedding & Compacted Granular Backfill
19 48" Dia. Manhole Sidewall wi Bedding & Compacted Granular Backfill
20 Manhole Frame and Cover
21 Intake 1 01-C Special wi Bedding & Compacted Granuler Backfill
22 Intake 1 01-B wi Bedding & Compacted Granular Backfill
23 Area Drain - Complete
24 Abandon Exieling S1Drm & S1ructuree
25 PC Concrete Sidewalk, 4", Construct
2B PC Concrete Access Ramp, Deleclable
27 PC Concrete Commerciel Drive, Type "A", - Construct
28 PC Concrete Curb and Guller, 2.5', Construct
29 HMA 3OOk, S, 1/2" (PG 70-34)
30 HMA 3OOk, I, lIZ' (PG 64-22)
31 Crushed Stone Base
32 Remove & RepIece Exist. EIec. Condu~ & Wiring - Inc. Handhole
33 Shoring Deaign & 11l$18llation (for Ex. Light)
34 Traffic and Safety Control
1 LS
304 CY
1825 SY
200 SY
1.00 EA
208 LF
274 LF
127 LF
204 LF
72 LF
40.5 LF
23 LF
2EA
20.9 VF
2EA
2EA
20.9 VF
1 EA
17.7 VF
3EA
1 EA
2 EA
1 LS
68.5 CY
960 SF
2EA
2B SY
294 LF
77 Ton
139 Ton
325 Ton
1 LS
1 LS
1 LS
TOTAl BID
$2,000.00
$10.00
$4.00
$10.50
$1,500.00
$78.50
$51.75
$155.00
$96.00
$55.00
$95.00
$44.00
$ 3,520.00
$175.00
$700.00
$2,800.00
$120.00
$5,900.00
$272.00
$240.00
$2,650.00
$3,270.00
$500.00
$100.00
$4.00
$800.00
$55.00
$15.00
$100.00
$100.00
$18.00
$1.00
$9,500.00
$17,400.00
Sub Total
#7 ft d!z~
$2,000.00
$3,040.00
$7,300.00
$2,100.00
$1,500.00
$18,351.55 ~
$14,179.50
$19,685.00
$19,584.00
$3,960.00
$3,442.50
$1,012.00
$7,040.00
$3,657.50
$1,400.00
$5,800.00
$2,508.00
$5,900.00
$4,814.40
$720.00
$2,650.00
$6,540.00
$500.00
$6,650.00
$3,840.00
$1,200.00
$1,430.00
$4,410.00
$7,700.00
$13,900.00
$5,650.00
$1.00
$9,500.00
$17,400.00
$207,565.45 I
$324,212.95 I
I? ~ )) 6
, .
CITY OF DUBUQUE, IOWA
CUSTER I ALLISON HENDERSON PHASE II
STORM SEWER CONSTRUCTION PROJECT
CIP NO. 7201378
BID FORM
DETENTION BASIN AND OVERFLOW PIPE
1 Erosion Control Measures During Construction
2 Excavation & Off Site Disposal
3 Topsoil- Strip, Stookpile, and Replace
4 T errs Seed - 2" Thickr1eS6
5 4" Draintile, IncValves, Fittings, rIEl in and Chips
6 rIEl into Existing Outlet Structure
7 Tie into Existing Manhole I Intake
8 24" RCP CL III wi Bedding & Compacted Granular Backfill
9 PC Concrete Sidewalk, 4", Construct
10 PC Concrete Access Ramp, Detectable
11 PC Concrete Curb and Gutter, 2.5', Construct wi ACC Patch
12 PC Concrete Pavement, (8") wi Curb & Dowela, CI_ "C"
13 Crushed Stone Base
14 Remove & Replace Exist EIec. Condu~ & Wiring - Inc. Handhole
15 Protect Exist. Hydrant
16 Traffic and Safety Control
UNIT TOTAL
QUANTITY PRICE PRICE
1 LS $1 ,000.00 $1 ,000.00
2390 CY $8.25 $19,717.50
600 CY $5.75 $3.450.00
4175 SY $5.60 $23,360.00
660 LF $8.25 $5,445.00
1 LS $1.200.00 $1 ,200.00
5EA $850.00 $4.250.00
150 LF $78.00 $11.700.00
320 SF $4.00 $1 ,260.00
2EA $800.00 $1 ,200.00
120 LF $250.00 $30,000.00
135 SY $25.00 $3.375.00
65 Ton $20.00 $1.300.00
1 LS $2,850.00 $2.850.00
1 LS $500.00 $500.00
1 LS $6.000.00 $6.000.00
SUb Total $116.647.50 I
NO. DESCRIPTION
P / / /2 //
~k/;!. /I~ !ij~
/
//
;/
J)~'
. .' " f
BID BOND
KNOWN ALL MEN BY THESE PRESENTS. that we McClain Excavating Company. Inc.
