Through the competitive quotation process for public improvements, the 2013
Pavement Marking Project was awarded on April 25, 2013, to Selco, Inc., in the amount
of $77,699.56.
City Engineer Gus Psihoyos recommends that the award for the 2013 Pavement
Marking Project be officially recorded in the minutes of the City Council.
duat4A., krt., italy,
Michael C. Van Milligen
MCVM:jh
Attachment
cc: Barry Lindahl, City Attorney
Cindy Steinhauser, Assistant City Manager
Teri Goodmann, Assistant City Manager
Gus Psihoyos, City Engineer
Masterpiece on the Mississippi
TO: Michael C. Van Milligen, City Manager
FROM: Gus Psihoyos, City Engineer
DATE: May 5, 2013
SUBJECT: 2013 Pavement Marking Project
Dubuque
kittil
AI-America City
II 1 1 1F
2012
The 2013 Pavement Marking Project provides for the painting of the centerlines, lane
lines, and edge lines, as well as transverse markings including arrows, crosswalks, and
other associated symbols, markings and curb markings. Removal of existing pavement
markings may also be required.
The following is a summary of the bids received:
Selco, Inc. $ 77,699.56
Through the competitive quotation process for public improvements, this project was
awarded on April 25, 2013 to Selco, Inc. of Dubuque, Iowa, in the amount of
$77,699.56.
In accordance with the competitive quotation requirements of Iowa Code, Section 26.14,
it is necessary that the award for the 2013 Pavement Marking Project to be officially
recorded in the minutes of the City Council.
cc: Troy Kress, Engineering Technician
2013 Pavement Marking Project
CIP: 3002245
Bid Results
25- Apr -13
PART #1 BIDDER
LONGITUDINAL MARKINGS Engineer's Estimate Selco Inc.
ITEM QTY. UNIT UNIT COST TOTAL COST UNIT COST TOTAL COST
1. Yellow Paint:
a. Centerline: Broken
approx. 35.4 miles
b. Centerline: Double
yellow) approx. 26.0 miles
136.1 Gal. 25.08 $3,413.39 25.75 $3,504.58
799.4 Gal. 25.08 $20,048.95 25.75 $20,584.55
c. Centerline: One Direction
No Passing
approx. 4.7 miles 91 Gal. 25.08 $2,282.28 25.75 $2,343.25
d. Single Dotted
approx. 0.1 miles 0.5 Gal. 25.08 $12.54 25.75 $12.88
e. Double Dotted
approx. 0.1 miles 1 Gal. 25.08 $25.08 25.75 $25.75
f. Edge Line
approx. 1.1 miles 17.1 Gal. 25.08 $428.87 25.75 $440.33
Subtotal YELLOW 1045.1 Gal. $26,211.11 $26,911.33
2. White Paint:
a. Centerline (broken)
approx. 15.1 miles
b. Solid Lane Line (Turn Line)
approx. 5.9 miles
c. Edge Line
approx. 26.2 miles
d. Single Dotted
approx. 0.2 miles
87.2 Gal. 24.96 $2,176.51 25.21 $2,198.31
90 Gal. 24.96 $2,246.40 25.21 $2,268.90
403 Gal. 24.96 $10,058.88 25.21 $10,159.63
1.2 Gal. 24.96 $29.95 25.21 $30.25
Subtotal WHITE 581.4 Gal. $14,511.74 $14,657.09
PART #1 TOTAL (YELLOW + WHITE) 1626.5 Gal. $40,722.85 $41,568.42
PART # 2
TRANSVERSE MARKINGS, INCLUDING: X -WALK, STOP LINE, ISLAND X- HATCHING,
SYMBOLS, LEGENDS, AND ALL INDICATED CURB PAINTING.
ITEM QTY. UNIT UNIT COST TOTAL COST UNIT COST TOTAL COST
1. Yellow Paint:
a. Island diagonal lines
& channelization approx.
3054 L.F. 17.8 Gal. 55.32 $984.70 55.77 $992.71
b. Curb painting
approx. 7655 L.F. 66.8 Gal. 55.32 $3,695.38 55.77 $3,725.44
c. Handicap stall symbol on Street
& limit lines -132 Residential No.of 15.8 Gal. 55.32 $874.06 55.77 $881.17
& limit lines -10 Non - Residential No.of 1.2 Gal. 55.32 66.384 55.77 66.924
Subtotal YELLOW 101.6 Gal. $5,620.51 $5,666.23
2. White Paint:
a. Island diagonal lines
& channelization approx.
1470 L.F. 8" equiv.
7.2 Gal.
55.24 $397.73
55.19 $397.37
b. Curb painting
approx. 2744 L.F. 24.0 Gal.
c. Crosswalks:
I Type A appr. 34591 LF 151.0 Gal.
II Type B appr. 323 (2'x10' Sections) 56.4 Gal.
55.24 $1,325.76
55.24 $8,341.24
55.24 $3,115.54
55.19 $1,324.56
55.19 $8,333.69
55.19 $3,112.72
d. 24" Stop line
approx. 6946 L.F. 121.3 Gal. 55.24 $6,700.61 55.19 $6,694.55
e. Do Not Block
Instersection approx. 2480 LF 21.6 Gal 55.24 $1,193.18 55.19 $1,192.10
Note: Paint 2 /year
e. Arrows
633 No. of 110.3 Gal. 55.24 $6,092.97 55.19 $6,087.46
f. Word Messages (Ahead, Bike, Ends
Lane, Only, School, Stop, X -ING, etc)
171 No. of 39.2 Gal. 55.24 $2,165.41 55.19 $2,163.45
g. Railroad crossings
14 No. of 18.9 Gal. 55.24 $1,044.04 55.19 $1,043.09
h. Sharrows 2.1 Gal. 55.24 $116.00 55.19 $115.90
28 No. of
Subtotal WHITE 552.0 Gal. $30,492.48 $30,464.88
PART #2 TOTAL (YELLOW + WHITE 653.6 Gal. $36,112.99 $36,131.11