TO: Michael C. Van Milligen, City Manager
FROM: Steve Sampson Brown, Project Manager
Dubuque
SUBJECT: Water & Resource Recovery Center Cogeneration Facilities
Strand Associates, Inc. Design, Bidding and Construction Related
Services Agreement - Amendment #2
DATE: May 23, 2013
INTRODUCTION
This memorandum is to seek your approval and execution of Amendment No. 2 to the
September 16, 2010 Agreement for Design, Bidding, and Construction Related Services
between the City of Dubuque and Strand Associates, Inc. (Strand) for the Water &
Resource Recovery Center (WRRC) Cogeneration Facilities Project.
BACKGROUND
The WRRC Cogen Project provides for the installation of electrical generation
equipment (microturbines) that will use biogas from the anaerobic digestion facilities to
produce electricity. In addition, heat recovery equipment will further recover energy as
heat to improve the overall energy recovery efficiency from the biogas use,
DISCUSSION
The need for the attached amendment results for the completion of the microturbine
project being completed 5 months after the substantial completion of the WRRC's
renovation project. Thus Strand's Resident Project Representative will not be able to
work on both projects that the same time.
The need for this amendment was anticipated at the time bidding was initiated on the
microtubine project. The additional amount of this agreement was included in the total
project cost for the microtubines project when the project was sent to the City Council
for bid initiation approval.
This amendment provides Strand to do the following:
1. Change Contract Administration Services to: Attend and provide meeting minutes
for up to 6 (instead of 10) monthly construction progress meetings and one pre -
installation meeting.
Page 1 of 2
2. Change item #8 listed under Contract Administration Services to: ENGINEER
anticipates conducting 6 (instead of 10) one -day site visits.
3. Add the following services: "Resident Project Representative (RPR) Services will
provide up to five months of part -time Resident Project Representative (RPR)
Services; a Resident Project Representative (RPR) is anticipated to be on -site an
average of one 8 -hour day each week. In furnishing observation services,
ENGINEER's efforts will be directed toward determining for OWNER that the
completed project will, in general, conform to the Contract Documents; but
ENGINEER will not supervise, direct, or have control over the contractor's work
and will not be responsible for contractor's construction means, methods,
techniques, sequences, procedures, or health and safety programs, or for the
contactor's failure to perform the construction work in accordance with the
Contract Documents ".
4. Delete number 8, in the Service Elements Not Included section of the original
contract, which reads that Resident Project Representative (RPR) Services are
not included.
BUDGET IMPACT
The original agreement was in the amount of $250,000. Amendment #1 increased that
total by $20,000 to equal $270,000. The cost of Amendment #2 additional services will
be $20,000, for additional Engineering Services and an estimated $30,000 for Resident
Project Representative Services on an estimated, hourly rate basis bringing the
agreement total to $320,000.00.
The funding for Amendment No. 2 will be from the W &RRC Cogeneration Facilities
Project budgeted amount for professional services.
ACTION TO BE TAKEN
The execution of Amendment No. 2 to the September 16, 2010 Strand Associates
agreement is requested.
cc: Gus Psihoyos, City Engineer
Jenny Larson, Budget Director
Jonathan Brown, Water Pollution Control Plant Manager
Attach.
Attachment C- Amendment #2
F: \PROJECTS \Water Pollution Control Plant Replacement \_PSA Negotiations \Strand\2013 03 -20 -13 MVM Memo re
WPCP Cogeneration Facilities Amendment No. 2.doc
Page 2 of 2
910 West Wingra Drive
Madison, \A/153715
(8) 608-251-4843
(0) 608- 251 -8655
January 18, 2013
City of Dubuque
50 West 13th Street
Dubuque, IA 52001 -4864
Attention: Mr. Michael C. Van Milligen, City Manager
Re: Amendment No. 2 to the September 16, 2010, Agreement for Design Services,
Bidding - Related Services, and Construction - Related Services
Cogeneration Facilities at the Water Pollution Control Plant
This is Amendment No. 2 to the referenced Agreement.
Under Scope of Services,
Contract Administration Services, items no. 4 and no. 8, CHANGE 10 to "six."
ADD the following:
"Resident Project Representative (RPR) Services
Provide up to five months of part-time RPR services; RPR is anticipated to be on -site an average
of one 8 -hour day each week. In furnishing observation services, ENGINEER's efforts will be
directed toward determining for OWNER that the completed project will, in general, conform to
the Contract Documents; but ENGINEER will not supervise, direct, or have control over the
contractor's work and will not be responsible for contractor's construction means, methods,
techniques, sequences, procedures, or health and safety programs, or for the contractor's failure to
perform the construction work in accordance with the Contract Documents."