as Principal (Contractor), and The Ohio Casualty Insurance Company ,as Surety, are held
and firmly bound unto the unto the City of Dubuque, Iowa (City), in the penal sum of _
(10% Amt Rid) in lawful money of the United States, for the payment of
which sum well and truly 10 bll made, we bInd ourselves, our heirs, executors,
administrators, and successors, jointly and severally, firmly by these presents. The
condition of this obligation is such that whereas the Principal has submitted the
accompanying bid, dated 23rd day of March , 2006, for the Custer I
Allison Henderson Phase II Storm Sewer Construction Project.
NOW, THEREFORE, if the Principal shall not withdraw said bid within the period
specified therein during the opening of same, or if no period specified, within thirty (30)
days after seid opening, and shall within the period specified therefore, if no period be
specified, within seven (7) days after the prescribed forms are presented to him for
signature, enter into a written contract with the Municipality, in accordance with the bid
as accepted, and give bond with good and sufficient surety or sureties, as may be
required for the faithful performance and proper fulfillment of such contract, then the
above obligation shall be void and of no effect, otherwise to remain in full force and
virtue,
By virtue ot statutory authority, the full amount ot this bid bond shall be forfeited
to the Municipality in liquidations of damages sustained in thB event that the afore
described bidder, Principal, fails 10 execute the contract and provide Ihe bond as
provided in the specifications or by law,
IN WITNESS WHEREOF, the above bounden parties have executed Ihis
instrument under Iheir several seals this 16th day of March , 2006,
the name and corporate seal of each corporate party being hereto affixed and these
presents duly signed by its undersigned representative pursuant to authority of its
governing body.
PRINCIPAL:
SURETY:
McClain Excavating Company, Inc.
co..n~clor .4 //_
By: A~ ~
Sig~e '
Pr<'.>,diLr-:+
Title
3/7-0 ( Z-G~ G
Dale
By:
The Ohio Casualty Insurance Company
Surety Company
~~
Slgnat e
--
Liz Mosca. Attorney-in-Fact
Title
March 16th. 2006
Date
ACKNOWLEDGM~NT {.)F'PRINCIPAL (Individual)
State of
}
County of
On this
day of
, in the year 20
, before me personally
come(s)
to me known and known to me to be the person(s) who (is) (are) described in and executed the foregoing instrument,
and acknowledge(s) to me that he executed the same.
Notary Public
ACKNOWLEDGMENT OF PRINCIPAL (Partnership)
State of
}
County of
On this day of , in the year 20 , before me personally
come(s)
a member of the co-partnership of
to me known and known to me to be the person who is described in and executed the foregoing instrument, and
acknowledges to me that he executed the same as for the act and deed of the said co-partnership.
State of
low(t..
Notary Public
ACKNOWLEDGMENT OF PRINCIPAL (Corporation)
County of .D v--bl"1 ~ .
