TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: 5 Points Traffic Signal Reconstruction Project
C I P 1021920
DATE: February 26, 2013
Dubuque
kital
All- America City
II 111!
2012
City Engineer Gus Psihoyos is recommending acceptance of the construction contract
for the 5 Points Traffic Signal Reconstruction Project, as completed by Portzen
Construction, in the final contract amount of $163,368.41. This is 9.3% over the original
contract amount of $149,432.00 due to the installation of a new traffic signal base and
signal at the southeast corner of Jackson and 20th Street. With the addition of the traffic
signal, additional sidewalk and curb and gutter had to be replaced.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
kr,„709,,,
Michael C. Van Milligen
MCVM:jh
Attachment
cc: Barry Lindahl, City Attorney
Cindy Steinhauser, Assistant City Manager
Teri Goodmann, Assistant City Manager
Gus Psihoyos, City Engineer
Masterpiece on the Mississippi
TO: Michael C. Van Milligen, City Manager
FROM: Gus Psihoyos, City Engineer
SUBJECT: 5 Points Traffic Signal Reconstruction Project
CIP 1021920
DATE: February 25, 2013
INTRODUCTION
Dubuque
ketd
AU- mnatcacfly
11111
2012
The enclosed resolution provides for the acceptance of the construction contract for the
5 Points Traffic Signal Reconstruction Project.
BACKGROUND
The 5 Points Traffic Signal Reconstruction Project provided for the reconstruction of
traffic signals at the intersection of Rhomberg Avenue and 20th and Elm Streets.
Improvements included: pedestrian buttons for the crosswalks; a dedicated left turn for
the westbound traffic on Rhomberg Avenue to Elm Street; and the reconstruction of
curb ramps to bring the intersection to ADA standards. This newly - rebuilt signal is tied
into the City -wide traffic management operations center at City Hall.
DISCUSSION
The 5 Points Traffic Signal Reconstruction Project was completed by Portzen
Construction, Inc. of Dubuque, Iowa, in the final contract amount of $163,368.41. This is
9.3 % over the original contract amount of $149,432.00. The extra cost is due to the
installation of a new traffic signal base and signal at the South East corner of Jackson
and 20th street. With the addition of the traffic signal additional sidewalk and curb and
gutter had to be replaced. This was an ideal time to update this corner since a fiber
vault was being placed at this intersection and portion of the sidewalk had to be
removed.
RECOMMENDATION
I recommend that the City Council accept the improvements and authorize payment of
the contract amount of $163,368.41.00 to Portzen Construction, Inc. for the 5 Points
Traffic Signal Reconstruction Project.
BUDGET IMPACT
The estimate of probable cost for 5 Points Traffic Signal Reconstruction Project is as
follows:
The project funding summary is as follows:
CIP
Award
Final
Construction Contract
$149,432.00
$163,368.41
Contingency
14,417.30
0.00
Construction Engineering & Inspection
21,625.00
19,644.21
Total Project Cost
$185,474.30
$183,012.62
The project funding summary is as follows:
CIP
Fund Description
Fund Amount
1021920
5 Points Intersection Rhomberg — 20th - Elm
$92,500.00
3001274
Traffic Signal Controller Replacement
4000.00
3001011
Signal Program
36,000.00
3001816
Traffic Signal Fiber Optic Network
1650.00
3501608
Street Lighting Downtown
4862.62
3001017
Fiber Optic Conduit Projects
24,000.00
2501017
Fiber Optic Conduit Projects
20,000.00
Total Project Funding
$183,012.62
ACTION TO BE TAKEN
I respectfully request that the City Council adopt the attached resolution accepting the
improvements and authorizing payment of the contract amount of $163,368.41 to
Portzen Construction, Inc. for the 5 Points Traffic Signal Reconstruction Rebid Project.
