TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: Public Hearing for the Bunker Hill Pump Station Improvement Project -
CIP #740 -1422, Fund Balance - $536,888
DATE: April 10, 2013
Water Department Manager Bob Green recommends City Council approval of the
plans, specifications, form of contract and estimated cost of $717,500 for the Bunker Hill
Pump Station Improvement Project.
The Bunker Hill Pumping Station Improvement Project consists of the construction of a
new pumping facility to replace the existing 140 year old station that has deteriorated
beyond repairs. This station provides control and booster pumps from pressure zone 1
to pressure zone 3 in the City distribution system. The project consists of various
components, the major items being: demolition of the existing pumping facility building,
the construction of a new 30'x40' block and brick building, with two 125 HP booster
pumps, 12" ductile iron pipe process piping, electrical, plumbing and mechanical
components, standby power and site work.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
kr,„709,,,
Michael C. Van Milligen
MCVM:jh
Attachment
cc: Barry Lindahl, City Attorney
Cindy Steinhauser, Assistant City Manager
Teri Goodmann, Assistant City Manager
Bob Green, Water Department Manager
Masterpiece on the Mississippi
TO:
FROM:
SUBJECT:
DATE:
Michael C. Van Milligen, City Manager
Bob Green, Water Department Manager
Dubuque
ktratd
All - America City
'1 111!
2012
Public Hearing for the Bunker Hill Pump Station Improvement Project
CIP #740 -1422, Fund Balance - $536,888
April 9, 2013
INTRODUCTION
The attached Resolution is to approve the plans, specifications, form of contract and
estimated cost for the Bunker Hill Pump Station Improvement Project.
DISCUSSION
The Bunker Hill Pumping Station Improvement Project consists of the construction of a
new pumping facility to replace the existing 140 year old station that has deteriorated
beyond repairs. This station provides control and booster pumps from pressure zone 1
to pressure zone 3 in the city distribution system. The project consists of various
components, the major items being: demolition of the existing pumping facility building,
the construction of a new 30'x40' block and brick building, with two 125 HP booster
pumps, 12" DIP process piping, electrical, plumbing and mechanical components,
standby power and site work (including PCC parking and driveway, site grading,
fencing, seeding and 480 LF of 12" DIP water main installation including valves and
hydrants).
PROJECT SCHEDULE
The schedule for the project is as follows:
Initiate Public Bidding Process
Publish Notice to Bidders, Advertise for Bids
Notice of Public Hearing Notice on Plans & Specifications
Public Hearing on Plans & Specifications
Pre -bid Conference
Receipt of Bid Proposals (Bid Letting)
Award Construction Contract
Project Completion Date
April 1, 2013
April 5, 2013
April 5, 2013
April 15, 2013
April 17, 2013
April 25, 2013
May 6, 2013
October 31, 2013
RECOMMENDATION
It is recommended that the City Council give approval to the plans, specifications
form of contract for the Bunker Hill Pump Station Improvement Project.
and
BUDGET IMPACT
The estimate of probable cost for Bunker Hill Pump Station Improvement Project is as
follows:
Estimated Construction Cost $614,000.00
Contingency (5 %) $ 31,000.00
Engineering Design & Inspection Fees $ 72,500.00
Total Estimated Project Cost $717,500.00
The project funding summary is as follows:
CIP NO. FUND DESCRIPTION
740 -1422 Bunker Hill Pump Station
Improvement Project
FUND AMOUNT BUDGETED
$ 565,225.00
BUDGET DEFICIT
$152,275.00
It is being recommended that this budget deficit be absorbed with the surplus funds
currently in the following CIP:
CIP NO.
740 -2261
FUND DESCRIPTION CURRENT BALANCE
Ramp Utility Relocation $ 430,209.59
HISTORY
CIP 740 -2261 Ramp Utility Relocation
These funds were originally allocated to support infrastructure improvements to the
city's water distribution system along Central Ave. as part of the new 9th Street Parking
Ramp Project and later as part of the Historic Millwork District Project. Over time, as
these projects were better defined and were constructed resulted in some of the
identified funds were not being utilized.
FY13 monies budgeted in this account were $631,861. To date, these monies have
supported a 12 inch water main extension along 5th Street to Ice Harbor Drive located
within the Port of Dubuque at an estimated cost of $191,126.40. These funds will also
support the proposed 8 inch water main extension along Elm Street from 9th to 11th
Street (Intermodal Parking Ramp Project) at an estimated cost of $98,000.00.