On this~C ~ day of f\A 6--v<..h , in the year 20 vC, before me personally
come(s)_ML,-vl'-.::r A,N~ CJ u..; n . '
to me known, who, being duly sworn, deposes and says that he resides in t~e City of .---D.cd;J.L-'1lAe.... .._
that he is the _.[\'o2...:?,d Q....n t of the MC'c.l0.'" [xC-.<:~V6-ti.":) en) I "'C:.
the corporation described in and which executed the foregoing instrument,and that he signed his name thereto by like order.
~'Z'" liNDA A. AUGUSTIN
:>:~,- Commission Number 28899
Jo.,,-~-- My Comm. Exp. ' { ;:)..Gl/L
}
~j0,--- A A-. 't-~
Notary Public r \~
ACKNOWLEDGMENT OF SURETY
State of Wisconsin
County of St. Croix }
On this 16th day of March
, in the year 2006 ,before me personally
come( s) Liz Mosca
Attorney(s)-in-Fact of The Ohio Casualty insurance Company with whom I am personally acquainted, and who,
being by me duly sworn, says that he/she reside(s) in Hudson. WI that he/she is (are) the Attorney(s)-in-Fact of company
The Ohio Casualty Insurance Comoanv ,the company described in and which executed the within instrument;
that he know(s) the corporate seal of such Company; and that the seal affixed to the within instrument is such corporate seal and that it
was affixed by order of the Board of Directors of said Company, and that he signed said instrument as Attorney(s)-in-Fact of the said
Company by like order. "',:.. ,. "".
._//.~. h(.,~;.",'\,
~ .,.-.._ J,
,- \ \ '~
: I,: I -' ~,~{ _'
" "
" .
,.~"-~.,:,.
',I
~~~-
NO~~~
I ' ,
CERTIFIED COPY OF POWER OF ATTORNEY
THE OHIO CASUALTY INSURANCE COMPANY
WEST AMERICAN INSURANCE COMPANY
No. 38-869
Know All Men by These Presents: That THE OHIO CASUALTY INSURANCE COMPANY, an Ohio Corporation, and WEST AMERICAN INSURANCE COMPANY, an
lndiana Corporation, pursuant to the authority granted by Article Ill, Section 9 orthe Code of Regulations and By-Laws of The Ohio Casualty Insurance Company and West
American Insurance Company, do hereby nominate, constitute and appoint Michael J. Douglas, Chris Stelnagel, Liz Mosca or Susan Forness of Hudson, WlscoDsln its true
and lawful agent (5) and attorney (s)-in-fact, to make, execute, seal and deliver for and on ils behalfas surety, and as its act and deed any and all BONDS, UNDERTAKINGS, and
RECOGNIZANCES, not exceeding in any single instance FIVE MILLION (55,000,000.00) DOLLARS, excluding, however, any bond(s) or undertaking(s) guaranteeing the
payment of notes and interest thereon
And the execution of such bonds or undertakings in pursuance of these presents, shall be as binding upon said Companies, as fully and amply, to all intents and purposes, as if they
had been duly executed and acknowledged by the regularly elected officers oflhe Companies at their administrative offices in Fairfield, Ohio, in their own proper persons.
The authority granted hereunder supersedes any previous authority heretofore granted the above named attomey(s).in-fact.
In WITNESS WHEREOF, the undersigned officer of the said The Ohio Casualty Insurance Company and West American Insurance Company
has hereunto subscribed his name and affixed the Corporate Seal of each Company this 24th day or August, 2005.
OMO"
,?)\\l.'.'J.t.'(~..
~ SEAL)}
"' /.
