MEMORANDUM
July 12, 2006
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: University Avenue Reconstruction (US 20 to University Avenue)
STP-U-2100 (623) -- 70-31
Reinforced Concrete Box (RCB) Culvert Extension (Twin Box)
City Engineer Gus Psihoyos is recommending the acceptance of the construction
contract for the reinforced concrete box culvert extension of the University Avenue
Reconstruction Project in the final contract amount of $1 ,248,555.21, which is a 10.6%
decrease from the original contract in the amount of $1 ,396,624.11.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
(l1t! [~/1{\
Michael C. Van Milligen
--
MCVM/jh
Attachment
cc: Barry Lindahl, Corporation Counsel
Cindy Steinhauser, Assistant City Manager
Gus Psihoyos, City Engineer
D~~~E
~<!k-~
MEMORANDUM
July 10, 2006
TO:
FROM:
Michael C. Van Milligen, City M~~
Gus Psihoyos, City Engineer ~
SUBJECT:
University Avenue Reconstruction (US 20 to University Avenue)
STP-U-2100 (623) - 70-31
Reinforced Concrete Box (RCB) Culvert Extension (Twin Box)
INTRODUCTION
The enclosed resolutions provide for the acceptance of the construction contract for the
reinforced concrete box (RCB) culvert extension of the University Avenue
Reconstruction Project.
BACKGROUND
The overall University Avenue Reconstruction Project (US 20 to University Avenue) is
intended to contribute to the improved flow of traffic and to decrease intersection
congestion along the US Highway 20 corridor in the western portion of the City.
The installation of the reinforced concrete box culvert is the first construction phase of
the project through which University Avenue is extended to the south to intersect with
US Highway 20 across from Theisen's driveway. This initial phase included
construction of a double-barrel, 12- by 12-foot box culvert and the grading of the
embankment for the future street.
Upon completion of this work, a follow-up construction phase will be necessary to
provide the pavement, traffic signals and other work necessary to complete the project.
DISCUSSION
The reinforced concrete box (RCB) culvert extension of the University Avenue
Reconstruction Project was completed by Tschiggfrie Excavating Co. of Dubuque, Iowa,
in the final contract amount of $1,248,555.21, which is a 10.6% decrease from the
original contract in the amount of $1 ,396,624.11.
I recommend that the City Council accept the improvements and establish the final
contract at $1,248,555.21.
BUDGET IMPACT
The project cost summary for the reinforced concrete box (RCB) culvert extension of the
University Avenue Reconstruction Project is as follows:
Total Project Cost (Phase 1)
Bid Award
$1,396,624.11
74,682.00
510,065.33
~1.981.371.44
Final
$1,248,555.21
o
510,065.33
$1.758.620.54
Construction Contract
Contingency
Construction Engineering & Inspection
In April, 2005, the City Council approved a request for seeking additional funding from
the Dubuque Metropolitan Area Transportation Study (DMATS) for the completion of
Phase 3 of the University Avenue Extension of the US 20 Improvements Projects. This
request was made because of increased project costs associated with environmental
mitigation, property acquisition, wetland mitigation, and engineering fees. The request
from DMATS for the STP funds was $904,127.65, with an additional $226,031.91 from
City funds.
The 20% City match of $226,031.91 would be funded by the postponement of the
Center Grove/Cedar Cross Intersection Improvements (CIP 3001632) of $93,000 and
Stoneman Road Storm Sewer Extension Project (CIP 7201664) of $97,500, with the
balance of $35,531.91 from the annual appropriation for the Street Program (CIP
3001626).
Therefore, the project will be funded from the Capital Improvement Project 3001254,
University Avenue Extension to US 20, as follows:
Surface Transportation Funds (STP)
Street Construction Funds - City of Dubuque
$ 3,372,127.65
843,031.91
Total Project Funding (All Phases)
~4.215.159.56
ACTION TO BE TAKEN
The City Council is requested to adopt the attached resolutions accepting the
improvement and establishing the final construction cost for the reinforced concrete box
(RCB) culvert extension of the University Avenue Reconstruction Project.
cc: Roger Walton, PE - Iowa DOT
Dawn Lang, Budget Director
Deron Muehring, Civil Engineer II
David Ness, PE
Todd Irwin, Engineering
RESOLUTION NO. 313-06
ACCEPTING THE REINFORCED CONCRETE BOX (RCB) CULVERT
EXTENSION OF THE UNIVERSITY AVENUE RECONSTRUCTION
PROJECT
Whereas, the contract for the reinforced concrete box (RCB) culvert
extension of the University Avenue Reconstruction Project (the Project) has been
completed and the City Manager has examined the work and filed a certificate
stating that the Project has been completed according to the terms of the
contract, plans and specifications and that the City Manager recommends that
the Project be accepted.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF DUBUQUE, IOWA:
Section 1. The recommendation of the City Manager is approved and the
Project is hereby accepted.
