Fifth St Reconstruction Award Contract i5~~%duE ~<Ik-~ MEMORANDUM June 13, 2006 TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager SUBJECT: 5th Street Reconstruction Project - Delhi Street to Alpine Street CIP 3001813: Fiscal Year 2007 Street Construction Program and the Lincoln School Pick-up/Drop-off Area Sealed bids were received for the 5th Street Reconstruction Project - Delhi Street to Alpine Street. City Engineer Gus Psihoyos recommends award of the contract to the low bidder, Portzen Construction Inc., in the amount of $1,024,519.20. This bid is 0.6% under the engineer's estimate of probable cost. I concur with the recommendation and respectfully request Mayor and City Council approval. ;1~j ~jJtL- Michael C. Van Milligen MCVM/jh Attachment cc: Barry Lindahl, Corporation Counsel Cindy Steinhauser, Assistant City Manager Gus Psi hoyos, City Engineer D~~~E ~<k~ MEMORANDUM June 9, 2006 TO: FROM: Michael C. Van Milligen, City .M~l1pr-) Gus Psi hoyos, City Engineer YJ .\0----: 5th Street Reconstruction Project - Delhi Street to Alpine Street CIP 3001813: Fiscal Year 2007 Street Construction Program and the Lincoln School Pick-Up/Drop-off Area SUBJECT: INTRODUCTION The enclosed resolutions authorize the award of the construction contract for the 5th Street Reconstruction Project - Delhi Street to Alpine Street. BACKGROUND The 5th Street Reconstruction Project - Delhi Street to Alpine Street will provide for the reconstruction of underground utilities, roadway sub-base and the construction of a new 31- foot wide concrete roadway between Alpine Street and Delhi Street. The project will be constructed in three phases. Phase I of the project will include the complete reconstruction of all underground utilities and mainline roadway construction from Alpine Street to Booth Street. This will also include the pick-up/drop-off drive at Lincoln School. The Phase I section of work is anticipated to be completed by August 25, 2006 and open to local residents and vehicular traffic. Phase II of the project will include the complete reconstruction of all underground utilities and mainline roadway construction from Booth Street to Glen Oak. The Phase II section of work is anticipated to be completed by November 3, 2006 and open to local residents and vehicular traffic. Phase III of the project will include the remainder of the underground utility work and the concrete roadway construction from Glen Oak to Delhi Street. The completion for the entire project is scheduled for June 29,2007. The project will incorporate upgrades to the existing sanitary sewer system that include: the complete reconstruction of approximately 1,465 lineal feet of 8-inch mainline sewer; the reconstruction of 7 deteriorated brick manholes; and the replacement of 39 private sanitary sewer laterals. The cost for the individual sanitary sewer lateral replacements will be assessed to each respective private property owner. The project will also include the reconstruction of approximately 2,065 lineal feet of watermain, mainline valves, fire hydrants, and the replacement of 23 lead