'''i7ili''~'
A~
~~
ST ATE OF OHIO,
COUNTY OF BUTLER
Sam Lawrence, Assistant Secretary
On this 24th day or August, 2005 before the subscriber, a Notary Public of the State of Ohio, in and for the County of Butler, duly commissioned and qualified, came Sam
Lawrence, Assistant Secretary of THE OHIO CASUALTY INSURANCE COMPANY and WEST AMERICAN INSURANCE COMPANY, to me personally known to be the
individual and officer described in, and who executed the preceding instrument, and he acknowledged the execution of the same, and being by me duly sworn deposes and says,
that he is the officer of the Companies aforesaid, and that the seals affixed to the preceding instrument are the Corporate Seals of said Companies, and the said Corporate Seals and
his signature as officer were duly affixed and subscribed to the said instrument by the authority and direction of the said Corporations.
IN TESTIMONY WHEREOF, I have hereunto set my hand and affixed my Official Seal at the City of Hamilton, State of Ohio, the day and year first above wrinen.
6\1l11lWIlIIII
",..\~~.L.Y(I'
!~\'
\~-;)
~ '.n"A
"............-
t!kf xl 1f~
Notary Public in and for County of Butler, Stale of Ohio
My Commission expires August 6, 2007.
This power of attorney is granted under and by authority of Article III, Section 9 of the Code of Regulations and By-Laws of The Ohio Casualty Insurance Company
and Wesl American Insurance Company, extracts from which read:
Article 1II, Section 9. Annointment of Attornevs-in-Fact. The Chairman of the Board, the President, any Vice.President, the Secretary or any Assistant
Secretary of the corporation shall be and is hereby vested with full power and authority to appoint attorneys-in-fact for the purpose of signing the name of the
corporation as surety to, and to execute, attach the seal of the corporation to, acknowledge and deliver any and all bonds, recognizances, stipulations, undertakings or
other instruments of suretyship and policies of insurance to be given in favor of any individual, firm, corporation, partnership, limited liability company or other entity,
or the official representative thereof, or to any county or state, or any official board or boards of any county or state, or the United States of America or any agency
thereof, or to any other political subdivision thereof
This instrument is signed and sealed as authorized by the following resolution adopted by the Boards of Directors of the Companies on October 21,2004:
RESOLVED, That the signature of any officer of the Company authorized under Article III, Section 9 of its Code of Regulations and By.laws and the
Company seal may be affixed by facsimile to any power of attorney or copy thereof issued on behalf of the Company to make, execute, seal and deliver for and on its
behalf as surety any and all bonds, undertakings or other written obligations in the nature thereof; to prescribe their respective duties and the respective limits of their
authority; and to revoke any such appointment. Such signatures and seal are hereby adopted by the Company as original signatures and seal and shall, with respect to
any bond, undertaking or other written obligations in the nature thereof to which it is attached, he valid and binding upon the Company with the same force and effect as
though manually affixed.
CERTIFICATE
1, the undersigned Assistant Secretary of The Ohio Casualty Insurance Company and West American lnsurance Company, do hereby certily that the foregoing power of attorney,
the referenced By-Laws of the Companies and the above resolution of their Boards of Directors are true and correct copies and are in full force and effect on this date.
IN WITNESS WHEREOF, I have hereunto set my hand and the seals of the Companies this I gth day of M""r{"h ?OOn
\\,\\\.l!AII...: '"'''~
...... ...~.. '"
.:' \,
!~"SEAL J!