Under Service Elements Not Included, DELETE No. 8 in its entirety.
Under Compensation, REPLACE the entire first paragraph with the following:
"OWNER shall compensate ENGINEER for all Services, except RPR Services, a lump sum of
$290,000.
OWNER shall compensate ENGINEER for RPR Services on an hourly rate basis plus expenses
an estimated fee of $30,000. Expenses incurred for RPR Services will be billed at actual cost plus
10 percent."
RAW:mro:skb\R:\MAD\ Documents\ Agreements\D\Dubuque, City of ( IA)\ CogenerationFacilities@ WPCP .2010\Agr \Amd \I154.033.2.docx
Arizona I Illinois I Indiana I Kentucky I Ohio I Wisconsin wytvw.stranci.cOrn
City of Dubuque
Page 2
January 18, 2013
Under Schedule, REPLACE the table with the following:
"Project Milestone
Notice to Proceed
Submit Brief Report
Submit Design Documents to IDNR
Bid Date
Notice to Proceed of Construction Contract
Substantial Completion of Construction
Final Completion of Construction
Anticipated Completion Date
October 2010
January 2011
January 2012
February 2013
April 2013
January 2014
March 2014"
IN WITNESS WHEREOF the parties hereto have made and executed this Amendment.
ENGINEER: OWNER:
STRAND ASSOCIATES, INC.°
CITY OF DUBUQUE
Matthew S. Richards Date Michael C. Van Milfigan
Corporate Secretary City Manager
RAW:mro:skb \R:\ MAD\ Documents\Agreements\D\Dubuque, City of ( IA)\ CogenerationFacilities@ WPCP .2010\Agr \Amd \1154.033.2.docx
Date
wvotanstrandcom
910 West Wingra Drive
Madison, VVI 53715
(P) 608 - 251 -4843
(F) 608 -251 -8055
January 18, 2013
City of Dubuque
50 West 13th Street
Dubuque, IA 52001 -4864
Attention: Mr. Michael C. Van Milligen, City Manager
Re: Amendment No. 2 to the September 16, 2010, Agreement for Design Services,
Bidding - Related Services, and Construction- Related Services
Cogeneration Facilities at the Water Pollution Control Plant
This is Amendment No. 2 to the referenced Agreement.
Under Scope of Services,
Contract Administration Services, items no. 4 and no. 8, CHANGE 10 to "six."
ADD the following:
"Resident Project Representative (RPR) Services
Provide up to five months of part-time RPR services; RPR is anticipated to be on -site an average
of one 8 -hour day each week. In furnishing observation services, ENGINEER's efforts will be
directed toward determining for OWNER that the completed project will, in general, conform to
the Contract Documents; but ENGINEER will not supervise, direct, or have control over the
contractor's work and will not be responsible for contractor's construction means, methods,
techniques, sequences, procedures, or health and safety programs, or for the contractor's failure to
perform the construction work in accordance with the Contract Documents."
Under Service Elements Not Included, DELETE No. 8 in its entirety.
Under Compensation, REPLACE the entire first paragraph with the following:
"OWNER shall compensate ENGINEER for all Services, except RPR Services, a lump sum of
$290,000.
OWNER shall compensate ENGINEER for RPR Services on an hourly rate basis plus expenses
an estimated fee of $30,000. Expenses incurred for RPR Services will be billed at actual cost plus
10 percent."
RAW:mro:skb\R:\ MAD\ Documents \Agreements\D\Dubuque, City of ( IA)\ CogenerationFacilities@ WPCP .2010\Agr\Amd \1154.033.2.docx
Arizona I Illinois I Indiana I Kentucky Ohio I Wisconsin
r;J VA AL ti° -ana„ If
City of Dubuque
Page 2
January 18.2013
Under Schedule, REPLACE the table with the following:
"Project Milestone
Notice to Proceed
Submit Brief Report
Submit Design Documents to IDNR
Bid Date
Notice to Proceed of Construction Contract
Substantial Completion of Construction
Final Completion of Construction
Str
Anticipated Completion Date
October 2010
January 2011
January 2012
February 2013
April 2013
January 2014
March 2014"
IN WITNESS WHEREOF the parties hereto have made and executed this Amendment.
ENGINEER:
STRAND ASSOCIAZES, INC.`
Matthew S. Richards
Corporate Secretary
OWNER:
CITY OF DUBUQUE
Date
Michael C. Van Milligan
City Manager
RAW:mro :skb\R :\ MAD \Documents\Agreements\D \Dubuque, City of ( IA) \CogenerationFaeilities @WPCP .2010 \Agr \Amd \1154.033.2.docx
Date