City Engineer Gus Psihoyos recommends initiation of the bidding process for the Elm
Street Reconstruction Project (9th to 12th), and further recommends that a public hearing
be set for August 5, 2013.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
Michael C. Van Milligen
MCVM:jh
Attachment
cc: Barry Lindahl, City Attorney
Cindy Steinhauser, Assistant City Manager
Teri Goodmann, Assistant City Manager
Gus Psihoyos, City Engineer
Masterpiece on the Mississippi
TO: Michael C. Van Milligen, City Manager
FROM: Gus Psihoyos, City Engineer
SUBJECT: Elm Street Reconstruction Project (9th to 12th)
Iowa DOT Project No. TCSP- 052 - 2(129) -9S -31
Iowa DOT Agreement No. 2013 -E -259
DATE: July 5, 2013
INTRODUCTION
Dubuque
Al-America City
'I I,
2012
The enclosed resolutions authorize the public bidding procedure for the Elm Street Reconstruction
Project (9th to 12th), Iowa DOT Project No. TCSP – 052 - 2(129)- 9S -31.
BACKGROUND
In 2012 the City of Dubuque received a $600,000 TCSP (Transportation and Community System
Preservation grant from the US Department of Transportation. This grant was awarded to assist in
the complete reconstruction of Elm Street between 9th Street and 12th Street in the Historic Millwork
District. The City of Dubuque executed the development agreement with the Iowa Department of
Transportation in March of 2013.
The reconstruction of Elm Street will re -align the street to accommodate the Intermodal
Transportation Center, allow for bus turning traffic and accommodate two -way traffic.
DISCUSSION
This project will re -align Elm Street between 9th Street and Elm Street so that bus traffic can access
the proposed intermodal transportation center terminal and provide for two way traffic in the
corridor. The project will also include complete street elements including pedestrian cross -walks
and pedestrian access ramps that meet ADA guidelines. The project will also install fiber optic
conduits and street light foundations. Minor storm sewer improvements will also occur due to
pavement grade changes.
This project will occur during the same timeframe as the 30" forcemain project and will share
detours with that project. Additionally, the 9th Street and 11th Street One -way to Two -way
Conversion Project will coordinate with this project.
PROJECT SCHEDULE
The project development schedule for the Elm Street Reconstruction Project (9th to 12th) is as
follows:
Iowa DOT Advertisement for Bids
Notice of Hearing on Plans & Specifications
Iowa DOT Receipt of Bids (Bid Letting)
City Public Hearing on Plans & Specifications
City Award of Contract (Subject to Iowa DOT Approval)
Iowa DOT Start Date
Contract Completion Date
June 11, 2013
July 19, 2013
July 16, 2013
August 5, 2013
August 5, 2013
August 19, 2013
90 Working Days
Completed Fall 2013
Because this project is bid through the Iowa DOT in Ames, it is acceptable for the City to hold a
public hearing on the Elm Street Reconstruction Project (9th to 12th) following the receipt of bids. At
the August 5th meeting, following the public hearing, the City Council will be requested to concur in
the award of the Improvement Contract, subject to Iowa DOT approval.
RECOMMENDATION
I recommend that the City Council set August 5, 2013, as the date for a public hearing on the Elm
Street Reconstruction Project (9th to 12th)
BUDGET IMPACT
The estimate of probable cost for the Elm Street Reconstruction Project (9th to 12th) is as follows:
Description Amount
Construction Contract $750,000.00
Contingency 75,000.00
Contract Administration / Construction Engineering 50,000.00
Total Project Cost $875.000.00
The project funding summary is as follows:
CIP Funding Source Amount
Transportation and Community System Preservation — TCSP Funds $ 600,000.00
3002142 Street Construction - General 25,000.00
7201008 Storm Sewer improvement/Extension 25,000.00
3501630 Decorative Concrete Maintenance 75,000.00
3001287 Stone Retaining Walls 150,000.00
Total Project Funding $875,000.00
During the development of the project, IIW estimated the project and costs are expected to be higher than
originally anticipated. In order to fund these additional costs, additional funding has been identified from the
Street Construction - General fund, the Storm Sewer Improvement/Extension Fund, the Decorative Concrete
Maintenance Fund and the Stone Retaining Walls Fund. Once project bid results are known, the City will re-
evaluate the funding amounts for the award of the project.