residential water services. The cost of the individual lead residential water service replacements will be assessed to each respective private property owner. The project also provides for the construction of approximately 1,070 lineal feet of new storm sewer and 16 catch basins to improve the stormwater conveyance in the area; the installation of fiber optics and telecommunications conduit infrastructure; and the replacement of existing sidewalks along both sides of West 5th Street. City staff met with the City Forester on this project to discuss the condition and impact to the existing City trees within the project corridor. There are approximately 9 mature trees in this corridor. The City Forester has identified that 5 trees will be removed due to the proposed construction operations. The Dubuque Community School District (DCSD) has requested that the City include a pick-up/drop-off area for Lincoln School in the West 5th Street Reconstruction Project. The DCSD portion of the project was handled as separate bid items with the intent of more favorable bidding. This arrangement also insured that the same contractor will perform both projects and thus better construction coordination. The DCSD will fully fund its portion of the work. BID RESULTS Sealed bids were received on the project on June 8, 2006. Portzen Construction, Inc. of Dubuque, Iowa, submitted the low bid in the amount of $989,990.50 for the base bid and $34,528.70 for the alternate bid (Lincoln School Drop-off Drive). This amount is 0.6% under the engineer's estimate of probable cost. A summary of the bid proposals received are as follows: Contractor Name Total Bid Portzen Construction, Inc. Tschiggfrie Excavating, Inc. Horsfield Construction,lnc. $ 1,024,519.20 $ 1,077,316.50 $ 1,234,567.89 RECOMMENDATION I recommend that the contract be awarded to Portzen Construction, Inc in the amount of $1,024,519.20. PROJECT COST-BUDGET IMPACT The estimate of probable costs for the 5111 Street Reconstruction Project - Delhi Street to Alpine Street is summarized as follows: Cost Estimate Construction Contract Bid Alternate NO.1 - Lincoln School Pick-up/Drop-Off Access Drive Contingency (10%) Construction Engineering & Inspection (15%) $ 995,817.55 34,830.50 99,581.76 164,309.90 Bid Award $ 989,990.50 34,528.70 99,581.76 164,309.90 ~ 1,294,539.71 .$1,288,410.86 CIP No. Fund Description 3001813 FY 2007 Street Construction Program Special Assessment - Street Improvement, Residential Properties Special Assessment - Street Improvement, Commercial Properties Special Assessment - Water Services, Residential Properties Special Assessment - Sanitary Sewer Laterals, Residential Prop. 7401405 FY 2007 Watermain Replacement Program 7101638 Street Program Related Sanitary Sewer Improvements 1021609 Fiber Optic Conduit - Private Sub. and Miscellaneous Projects Dubuque Community School District - Reimbursement Total Project Funding Fund Amount $ 703,542.35 111,845.16 26,074.91 30,897.63 50,916.25 158,844.47 96,433.80 75,327.59 34,528.70 ~ 1,288,410.86 The 5th Street Reconstruction Project - Delhi Street to Alpine Street