~-/ /;,~4""
S-4300 3/99
Assistant Secretary
~{fJno"'o:; "':;;':-fUlWO<DC"WUl1lfh,fIJ -0 _ ~ <ll:
~ ~g ~~:<O ~ ~~2 {i;ii~_~_~~~* ~ -o.9.Q Ui-g2:! <i-zg,,: <1> W ffi~g~o
3 ~-u 315$ s.ii:u n.:...~~::J 2.2" <L 0 3..2,~:3 g ~s.g I(\l ~~.~ OcnzO.....m::!O
\l)fJ>......11I~ ([l-",<oc-o<," III 0..-'" ([I~ c: ^"l1IO<o.<1l O....OC:r:u
::J<DO~ uQ~<1>~~o<~~g~m-~a ~In~ == Q ZOmmmmm
~.~ ~=~~O~8 g g ~l5-~~ ~~~! ~ ~ ~ ~g~~ ~ 2 ~-:3 ~~~~;;lg~6
(J)- -=r-;:;;: ::>1'030 ~(Oo_:;Io-' V> ....ro' llloc::Y-oc..:tJ OJJZ"tJat
gO~<D~'~~~~-~~~~_~~*!~Q O~s.rvo~~g~omC~Z_oo""6
(O-g,u"'Ill(l102:-:TUJn.>--,~011l2' "'st"6- 00 8::>....,;:+-D;::o:~OO::E.-o)>-tO
--l<.52.:iw:T2%<;rm "'-::> 8 ['5 ~g.:€, ;!~.~ g- ~ ~~.rn:T~'< ffi:=' w-lgm~:=~"Tl~
!S(j)lll~([)~~[La.~5!!~_~g-:rro=<'D::r--~ 2~~o([l:;l~~<i>~_ z:D(Ilcn~~:tI
00:;1-'" mLwO.....WQlOO::JO {fJO o{fJm""'rvN' 0-,= mo-ccn
~~m~m_....,mlll~m~...., n~o~mo-f ~m....,-w..^~^ -zocno
g?I~~Qmo~2~~~~~g~~~~15 g=-15ag~?s.g - Z "Tl
o ~-~Q.O(jja;-o!ll~::t"O(Ilolllro1700roo-o 05-"U(JJ~=tg:305-lilmn-lOO~CDCTQ:!i!a.-nii tCO!"'llfS-~O ~=I:E "2.2:,-0. >d:::l~(t)i!:ECi)i:E:::I3.ZtT
o----'g5.!!!3-~~t~-a5.g~3.~ :g.g:g:a:g---.,Q ,g~~~=~8:a~....~2"~re~w'Q.~'<.<>2~3Q.~5: ~s lDg;"";t ~=~~il....8b>~g~:;C;m~=ftI =a.r,oe
:J--'(/J ~3 (/J-o==-.....'oc.::r 0. ~----,(/J~OC - ro ::ru''''<(/J'' 0 n --::0. Z:;::- - CTl" ::r.....C CT::J- 5, III. ;:r.
:::-~ 0" (/J g,~ (JJ-o (JJ m -'310 a;$! ~.__CIJ ~ __~ P.1 a;:::-CIJ 3 3:~-o~ o.--:::;:CIJ o~:J ~ "'0 ~ 5.(tI ~-- g g:....m <'82. i"!t!'2O-ct a.. am ;I~-!!t2.E.Q.Gl Q.ib; ~m CD","",ID:To
~ -~ID n~""::r....:J c CIJ~(JJo~~2o C5 -m-'~ o~- omu~ m~~Ou a.~CD ~ .-~ ~.3 ",~: i~' ~~~~::JCD3
~(JJ~~~~(/J:J-o~::rc.~~oc.~_o~m~o(/Jg-,~m n.=~*3""~:J-'ro(IJ~Q.~=::Jo....w~~ 3~~ ~- 'm.... ~~-n=~ ~ "2.:eo.mCDo.::Ja
OCClJl()o.umo.ro-ro,..:JPJ;:+ roo::>m:J -,co-3o Uo ~o::r-~ro ,<::TO -. c.C::r o~o alc 0..,<U1~. lD= <sa, _::J Q.
~g~~~3~~~]~~~g~~o[~g~i3roi~~~~Q~~~~~~~~g~~~~~~:ga;~~~]i~~~iil{~~!nw~~g1lio~~~~~go~~2.~
-'(IJ:J'< ro::r ::lOll (/Jam m__....-,O-U-(/Joro ....-,~::T ::l([l::l ~ '_"":103--'" 1l:!..~_. ''lJ-gm.-cCi::r ';:+CS-- dcri!CD Ill~ . .