Section 2. The City Treasurer is hereby directed to pay to the contractor
from the Surface Transportation Funds (STP) and the Street Construction Fund
appropriation for the contract amount of $1,248,555.21 less any retained
percentage provided for therein as provided in Iowa Code chapter 573, and to
pay such retainage only in accordance with the provisions of Iowa Code chapter
573.
Passed, approved and adopted this 17th day of July, 2006.
Roy D. Buol, Mayor
Attest:
Jeanne F. Schneider, CMC, City Clerk
RESOLUTION NO. 314-06
FINAL ESTIMATE
Whereas, the construction contract for the reinforced concrete box (RCB)
culvert extension of the University Avenue Reconstruction Project, has been
completed and the City Engineer has submitted his final estimate showing the
cost thereof including the cost of estimates, notices and inspection and all
miscellaneous costs.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF DUBUQUE, IOWA:
Section 1. That the cost of said improvement is hereby determined to
be $1,758,620.54 and the said amount shall be paid from the Surface
Transportation Funds (STP) and the Street Construction Fund of the City of
Dubuque, Iowa.
Passed, approved and adopted this 17th day of July, 2006.
Roy D. Buol, Mayor
Attest:
Jeanne F. Schneider, CMC, City Clerk
ItemNoJ Plan I Unit Price II Quantity I 0/. Complete
Description Unit Quantity Completed Total I by Cost
1 CLEARING AND GRUBBING ACRE 2 $6,175.00 2 $12,350.00 100%
2 EXCAVATION, CLASS 10, ROADWAY AND BORROW' CY 56,293 $5.80 56,293 $326,499.40 100%
3 EXCAVATION, CLASS 10, UNSUITABLE OR UNSTABLE CY 3,220 $3.65
MATERIAL . 3,220 $11,753.00 100%
4 TOPSOIL, FURNISH AND SPREAD. CY 0 $8.65
5 GRANULAR MATERiAl FOR BLANKET AND SUBDRAIN CY 280 $16.35 461 $7,537.35 165%
6 ADJUSTMENT OF FIXTURES. EACH 0 $490.00
7 GRANULAR SURFACING ON ROAD, CLASS A CRUSHED TON 2,700 $10.00
STONE 2,115.11 $21,15-1.10 78%
8 REMOVAL OF EXISTING STRUCTURES LUMP 1 $12,730.00 1 $12,730.00 100%
9 REMOVAlS, AS PER PlAN LUMP 1 $6,600.00 1 $6,600.00 100%
10 GRANUlAR BACKFILL TON 3,795 $9.70 3,795.00 $36,811.50 100%
11 EXCAVATION, CLASS 20 CY 1,100 $6.00 1,100 $6,600.00 100%
12 EXCAVATION, ClASS 22 CY 835 $18.50 835 $15,447.50 100%
13 STRUCTURAL CONCRETE (RCB CULVERT) . CY 1,230.8 $260.95 1,230.8 $321,177.26 100%
14 REINFORCING STEEL' LB 166,729 $0.65 166,729 $108,373.85 100%
15 APRONS, CONCRETE, 24 IN. DIA. EACH 1 $830.00 1 $830.00 100%
16 STORM SEWER UTILITY ACCESS, RA-50 EACH 2 $1,950.00 2 $3,900.00 100%
17 REMOVE STORM SEWER PIPE LESS THAN OR EQUAl LF 40 $11.60
TO 36 IN. 40 $464.00 100%
18 SEWER PIPE, DUCTILE IRON STORM, 24 IN DIA. LF 94 $74.00 94 $6,956.00 100%
19 SEWER PIPE, 20000 STORM, 24 IN. DIA LF 19 $38.70 19 $735.30 100%
20 ENGINEERING FABRIC .. SY 2,834 $2.55 2,833.90 $7,226.45 100%
21 REVETMENT, CLASS E TON 188 $16.00 199.1 $3,185.60 106%
22 REMOVAL OF SIDEWALK SY 7 $6.55 7 $45.85 100%
23 REMOVAl OF PAVED DRIVEWAY SY 78 $4.55 78 $354.90 100%
2. SAFETY CLOSURE EACH 1 $2,500.00 1 $2,500.00 100%
25 FIELD OFFICE EACH 1 $3,500.00 1 $3,SOO.00 100%
26 TRAFFIC SIGNALIZATION LUMP 1 $22,740.00 1 $22,740.00 100%
27 MOBILIZATION LUMP 1 $60,000.00 1 $60,000.00 100%
28 EXCAVATION, SOIL WITH ELEVATED LEAD CY 0 $58.35
CONCENTRATIONS .