will be funded through the annual capital improvement project appropriation of City funds as noted above in the amount of $1,034,148.21. The project, as outlined, will require Special Assessments in the amount of $219,733.95 and expenditure from the Annual Street Construction Program (Funded through Local Option Sales Tax) in the amount of $703,542.35. The Lincoln School drop-off/pick-up area will be fully reimbursed (current bid of $34,528.70) by the Dubuque Community School District. ACTION TO BE TAKEN I recommend that the City Council adopt the attached resolution awarding the 5th Street Reconstruction Project - Delhi Street to Alpine Street to Portzen Construction, Inc. in the amount of $989,990.50 for the Base Bid and $ 34,528.70 for the Alternate Bid. Prepared by Jon Dienst, PE cc: Dawn Lang, Budget Director Don Vogt, Public Works Director Bob Green, Water Plant Manager Bob Schiesl, Assistant City Engineer Deron Muehring, Civil Engineer Greg Doeden, Civil Engineer RESOLUTION NO. RESOLUTION ADOPTING PLANS AND SPECIFICATIONS Whereas, on the 10th day of May, 2006, plans, specifications, form of contract and estimated cost were filed with the City Clerk of Dubuque, Iowa for the 5th Street Reconstruction Project - Delhi Street to Alpine Street. Whereas, notice of hearing on plans, specifications, form of contract, and estimated cost was published as required by law. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: That the said plans, specifications, form of contract and estimated cost are hereby approved as the plans, specifications, form of contract and estimated cost for said improvements for said project. Passed, adopted and approved this day of ,2006. Roy D. Buol, Mayor Attest: Jeanne F. Schneider, CMC, City Clerk RESOLUTION NO. 236-06 AWARDING CONSTRUCTION CONTRACT FOR THE 5TH STREET RECONSTRUCTION PROJECT - DELHI STREET TO ALPINE STREET Whereas, sealed proposals have been submitted by contractors for the 5th Street Reconstruction Project - Delhi Street to Alpine Street pursuant to Resolution No. and notice to bidders published in a newspaper published in the City of Dubuque, Iowa on the 19th day of May, 2006. Whereas, said sealed proposals were opened and read on the 8th day of June, 2006, and it has been determined that the bid of Portzen Construction, Inc. of Dubuque, Iowa, in the amount of $1,024,519.20 was the lowest bid for the furnishings of all labor and materials and performing the work as provided for in the plans and specifications. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: That the contract for the above improvement be awarded to Portzen Construction, Inc. and the Manager be and is hereby directed to execute a contract on behalf of the City of Dubuque for the complete performance of the work. BE IT FURTHER RESOLVED: That upon the signing of said contract and the approval of the contractor's bond, the City Treasurer is authorized and instructed to return the bid deposits of the unsuccessful bidders. Passed, approved and adopted this 19th day of June, 2006. Roy D. Buol, Mayor Attest: Jeanne F. Schneider, CMC, City RESOLUTION NO. 237-06 APPROVING CONSTRUCTION CONTRACT WITH (CONTRACTOR NAME) FOR THE 5TH STREET RECONSTRUCTION PROJECT - DELHI STREET TO ALPINE STREET Whereas the City Council by Resolution No.013? -tJ~ awarded the construction contract for the 5th Street Reconstruction Project - Delhi Street to Alpine Street to Portzen Construction, Inc.; and Whereas Portzen Construction, Inc. has submitted the attached executed contract and bond. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: 1. The contract and bond attached hereto are hereby approved. 2. The City Manager is hereby authorized and directed to execute the contract on behalf of the City of Dubuque. Passed, approved and adopted this 19th day of June, 2006. Roy D. Buol, Mayor Attest: Jeanne F. Schneider, CMC, City Clerk CITY OF DUBUQUE - ENGINEERING DIVISION _ BID TABULATION SHEET tie Excavating Co. BIDDER: Horsf"leld Construction,Jn' BIDDER: Tschi TOTAL COST UNIT COST TOTAL COST UNIT COST $3,255.00 $1,850,00 $11,83050 $1.000.00 $825.00 $275.00 $31,00 $10.00 $3.30 $200.00 $275.00 275,00 $2,042-25 $1,285,75 $10,75500 $460.00 $1,425.00 $415,00 $19,45 $695 $3,00 $92.00 ~ $415.00 $46,91950 $6,000.00 $88.256.00 $26,555.50 $29,104.00 $64,680,00 $2e600.00 $10,70 $100.00 $6.40 $17.30 $13.60 $12.00 $13,00 $26.967.75 $6,000.00 $89,635.00 $3,684,00 $28,78300 $66.021.50 $2c250.00 $6.15 $100.00 $6,50 $2,40 $13,45 $12.25 $11.25 $205,400,00 $3,055.00 $14,880.00 $7,525.00 $12,000.00 $52,461.00 $7.493,25 $6,650.00 $3,780.00 $3,135.00 $21,068,00 $32.50 $65.00 $96,00 $215,00 $48.00 $4,35 $4,85 $19.00 $42.00 $165.00 $11,45 $184,860.00 $1,595.65 515,174.50 $308.00 $7,837.50 $39,798.00 $5,716.50 $5,02250 $3,640.50 $3.059.00 $15c916.00 529.25 $33.95 $91,90 $8.80 $31.35 $3,30 $3.10 $14.35 $40.45 $~O $8,65 $25,340.00 $4.350,00 $5,300.00 $15080,00 $6,860.00 $7,962.50 $lL140.00 $1,810,00 $2,175.00 $2,650.00 $26.00 $28.00 $32.50 $190.00 $25,200,00 $4,800.00 $5,830,00 $16,588,00 $7,546.00 $8,158.15 $882,00 $1,800.00 $2,400.00 $2,91500 $28.60 530.80 53575 514700 548,711.25 $4,315.00 $6,835.50 $1,932.00 533,150.00 $2,925.00 $7,800,00 $19,720.00 $68.00 $8,250.SO $28.45 BIDDER: Portzen ConstructionL Inc. e8,2006 81DDATE WEST 5TH STREET (DELHI _ ALPINE) RECONSTRUCTION BID TABULATION FOR ESTIMATE COST ESTIMATE UNIT COST ESTIMATE QUANTITY I UNIT I BID ITEM DESCRIPTION TOTAL COST UNIT COST $2,310.00 $1,110,00 $7,17000 $490,00 5900.00 $300,00 $22,00 $600 $2.00 $98.00 ~ $300.00 526,310,00 $6,000.00 $94,461.50 $5,312.50 $27,178.00 $60,637,50 $2,000.00 $6,00 $100,00 $6.85 $3.50 $12,70 $11.25 $10,00 I ! 525,00 ~ ,137.75 ! 7,170.00 ! 625,00 ! 1,71000 $ 500.00 . "","" ! 6,000.00 $ 96,530.00 ! 4,605,00 $ 24,610.00 53,900.00 2e650.00 BASI; BID; 5,00 ~ 2,00 25,00 570.00 500.00 ~ .' 3,~85 , , 1 ID ~ !i. Cy E,," Eael DEMOUTlON & REMOVAL Clearing & Grubbin\!, Inch Diamete Remove Pavement Remove Curb & Gutter ~sting~ Remove Exi' Manhole ~Stormlntake 1 , 3 , , 6 5,50 00.00 --L.QQ. ...!.QQ. ~ 10.00 32: 4,385 --"'-- 13,790 ~ ~ 5,390 '" Cy "'- Too SY ~ T" T" EXCAVATIQN & STONE Excavation, Undassi~ed Excavation, Rock Backfill,Limestone Bac"fill, Topsoil GranularSub-Base 3" Crushed Stone Base Trench Stabilization Stone 7 . 