;!!!..:::-.....~-=-~ Q....jli 0 0.> ---h<=::g o.>Q"gj-o g 5 ~ u. ~g ~s-s-~ ffi s-.3:m g,~n::g,o-Q ~g:..... 00 <ll::J Q.tT 5l!lCT~ l>> ~ 0.'3 5" 3 ~ ~'< 3'CT~ !D~-"'~;2 i'::J ~5 8'~~."
-c::0.>::Tmo3 0::>0::>....--'::>0 c'-,~....- c mro..........-.. 0.C::J -<Om:l_ CD g""<-::Jt'm c""~, CD! ;:.0.,_.. ---"'i.:t:
ii~i :;[ii:Ha:U;~~!iHIUiiH !ii rHnlj~~!~~li ~~!li <>i~l ~i!~~~l~ !iiiJgl~i ~~~
,-, .,<3m" CD. -.-, ~.nm,<o>n~oroo., ro__-,o., ([l,._ m-,. '<o......o.&::r.!!,. ,m ,i::rC....8.8: ...~... 0,3.::1 CD I _ ::r:)(Io&.......I... ,,<CD
0-0<(0- -';::0-0'030".0 .--+ro<:t3<(J)o",,"_Oo. ro-3ro-<>.oro0"3 Ylo:JU>-......-c.aol>>fjl.AlO 3,.::s1?lrC'""O O=:=t"'Og:J3!!l::S..oo CT~I!OO-3U1-g'..Q
:8.~:~-~~g2 ~ ~ g:Z ffi ;!~g 9.~~:-g Kg ~~-;J8 ~~~ Q ~.g.:~:p-g.z~~]-~lg.a:g.5."s'~8 g ~c a5 n ~ CD ~ ~g ~ l~ ~ ~ i~ ~g -i~tt."< ~~~~g-~::s ~
~ ~ ~ ~f~-~-~-~~~~ ~~~-n> W: ;~:I~ ~~i~: iJ~~~g;~-g!g~;~Q ~:!~~~I~~~Jgl~b>~~~o Ka1~~tr~:a~ [: ~~J!~;5!
IX> ~~Dro ro- ~=cr2 :JcUm~:J~~.... -0 ~ o.~ 0 :Jm-- C<D~O~'<~O...~_ ::J~C ~8 -&~I$~_oc-~2::JuUl "'0_-
~t~ n~ ~HalJ a~:~ >f:f;~ij;~ ;!~in ~!!U:Ui ~~83.J !s.~~;lii~~n"i!I!~~>l!3-afiiin~i!;3H~!i;~
-o-PJ oc grom:J:::r-. 0.... 0. --OIl..... n.c -:J- ([lroO (11-- ,<!PI>> UI 1"i g ~ 103 tD<Illiji"C~,<..;:: o3111U1(Ji
..,.::r:Jrom_ m~~oo>~1 ~g::Tn....o~.....()ro 0- ~~~ (Dc3 :Jn~:JQ ~(tI~Qo =0 i~ l>> 0_ _ ~~~o- 3 i:E-::Sc::sc.~
<mo.:J 0 l.J>o~- :::r ....-..ro::y::TO <-:J ---.,__CD uro-'c 0 '< -::J QI::J 3 ::;t!OCT--::e-CD::J 0 5 ~ =::0. :r IDl!o.'1J_ III
\llen o.~-< ~~&i-!2g,~ ~mo~CIl~iii-ro.zg- 3Q~3_-g_ro-'~-~ -~3S.3~coI03~Qga.'<a.~_~-CII ,a. ~3~3'~i!_!tCe.ig: ~CD ~ 0Tl-g,g,!'<
OOj()"Q-m ([lro Ill~O.... --om"QiD )> :J III (flo....lll::::S- ,_Ill....O "OO_C::JDll:!:~.(D. !'i-a. -1";:J! ..."2.rac::_::J ca 0.. 0 ;:f_"iiGl _;I,