29 INTAKE, CASTING AND GRATE ONLY EACH 1 $448.00 1 $448.00 100%
30 MULCHING ACRE 0.84 $350.00 1.6 $560.00 190%
31 SEEDING AND FERTILIZING (URBAN) ACRE 1.34 $1,500.00 1.68 $2,520.00 125%
32 SLOPE PROTECTION, WOOD EXCELSIOR MAT (RC-14) sa 581 $8.00 378.34 $3,026.72 65%
33 STABILIZING CROP - SEEDING AND FERTILIZING ACRE 0.84 $750.00
(URBAN) 0.71 $532.50 85%
34 WATERING FOR SOD, SPECIAL DITCH CONTROL, OR MGAL 233 $25.00
SLOPE PROTECTION 11.3 $282.50 5%
35 SILT FENCE LF 1,235 $1.70 2,495 $4,241.50 202%
36 REMOVAL OF SILT FENCE LF 1,235 $O.SO
37 CLEAN-OUT OF SILT FENCE LF 1,235 $O.SO
City of Dubuque
University Avenue Extension
R.C.B. Culvert and Grading
STP-U-2100(623)-70-31
Pay Estimate #: 8
Ending Date: 21-Apr-Q6
Final Payment
HRG # 176290J02
Total Completed of Original Contract "ems
$1,011,080.28
. Item eliminated from contract or original contract quantity
reduced through Change Order.
.. Completed quantity reduced from previOUS Pay Request
due to error in measurement. Contract quantity reduced
through Change Order.
City of Dubuque
University Avenue Extension
R.C.B. Culvert and Grading
STP-U-21 00(623)-70-31
Pay Estimate #: 8
Ending Date: 21-Apr-06
Final Payment
Total Completed of Original Contract Items (from page 1)
$1,011,080.28
8001 CERTIFIED PLANT INSPECTION CY 1,230.8 $3.60 1,230.8 $4,430,88 100%
REMOVE SANITARY SEWER PIPE LESS THAN OR
8002 EQUAL TO 36 INCHES LF 184.0 $14.80 184 $2,723.20 100%
8003 TOPSOIL STRIP, SALVAGE, AND SPREAD CY 2,584.0 $6.75 2,584 $17,442.00 100%
EXCAVATION AND PLACEMENT, SOIL WITH ELEVATED
8004 LEAD CONCENTRA lIONS CY 4,972.0 $47.28 4,972 $235,076.16 100%
8005 SUBDRAIN, LONGITUDINAL, 4 IN. DIA. LF 29.0 $8.50 29 $246.50 100%
8006 FLOWABlE MORTAR CY 21.6 $82.50 21.6 $1,782.00 100%
8007 (PRICE ADJUSTMENT) SLUMP TEST DEVIATION EA 1.0 $4,488.34 1 -$4,488.34 100%
8008 (PRICE ADJUSTMENT) AIR CONTENT TEST DEVIATION EA 1.0 $9,916.09 1 -$9,916.09 100%
8009 (PRICE ADJUSTMENT) FUEL ADJUSTMENT EA 1.0 $404.60 1 $404.60 100%
8010 (PRICE ADJUSTMENT) SLUMP TEST DEVIATION EA 1.0 $5,871.38 1 -$5,871.38 100%
8011 (PRICE ADJUSTMENT) AIR CONTENT TEST DEVIATION EA 1.0 $4,354.60 1 -$4,354.60 100%
Total Completed of Change Orders
$237,474.93
Summary of Request
Original Contract Price
Revised Contract Price
Work Completed 10 Date
Retainage (3%)
Total Earned Less Retainage
Previously Approved Pay Requests (list each)
Pay Request #1
Pay Request #2
Pay Request #3
Pay Request #4
Pay Request #5
Pay Request #6
Pay Request #7
$1,396,624.11
$1,256,845.44
$1,248,555.21
$0.00
$1,248,555.21
$23,132.08
$142,550.66
$525,693.16
$311,597.61
$161,549.77
$29,951.89
$48,679.67
Total Previously Approved Pay Request
$1,243,154.84
Amount Due This Request
1-
Percent Contract Complete
Percent of Time Used
100.0%
90.0%
Prepared By:
~
Howard R. Green
S/V/06
Date
Reviewed By:
j-f-Cb
Date
Reviewed By:
s--/2-06
City of Dubuque
Date