ACTION TO BE TAKEN
The City Council is requested to set the date for a public hearing on the Elm Street Reconstruction
Project (9th to 12th) through adoption of the enclosed resolution.
Prepared by Jon Dienst, P.E.
cc: Jenny Larson, Budget Director
Teri Goodmann, Assistant City Manager
Robert Schiesl, Assistant City Engineer
Tim Horsfield, Parking Division Manager
Phil Wagner, Acting Economic Development Director
RESOLUTION NO. 233 -13
ELM STREET RECONSTRUCTION PROJECT (9th to 12th)
IOWA DOT PROJECT NO. TCSP- 052 - 2(129) -9S -31
SETTING DATE OF PUBLIC HEARING ON PLANS, SPECIFICATIONS, FORM OF
CONTRACT, AND ESTIMATED COST
NOW THEREFORE, BE IT RESOLVED BY THE CITY OF THE CITY
OF DUBUQUE, IOWA:
The proposed plans, specifications, form of contract and estimated cost for the
Elm Street Reconstruction Project (9th to 12th), Iowa DOT Project No. TCSP- 052 -
2(129)-9S-31 in the estimated amount $875,000, are hereby preliminarily approved
and ordered filed in the office of the City Clerk for public inspection.
A public hearing will be held on the 5th day of August, 2013, at 6:30 p.m. in the
Historic Federal Building Council Chambers (second floor), 350 West 6th Street,
Dubuque, Iowa, at which time interested persons may appear and be heard for or
against the proposed plans and specifications, form of contract and estimated cost of
said Project, and the City Clerk be and is hereby directed to cause the attached notice
of the time and place of such hearing to be published in a newspaper having general
circulation in the City of Dubuque, Iowa, which notice shall be published not Tess than
four days nor more than twenty days prior to the date of such hearing. At the hearing,
any interested person may appear and file objections to the proposed plans,
specifications, form of contract, or estimated cost of the Project.
Attest:
Passed, adopted and approved this 15th day of July, 2013.
7 49
Kevi S. Firnstahl, MC, y Clerk
oy D. Buol, Mayor
NOTICE OF PUBLIC HEARING ON PLANS, SPECIFICATIONS, FORM OF
CONTRACT, AND ESTIMATED COST FOR ELM STREET RECONSTRUCTION
PROJECT (9th to 12th) IOWA DOT PROJECT NO. TCSP- 052 - 2(129) -95 -31
NOTICE IS HEREBY GIVEN: The City Council of the City of Dubuque, Iowa will
hold a public hearing on the proposed plans, specifications, form of contract and
estimated cost for the Elm Street Reconstruction Project (9th to 12th), Iowa DOT Project
No. TCSP- 052 - 2(129)- 9S -31, in accordance with the provisions of Chapter 26, Code
of Iowa, at 6:30 p.m., on the 5th day of August, 2013, in the Historic Federal Building
Council Chambers (second floor), 350 West 6th Street, Dubuque, Iowa. Said proposed
plans, specifications, form of contract and estimated cost are now on file in the office of
the City Clerk. At said hearing any interested person may appear and file objections
thereto.
The scope of the Project is as follows:
• The project will provide for the complete reconstruction of Elm Street between
9th Street and 12th Street.
Any visual or hearing- impaired persons needing special assistance or persons
with special accessibility needs should contact the City Clerk's office at (563) 589 -4120
or TDD at (563) 690 -6678 at least 48 hours prior to the meeting.
Published by order of the City Council given on the day of 2013.
Kevin S. Firnstahl, CMC, City Clerk