Prepared by David Ness, Civil Engineer II
cc: Jenny Larson, Budget Director
Don Vogt, Public Works Director
RESOLUTION NO. 67 -13
ACCEPTING THE 5 POINTS TRAFFIC SIGNAL RECONSTRUCTION PROJECT AND
AUTHORIZING THE PAYMENT OF THE CONTRACT AMOUNT TO THE
CONTRACTOR
Whereas, the Public Improvement Contract for the 5 Points Traffic Signal
Reconstruction Project (the Project) has been completed and the City Engineer has
examined the work and filed a certificate stating that the Project has been completed
according to the terms of the Public Improvement Contract and that the City Engineer
recommends that the Project be accepted; and
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF DUBUQUE, IOWA:
Section 1. The recommendation of the City Engineer is approved and the Project
is hereby accepted.
Section 2. The Finance Director is hereby directed to pay to the Contractor from
the 5 Points Intersection Rhomberg — 20th - Elm capital improvement appropriation for
the contract amount of $163,368.41 less any retained percentage provided for therein
as provided in Iowa Code chapter 573, and to pay such retainage only in accordance
with the provisions of Iowa Code chapter 573.
Passed, approved and adopted this 4th day of March
Attest:
Kevi ' . Firnstahl, C rThity Clerk
, 2013.
Kevi
h, Mayor Pro Tem
CITY ENGINEER'S CERTIFICATE OF FINAL COMPLETION OF THE 5 POINTS
TRAFFIC SIGNAL RECONSTRUCTION PROJECT
The undersigned City Engineer of the City of Dubuque, Iowa, hereby certifies that
he has inspected the 5 Points Traffic Signal Reconstruction Project, and that said
Project has been performed in compliance with the terms of the Public Improvement
Contract, and that the total cost of the completed work is $183,012.62.
Dated this 26 441 day of e6r'a, , 2013.
Gus Psihoyos, City Engineer
Filed in the office of the City Clerk on th ' day of
Kevin S Fi ns ahl, CMC City Clerk
, 2013.
$ 161,631.41 I
$ 1,737.00I
THE CITY Op
DUB
tau
Masterpiece on the Mississippi
PARTIAL PAYMENT NO
Council Final
City of Dubuque - Engineering Division
Partial Payment Form
PROJECT NAME: 5 - POINTS TRAFFIC SIGNAL RECONSTRUCTION
CONTRACTOR: Portzen Construction
BID ITEM DESCRIPTION
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
28
27
28
29
30
b IMPROVEMENTS
MOBILIZATION & MISCELLANEOUS
UNIT
LS
PLAN
QUANTITY
DATE: February 11, 2013
CONTRACT AMOUNT: $149,432.00
CONTRACT
UNIT COST
REMOVE PAVEMENT OR DRIVEWAY
SY
REMOVAL OF SIDEWALK
SY
REMOVAL EXISTING HANDOLE
BASE STONE
SIDEWALK, P.0 CONCRETE 41N.
QUANTITY
TO DATE
gEnT
AMOUNT EARNED
TO DATE
COMP.