9m~9g7 ';>!ll~6.q>7q> ~_~7~9Sl3'?s.~- $~ii:"s.mq>5.~g q>a;7a;!f:~.g~i6'i!.g,t{g,~~. =t3g~~V i'i4~~f ,_~If'~ g"92.~~9Y1~lBa'l
;::;~ I'V::TOO U-D5'{"J(.l(")::z:c.&'nc'n~OO -I!.g 3
~ ~gwfr~~*~~~Q~m~_~~a~~i~~~-lD~m
.... cn.......EoS[-,3..-+iDa.ro-I!!O:l(~:::r :::I-iii::JQ"::::!CD~_
o L oc01i:i~L~3()m""'''''''~CT:::!I;;S:. oQg,ffina.COoo
([l ....roc:::::s-::>3 -'< ...... m::J3.:;)gJ: . l>>U1;:l:~r
~ ::T_ :Jro([lrom::Eo(J)5'> I!!.. ~_~l>>- - '<AI
o~ no~o. mO=~(.l ci~5cl::J eg~o,g
~([l w::Eo~ (J}~rr)>o~~~~_~ ea.l 3_ao~
,071 '< 0.>:0 ~~ ([I-g."P iilos-g i l>> ~!'?dJ__- O'iD~
00 g,m::TQ ([l()~~3~~""l>>o::Ja8~i ~:ES~
;::;:~ 5.ro(f) o:rroI'V- - 3~-.;fC. Q.Gll>>iil
'<~ s: 0-' ~(flQoof!l.. -alii :EQ.Cl_CT-g --~:::Iiii
o~. o.>~;:+g, 5-ro5l~ c3~~o-..cg: 3 ''<Gl
IDa} o(ii'<..... 3(IJQ.. .....g;wCTlB o-(r ~ml>><
~_.... _::rnQ,ii:" ~ cp ~>15o.:~5'7 ,.ig,~i-< T~ 5.::
-~""';
,', ..,.
. . ,
.' .
I.;;".
~O3:
~O,.
03"
03-<
3..-
3!!.:;Jl;
O'
~":::. ~
uZm
~3~
m~m
PJ~:o
-_3:
d~
n
::;-
'"
'"
0..
0'
..,
n
o
"
'"
~
~
o
:E
po
5'[fJ
_. "
~ U'
~ v;
()
..,
5'
()
0..
0
U'
0.. ()
'" 0'
'< ..,
0 ()
-+; a
~n
'"
:..-:
0
p;
..,
'<
'U
"
:.
()
'"
'"
'"
0..
N 0'
-<
0 tJ
~ "
U'
"
..0
"
"
n
0
"
'"
~
'::"
0
:E
?
-'",
~"
,'>c.
,
~- \'
"
f.
~
,'0
--....lJ
~
r
(
'-+-n~~
::r 0 ==t. ~
" :E () ~ '"
O'P cOP'
~~[~&
o " -
:E .., 0 n ::r:
__ g. '" 0
~,<-g:a ~
....... () r::r 0
....... (tl ....... '"'"I
a::+..... a 6
ro ....... ~ o. 0
~-<(tl~~
C>' 0.. - N
;:::;., S' .....'"0 5.
~ P' =:! C
ri::&~~
::r"~ (tl Ci).";'
.......('I)n~~
,,0 ~ ..... ~ t;rj
NS-Q"O
0(') 0 >--t;.....
o::r">--t;'-+=:!
O\g.tJ~[]O
!:J '" g. .-J 0
0.. 9. c r.:e... ~
..........0 ('I) :;<;-'
0' () C CJO
'"'"I ('I) ('I) '"'"I 0-
:E :E ~ ,g ..,
::r",n::r..,.;
_. v; 0 ..,.. <;
(') '"0 C ...... 0
p-' c g ~ 0
.-+ g~ P' 0..