At this time, there is an estimated fund balance in this account in the amount of
$390,734.40. In review of this CIP and its proposed future activities, there will be a
surplus fund balance in the estimated amount of $292,734.40. $92,198.50 of the
surplus fund has been allocated to the Asbury Tank Reconditioning Project, leaving
$200,535.90 available. We are requesting that part of this surplus be approved to
support the projected increase cost to the Bunker Hill Pump Station Improvement
Project. The total cost increase will be determined when the proposals are received.
ACTION TO BE TAKEN
The City Council is requested to approve the plans, specifications, form of contract and
estimated cost for the Improvement Project through the adoption of the attached
Resolution.
Attachments
cc: Jenny Larson, Budget Director
Kevin Firnstahl, City Clerk
Jacqueline Rodriguez, Water Plant Manager
File
RESOLUTION NO. 128 -13
APPROVAL OF SPECIFICATIONS, FORM OF CONTRACT, AND ESTIMATED COST
FOR THE BUNKER HILL PUMP STATION IMPROVEMENT PROJECT - CITY OF
DUBUQUE, IOWA WATER DEPARTMENT BUNKER HILL PUMP STATION
IMPROVEMENT PROJECT
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF DUBUQUE, IOWA:
That the proposed plans, specifications, and form of contract now on file with the
office of City Clerk and estimated cost for the Bunker Hill Pump Station Improvement
Project, in the amount of $717,500.00, are hereby approved.
Attest:
Passed, adopted and approved this 15th day of April, 2013.
Kevi Firnstahl, Ci y Clerk
oy D. Buol, Mayor
CITY OF DUBUQUE,
IOWA
OFFICIAL NOTICE
NOTICE OF PUBLIC
HEARING OF THE
CITY COUNCIL OF DU-
BUQUE, IOWA, ON
THE ' - MATTER OF THE
SPECIFICATIONS,
FORM OF CONTRACT,
AND ESTIMATED
COST FOR THE BUNK-
ER HILL PUMP STA-
TION IMPROVEMENT
PROJECT
NOTICE 15 HEREBY
GIVEN: The City Coun-
cil of the City of Dubu-
que, Iowa will hold a
public hearing on the
proposed specifica-
tions, form of contract
and estimated cost for
the Bunker Hill Pump
Station Improvement
Project, in accordance
with the provisions of
Chapter 26, Code of Io-
wa, at 6:30 p.m., on the
15th day of April, 2013,
in the Historic Federal
bers (Second Floor) 350
West 6th Street, Dubu-
que, Iowa. The scope of
the Project is as fol-
lows:
The Bunker Hill Pump-
ing Station Improve-
ment Project consists
of the construction of a
new pumping facility
to provide control and
booster pumping from
pressure zone 1 to
pressure zone 3 in the
city distribution sys-
tem. The project con -
sistsiof various compo-
nents, the major items
being: demolition of
the existing pumping
facility building, the
construction of a new
30'x40" block and brick
building, with two 125!
HP booster pumps, 12 "
DIP process piping,
electrical, plumbing
and mechanical com-
ponents, standby pow-
er and site work (in-
cluding PCC parking
and driveway, site
grading, fencing, seed-
ing and 480 LF of 12"
DIP water main instal-
lation including valves
and hydrants).
Copies of supporting
documents for the pub-
lic hearing are on file in
the City Clerk's Office
and may be viewed
during normal working
hours.
Written comments re-
garding the above pub-
lic hearing may be sub -
miffed to the City
Clerk's Office on or be-
fore said time of public
hearing. Any visual or
hearing - impaired per-
sons needing special
assistance or persons
with special accessibil-
ity needs should con-
tact the City Clerk's of-
fice at (563) 589 -4120
or TDD at (563) 690 -
6678 at least 48 hours
prior to the meeting.
Published by order of
the City Council given'
on the 1st day of April,
2013.
Kevin Firnstahl,
CMC, City Clerk
It 4/5
NOTICE TO BIDDERS
CITY OF DUBUQUE
PUBLIC IMPROVE-
MENT PROJECT WA -_
TER' SYSTEM IM -_
PROVEMENTS BUNK -
ER HILL PUMPING FA-
CILITY 2013
Time and Place for
Filing Sealed Propos-
als. Sealed bids for the
work comprising each
improvement as stated
below must be filed be-
fore 2:00 p.m. on the
25th day of April, 2013,
in the Office of the City
Clerk, City Hall - First
Floor, 50 West 13th
Street, Dubuque, Iowa.