9 '" 11 12 " $176,96{LOO $1,880.00 $17,050.00 $6,650.00 $10,000.00 $45,225.00 $6,566-25 $7,700.00 $4,050.00 $3,325.00 $16,100.00 $28.00 $40.00 $110.00 $190,00 $40.00 $3.15 $4.25 $22.00 $45.00 $175.00 $8.75 176,960.00 1,880,00 19,375,00 6,415.00 9,750.00 54,270.00 7,725.00 5,250.00 3,600.00 3,32500 16,560.00 28.00 40,00 125,00 185.00 39.00 ~ -2.QQ. ~ 40,00 5.00 9.00 6,320 ~ ~ -"-- ~ 12,060 1,545 '" ~ -"'-- 1,840 Sy ~ Too EA SY ~ '" .!i. .!i. E~ LF "C" '," PAVEMENT 14 PC Concrete Pavement, (71 wllnte9ral Curb, Cia 15 PC Concrete Pavement, (8'~ wllnte\!ral Curb, Cia 16 HMA300kSurfaceCourse,112"(PG64-22l 17 FixtureAdiustment 18 PC Concrete Drivewav, 6", Remove & Construct 19 PC Concrete Sidewalk, 4", Remove & Construct 20 PC Concrete Sidewalk, 6", Remove & Construct 21 PC Concrete Curb and Gutter, 2.5', Construct 22 PC Concrete Steps, Remove & Construct 23 PC Concrete Access Ramp, Detectable 24 6"Subdrain, Perforaled Plastic: DraioTile $22.150.00 $4,300.00 $5,000.00 $16,820.00 $7,595,00 $8,33000 $750.00 $1,625.00 $2,150.00 $2,500.00 $29.00 $31.00 ~ $125.00 22,400.00 ~ 5,000.00 20,300,00 9,065.00 10,535.00 720.00 600.00 2,300.00 2,500,00 ~ 37.00 43.00 120,00 " ~ ~ 58' '" 2~5 6 E.", Each Eilcl ~ ~ ~ Eacl 262-3 STORM SEWER ~ ~ Manhole 48" Diameter, Complete Storm Sewer, 15" RCP, CL III Storm Sewer, 18" RCP, CL III Storm Sewer, 21" RCP, CL III Storm Water Curb Opening Neenah R 25 26 27 28 26 30 " $33.25 $625.00 $105,00 $276.00 $34.00 $75,00 $200.00 $53,619.00 $4,812,50 $7,519,05 $2,254.00 $26,812.50 $3,217.50 $8~580.00 $36,60 $687.50 $115.50 $322,00 $27.50 $82.50 $220.00 $51,64125 $3,500.00 $7,161.00 $2,10000 $32,175,00 $3,315.00 $8~190.00 $35,25 $500.00 $110.00 $300,00 53300 $85.00 $210.00 $8,845.00 $30.50 ! 58,600.00 ! 5,600,00 ! 6,965.70 ! 2,205,00 .t~ ! 5,85000 I $ 8,160,60 4000 800.00 107.00 ~ 40,00 150.00 220.00 ~ l... 65.1 7 9~0 " " I"C Eael ~ Each -'L Each Each SAMTARY SEWER 32 8" PVC w.f Backfill 33 48" Diameter Maohole Base 34 48" Diameter Manhofa Sidewall 35 Manhole Frame & Cover 36 4"PVCLateralw./Backfill 37 8"x4"PVCl/Vye 38 Locate Existing LateraVExpjoration 28.14 90 LF 2w./P, WATER MAIN DIP,Cla 96 CITY OF DUBUQUE - ENGINEERING DIVISION _ BID TABULATION SHEET BID TABULATION FOR WEST 5TH STREET (DELHI. ALPINE) RECONSTRUCTION BID DATE: ne 8, 2006 rie Excavating Co. BIDDER: Horsrleld Construction1.ln. $39,550.00 $11,684.50 $37L800,00 $1,189,7.5.29 $ 1,189,745.29 19,47% 8.... 8id $ub--Totlll %Under/Ovel $22.60 $28.45 $3,15000 $1,175,00 $1,780.00 $1,040.00 $9,670.50 $1,980,00 $1,000,00 $3,420.00 $1,500.00 $24,800.00 $3,750,00 $800,00 $911.35004 $5.00 $4.00 $52.00 $6,30 $36.00 $1,00000 $36.00 $1,500.00 $24,800.00 $150,00 ~ $91,350.04 BIDDER: Tschi TOTAL COST $47,62500 $12,581,25 $1,920.00 $2,250,00 $1,32000 $405.00 $160.00 $470,00 $235,00 $210.00 $660.00 $7,645.00 $8,700.00 $2,930.00 $3!l5,OO $2,580.00 $475.00 $680.00 $2,520.00 $800,00 $550.00 $7,800,00 $240,00 $910.00 $8,580,00 $1,370.00 $18,630,00 $!l,200.00 54.48500 $40,175,00 $12,177.00 $38,505.60 $23.30 $29,70 $3e208.80 $857,75 $1,201.50 $550.00 $16,88500 $151.25 $1,650.00 $261.25 $2,750,00 $37,28000 $2,750.00 sm-oo ~23L900.00 $3,65 $2.70 $27.50 $11.00 $2.75 $1,650.00 $2.75 $2,750,00 $37,280,00 $110.00 $8,80 $23e900,00 UNIT COST $31.75 $45.75 $80,00 $90.00 $120,00 $135.00 $160.00 $235.00 $235,00 $135.00 $165,00 $695.00 $870.00 $1,465.00 U!l500 $430.00 $475.00 ~ $360.00 $400.00 $275.00 $l,!lSOOO $240.00 $455.00 $16.50 $137.00 $810.00 $575.00 $115,00 $1-,-036L440.30 1,036,440.30 4.08% 8an81~Sub--T_ % Under/Over BIDDER: Portzen ConstructionL Inc. ESTIMATE COST ESTIMATE UNIT COST ESTIMATE QUANTITY I UNIT I BID ITEM DESCRIPTION TOTAL COST $48,37500 $12,168.75 $2,04000 $2,315,00 $1,650,00 $420,00 $170.00 ~ $270.00 $280.00 $700.00 $6,380.00 $7,550.00 $2,580,00 $275.00 $1,860.00 $360,00 $505.00 $1,225,00 $430.00 $640.00 $7,600.00 $200,00 $590.00 $11,986,00 $1,140.00 $21,344.00 $8,116,00 $7e176.00 UNIT COST $32,25 $44.25 $85.00 $9500 ~ $140.00 ~ $270.00 ~ $14000 $17500 $580.00 $755.00 $1,290.00 $275.00 $310,00 $360.00 $505.00 $175,00 $21500 $320,00 $1,900.00 $200.00 $2!l5,00 $23.05 $114,00 $928.00 $511.00 $184,00 TOTAL COST $51,525.00 $11,783.75 $1,20000 $1,500,00 $1,100.00 $45000 $190,00 $650.00 $325.00 $300.00 $720,00 $7,15000 $8,700,00 $2,800.00 ~ $1,710.00 $335.00 """i4sO:OO $1,190.00 $450.00 $650.00 $7,000.00 $225.00 $810.00 $14,560.00 $35Q.OO $13,80000 $6,400.00 $5,850.00 UNIT COST $3435 $42.85 $50.00 $60,00 $100.00 $150.00 $190.00 $325,00 $32500 ~ $180.00 ~ $87000 $1,400.00 $250,00 $285.00 $33500 $450.00 $170.00 $225.00 $32500 $1,750.00 $225,00 $405.00 $2800 $3500 $600.00 $400.00 $150.00 45,22500 12,430,00 1,320.00 1,500,00 935.00 450,00 230.00 620.00 ~ 300,00 920.00 8,800.00 ~ 3,000.00 ~ 1,860.00 ~ 500.00 1,050.00 360,00 700.00 7,20000 350,00 1,000.00 13,000.00 300,00 15,687.20 7,712.80 5e850.00 ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! . 30,15 45.20 55,00 60.00 85.00 150.00 230.00 310.00 310.00 150.00 230.00 800,00 900.00 ,500.00 275,00 310,00 325.00 500.00 150,00 180,00 350,00 ,800.00 350,00 500,00 25.00 30.00 682.05 482,05 150.00 ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! $ 1500 m -'!. ~ -'l -'- 1 -'- 1 -'- , -'l -'" -'- -"- 2- -"- -"- 2- 2- 2- .i.. -'- 2- gQ l" E. l" " LF hi'. Each Each Each E'''' Each Each Each Each Each Each Each Each E,'" Each Each Each Each Eaeh Each E,'" E,'" Each ~ ~ Each Each Each 314" Taplnslallatiol BASEBlQ;, 40 8" DIP, Class 52 w./Pol 41 12"DIP, Class 52 w./P, 42 6"MegaLullMJ 43 8" Mella Lug MJ 44 12"MegaLu1IMJ 45 6"11114deg BendMJ)(MJ 46 8"11114dell.BendMJxMJ 47 12"111/4dell.BendMJxM, 48 12"221f2dell.BendMJxM, 49 6"4SdeqBendMJ)(MJ 50 8"45degBendMJxMJ 51 6"ValveMJwJ8ox 52 8"ValveMJwtBox 53 12"ValveMJwtBox 54 6"xS"x6"Anc:horinIlTeeMJ 55 8"x8"xS"AnchoringTeeMJ 56 8"x8"x8"AnchorinllTeeMJ 57 12"x12"x12"AnchorinIlTeeMJ 58 6".441 Sleeve 59 S"-441 Sleeve 60 12".441 Sleeve 61 HydrantMJ 62 12"x8"ReducerPExPE 63 8"x6"CrossMJ 64 314"CopperServiceLineTYPEK 65 11/4"CopperServiceLineTYPEK 66 Water Service LinesSlopBox,CurbSt, 66A 314" Copper Service Reconnect 67 Re--AdiustStopBoxes $21,437.50 $4,51000 $33,60000 $12.25 $11.00 $2,800,00 $822.50 $1,223.75 $300.00 $9,210,00 $2,6!l5.00 $2,500.00 $1,900,00 $5,00000 $25,000,00 $3,750.00 $400.00 $23~000,00 $3.50 $2.75 $1500 $6,00 $49.00 $2,500,00 $2000 $5,000.00 $25,00000 $150.00 ~ $23,000.00 $989L990.50 989,990.50 -O.S9% lla...BidSub.T_ % Under/Over $ 28,000.00 $' 9,02000 ~ ''''<';'.,, '..:-'1 $ 728,50 $ 1,335.00 $ 700.00 $ B,442,50 $ 1,375.00 ! 