~ en. 0 P: ~
(') ~ >--t; P, e;
g-g.tJ", 0..
'"'"I ....... g. (l) n
[]O '" " :E 0
('I) 'JJ ...0 r.n S
~. e:. c -g S
V'J 0.. ro '"i:j C
O\;::j~(l)::::l
0('1) ::::l '"'"I (S'
VJ :E 0.. 0 '"
N'JJ[J:l>--t;.-+
. '"0 .-+ CJO o.
~ ~ ('I) ....
'"0 -- ::::: ,.....
('I) rn ('I) ,,'JJ
'"'"I 0 '""' __
o >--t; E:. ::::l
'" ~
n
t'j
El
.....
"'l
.....
n
>
--i
.....
o
z
o
"'l
":l
C
t:ll
t"'
.....
n
>
--i
.....
o
z
~\FJ
C""'3
~>
C""'3
OM
cO
M~
(j......
00
C~
z>
""'3
><
,---.
\FJ
\FJ
..
NOTICE OF HEARING
ON PLANS AND
SPECIFICATIONS
Notice of public hearing
on proposed plans and
specifications, proposed
form of contract and esti-
mate of cost for the
Custerl Allison-Henderson
Sewer and Detention Ba~
sin Project Project.
Project Description: The
storm sewer project con-
sists of two parts with sep-
arate deadlines. The first
part of the project will con-
sist of creating a detention
basin adjacent to the hock-
ey rink and constructing an
overtlow pipe across Laras
Boulevard to outlet in an
existing structure on Adair
Street. This portion of the
project will have a comple-
tion deadline of May 12,
2006 due to the need to
have that area of the park
available for summer activ-
ities. The second part of the
project will consist of ex-
tending a new storm sewer,
to the South, from an ex-
isting junction box located
between the North end of
the hockey rink and Grand-
view Avenue. The new storm
sewer will serve the Custer
Street area and the Univer-
sity/Grandview intersection
and will replace an existing
smaller storm sewer in
Grandview Avenue which
will be abandoned in place.
The deadline for this portion
of the project will be Au-
gust 11, 2006.
NOTICE IS HEREBY GIV-
EN: The City Council of Du- ,
buque, Iowa will hold a
public hearing on the pro-
posed plans, specifications,
form of contract and esti-
mate of cost for the Custerl
Allison Henderson Sewer
and Detention Basin Proj-
ect in accordance with the
provisions of Chapter 384
City Code of Iowa, at 6:30
p.m., o.n the 3rd day of April,
2006, In the Public Library
Auditorium, 360 West 11 th
St~eet, in Dubuque, Iowa.
Said proposed plans, speci-
ficattons, form of contract
and estimate of cost are
now on file in the office of
the City Clerk. At said hear-
ing any interested person
may appear and file Objec-
tions thereto or to the cost
of the improvements.
. A~y visual or hearing-
ImpaIred persons needing
special assistance or per-
sons with special accessi-
bility needs should contact
the City Clerk's office at
(563) 589-4120 or TOD at
(563) 690-6678 at least 48
hours prior to the meeting.
Published by order of the
City Council given on the
6th day of March, 2006.
Is/Jeanne F. Schneider
CMC, City Clerk '
113/24
STATE OF IOWA
DUBUQUE COUNTY
{ss:
CERTIFICATION OF PUBLICAT
I, Bev Engler, a Billing Clerk for Woodward Comml
corporation, publisher of the Telegraph Herald,a new
published in the City of Dubuque, County of Dubuql
certify that the attached notice was published in said
dates: March 24, 2006, and for which the charge is $:
r--:~n~ ~~
Subscribed to before m~otary Public in and for]
this ~~ day of ?dd/-"0 , 2C
~~u.
Notary Public in and fi
~)
MA
GOI
My