Time and Place
Sealed Proposals
Will be Opened? and
Considered. Sealed
proposals will be
opened and bids tabu-
lated
25 at 2 :00 p.m. on y
April 2013, at Cit
Hall - Conference Room
A, 50 West 13th Street,
Dubuque, Iowa, for
consideration by the
City Council (Council)
at its meeting on May
6, 2013. The City of Du-
buque, iIowa, reserves
the right to reject any
and all bids.
Time for Com-
mencement and
Completion of Work.
Work on each improve-
ment shall be com-
menced within 10 days
after the Notice to Pro -
ceed has been issued
and shall be fully com-
pleted within 180 con-
secutive calendar days.
Mandatory Pre-Bid
Conference. A manda-
tory pre -bid confer-
ence will be held at
10 :00 a.m. on April 17,
2013, at 10:00 a.m. at
City Hall - Conference
Room A, 50 West 13th
Street, Dubuque, Iowa.
Work on each improve-
ment shall be 'com-
menced= within 10 days
after the Notice to Pro-
ceed has been issued
and shall be fully com-
pleted within 180 con-
secutive calendar days.
Bid Security. Each
bidder shall accompa-
ny its bid with a bid se-
curity as security that
the successful bidder
will enter into a con-
tract for the work bid
upon and will furnish
after the award of con-
tract a corporate sure-
ty bond, acceptable to
the governmental enti-
ty, for the faithful per -
formance of the con -
tract, in an amount
equal to one hundred
percent of the amount
of the contract. The bid
security shall be in the
amount of ten percent
(10 %) of the amount of
the contract and 'shall
be in the form 'of a
cashier's check or cer-
tified check drawn on a
state- chartered or fed -
erally chartered `bank,
or a certified share
draft drawn on a state
chartered or federally
chartered credit union,
or the governmental
entity may provide for
a bidder's bond 'with
corporate surety satis-
factory to the govern -
mental entity. The bid
bond shall contgin no
conditions excepted as
provided in this sec -
tion
Contract Docu-
ments. Copies of the
plans and specifica-
tions prepared by IlW,
P.C. may be obtained
from Tri -State Blue-
print, 696 Central Ave -
nue, Dubuque, :Iowa
52001, phone 563-556 -
3030. No deposit is re-
quired.
Preference for Iowa
Products and Labor.
By virtue of statutory
authority, preference
will be given to prod -
ucts and provisions
grown and I
duced within the coal State
of Iowa and to Iowa
domestic labor, to the
extent lawfully re-
quired under Iowa stat-
utes.
Sales Tax, The bidder
should not include
sales tax in its bid. A
sales tax ! exemption
certificate will be avail -'
able for all material
purchased for incorpo-
ration in the project.
General 'Nature of
Public Improvement.
The extent of the work
involved in the City of
Dubuque, Iowa, Water
System Improvements
Bunker Hill Pumping
Facility 2013 project
consists of the con-
struction of a new
pumping facility to pro-
vide control and boos-
ter pumping from pres-
sure zone 1 to pressure
zone 3 in the city distri-
bution system. The
project consists of vari-
ous components, the
major items being:
demolition of the exist
ing pumping facility
building, the construc-
tion of a new 30'x40'
block and brick build-
' , with two 125 HP
booster pumps, 12" DIP
process piping, electri-
cal, plumbing and me-
chanical components,
standby power and site
work (including PCC
parking and driveway,
site grading, fencing,
seeding and 480 LF of
12" DIP water main in-
stallation including
valves and hydrants).
STATE OF IOWA {SS:
DUBUQUE COUNTY
CERTIFICATION OF PUBLICATION
I, Suzanne Pike, a Billing Clerk for Woodward Communications, Inc., an Iowa
corporation, publisher of the Telegraph Herald,a newspaper of general circulation
published in the City of Dubuque, County of Dubuque and State of Iowa; hereby
certify that the attached notice was published in said newspaper on the following
dates: April 5, 2013, and for which the charge is $78.39.
f2a,
Subscribed to before me, a Notary Public in and for Dubuque County, Iowa,
this /® day of , 20 / .
Notary Public in and for Dubuque County, Iowa.
RYK.VL S
•