1,000.00 $ 2,375.00 i 2,50000 $ 15,000.00 '$ 4,000.00 i 600.00 $ 11,500,00 16.00 22.00 2L600,00 1,750 ~ 12 hi'. hi'. Each FJB.ER OPTICS 68 Conduit, 4" PVC Sch 40 wfTrace Wire 69 Conduit,4"PVCSch80wfTraceWire 70 FiberOplic:sJunctionVauKcPrecastConc:rate MISCEuANEOUS ~ 3.00 35.00 ~ 25.00 ,000.00 25.00 2,500,00 15,000.00 160.00 15:00 l1LSOO.00 235 '" ~ 1,535 " -'-- 95.0 -'- -'- :!5. 'P 1 hi'. hi'. hi'. ~ MGAL ~ MGAL ~ ~ E~H hi'. LS Sawcut, Concrete Sawcut.AsphaK RemoveandReplace_HandRall Sod Waterinll Tree Preservation Measures Dust Control Surface Treatmen! Erosion Control Plan-Operatinll Procedure TrafficControl&SaletvControl Sign Post, Removal & Inslallatiol AsphaKicCurb Mobilization 71 72 71 " 75 76 77 78 79 80 " 82 995,817,55 $99,581.75 $164,309.90 1,259,709.20 Base BidS"b-Total Contingency (10%) Construction Engineering & Inspedon (lS%) Totaf Construction Estimale: CITY OF DUBUQUE - ENGINEERING DIVISION _ BID TABULATION SHEET BIDDER: Horsfield Construction,)n Co, rieEl<cavatin, BIDDER: Tschi BIDDER: POrU:en Construction!.lnc. ne8,2006 BID DATE WEST 5TH STREET (DELHI_ ALPINE) RECONSTRUCTION BID TABULATION FOR TOTAL COST UNIT COST ESTIMATE COST ESTIMATE UNIT COST ESTIMATE QUANTITY I U'IT I BID ITEM DESCRIPTION TOTAL COST UNIT COST TOTAL COST UNIT COST BASE BID: ALTERNATE BID~ $11,350,00 $500.00 $2.430,00 ~ $4,350.00 $80000 $1,509.60 $2,01600 $13,760,00 $5,838,00 $330.00 $1,575.00 ~ $<<,822.601 $11,350,00 $50000 $30.00 $40.00 $150.00 $800.00 $13,60 $12.00 $40.00 $4.20 $165,00 $6.30 $3600 $6,183.00 $1,100.00 $2,097.90 $17900 $5,394.00 $495.00 $1,492,95 $2,058.00 $9,511.60 $5,143.00 $322.00 56,875.00 ~ 1 $40,876.201 $6,183,00 $1,10000 $25.90 $179.00 $186.00 $49500 $13,45 $12.25 $27.65 $3.70 $161.00 $27,50 $2.75 $2,000,00 $450.00 $2,268.00 $150,00 $4,350,00 $500,00 $1,409.70 $1,890.00 $13,760.00 $5,560.00 $250,00 $1,500.00 ~ $34,528.701 $2,000.00 $450,00 $28.00 $150.00 $15000 $500,00 $12,70 $11.25 $40.00 $4.00 $125,00 $6,00 $49,00 2,000.00 800.00 1,215.00 27500 5,80000 500.00 1,276.50 1,680.00 12,384.00 6,95000 350,00 1,37500 225.00 34,830.50 2,000.00 800.00 15,00 275.00 200,00 500.00 ~ .!.Q.B2. 3600 2.:.QQ. 75.00 ~ 25.00 1 ! "! -'- '" -'- !...!:Q ~ ~ ,390 2. '50 9 " '" LF Each -.!L -"'- ~ ~ ~ SF E.," ~ MGAL UNCOLNSCHOOLDROPOFF_OCSD SileGradil Tree Removai Storm Sewer {4--incl11 SDR 26 PVC Clean Out (4-inchl Trench Dr.lln 12-inch (4-inch Outlet); Neenah R-4996C or Zum Z-882 Connect To El<istin!l Storm Catch Basin Granular Sub-Base 3" Crushed Stone Base PC Concrete Pavement, (6'~ w1lnlellral PCConcreteSidewalk,6",Construct PC Concrete Access Ramp, Delectable ~ Watel Curb and Guller "' " " 86 87 88 89 " 91 " 89 " " 28.69% %Under/Ovel 7,36% %Under/avel 0.87% % Under/Over Total Construction Estimate (DCSD)