$ 6,000.00 1.00 $ 6,000.00 100.0%
103 $ 12.00 112.88 $ 1,354.56 109.6%
119 $ 9.00 212.96 $ 1,918.64 179.0%
EA $ 350.00 1.00 5 350.00 100.0%
TON so $ 20.00 99.51 5 1,990.20 110.6%
SY 97 $ 36.00 152.56 $ 5,492.16 157.3%
SY 34 $ 80.00 60.48 $ 3,828.80 177.9%
LF 82 $ 20.00 $ - 0.0%
SY 38 $ 85.00 118.82 $ 10,099.70 330.1%
TON 17 $ 125.00 11.91 $ 1,488.75 70.1%
SF 84 $ 45.00 84.00 S 3,780.00 100.0%
STA 17 $ 80.00 18.02 $ 1,281.60 94.2%
EA 2 $ 110.00 2.00 $ 220.00 100.0%
STA 8.2 $ 80.00 7.98 $ 636.80 128.4%
$ 5,000.00 1.00 $ 5,000.00 100.0%
EA $ 1,050.00 3.00 $ 3,150.00 300.0%
EA 3 $ 3,200.00 3.00 $ 9,600.00 100.0%
EA $ 6,800.00 1.00 $ 6,800.00 100.0%
EA 79 $ 105.00 31.00 $ 3,255.00 163.2%
EA $ 1,700.00 1.00 $ 1,700.00 100.0%
LS $ 4,100.00 1.00 $ 4,100.00 100.0%
LS $ 53,000.00 1.00 $ 53,000.00 100.0%
LF 185 $ 17.00 298.46 $ 5,073.82 161.3%
LF 78 $ 25.00 43.52 $ 1,088.00 55.8%
LF 851 $ 28.00 857.50 $ 24,010.00 90.3%
LF 92 $ 10.00 248.65 $ 2,486.50 270.3%
LF 72 $ 16.00 117.43 5 1,878.88 163.1%
SIDEWALK, P.C. CONCRETE, 61N
CURB & GUTTER P.C. CONCRETE
8' PCC PAVEMENT WITH INTEGRAL CURB AND GUTTER
HMA 300k SURFACE COURSE. 12' (PG64 -22) PAVEMENT
DETECTABLE WARNING - CURB RAMP
PAINTED PAVEMENT MARKING, WATERBORNE OR SOLVENT -BASED
PAINTED PAVEMENT MARKING SYMBOL
PAVEMENT MARKING REMOVAL
TRAFFIC CONTROL
LS
24' ROUND HANDHOLE
FIBER VAULT, SQUARE
PROVIDE FIBER HUB FOUNDATION AND INSTALL FIBER HUB CABINET
CORE DRILL FIBER VAULT OR HANDHOLE
PRECAST HANDHOLE WITH LID MARKED 'TRAFFIC SIGNALS'
REMOVAL OF TRAFFIC SIGNALIZATION
TRAFFIC SIGNALIZATION
CONDUIT, HOPE, PUSHED 2'
CONDUIT, HOPE, PUSHED 4'
CONDUIT, HDPE, 4' WITH 4 -1' INNER DUCT CONDUITS, PUSHED
CONDUIT, RIGID PVC, TRENCHED 2'
CONDUIT, RIGID PVC, TRENCHED 4'
SUBDRAIN, PLASTIC PIP, 4'
CONNECT SUBDRAIN TO EXISITNG INTAKE
ADJUST EXISTING MANHOLE
LF Too $ 10.00
EA $ 400.00
EA $ 750.00
$
3.00 $
TOTAL AMOUNT EARNED TO DATE:
0.0%
2,250.00 300.0%
CHANGE ORDER - EXTRA WORK ITEMS
1
REMOVE & DISPOSE OF OLD INTAKE
2 REMOVE SIGN FOUNDATIONS
3 REMOVE OLD ROCK FOUNDATION
4 PATCH CLAY STORM SEWER WITH COLLAR
5 INSTALLATION OF TESCO FOUNDATION
LS
LS
LS
LS
LS
$ 175.00 1
$ 309.00 1
$ 698.00 1
$ 115.00 1
$ 440.00 1
TOTAL AMOUNT EARNED TO DATE:
TOTAL AMOUNT EARNED TO DATE:
175.00
309.00
698.00
115.00
440.00
$ 163,368.41
CERTIFICATE OF THE CITY MANAGER:
I hereby certify that the above statement shows in detail the orrect amount of all work required to complete the above improvement
APPROVED:
APPROVED:
Michael Van Milligen, City Manager
City of Dubuq : , lo
Gus Psihoyos, City Engineer
City of Dubuque, Iowa
CERTIFICATE OF THE CONTRACTOR:
The undersigned, contractor for the above improvement, does hereby
accept the above "Total Due Contractor ", as full settlement for all claims for said improvement.
CONTRACTOR;
BY: (AG
TITLE: TQ'c's_k, Mar 554'
DATE: a ((� j`